HomeMy WebLinkAboutBig D's Construction - NW Area Sewer LID - Change Order No. 1 (#1800076)CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 1
Project No: 1800076 Project Title: Northwest Area Sewer LID
Contractor: Big D's Construction
Description of Change: Adjust the location of Manholes 18 through 22 approximately 92 feet west of
the originally designed locations for consistency with proposed platting of Mr.
Adams Lot No. 8
Detail as Appropriate:
Contract Bid Amount:
SALES TAX @ 8.6%:
Total:
$ 1,590,111.00
$ 136,749.55
$ 1,726,860.55
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal
Subtotal $ 49,703.50
Sales tax @ 8.6% $ -
Sales tax @ 8.6% $ 4,274.50
Total $ -
Total $ 53,978.00
Total Change Orders To Date $ 53,978.00
New Contract Amount $ 1,780,838.55
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
YES NO
120
1
121
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are)
being made and that the compensation for this Change Order is full and complete and is the only
compensation due or owing for this Change Order. Further, it is mutually agreed that this document will
supplement the present Contract Documents and that the provisions of the previously executed Contract
Documents shall apply to this Change Order.
AGREED TO AND ACCEPTED:
--61.g„
Brett Hisle =p;os s.=-'CN=BM—
CONTRACTOR
Date
APPROVED:
rl-rluitu MAN G R Date
�l
Main Office: Big D's
3902 N. Swallow Ave.
Pasco, WA 99301 Construction
Excavation & Underground
Proposal Submitted To:
Attention: Ryan Withers
Street Address:
City, State, & Zip:
E -Mail: rwithers()RH2.com
Phone: (509)542-8322
Fax: (509)542-8362
WA# BIGDSDC893DT
Date 8/4/2021
Phone:
Fax:
Pasco NW Area Sewer LID
Job Name:
Job Location: Pasco, WA
30"x30" Nyloplast Coupling
1 EA $2,541.50
$2,541.50
- Material and Install
24" Heavy Wall Gasketed PVC Sewer Pipe
56 FT $187.00
$10,472.00
- Material and Install
30" Heavy Wall Gasketed PVC Sewer Pipe
70 FT $279.00
$19,530.00
- Material and Install
30" ADS Triple Wall Pipe
65 FT $264.00
$17,160.00
- Material and Install
Subtotal $49,703.50
Tax
Total $49,703.50
Surveying, Compaction testing, permits, rock ex
Authorized Signature:
Acceptance ot ?-mposal
Date of Acceptance : Signature:
Name: Title:
8/4/2021 3:13 PM 1 of 1 Big D's Construction