HomeMy WebLinkAboutRH2 Engineering, Inc. - Addendum to Sewer Comp Plan (#19038) - Amendment No. 4 - ExecutedAMENDMENT NUMBER 4 to
PROFESSIONAL SERVICES AGREEMENT
19250 — Addendum to Comprehensive Sewer Plan
PROJECT: CP7.SE.2A.19.00
AGREEMENT NO. 19038
WHEREAS, the City and RH2 Engineering, Inc. entered into a Professional Services
Agreement on 9/4/2019 to provide engineering services with respect to the Addendum to the
Comprehensive Sewer Project.
WHEREAS, the City and RI -12 Engineering, Inc. entered into the first Amendment to the
Professional Services Agreement No. 19038 on 7/30/2020 for additional time for performance
with no additional cost to the City;
WHEREAS, the City and RI -12 Engineering, Inc. entered into the second Amendment to
the Professional Services Agreement No. 19038 on 10/29/2020 for additional time for
performance with no additional cost to the City;
WHEREAS, the City and RI -12 Engineering, Inc. entered into the third Amendment to
the Professional Services Agreement No. 19038 on 12/2/2020 to add a new task (No. 12: West
Broadmoor Lift Station Flow and Sizing Analysis) without any additional cost to the City;
WHEREAS, all parties to this agreement agree that this addendum will not modify or
change any other terms of the professional services agreement (Agreement No. 19038).
NOW, THEREFORE, this agreement is amended to allow RI -12 Engineering, Inc. to add a new
task (No. 13: Expanded UGA LID Breakout Analyses), thus adding professional engineering
services described within Exhibit A. There will be no additional dollar amount added to this
agreement based upon the current contract balances remaining.
1. Scone of Work:
See Exhibit A.
2. Fee:
No Change.
Time of performance:
No Change. The services shall be complete for the project on or before 12/31/2021.
Iff-
DATED THIS DAY OFcJV, 202b?'
CITY OF PASCO: CONSULTANT
City of Pasco, R142 Engineering, Inc.
Steve Worley, Public Works DVis
Paul Cross, PE — Project Manager
Amendment No. 4 to Professional Seeement Page 1
RI -12 Engineering, Inc.
19250 — Addendum to the Comprehensive Sewer Plan
EXHIBIT A
Scope of Work
Amendment No. 4
City of Pasco
Addendum to the Comprehensive Sewer Plan
Expanded UGA LID Breakout Analyses
June 2021
Background
The City of Pasco (City) desires to complete a more detailed analysis of the expanded Urban Growth
Area (UGA) boundary and how it might logically be broken out into future local improvement district
(LID) areas based upon concurrency of urban services with desired growth.
The City has retained RH2 Engineering, Inc., (111-112) to complete an addendum to the Comprehensive
Sewer Plan (CSP). The City requested RH2 prepare a technical memorandum to supplement the CSP
that provides a detailed analysis of the specific sub -basins within the UGA that might logically be
developed into future LIDs with the goal of minimizing the contributions the City needs to make for
oversizing lines. This analysis will include the ability of some subareas to temporarily connect to existing
gravity line routes that need to be part of a regional pump station in the future. To the extent possible,
the information developed more generally in the addendum to the CSP will be used as the basis for the
technical memorandum.
The work will rely upon data provided by the City prior to commencement of the activities contained in
this Scope of Work. All RH2 deliverables will be provided in electronic format unless denoted otherwise.
Task 13 — Expanded UGA LID Breakout Analyses
Objective: Develop the 10- and 20 -year and build -out planning data for flow and loads for use in
analyses of each sub -basin in the expanded UGA.
Approach:
13.1 Compile the wastewater flow rate and peaking factors based on information developed in
the addendum to the CSP.
13.2 Identify LID areas within each sub -basin system for further study of flow and/or load.
Compare and contrast the depth of gravity lines necessary to serve increased areas. Provide
recommendations to the City for limiting the size of the LIDS based upon depth of gravity
sewers.
13.3 Estimate wastewater flow for the 10- and 20 -year and build -out projections based on
information provided by the City on proposed commercial developments, population growth,
and wastewater flow rate developed in the addendum to the CSP. It is assumed that property
will generally develop sequentially from areas closest to sewer to areas most distant from
existing utilities.
1
City of Pasco
Addendum to the Comprehensive Sewer Plan
Expanded UGA LID Breakout Analyses
Amendment No. 4
Exhibit A
Scope of Work
13.4 Lay out up to two (2) possible gravity collection system alignments and determine the depth
of the lowest invert into the point of connection necessary to serve the LIDS. Adjust flows
based upon collection system constraints and prepare cost estimates.
13.5 Estimate the relative size and cost of the lift station and force main for LID alone and for the
10- and 20 -year and build -out projections of those sub -basins planned to be served by a
future lift station.
13.6 Identify LIDs that might be allowed temporary connections to gravity lines within the existing
system that might have capacity to provide limited service until the sub -basin is built out
enough to require the lift station to be constructed.
13.7 Prepare a draft of the Expanded UGA LID Breakout Analyses technical memorandum.
13.8 Meet with the City regarding LID breakouts, oversizing and lift station and force main sizing,
and timing and cost projections. It is assumed that RH2 will attend this meeting virtually.
13.9 Make changes in the analysis, sizing, and cost based upon City input and finalize the Expanded
UGA LID Breakout Analyses technical memorandum. The finalized memorandum will be
submitted to the Washington State Department of Ecology for inclusion as an appendix in the
addendum to the CSP.
Assumptions:
• Amendment No. 4 will be a no -cost change order based upon the current contract balance
remaining and the expected level of effort of this Scope of Work.
• The build -out scenario will be based on developable land use analysis and lot counts provided
by the City.
• The City -provided LiDAR information will be used to identify elevations within the properties
and the upstream basin.
• RH2 will rely upon the accuracy and completeness of any information, data, and materials
generated or produced by the City in relation to this Scope of Work.
Provided by City:
• The City will provide the anticipated land use and density of the expanded UGA areas or
provide concurrence that the estimates shown in the addendum to the CSP are to be used
for these analyses.
• Developable land use analysis and lot counts at buildout within the expanded UGA.
RH2 Deliverables:
• Attendance at virtual meeting with the City and meeting agenda and minutes.
• Draft and final Expanded UGA LID Breakout Analyses technical memorandum for City review
and comment.
2
City of Pasco
Addendum to the Comprehensive Sewer Plan
Expanded UGA LID Breakout Analyses
Schedule
Amendment No. 4
Exhibit A
Scope of Work
RH2 will provide the draft memorandum to the City for first review within five (5) weeks of execution
of this amendment. The nature and extent of comments received from the City are difficult to
estimate, but it is assumed that the comments will be minimal in nature. The memorandum will be
finalized within two (2) weeks of receiving final comments.
EXHIBIT B
Fee Estimate
Amendment No. 4
City of Pasco
Addendum to the Comprehensive Sewer Plan
Expanded UGA LID Breakout Analyses
Jun -21
PROJECTTOTAL I $ 1 $ - $ (0) $(0)
Total
Description
Total Labor
Total Subconsultant
Total Expense
Total Cost
Hours
...............................................................................................................................................................
Classification
Task 13 Expanded UGA LID Breakout Analyses
67
1 $ 11,238
1 $
$ 1,787
$ 13,025
PROJECTTOTAL I $ 1 $ - $ (0) $(0)