HomeMy WebLinkAboutPOW Contracting - Road 36 Lift Station - Change Orders 2, 3, 4 (#16006)CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.2
Project No: 16006 Project Title: Road 36 Lift Station
Contractor: POW Contracting
Description of Change: Additional trenching, conduit and wire.
Detail as Appropriate: PUD requires the fiber line run to 3rd pole from Lift Station, which will
mean additional trenching, conduit and wire.
Contract Bid Amount: $ 546,671.10
SALES TAX @ 8.6%: $ 47,013.71
Total: $ 593,684.81
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ (7,500.00)
Subtotal $ 1,997.15
Sales tax @ 8.6% $ 645.00
Sales tax @ 8.6% $ 171.75
Total $ (8,145.00)
Total $ 2,168.90
Total Change Orders To Date $ (5,976.10)
New Contract Amount $ 587,708.71
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
YES I NO -
130
0
130
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are)
being made and that the compensation for this Change Order is full and complete and is the only
compensation due or owing for this Change Order. Further, it is mutually agreed that this document will
supplement the present Contract Documents and that the provisions of the previously executed Contract
Documents shall apply to this Change Order,
AGREED TO AND ACCEPTED:
u 10/28/21
CONTRACTOR Date
APPROVED:
APPROVED:
PROJECT MANAGER Date
ffif
ZEN
Date Date
DIRECTOR
Project No:
16006
Contractor: POW Contracting
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.3
Project Title: Road 36 Lift Station
Description of Change: COR #3 - Additional Copper Wire
Detail as Appropriate: Utility feeders not supplied by PUD, approx. 440 ft of 3/0 AWG
copper wire
Contract Bid Amount: $ 546,671.10
SALES TAX @ 8.6%: $ 47,013.71
Total: $ 593,684.81
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ (5,502.85)
Subtotal $ 3,004.19
Sales tax @ 8.6% $ 473.25
Sales tax @ 8.6% $ 258.36
Total $ (5,976.10)
Total $ 3,262.55
Total Change Orders To Date $ (2,713.55)
New Contract Amount
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
$ 590,971.26
YES NO
130
0
130
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are)
being made and that the compensation for this Change Order is full and complete and is the only
compensation due or owing for this Change Order. Further, it is mutually agreed that this document will
supplement the present Contract Documents and that the provisions of the previously executed Contract
Documents shall apply to this Change Order.
AGREED TO AND ACCEPTED: APPROVED:
u 10/28/21 ,v T /0-7& "Z/
CONTRACTOR Date PROJECT MANAGER Date
LABOR
DATE PERFORMED: Future
DESCRIPTION OF WORK: New Wire per PUD for power not on drawings
PROJECT NAME: City of Pasco Road 36 Lift Station
PROJECT NUMBER: POW 210
CLASSIFICATION
HOURS OT WAGE RATE TAXES
REGULAR 13.87%
L&I INS. FRINGE AMOUNT
$3.29
PROJECT MANAGER
0.5 $55.00 $3.81
$1.65 $32.96
SUPERINTENDENT
$55.00
HITACHI ZAXIS 240 LC EXCAVATOR
FOREMAN
$51.50
$25.84
EXCAVATOR OPERATOR
$49.39
$94.50
LOADER OPERATOR
$48.95
2009
LABORER - UG SEWER
$42.54
JOHN DEERE 120D EXCAVATOR
PIPELAYER - UG SEWER
$43.08
1 $16.25
IRONWORKER
$64.91
$163.38
CARPENTER
$56.75
2012
TRUCK DRIVER
$49.50
CAT 315C EXCAVATOR
SUBTOTAL $32.96
WSDOT LABOR FA 31% $10.22
LABOR TOTAL $43.18
EQUIPMENT
MAKE & MODEL
YEAR
HOURS HOURS
REGULAR STANDBY RATE
STANDBY AMOUNT
RATE
HITACHI ZAXIS 200 LC EXCAVATOR
2011
$91.50
$22.67
HITACHI ZAXIS 240 LC EXCAVATOR
2006
$107.54
$25.84
HITACHI ZX130-5 EXCAVATOR
2010
$94.50
$22.25
JOHN DEERE 270D EXCAVATOR
2009
$116.62
$28.66
JOHN DEERE 120D EXCAVATOR
2008
$63.39
1 $16.25
CAT 330 DL EXCAVATOR
2006
$163.38
$40.94
CAT 320D EXCAVATOR
2012
$83.38
$19.52
CAT 315C EXCAVATOR
2007
$74.62
$18.61
CAT 305 -CR MINI EXCAVATOR
2007
$27.93
$7.19
CAT 304-C MINI EXCAVATOR
2010
$25.16
$6.33
KAMATSU LOADER
2007
$68.05
$15.43
JD 544K LOADER
2010
$59.14
$14.02
CAT 938G LOADER
2001
$50.05
$10.17
CAT 93OG LOADER
2006
$50.72
$10.84
CAT 42OF BACKHOE
2013
$45.40
$11.23
CAT Skid Steer
2007
$25.00
$8.38
GMC DUMP TRUCK
1985
$51.42
$7.58
INTERNATIONAL DUMP TRUCK
1988
$51.42
$7.58
KW 10-12 CY DUMP TRUCK
2007
$86.53
$13.67
KW 10-12 CY DUMP TRUCK
2005
$84.94
$12.87
PETERBILT 10-12 CY DUMP TRUCK
1998
$83.81
$12.30
FORD H2O TRUCK - LOUISVILLE 2000 Gal
1997
$33.82
$3.99
INTERNATIONAL H2O TRUCK - 4000 GAL
2004
$52.70
$9.42
1 TON SERVICE TRUCK W/SMALL TOOLS
2008
$18.00
$3.00
CAT ROLLER CS433
2008
$44.71
$9.23
CAT DOZER D5GXL
2006
$60.59
$13.13
270 HAMMER
2009
$90.00
$2.55
Jump n Jack
2012
$5.00
SUBTOTAL $0.00
WSDOT EQUIPMENT FA 21% $0.00
EQUIPMENTTOTAL $0.00
MATERIALS
SUPPLIER NAME DESCRIPTION INVOICE AMOUNT
SUBTOTAL $0.00
WSDOT MATERIAL FA 21% $0.00
MATERIAL TOTAL $0.00
SUBCONTRACTORS
SUBCONTRACTOR NAME DESCRIPTION INVOICE AMOUNT
Townsend Electrical Feeder Wires $2,578.34
SUBTOTAL $2,578.34
WSDOT SUBCONTRACTOR FA 127. $309.40
SUBCONTRACTOR TOTAL $2,887.74
SUBTOTALAABOR, EQUIPMENT, MATERIALS, SUBCONTRACTORS $2,930.92
BONDING AND INSURANCE $73.27
TOTAL WITHOUT SALES TAX $3,004.19
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.4
Project No: 16006 Project Title: Road 36 Lift Station
Contractor: POW Contracti
Description of Change: Wet Well Discharge Pipe
Detail as Appropriate: Changing out 6" wet well discharge pipe
Contract Bid Amount: $ 546,671.10
SALES TAX @ 8.6%: $ 47,013.71
Total: $ 593,684.81
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 2,498.66
Subtotal $ 1,173.21
Sales tax @ 8.6% $ 214.88
Sales tax @ 8.6% $ 100.90
Total $ (2,713.54)
Total $ 1,274.11
Total Change Orders To Date $ (1,439.43)
New Contract Amount $ 592,245.38
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
130
0
130
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are)
being made and that the compensation for this Change Order is full and complete and is the only
compensation due or owing for this Change Order. Further, it is mutually agreed that this document will
supplement the present Contract Documents and that the provisions of the previously executed Contract
Documents shall apply to this Change Order
AGREED TO AND ACCEPTED:
,t6eh� 12/21/21
CONTRACTOR Date
APPROVED:
/1 -J?
Date
ZI
APPROVED:
Z -/ 7 - Z/
PROJECT MANAGER Date
DIRECTOR
N � 2
0
WnS;;7
LABOR
DATE PERFORMED: 12/8/2021
DESCRIPTION OF WORK: Changing out 6" Wet Well discharge pipe
PROJECT NAME: City of Pasco Road 36 Lift Station
PROJECT NUMBER: POW 210
CLASSIFICATION
HOURS
REGULAR
OT WAGE RATE
TAXES
13.87%
L&I INS.
$3.29
FRINGE AMOUNT
PROJECT MANAGER
0.25
$55.00
$1.91
$0.82
$16.48
SUPERINTENDENT
2
$55.00
$15.26
$6.58
$131.84
FOREMAN
$28.66
$51.50
2008
1 $63.39
$16.25
EXCAVATOR OPERATOR
2006
$49.39
$40.94
CAT 320D EXCAVATOR
2012
LOADER OPERATOR
$19.52
$48.95
2007
$74.62
$18.61
LABORER - UG SEWER
6
$42.54
$35.40
$19.74
$310.38
PIPELAYER - UG SEWER
2
$43.08
$11.95
$6.58
$104.69
IRONWORKER
2010
$64.91
$14.02
CAT 93BG LOADER
2001
CARPENTER
$10.17
$56.75
2006
$50.72
$10.84
TRUCK DRIVER
2013
$49.50
$11.23
CAT Skid Steer
2007
SUBTOTAL $563.39
WSDOT LABOR FA 31% $174.65
LABOR TOTAL $738.04
EQUIPMENT
MAKE & MODEL
YEAR
HOURS HOURS
REGULAR STANDBY RATE
STANDBY AMOUNT
RATE
HITACHI ZAXIS 200 LC EXCAVATOR
2011
$91.50
$22.67
HITACHI ZAXIS 240 LC EXCAVATOR
2006
$107.54
$25.84
HITACHI ZX130-5 EXCAVATOR
2010
$94.50
$22.25
JOHN DEERE 270D EXCAVATOR
2009
$116.62
$28.66
JOHN DEERE 120D EXCAVATOR
2008
1 $63.39
$16.25
CAT 330 DL EXCAVATOR
2006
$163.38
$40.94
CAT 320D EXCAVATOR
2012
$83.38
$19.52
CAT 315C EXCAVATOR
2007
$74.62
$18.61
CAT 305 -CR MINI EXCAVATOR
2007
$27.93
$7.19
CAT 304-C MINI EXCAVATOR
2010
$25.16
$6.33
KAMATSU LOADER
2007
$68.05
$15.43
JD 544K LOADER
2010
$59.14
$14.02
CAT 93BG LOADER
2001
$50.05
$10.17
CAT 93OG LOADER
2006
$50.72
$10.84
CAT 42OF BACKHOE
2013
$45.40
$11.23
CAT Skid Steer
2007
$25.00
$8.38
GMC DUMP TRUCK
1985
$51.42
$7.58
INTERNATIONAL DUMP TRUCK
1988
$51.42
$7.58
KW 10-12 CY DUMP TRUCK
2007
$86.53
$13.67
KW 10-12 CY DUMP TRUCK
2005
$84.94
$12.87
PETERBILT 10-12 CY DUMP TRUCK
1998
$83.81
$12.30
FORD H2O TRUCK- LOUISVILLE 2000 Gal
1997
$33.82
$3.99
INTERNATIONAL H2O TRUCK- 4000 GAL
2004
$52.70
$9.42
1 TON SERVICE TRUCK W/SMALL TOOLS
2008
2.0 $18.00
$3.00 $36.00
CAT ROLLER CS433
2008
$44.71
$9.23
CAT DOZER D5GXL
2006
$60.59
$13.13
270 HAMMER
2009
$90.00
$2.55
Jump n Jack
2012
$5.00
SUBTOTAL $36.00
WSDOT EQUIPMENT FA 21% $7.56
EQUIPMENTTOTAL $43.56
MATERIALS
SUPPLIER NAME
DESCRIPTION INVOICE
AMOUNT
Consolidated Supply
6" x 5' FL x PE Prime coated spool
$300.00
SUBTOTAL $300.00
WSDOT MATERIAL FA 21% $63.00
MATERIAL TOTAL $363.00
SUBCONTRACTORS
SUBCONTRACTOR NAME DESCRIPTION INVOICE AMOUNT
SUBTOTAL $0.00
WSDOT SUBCONTRACTOR FA 12% $0.00
SUBCONTRACTOR TOTAL $0.00
SUBTOTAL:LABOR, EQUIPMENT, MATERIALS, SUBCONTRACTORS $1,144.60
BONDING AND INSURANCE $28.61
TOTAL WITHOUT SALES TAX $1,173.21