HomeMy WebLinkAboutC&E Trenching LLC - 9th and Washington and S Maitland Lift Stations (#15003)Project No:
16007 / 15003
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.1
Project Title: 9th & Washgington / S Maitland Lift Stations
Contractor: C&E Trenching, LLC
Description of Change: RFC 02: Reinstall 12" plug valves; and RFC 03: Added gravel
Detail as Appropriate: RFC 02: Reinstall 12" plug valves including install fence and landscape
removal (-$2,500.00); includes cost to modify angle iron and expand
hatch ($781.00) (41,719.00); RFC 03: Install 6" of gravel in 35 x 13 foot
area and curb cut ($2,435.53) TOTAL: $716.53
Contract Bid Amount: $ 587,360.00
SALES TAX @ 8.6%: $ . 50,512.96
Total: $ 637,872.96
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal
Subtotal $ 716.53
Sales tax @ 8.6% $ -
Sales tax @ 8.6% $ 61.62
Total $ -
Total $ 778.15
Total Change Orders To Date $ 778.15
New Contract Amount $ 638,651.11
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
YES I NO
a
0
.o
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
C4-e'� Gf 5-12-21
CONTRACTOR V Date
APPROVED:
f' -Ll
Date
APPROVED:
'
5- /l -Z l
ROJECT MANAGER Date
ilZ/ZI
-%—PUBLIC WORKS Date
DIRECTOR
C&E Trenching LLC
PO Box 3788
Pasco, WA 99302
Phone: (509) 545-6940
Fax: (509) 545-8671
,J JJ ;,a r 'dr
To: City of Pasco
PO Box 293
Pasco, WA 99301
Project: 9th & Washington Maitland
RFC No: 02
Date: 5/7/2021
Description: Cost savings to reinstall 12" plug valves in orginal location includes
installing fence and removing landscape per C001 (2020.06.12) Revised
plan and a Credit of $2,500.00.
Change also includes cost to modify angle iron and expand hatch per RFI
#10 Subcontract cost of $710 plus mark up of 10% total cost of $781 see
supporting estimate from Monarch.
The above work is subject to the same conditions as specified in the original contract
unless otherwise stipulated.
Upon approval the sum of $-1,719.00will be added to the contract price.
Original Contract $587,359.99
Other Approved Change Orders $0.00
Total Contract to Date $587,359.99
This Request $-1,719.00
Other Pending Requests $0.00
Total Contract plus Pending RFCs $585,640.99
Authorized Signature: czm -� U' Date: 5-7-21
C&E Trenching LL
Authorized Signature:
City of Pasco
Date:
C&E Trenching LLC
PO Box 3788
Pasco, WA 99302
Phone: (509) 545-6940
Fax: (509) 545-8671
raj Jrz:r
To: City of Pasco
Co 1 -6
PO Box 293
Pasco, WA 99301
Project: 9th & Washington + Maitland
RFC No: 03
Date: 5/7/2021
Description: Cost to install 6" of Gravel in 35 by 13 foot area, plus cut curb down for
35'.
Cost of Labor $699.82 Equipment 821.46 Gravel $303.30 Sub for curb cut
$350.00 and markup $260.95
The above work is subject to the same conditions as specified in the original contract
unless otherwise stipulated.
Upon approval the sum of $2,435.53will be added to the contract price.
Original Contract $587,359.99
Other Approved Change Orders $0.00
Total Contract to Date $587,359.99
This Request $2,435.53
Other Pending Requests $-1,719.00
Total Contract plus Pending RFCs $588,076.52
Authorized Signature: C'a� !,t/ Date: 5-7-21
C&E Trenching ftC
Authorized Signature:
City of Pasco
Date: