HomeMy WebLinkAboutDW Excavating - Columbia East Force Main - Change Order Nos. 2 & 3 (Agreement No. 17-003)CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.2
Project No: 17003 Project Title: Columbia East Force Main
Contractor: DW Excavating, Inc.
Description of Change: Increased pipe price due to EDA approval delay.
Detail as Appropriate: Due to COVID-19, HDPE material suppliers did not have a large inventory
of material on -hand. After bids were opened, a cold -weather event in Texas caused state-wide power
outages, which caused extensive damage at HDPE production facilities, shutting down production
and causing a severe shirtage of HDPE and rapid price escalation. The HDPE pipe incresed in
.price by $664,215.30 and the City, negotiated a change order amount of $299,000.00
Contract Bid Amount: $ 5,511,103.00
SALES TAX @ 8.6%: $ 473,954.86
Total: $ 5,985,057.86
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 33,514.69
Subtotal $ 299,000.00
Sales tax @ 8.6% $ 2,882.26
Sales tax @ 8.6% $ 25,714.00
Total $ 36,396.95
lTotal $ 324,714.00
Total Change Orders To Date $ 361,110.95
New Contract Amount
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
$ 6,346,168.81
YES I NO
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED: APPROVED:
10-22-21
CONTRACTOR Date ROJECT M AGER Date
APPROVED:
Date'WORKS Dat
DIRECTOR
1-Rti'5r�w no.J ,3o , 41
* U.S. DEPARTMENT OF COMMERCE
Economic Development Administration
915 Second Avenue, Room 1890
Seattle, Washington 98174
yt * Fax: 206.220.7669
Voice: 206.220.7660
September 8, 2021
Mr. Steve Worley
Public Works Director
City of Pasco
525 N. Yd Ave.
Pasco, WA 99301
RE: EDA Award No. 07-01-07483 — Columbia East Force Mains
Change Order No. 2 — Approval Memo
Dear Mr. Worley:
EDA has reviewed and approves the contract change between the City of Pasco and DW
Excavating in Change Order No. 2.
Change Order No. 2 is a contract cost increase of $324,714 to cover an increased cost of HDPE
pipe, a major project construction component. This price increase is considered allowable and is
within the Authorized Scope of Work for the grant.
The cost increase from Change Order No. 2 does not increase the approved project budget and
EDA's participation will be unchanged.
If you have any questions, please contact Project Officer Richard Moore at (206) 507-4839.
Sincerely,
Maiea Sellers
YVLa� 2021.09.08
19:17:45 -07'00'
Maiea Sellers
Acting Regional Director
Copy to: Richard Moore, Project Officer
Kerstin Millius, SRO Area Director
Maria Serra, City of Pasco CIP Mgr
RESOLUTION NO. 4089
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO.
2 TO THE CONSTRUCTION CONTRACT WITH DW EXCAVATING, INC.
FOR THE COLUMBIA EAST FORCE MAIN PROJECT; CONTINGENT UPON
CHANGE ORDER APPROVAL BY OUR FUNDING PARTNER, THE US
ECONOMIC DEVELOPMENT ADMINISTRATION.
WHEREAS, the City and DW Excavating, Inc. entered into a Construction Contract on
March 30, 2021 to provide Improvements to the Columbia East Force Main Project; and
WHEREAS, the City and DW Excavating, Inc. executed one Change Order to the
Construction Contract to accommodate unlocated utilities (water lines, sewer lines), and adjust the
construction sequence to avoid damaging crops around a field owned by Frank Tiegs.
WHEREAS, Change Order No. 1 in the amount of $36,396.95 (including sales tax) was
authorized under the authority provided to the City Manager and Public Works Director; and
WHEREAS, Change Order No. 2 relates to a series of events beyond the control of the
Contractor resulting in a substantial increase in pipe costs after award of the bid; and
WHEREAS, Change Order No. 2 in the amount of $324,714.00 exceeds the City
Manager's authority and thus requires Council approval.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PASCO, WASHINGTON:
Section 1. That Change Order No. 2 to DW Excavating, Inc. is hereby approved by City
Council.
Section 2. The City Manager of the City of Pasco, Washington, is hereby authorized,
empowered, and directed to execute Change Order No. 2, a copy of which is attached hereto, and
incorporated herein by this reference as Exhibit A, on behalf of the City of Pasco.
Resolution — CE FM Project - CO - I
PASSED by the City Council of the City of Pasco, Washington this 7t' day of September,
2021.
Saul 4artinez
Mayor
ATTEST:
-) 4 r" A " k-, �
Debra Barham, CMC
City Clerk
Resolution — CE FM Project - CO - 2
APPROVED AS TO FORM:
F �!
Kerr guson Law, PLLC
Attorney
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.3
Project No: 17003 Project Title: Columbia East Force Main
Contractor: DW Excavating, Inc.
Description of Change: Reconciliation for Final Pay Application
Detail as Appropriate: Final reconciliation of item overages/underages
Contract Bid Amount: $ 5,511,103.00
SALES TAX @ 8.6%: $ 473,954.86
Total: $ 5,985,057.86
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 332,514.69
Subtotal $ 5,537.18
Sales tax @ 8.6% $ 28,596.26
Sales tax @ 8.6% $ 476.19
Total $ 361,110.95
Total $ (6,013.37)
Total Change Orders To Date $ 355,097.58
New Contract Amount
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
$ 6,340,155.44
YES I NO
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
l� 10-22-21
CONTRACTOR Date
APPROVED:
/� 2S
Date
APPROVED:
P OJECT MANAGER Date
Orit i
Date ,V-. ..
DIRECTOR