HomeMy WebLinkAboutPavement Surface Control - Road 68 Signage and Striping - Change Orders 1 and 2 (# 20-008)CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 1
Project No: 20008 Project Title: Signage & Striping at Rd 68/Burden Blvd
Contractor: Pavement Surface Control
Description of Change: Remove and replace concrete curbing taper
Detail as Appropriate: To include roadway excavation, remove & replace conc. Traffic curb,
HMA, CSBC, removing plastic traffic marking, and temp. traffic control
Contract Bid Amount: $ 95,924.00
SALES TAX @ 8.6%: N/A
Total: $ 95,924.00
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal
Subtotal $ 57,800.22
Sales tax @ 8.6% NIA
Sales tax @ 8.6% N/A
Total $ -
Total $ 57,800.22
Total Change Orders To Date $ 57,800.22
New Contract Amount $ 153,724.22
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ................................. 15
Modification to Contract time by this Change Order .................... 10
revised Total Contract Time .................................................... 25
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are)
being made and that the compensation for this Change Order is full and complete and is the only
compensation due or owing for this Change Order. Further, it is mutually agreed that this document will
supplement the present Contract Documents and that the provisions of the previously executed Contract
Documents shall apply to this Change Order,
AGREED TO AND ACCEPTED:
34
Date
APPROVED:
g' -/Y
'.MANAGER
APPROVED:
C z�
PROJECT NMAGEW Date
/0/A//z/ 1-111 L I1 y""
Construction Ahead Inc, dba
C
PAN'EMENT SURFACE CONTROL
91312 W. 10TH AVE
KENNEWICK, WA 99336
PHONE: (509) 586-1969
EMAIL: ESTIMATING@PAVEMENTSURFACE.COM
OREGON CCB # 125652 CONSTAI0831-5 DBE # D2F2315595
To:
Address:
CITY OF PASCO
Po Box 293
Pasco,wa 99301
Contact:
Phone:
Fax:
KENT MCCUE
(509) 545-3456
Project Name:
Project Location:
111020_SIGNING AND STRIPING AT ROAD 68/BURDEN BLVD
Bid Number:
Bid Date:
11/10/2020
Item # Item Description
Estimated Quantity Unit
Unit Price Total Price
CHANGE ORDER TO REMOVE CONCRETE CURBING 1.00 LS $57,800.22 $57,800.22
TAPER AND REPLACE
Total Bid Price: $57,800.22
Notes:
• PAVEMENT SURFACE CONTROL IS A FEDERALLY CERTIFIED WOMAN OWNED DISADVANTAGED BUSINESS ENTERPRISE WITH
FULL BONDING CAPABILITIES
• ANY MODIFICATIONS OR DELETIONS TO OUR BID MUST BE AGREED UPON PRIOR TO BID OPENING (I.E. NO ITEM MAY BE
DELETED OR MODIFIED WITHOUT DISCUSSION). THIS QUOTE IS PRIVELEGED AND CONFIDENTIAL
• THIS QUOTE MUST BE ATTACHED TO AND BECOME PART OF ANY SUBCONTRACT AGREEMENT
• QUOTE IS BASED ON **** WORKING DAYS. EXTENSION OF DAYS WILL RESULT IN EXTENDED RENTAL PRICING OF APPLICABLE ITEMS AND
LOST REVENUES AS A RESULT
• UNLESS OTHERWISE STATED, EACH ITEM INCLUDES ONE MOBILIZATION TO THE PROJECT. ADDITIONAL MOBILIZATIONS WILL BE BILLED
ACCORDINGLY IF MOBILIZATIONS ARE OUT OF PSC CONTROL
• THIS QUOTE DOES NOT INCLUDE PERFORMANCE OR PAYMENT BOND. PSC IS FULLY BONDABLE, LICENSED, AND INSURED TO PERFORM WORK
DESCRIBED IN QUOTE
• PAVEMENT SURFACE CONTROL INCLUDES INSURANCE COVERAGE THAT MEETS WSDOT STANDARD SPECIFICATIONS. ADDITIONAL INSURANCE
OR COVERAGE LIMITS THAT EXCEED THIS STANDARD ARE NOT INCLUDED. IF ADDITIONAL COVERAGE IS REQUIRED, THE COST TO INCREASE
LIMITS AND COVERAGE WILL BE BILLED TO THE PRIME CONTRACTOR
• LAYOUT, CONTROL, AND VERIFICATION TO EB PERFORMED BY OTHERS. THIS INCLUDES ALL FIELD VERIFICATIONS FOR ENGINEERED SHOP
DRAWINGS OR ANY ITEMS REQUIRING FIELD VERIFICATION
• DISPOSAL SITE TO BE PROVIDED BY CONTRACTOR WITHIN 10 MILES OF WORK BEING PERFORMED. DISPOSAL FEES WILL BE CHARGED IF SITE
CANNOT BE PROVIDED.
• SALES/USE TAX WILL BE CHARGED AS A LINE ITEM WHEN CONTRACTOR IS END USER ACCORDING TO JURISDICTION WHERE WORK IS
PERFORMED.
• ALL QUANTITIES WILL BE BILLED FOR ACTUAL AMOUNT USED. ANY MATERIAL NECESSARY, BUT NOT MENTIONED IN THIS QUOTE WILL BE
BILLED ADDITIONALLY ACCORDINGLY
• QUOTE DOES NOT INCLUDE WEEKEND, OVERTIME OR HOLIDAY WORK
ACCEPTED:
The above prices, specifications and conditions are satisfactory and
are hereby accepted.
Buyer:
Signature:
Date of Acceptance:
CONFIRMED:
CONSTRUCTION AHEAD, INC. Dba PAVEMENT
SURFACE CONTROL
Authorized Signature:
Estimator: MATT MCDANIEL
(509) 727-7236 MATT@PAVEMENTSURFACE.COM
4/21/2021 11:13:36 AM Page 1 of 1
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.2
Project No: 20008 Project Title: Signage & Striping at Rd 68/13urden Blvd
Contractor: Pavement Surface Control
Description of Change: Additional Sawcutting
Detail as Appropriate: For additional sawcutting and removal/replacement of asphalt
Contract Bid Amount: $ 95,924.00
SALES TAX @ 8.6%: NIA
Total: $ 95,924.00
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 57 800.22
Subtotal $ 27,138.54
Sales tax @ 8.6% N/A
Sales tax @ 8.6% N/A
Total $ 57,800.22
Total $ 27,138.54
Total Change Orders To Date $ $4,938.76
New Contract Amount $ 180,862.76
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ................................. 25
Modification to Contract time by this Change Order .................... 0
revised Total Contract Time .................................................... 25
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are)
being made and that the compensation for this Change Order is full and complete and is the only
compensation due or owing for this Change Order. Further, it is mutually agreed that this document will
supplement the present Contract Documents and that the provisions of the previously executed Contract
Documents shall apply to this Change Order.
AGREED TO AND ACCEPTED:
CONTRACTQ& a
APPROVED:'
APPROVED:
PROJECT MANAGER Date
APPR
1)
ea�er�-
�'i MR�rtt�E,e..
Ca nitruction %bead Inc, dba
P..'S'c
PAVEMENT SURFACE CONTROL
9312 W. TOTH AVE
KENNEWICK, WA 99336
PHONE: (509) 5WI969
EMAIL: ESTIMATING@PAVEMIENTSI..IRFACE.COM
OREGON CCB ## 125652 CONSTA1083LS OBE It 021'2315595
To:
CITY OF PASCO
Contact: KENT MCCUE
Address:
Po Box 293
Phone: (509) 545-3456
Pasco,wa 99301
Fax:
Project Name:
111020_SIGNING AND STRIPING AT ROAD 68/BURDEN BLVD
Bid Number:
Project Location:
Bid Date: 11/10/2020
Item # Item Description Estimated Quantity Unit Unit Price Total Price
CHANGE ORDER FOR ADDITIONAL SAWCUTTING AND 1.00 LS $27,138.54 $27,138.54
REMOVAL OF ASPHALT AND REPLACM ENT
Total Bid Price: $27,138.54
Notes:
• PAVEMENT SURFACE CONTROL IS A FEDERALLY CERTIFIED WOMAN OWNED DISADVANTAGED BUSINESS ENTERPRISE WITH
FULL BONDING CAPABILITIES
• ANY MODIFICATIONS OR DELETIONS TO OUR BID MUST BE AGREED UPON PRIOR TO BID OPENING (I.E. NO ITEM MAY BE
DELETED OR MODIFIED WITHOUT DISCUSSION). THIS QUOTE IS PRIVELEGED AND CONFIDENTIAL
• THIS QUOTE MUST BE ATTACHED TO AND BECOME PART OF ANY SUBCONTRACT AGREEMENT
• QUOTE IS BASED ON **** WORKING DAYS. EXTENSION OF DAYS WILL RESULT IN EXTENDED RENTAL PRICING OF APPLICABLE ITEMS AND
LOST REVENUES AS A RESULT
• UNLESS OTHERWISE STATED, EACH ITEM INCLUDES ONE MOBILIZATION TO THE PROJECT. ADDITIONAL MOBILIZATIONS WILL BE BILLED
ACCORDINGLY IF MOBILIZATIONS ARE OUT OF PSC CONTROL
• THIS QUOTE DOES NOT INCLUDE PERFORMANCE OR PAYMENT BOND. PSC IS FULLY BONDABLE, LICENSED, AND INSURED TO PERFORM WORK
DESCRIBED IN QUOTE
• PAVEMENT SURFACE CONTROL INCLUDES INSURANCE COVERAGE THAT MEETS WSDOT STANDARD SPECIFICATIONS. ADDITIONAL INSURANCE
OR COVERAGE LIMITS THAT EXCEED THIS STANDARD ARE NOT INCLUDED. IF ADDITIONAL COVERAGE IS REQUIRED, THE COST TO INCREASE
LIMITS AND COVERAGE WILL BE BILLED TO THE PRIME CONTRACTOR
• LAYOUT, CONTROL, AND VERIFICATION TO EB PERFORMED BY OTHERS. THIS INCLUDES ALL FIELD VERIFICATIONS FOR ENGINEERED SHOP
DRAWINGS OR ANY ITEMS REQUIRING FIELD VERIFICATION
• DISPOSAL SITE TO BE PROVIDED BY CONTRACTOR WITHIN 10 MILES OF WORK BEING PERFORMED. DISPOSAL FEES WILL BE CHARGED IF SITE
CANNOT BE PROVIDED.
• SALES/USE TAX WILL BE CHARGED AS A LINE ITEM WHEN CONTRACTOR IS END USER ACCORDING TO JURISDICTION WHERE WORK IS
PERFORMED.
• ALL QUANTITIES WILL BE BILLED FOR ACTUAL AMOUNT USED. ANY MATERIAL NECESSARY, BUT NOT MENTIONED IN THIS QUOTE WILL BE
BILLED ADDITIONALLY ACCORDINGLY
• QUOTE DOES NOT INCLUDE WEEKEND, OVERTIME OR HOLIDAY WORK
ACCEPTED:
The above prices, specifications and conditions are satisfactory and
are hereby accepted.
Buyer:
Signature:
CONFIRMED:
CONSTRUCTION AHEAD, INC. Dba PAVEMENT
SURFACE CONTROL
Authorized Signature:
Date of Acceptance: I Estimator: MATT MCDANIEL
(509) 727-7236 MATT@PAVEMENTSURFACE.COM
8/24/20214:02:47 PM Page 1 of 1
Memo
To: File
From: Kent McCue, Construction Manager t4J#A-
Date: November 1, 2020
Re: Clarification to change order #2
0„cryo
4110�
Pasco
Public Works Department
EnginR eer�ng Div' ion
During the construction on change order #1 (reconfiguration of the intersection of Burden
Blvd and Clemente Lane) it was discovered that the existing asphalt would not drain
properly to the curbs on each side of the road. We needed to remove additional asphalt to
correct the drainage issue and eliminate potential water ponding and safety hazards.
0 Page 1