HomeMy WebLinkAboutGSI Water Solutions, Inc - Aquifer Storage & Recovery Feasibility Study - Amendment No. 1 (Agreement No. 20-044)AMENDMENT NUMBER 1 to
PROFESSIONAL SERVICES AGREEMENT
Aquifer Storage & Recovery Feasibility Study
AGREEMENT NO. 20-044
WHEREAS, the City and GSI Water Solutions, Inc. (GSI), entered into a Professional
Services Agreement on 10/29/2020 to provide professional geotechnical services with respect to
the Aquifer Storage & Recovery Feasibility Study project; and
WHEREAS, GSI provided additional unplanned services beyond the scope of the
original contract related to numerous Ecology review comments on the Task 2 Hydrogeologic
Feasibility Assessment technical memorandum as well as providing additional communications,
meetings, task management and administrative support; and
WHEREAS, the City agrees to expand the scope of work for Task 2 to include the
additional work identified above and compensate GSI for these efforts.
NOW, THEREFORE, this agreement is amended to modify Task 2 to include the
following additional professional geotechnical services:
Scope of Work:
• Review and address Ecology's review comments on the Hydrogeologic Feasibility
Assessment technical memorandum
• Additional Communications, meetings, task management and administrative support
related to Ecology's review comments.
2. Fee:
The compensation for the additional work is based on a Time and Materials in the
amount of $4,235.00, increasing the overall total authorization amount to $122,235.00.
3. Time of performance:
No Change. The services shall be complete for the project on or before 12/31/2021.
DATED THIS a3 DAY OF :Ty(Y , 2021.
CITY O$ PASCP; , _ CONSULTANT
City of Pas�-
Steve M. Worley — Public Works
Digitally signed by Kenny
Kenny Janssen Janssen
Date: 2021.07.23 09:39:30 -07'00'
GSI Water Solutions, Inc.
Kenny Janssen — Principal Hydrogeologist
Amendment No. 1 to Professional Services Agreement Page 1
GSI Water Solutions, Inc.
Pasco ASR Feasibility Study
EXHIBIT A
ly
Project:
Date:
Water Solutions, Inc.
Amendment No. 1
City of Pasco ASR Feasibility Study
July 12, 2021
Contract Reference/ Date: Agreement No. 20-044 / October 29, 2020
GSI Project Number: 880.001
Amended Scope of Services
This Amendment No. 1 (Amendment) modifies the scope of services and budget of Agreement No. 20-044
(Agreement) between the City of Pasco (City) and GSI Water Solutions, Inc. (GSI) dated October 29, 2020. The
purpose of this Amendment is to cover additional project costs incurred to address Ecology review comments
on the technical memorandum prepared for Task 2:
Task No. Description Cost
• Review and address Ecology's review comments on the Hydrogeologic
2 Feasibility Assessment technical memorandum $4,235.00
• Communications, meetings, task management and administrative support
TOTAL $4,235.00
Change in Agreement Cost
Original Agreement Cost:
$118,000.00
Current Agreement Cost (as adjusted by previous Amendments):
$118,000.00
Increase/Decrease in Agreement Cost due to this Amendment:
$4,235.00
New Agreement Cost due to this Amendment:
$122,235.00
Change in Agreement Schedule
Increase/Decrease in Agreement time due to this Amendment: 0 calendar days
Terms and Conditions
The work described by this Amendment No. 1 shall be performed under the same terms and conditions as
those included in the original Agreement. All other terms and conditions of the original Agreement, as it may
have been modified, will remain the same.
GSI Water Solutions, Inc. ■ 1