CITY OF PASCO
ADMINISTRATIVE & COMMUNITY SERVICES DEPARTMENT
CONTRACT CHANGE ORDER NO.2
16014
Project Title: Peanuts Park Rehabilitation
Contractor: Booth and Sons Construction, Inc.
Description of Change: COP #2 - Columns on Torrino Market; COP #7 - EIFS Torrino's Market
Detail as Appropriate:
Fix columns on Torrino Market where planters were removed ($6,033.34
EIFS to westside of Torrino's Square ($17,000.95)
Contract Bid Amount: $ 5,389,063.96
SALES TAX @ 8.6%: $ 463,459.50
Total: $ 5,852,523.46
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 43,086.30
Subtotal $ 23,034.29
Sales tax @ 8.6% $ 3,705.42
Sales tax @ 8.6% $ 1,980.95
Total $ 46,791.72
Total $ 25,015.24
Total Change Orders To Date $ 71,806.96
New Contract Amount $ 5,924,330.42
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
r—Y—E—S-1 NO
170
6
176
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are)
being made and that the compensation for this Change Order is full and complete and is the only
compensation due or owing for this Change Order. Further, it is mutually agreed that this document will
supplement the present Contract Documents and that the provisions of the previously executed Contract
Documents shall apply to this Change Order.
AGREED TO AND ACCEPTED:
Uee 7/30/21
XONTRACTOR Date
APPROVED:
7`c�''Zt'
PRUECT MANAGER Date
L.
�\ 0"C�
Change Order Proposal
Booth & Sons Construction Inc.
P.O. Box 608
Richland ,WA 99352
2
To: Kent McCue
City of Pasco
Pasco, WA 99301
For: Peanuts Park 4/14/2021
Fix columns on Torrino market
where planters were removed
Proposal price
Sub -Contractor
Generation Plastering $5,200.00
Subtotal
$5,200.00
Commission
10%
$520.00
Total A
$5,720.00
Contractor
Demo 0 hrs.
70
$0.00
Material
$0.00
equip rental
$0.00
Labor 0 hrs
70
$0.00
Clean 1 hrs.
70
$70.00
hrs
0
$0.00
Manage 1 hrs
90
$90.00
subtotal1�
60.00
overhead
15%
$24.00
Sub -Total B
$184.00
Profit
6.00%$11.04
Total B
$195.04
Total A+B
$5,915.04
$5,915.04
Bond
2%
$118.30
6,033.34
TOTAL
please add 3 working days
Change Order Proposal
Booth & Sons Construction Inc.
P.O. Box 608
Richland ,WA 99352
For: Pasco Peanuts Park
EIFS Torrino's market
7
To: Kent McCue
City of Pasco
Pasco WA, 99301
6/8/2021
Proposal price
Sub -Contractor
Generation Plastering $14,836.00
Subtotal $14,836.00
Commission 10% $1,483.60
Total A $16,319.60
Contractor
Demo 2 hrs.
70
$140.00
Material/equip rental
$0.00
Labor 0 hrs
70
$0.00
Clean 1 hrs.
70
$70.00
hrs
0
$0.00
Manage 1 hrs
90$90.00
subtotal
$300.00
overhead
16%
$48.00
Total B
$348.00
Profit
6.00%
$20.88
Total A+B
$16,667.60
$16,667.60
Bond
2%$333.35
17, 000.95
TOTAL
please add 3 working days