HomeMy WebLinkAboutBooth & Sons Construction, Inc. - Peanuts Park Restoration Project Change Order #2 (16014)Project No: CITY OF PASCO ADMINISTRATIVE & COMMUNITY SERVICES DEPARTMENT CONTRACT CHANGE ORDER NO.2 16014 Project Title: Peanuts Park Rehabilitation Contractor: Booth and Sons Construction, Inc. Description of Change: COP #2 - Columns on Torrino Market; COP #7 - EIFS Torrino's Market Detail as Appropriate: Fix columns on Torrino Market where planters were removed ($6,033.34 EIFS to westside of Torrino's Square ($17,000.95) Contract Bid Amount: $ 5,389,063.96 SALES TAX @ 8.6%: $ 463,459.50 Total: $ 5,852,523.46 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal $ 43,086.30 Subtotal $ 23,034.29 Sales tax @ 8.6% $ 3,705.42 Sales tax @ 8.6% $ 1,980.95 Total $ 46,791.72 Total $ 25,015.24 Total Change Orders To Date $ 71,806.96 New Contract Amount $ 5,924,330.42 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER Contract Time Prior to this Change Order ................................. Modification to Contract time by this Change Order .................... revised Total Contract Time .................................................... r—Y—E—S-1 NO 170 6 176 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: Uee 7/30/21 XONTRACTOR Date APPROVED: 7`c�''Zt' PRUECT MANAGER Date L. �\ 0"C� Change Order Proposal Booth & Sons Construction Inc. P.O. Box 608 Richland ,WA 99352 2 To: Kent McCue City of Pasco Pasco, WA 99301 For: Peanuts Park 4/14/2021 Fix columns on Torrino market where planters were removed Proposal price Sub -Contractor Generation Plastering $5,200.00 Subtotal $5,200.00 Commission 10% $520.00 Total A $5,720.00 Contractor Demo 0 hrs. 70 $0.00 Material $0.00 equip rental $0.00 Labor 0 hrs 70 $0.00 Clean 1 hrs. 70 $70.00 hrs 0 $0.00 Manage 1 hrs 90 $90.00 subtotal1� 60.00 overhead 15% $24.00 Sub -Total B $184.00 Profit 6.00%$11.04 Total B $195.04 Total A+B $5,915.04 $5,915.04 Bond 2% $118.30 6,033.34 TOTAL please add 3 working days Change Order Proposal Booth & Sons Construction Inc. P.O. Box 608 Richland ,WA 99352 For: Pasco Peanuts Park EIFS Torrino's market 7 To: Kent McCue City of Pasco Pasco WA, 99301 6/8/2021 Proposal price Sub -Contractor Generation Plastering $14,836.00 Subtotal $14,836.00 Commission 10% $1,483.60 Total A $16,319.60 Contractor Demo 2 hrs. 70 $140.00 Material/equip rental $0.00 Labor 0 hrs 70 $0.00 Clean 1 hrs. 70 $70.00 hrs 0 $0.00 Manage 1 hrs 90$90.00 subtotal $300.00 overhead 16% $48.00 Total B $348.00 Profit 6.00% $20.88 Total A+B $16,667.60 $16,667.60 Bond 2%$333.35 17, 000.95 TOTAL please add 3 working days