HomeMy WebLinkAboutCulbert Construction - Wrigley Drive Extension Change Order No. 3 (15009) [STPUL-3552(001)]CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.3
Project No: 15009 Project Title: Wrigley Dr. Extension
STPUL-3552(001)
Contractor: Culbert Construction, Inc.
Description of Change: #13.05 - Curb & Grading Revisions @ Convention
Detail as Appropriate: Curb removal and replacement, and re -grading
Contract Bid Amount: $ 277,399.94
SALES TAX @ 8.60/o(Sch B): $ 7,600.23
Total: $ 285,000.17
PREVIOUS CHANGE ORDERR
CURRENT CHANGE ORDER
Subtotal $ 6,811.79
Subtotal $ 7,975.87
Sales tax @ 8.6% $ 105.95
Sales tax @ 8.6% N/A
Total 6,917.74
Total 7,975.87
Saies I ax Schedule is 0my
Total Change Orders To Date $ 14,893.61
New Contract Amount $ 299,893.78
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER L NO
Contract Time Prior to this Change Order ................................. 34
Modification to Contract time by this Change Order .................... 2
revised Total Contract Time .................................................... 36
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TOANDACCEPTED: APPROVED:
- —g2z— 0%29 2d'24 r
CONTRACTOR Date P OJECT MANAGER Date
APPROVED: Q
CONST. MANAGER Date CiP Manager Dam PUBLIMORW Dat
DIRECTOR
CULBERT CONSTRUCTION RFC
CONTRACT NAME:
ve
D
CONTRACT NO' #
!Wdgle
552E 01nsion_Project_�-�
-L----------------------------
- - -
- - --
- ---_-_-_
-+-- ----�
!Please see the below pricing covering the work included in Curb & Grading Revisions @ Convention.
13.05
!Please review the below pricing for incorporation into the contract, by way of Change Order.
DATE OF EVENT
EXTRA DAYS REQUESTED
-
HOURS WORKED
RFG OT I E OT RATE AMOUN
GL
7.5 $51.94_
$389.55
OP
1 f_ 6 _L�_ $59.70
J
$358.20
TD_-_---- ---- -
_-_-� 3 - _-_ ----� - $52.55 ! ---
--»
$157.65
PM
!_ 4 $75.00-______
$300.00
--_-__-_-__-_-_-�
' ---1------ ------_i _-_-__
1
$0.00
3 I ! I
I
$0.00
-------------------
SUBTOTr _-_-_----------------
EQUIPMENT
HOURS RATE
UTILITY TRUCK
4 1 1 40.00
$160.00
EXCAVATOR ----- ------
1 i- 2 - j---__-- t ------+------
- - 1---- �r-------� -$95.00 -F------
a
i
$190.00
LOADER
j 2
----
$170.00
DEMO SAW --_--------
-
I�-3$4500 _--___-�
$135.00
$85.00
BLADE _
1 1 L_ -__-_x_$85.00 1
ROLLER ��__�_
i i--1 - i-------$65.00-_--_�
$65.00
DUMP TRUCK_---__-----_
{ 3 ... i_-_�_ $75.00----
_J
$225.00
SUBTOTA
EQUIPMENT RENT
QUANTITY UNIT PRICE
$0.00
---_----_-__-_-__j
;---- t -------t __-_-- �--_-_
_
$0.00
SUBTOTk
MATERIAL
QUANTITY UNIT PRICE
CONCRETE DISPOSALi
--1 _ -- LS -- _ $50000-_-__J
$500.00
_-_------------
I-----1--------� -------^---
-- i
$0.00
--------_-----------�
i
I-----�---------4------+-----
$0.00
----------__-_-__1
I---- ------------1---
---�
$0.00
$0.00
$0.00
USE TA a .6°%---------�
---- 1�-------r- $43.00 i
----
$0.00
$0.00
SUBCONTRACTOR
QUANTITY UNIT PRICE
GILBERT PATTERSON4,080.L
- -----------
GL 00-
i - ;--__-_-f __-}------
a
$4,080.00
80.00
-- ---------------i
i --__-E _-__-_-__ - --f----
---i
$0.00
$0.00
W
$0.00
_
i
_-_- ----- ----
---� '------------� ------y------�
$0.00
SUMMARY OF COST
LABOR
$1,205.40
MARK UP 29%
$349.57
TOTAL LABOR
1,554.97
EQUIPMENT
$1,030.00
MARK UP 21 %
$216.30
IOIAL EQUIPMENT
$1,246.30
EQUIPMENT RENT
$0.00
MARK UP 21 %
$0.00
TOTAL EQUIPMENT RENT
0.00
MATERIAL
$500.00
MARK UP 21%
$105.00
TOTAL MATERIAL
$605.00
SUBCONTRACTOR
$4,080.00
MARK UP 12%
$489.60
TOTAL SUBCONTRACTOR
$4,569.60
TOTAL CHANGE
$7,975.87