HomeMy WebLinkAbout4056 Resolution - J-U-B Supplement 3 for Lewis Street OverpassRESOLUTION NO. 4056
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
AUTHORIZING THE CITY MANAGER TO SIGN AND EXECUTE
SUPPLEMENT NO. 3 FOR THE PROFESSIONAL SERVICES AGREEMENT
(PSA) WITH J -U -B ENGINEERS, INC. FOR THE LEWIS STREET OVERPASS
PROJECT.
WHEREAS, the City and J -U -B Engineers, Inc. entered into a Professional Services
Agreement (PSA) on February 5, 2018 to provide design services with respect to the Lewis Street
Overpass Project; and
WHEREAS, the City and J -U -B Engineers, Inc. entered into the first Supplement to the
PSA, Contract No. 30-18-2020 on January 22, 2020 to add right-of-way tasks, a right-of-way sub
consultant (Universal Field Services), along with various design revisions; and
WHEREAS, the City and J -U -B Engineers, Inc. entered into the second Supplement to the
PSA, Contract No. 30-18-2020 on February 26, 2021 to include additional design engineering and
right-of-way services; and
WHEREAS, the City and J -U -B Engineers, Inc. (the project's Engineer of Record) desire
to enter into a third Supplement to the PSA No. 30-18-2020 to add construction support services;
and
WHEREAS, the additional construction support services are necessary to fulfill the
original intent of the PSA with J -U -B Engineers, Inc., and its addition, by amendment, to this PSA
represents a fair and reasonable agreement as determined by the Public Works Director.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF PASCO, WASHINGTON:
Section 1. That the subject agreement is amended to allow J -U -B Engineers, Inc. to
provide additional construction support services as described within Exhibit A attached hereto.
Section 2. The City Manager of the City of Pasco, Washington, is hereby authorized,
empowered, and directed to sign and execute said Supplement on behalf of the City of Pasco.
Resolution — PSA Supplement No. 3 for
Lewis Street Overpass Engineering Services - 1
PASSED by the City Council of the City of Pasco, Washington this Yd day of May, 2021.
Saul Martinez
Mayor
ATTEST:
Debra Barham, CMC
City Clerk
Resolution — PSA Supplement No. 3 for
Lewis Street Overpass Engineering Services - 2
APPROVED AS TO FORM:
Kerr F so C
City Attorney
Washington State
Department of Transportation
Supplemental Agreement
Organization and Address
Number 3
J -U -B ENGINEERS, INC.
2810 W. Clearwater Ave., Suite 201
Original Agreement Number
Kennewick, WA 99338
30-18-020
Phone: (509) 783-2144
Project Number
Execution Date
Completion Date
STPUS-HLP-3530(006)
February 5, 2018
December 31, 2023
Project Title
New Maximum Amount Payable
Lewis Street Overpass
$1,720,000.00
Description of Work
This supplement provides for engineering support during construction and project closeout. The total estimated cost of Supplement
3 is $97,0000.
The Local Agency of City of Pasco
desires to supplement the agreement entered in to with J -U -B ENGINEERS, INC.
and executed on February 5, 2018 and identified as Agreement No. JUB No. 30-18-020
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Section 1, SCOPE OF WORK, is hereby changed to read:
See Attached Exhibit A Scope of Work
11
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days
for completion of the work to read: Time for Completion extended through construction closeout December 31, 2023
III
Section V, PAYMENT, shall be amended as follows:
Supplement No. 3 total estimated cost is $97,000.00 for a total increased budget of $1,720,000.00
as set forth in the attached Exhibit A, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the Appropriate
spaces below and return to this office for final action.
By. Richard -IJ. Door - Project Manager
Consultant Signature
DOT Form 140-063
Revised 09/2005
0
Approving Authority Signature
Date
Lewis Street Overpass
4/22/2021
Summary of Payments
Supplement No. 3 - Engineering Construction Support
Basic
Basic
Agreement with
Agreement
Adjustment
Supplement 1
Supplement 2 Supplement 3
Total
Direct Salary
$308,504.37
$301,767.71
$18,911.61
$39,312.12
$29,257.42
$389,248.86
Overhead
$586,027.86
$573,231.05
$32,930.45
$65,622.83
$48,838.75
$720,623.08
* Direct Non-Salary
$399,226.27
$399,226.27
$69,031.45
$15,000.00
$10,160.50
$493,418.22
** Adjustment
Fixed Fee
$92,551.31
$90,530.31
$5,673.48
$11,793.64
$8,777.23
$116,774.66
Total
$1,364,755.34
$1,364,755.34
$126,546.99
$131,728.59
$97,033.89
$1,720,064.81
Rounded
$1,364,800.00
$1,364,800.00
$126,500.00
$131,700.00
$97,000.00
$1,720,000.00
irect Non-Salary Costs
Direct Expenses
$2,147.60
$2,147.60
$570.45
$0.00
$160.50
$2,878.55
Subconsultants
$397,078.67
$397,078.67
$68,461.00
$15,000.00
$10,000.00
$490,539.67
irec on a ary
$399,226.27
$399,226.27
$69,031.45
$15,000.00
$10,160.50
$493,418.22
— Base
Agreement
Credit from
2010 Scope
l—
C JU
J-U-B ENGINEERS, INC.
J -U -B ENGINEERS, Inc.
SUPPLEMENT NO. 3
Exhibit A – Scope of Services
PROJECT NAME: Lewis Street Overpass Construction Support
CLIENT: City of Pasco
J -U -B PROJECT NUMBER: 30-21-027
CLIENT PROJECT NUMBER: 13007
PART 1 -PROJECT UNDERSTANDING
J -U -B's understanding of this project's history and CLIENT's general intent and scope of the project are
described as follows:
The City of Pasco awarded the Lewis Street Overpass construction contract March 1, 2021 to Cascade
Bridge LLC. Whereas, J -U -B provided the design and is the Engineer of Record for this project. The
CLIENT wishes to enter into an agreement for engineering support during construction. Full time
construction management is contracted with a separate Consultant which J -U -B has no contractual
relationship with for this project. J -U -B will report only to the CLIENT as requested.
PART 2 - SCOPE OF SERVICES BY J -U -B
J -U -B's Services under this Agreement are limited to the following tasks. Any other items necessary to plan
and implement the project, including but not limited to those specifically listed in PART 3, are the
responsibility of CLIENT.
J -U -B will coordinate with subconsultant(s) as needed. For budget purposes assumed budget has been
included for subconsultants to assist in tasks representing their design responsibility.
A. Task 010: Project Management
1. Set up project into J -U -B's financial and record keeping systems for document retention and
project controls.
2. Communicate and coordinate subconsultant activities under J -U -B, if necessary.
3. Regularly monitor project status, budget and schedule.
4. Attend client meetings as requested or needed to report assigned task status.
5. During periods of project activity, provide a regular report to CLIENT on project status, budget
and schedule.
6. Provide a monthly invoice including budget status.
7. Provide ongoing document handling and fling.
a. Assumptions:
i. 20 months of Project Management
b. Deliverables:
Invoices with Status and Budget Tracking
B. Task 015: Conformed Contract Documents
1. J -U -B shall prepare a set of Contract Documents incorporating the addendum revisions during
bidding. The Conformed plans and specifications will be provided for information only and not
replace the official signed contract documents.
a. Assumptions:
J -U -B Agreement for Professional Services
Attachment 1— Scope of Services, Schedule, and Basis of Fee Page 1
i. Addendum No. 1 Dated December 22, 2020
(a) Reference Document —1936 Lewis Street Underpass Plans and Miscellaneous
Drawings. Due to the size of this reference material a separate file may be provided.
(b) Bid Proposal revisions
(c) City of Pasco Standard Drawing DWG W-7 3" TO 8" WATER SERVICES
(d) Construction Plans revisions
(e) Contract Specification revisions
ii. Addendum No. 2 Dated January 5, 2021
(a) Bid Proposal revisions
(b) Construction Plans revisions
(c) Contract Specification revisions
iii. Addendum No. 3 Dated January 20, 2021
(a) Contract Documents revisions
1. BNSF Overpass Agreement Exhibits. Due to the size of this reference
material a separate file may be provided.
2. Wage Rates update
3. Notice of Intent
(b) Construction Plans revisions
(c) Contract Specification revisions
iv. Addendum No. 4 Dated January 22, 2021
(a) Contract Documents revisions — Excel Spreadsheet bid proposal provided
(b) Contract Bid Proposal revisions
(c) Construction Plans revisions
(d) Contract Specification revisions
v. Electronic files will be provided unless specific request for hard copies and is subject to
additional costs for printing and binding.
b. Deliverables:
Electronic file(s) representing Conformed Contract documents in PDF file format.
C. Task 020: Preconstruction Meeting
1. J -U -B shall prepare as needed and attend the preconstruction meeting. It is anticipated that no
out of town travel will be needed and the meeting will likely be remote due to COVID restrictions.
J -U -B will have representative Engineer of Record staff available for the preconstruction meeting
and to follow up with any resulting issues or requests.
a. Assumptions:
i. J -U -B Engineers attendance representing Roadway, Structural, Storm Drainage,
Water/Sewer
ii. Subconsultant KPG representative for Illumination, Irrigation, and Urban Design
D. Task 030: Site Visits
1. For this task, J -U -B will:
a. As requested by CLIENT, J -U -B will visit the site with CLIENT to evaluate any apparent
defects in work, to assist in clarifications and interpretations, field orders, or change orders or
other construction phase services identified in Standard Exhibit A — Construction Phase
Services.
b. Assumptions:
i. For budget purposes assume (20) site visits by Kennewick J -U -B office staff.
c. Deliverables:
J -U -B Agreement for Professional Services
Attachment 1 — Scope of Services, Schedule, and Basis of Fee Page 2
Observation Daily Report if requested by CLIENT
E. Task 040: Request For Information and Submittal Review
J -U -B will respond to RFI's by the contractor, review contractor submittals and shop drawings as
assigned by the CLIENT.
a. Assumptions:
i. For budget purposes assume (20) RFI's/Submittal requests.
b. Deliverables:
Follow up responses via email
F. Task 050: Change Orders and Work Change Directives
1. As requested by CLIENT, J -U -B will assist in evaluation of Change Orders.
a. Assumptions:
I. For budget purposes a monetary estimate is assumed and will be supplemented as
needed.
b. Deliverables:
Documented evaluation as requested by CLIENT.
G. Task 060: Project Closeout
1. Prepare record drawings, if necessary.
a. The record drawings will be prepared based on information gathered during field
observations as well as information provided by others. The accuracy or completeness of
information provided by others will not be verified by J -U -B.
b. If the record drawings will be a public record, J -U -B will grant the public entity with jurisdiction
the right to copy and disseminate the hard copy or digital image to those who legitimately
request the information in writing. Any release, use, or reuse by the public entity, any
individual, or organization, shall be at the public entity's, individual's, and/or organization's
sole risk and without liability or legal exposure to J -U -B.
c. Any seals of the registrants included on the record drawings will represent that the drafting of
the record drawing information was completed by staff under the registrants' responsible
charge.
2. Archive paper and electronic files and records.
3. Communicate the project completion to CLIENT and other affected agencies and stakeholders,
as required.
4. Close financial billing and accounting records in J -U -B's financial and record-keeping systems.
H. Task 070: Subconsultant(s)
1. Assistance from subconsultants involved in the design and contract preparation as required to
assist CLIENT. Potential subconsultants include:
a. KPG -Illumination System, Irrigation, and Urban Design
b. Assumptions:
i. It is anticipated that KPG would be the only subconsultant needed for construction
support. For budget purposes a monetary estimate is assumed and will be supplemented
as needed. Other subconsultants used for design that could be supplemented include:
ii. UFS — Right of Way Certification
iii. GPI — Geotechnical Investigation
iv. Widener Associates — Environmental Permitting & BNSF Coordination
c. Deliverables:
i. To be determined as needed.
PART 3 - CLIENT -PROVIDED WORK AND ADDITIONAL SERVICES
J -U -B Agreement for Professional Services
Attachment 1— Scope of Services, Schedule, and Basis of Fee Page 3
A. CLIENT -Provided Work -CLIENT is responsible for completing, or authorizing others to complete,
all tasks not specifically included above in PART 2 that may be required for the project including, but
not limited to:
1. Construction Management
2. Railroad Approvals and Coordination
3. Inspections and Resident Project Representative
4. Material Testing
5. Construction Surveying QC
6. Construction Documentation and Funding Agency Coordination
B. Additional Services -CLIENT reserves the right to add future tasks for subsequent phases or
related work to the scope of services upon mutual agreement of scope, additional fees, and schedule.
These future tasks, to be added by amendment at a later date as Additional Services, may include:
1. Design for the removal of existing top of underpass and railroad track replacement.
2. Assisting CLIENT with audit reviews and requests for design documentation.
NOTE on Coronavirus and Schedule: J -U -B is committed to meeting your project schedule commitments as delineated
above. As our response to the COM-19pandemic, J -U -B is engaging in safety procedures in help to protect clients, staff, their
families, and the public. Our staff or offices may be subject to quarantine or other interruptions. Since COVID-19 impacts are
beyond J -U -B's control, we are not responsible for the force majeure impacts to delivery timelines, or subsequent project delays
and related claims, costs, or damages. Should circumstances related to the COVID-19 issue arise with J -U -B staff or in a J -U -B
office that will impact our delivery schedule, we will notify you of the circumstances and mutually agree to a schedule
adjustment.
For interna/ J -U -B use only:
PROJECT LOCATION (STATE): Washington
TYPE OF WORK: City
R&D: No
GROUP: Transportation
PROJECT DESCRIPTION(S):
1. Construction Management (C15)
2. Highway/Interstate/Roadway (1-107)
J -U -B Agreement for Professional Services
Attachment 1— Scope of Services, Schedule, and Basis of Fee Page 4
Exhibit D
Consultant Fee Determination - Summary Sheet
Cost Plus Fixed Fee
Project: Lewis Street Overpass
Supplement No. 3 - Construction Support
Direct Salary Cost (DSC):
Flle: City of Pasco - Lewis Street Overpass Supplement No. 3 Construction Suport PE Fees Exhibit D
2021
Classification
Man -Hours
Rates of Pay
Costs
Project Manager- Senior
116.0
$74.17
$8,603.72
Project Manager
76.0
$55.98
$4,254.48
Project Engineer -Senior
76.0
$55.95
$4,252.20
Project Engineer
86.0
$43.01
$3,698.86
Project Engineer- Senior (Structures)
60.0
$72.86
$4,371.60
Project Engineer (Structures)
40.0
$40.57
$1,622.80
Project Designer
32.0
$31.29
$1,001.28
CAD Designer- Lead
16.0
$40.73
$651.68
PFA -Senior
20.0
$40.04
$800.80
522.0
Total DSC =
$29,257.42
Overhead (OH Cost - including Salary Additives):
Updated 2018 OH Rate x DSC of
166.93%
$48,838.75
Fixed Fee Fixed Fee
30.00%
_
$8,777.23
Total DSC, OH & Profit
$86,873.39
Reimbursables:
Travel and Per Diem
Per Diem
0 days @
$41.00 $0.00
Air Travel
0 trips @
$800.00 $0.00
Mileage
300 miles
$0.535 $160.50
Lodging
0 nights
$100.00 $0.00
Title Report
0 each @
$380.10 $0.00
Survey Equipment
GPS
0.0 hours
$20.45 $0.00
Reimbursable Sub -Total
$160.50
Subconsultant Costs:
Total
KPG
$10,000.00
Subconsultant Costs
$10,000.00
Total
$97,033.89
Total (Rounded $100)
$97,000.00
Management Reserve 0%
$0.00
Grand Total
$97,000.00
Prepared by: Rick Door
Date: 4/22/2021
Flle: City of Pasco - Lewis Street Overpass Supplement No. 3 Construction Suport PE Fees Exhibit D
EXHIBIT F
WSDOT
Breakdown of Overhead Cost
Year Ending December 31, 2019
FRINGE BENEFITS
Direct Labor
Beginning Total
17,947,482
% of Direct Labor
FICA
2,323,619
12.95%
Unemployment
96,553
0.54%
Medical Aid and Industrial Insurance
68,022
0.38%
Company Insurance and Medical
2,976,737
16.59%
Vacation, Holiday, and Sick Leave
3,750,727
20.90%
Commission, Bonuses/Pension Plan
3,461,495
19.29%
Total Fringe Benefits
12,677,153
70.63%
GENERAL OVERHEAD
State B &0 Taxes
297,497
1.66%
Insurance
529,826
2.95%
Administration and Time Not Assignable
10,129,547
56.44%
Printing, Stationery, and Supplies
574,157
3.20%
Professional Services
326,308
1.82%
Travel Not Assignable
1,198,385
6.68%
Telephone and Telegraph Not Assignable
306,860
1.71%
Fees, Dues, Professional Meetings
157,022
0.87%
Utilities and Maintenance
348,909
1.94%
Professional Development
192,728
1.07%
Rent
1,170,561
6.52%
Equipment Support ; Depreciation ft Computer expense
1,867,654
10.41%
Cost of money
161,438
0.90%
Office Miscellaneous, Postage
21,280
0.12%
Total General Overhead
17,282,172
96.29%
Total Overhead Fringe + General
29,959,325
166.93%