HomeMy WebLinkAboutMurraysmith - WWTP Improvements Phase 1 Amendment No. 1 (Agreement No. 19048 - Project 19072)AMENDMENT NUMBER 1 to
PROFESSIONAL SERVICES AGREEMENT
WWTP Improvements — Phase 1
Project No. 19072
AGREEMENT NO. 19048
WHEREAS, the City and Murraysmith, entered into a Professional Services Agreement
on 1/10/2020 to provide engineering services with respect to the WWTP Improvements — Phase
1 project.
NOW, THEREFORE, this agreement is amended to allow Murraysmith, to modify their
original scope of work for professional and design engineering services as described within
Exhibit A.
Scope of Work:
See Exhibit A.
2. Fee:
No Change. The compensation for this project is based on a Time & Materials Basis
and remains limited to $2.321,567.00. However, based on modifications to the original
scope of work the allocation of budget between tasks 2-9 has been modified, as
described within Exhibit A.
3. Time of performance:
No Change. The services shall be complete for the project on or before 12/31/2021.
DATED THIS QDAY OF "��?2021.
CITY OF PASCO:
City of Pasco
Steve M. Worley, P.E. — Public W
Amendment No. 1 to Professional Services Agreement
Murraysmith
WWTP Improvements — Phase 1
CONSULTANT
Murraysmith
Craig Anderson, P.E.
Page 1
SCOPE OF WORK — AMENDMENT #1
WWTP Improvements, Phase 1
CITY OF PASCO, WA
Background
EXHIBIT A
Murraysmith (Consultant) entered into a contract to complete design of the Phase 1
Improvements to the City of Pasco, Washington (City) municipal wastewater treatment plant
(WWTP) in January 2020. The design was planned to be complete in December 2020 with bidding
through March 2021. Consultant has been asked to revise their original scope of work to the City
and this Amendment clarifies and expands the services to be completed.
The following Scope of Services describes the changes that were made. All work is still for the
design of the Phase 1 improvements only.
Scope of Services
The following subtasks from the January 2020 original contract have been modified. The previous
scope of services description for each is deleted per this contract amendment. All other tasks and
subtasks remain unchanged:
• Subtask 5.3 —
Constructability Review
• Subtask 5.5 —
Final Contract Document Overview Workshop
• Subtask 6.5 —
100% Contract Document Construction Cost Opinion
• Subtask 8.1—
Interim WAS Thickening Plan
• Subtask 8.2 —
Interim Blower Redundancy Plan
• Subtask 8.3 —
Detailed Equipment Selection Reviews
• Subtask 8.4 —
WWTP Site Visits
• Subtask 8,6 —
Permitting and Public Outreach
• Subtask 9.3 —
Bid Evaluation Support
The following new subtask scope of services descriptions are added per this contract amendment:
5.3A City Staff and Third Party 90% Constructability Review
Review documents will be provided a week in advance of review meetings. Budget includes up to
two review meetings of four-hour duration with the design team leads to discuss project
constructability and recommended alternative approaches.
Consultant will respond to comments provided by City and Third -Party Staff on the 90% Contract
Development Package in a detailed comment tracking spreadsheet. Tracking spreadsheet will
City of Pasco MURRAYSMITH WWTP Improvements, Phase 1
January 2021 Page 1
include compilation of comments, response from Consultant, changes needed, and changes
completed.
5.38 Washington Department of Ecology 90% Review
Consultant will prepare a comments tracking spreadsheet from detailed comments provided by
Washington Department of Ecology staff on the 90% Contract Development Package. Tracking
spreadsheet will include compilation of comments, response from Consultant, changes needed,
and changes completed. Consultant will prepare and distribute a summary of the review
comments received for discussion.
5.5 Washington Department of Ecology 100% Review
Consultant will prepare comments tracking spreadsheet from detailed comments provided by
Washington Department of Ecology staff on the 100% Contract Development Package. Tracking
spreadsheet will include compilation of comments, response from Consultant, changes needed,
and changes completed. Consultant will prepare and distribute a summary of the review
comments received for discussion.
9.2A Constructability Review Comments Incorporation
Following receipt of the Task 5 Contract Documents review comments, consultant will incorporate
constructability review comments, as appropriate, and prepare an addendum of changes to the
Contract Documents.
9.28 Process Control Descriptions
Consultant will develop process control descriptions (PCDs) for use by the City's selected
programming consultant. PCDs will describe the intended operation of unit processes/systems
and the general control and integration of the project equipment.
The City's selected programmer will be responsible for not only controlling the new equipment as
required, but also to remove or alter the logic for equipment that is being replaced or removed
and integrate the new equipment into the overall plant process. Additional coordination between
the design engineer and the City's selected programming consultant to finalize programming and
system integration details during construction are anticipated and will be covered in a subsequent
scope of work.
9.3 Bid Evaluation Support
Consultant will assist City in their evaluation of the bids received. Assistance may include items
such as preparation of a bid tabulation spreadsheet, a review of required bid materials (e.g. — bid
bond, listed subcontractors, acknowledgement of addenda, etc.), and/or a review of the
supplemental bidder responsibility criteria submitted. Consultant will discuss findings with the
City and aid in bidder communication as needed.
City of Pasco MURRAYSMITH WWTP Improvements, Phase 1
January 2021 Page 2
9.4 Conformed Set
Consultant will incorporate all changes made by addenda during the bid period into a conformed
set of documents (all 5 volumes) for use during the performance of the contract.
Budget
The work covered under this scope of work will be billed on a time and materials basis at the billing
rates for personnel working directly on the project, which will be made at the Consultant's Hourly
Rates, plus Direct Expenses incurred. The overall budget estimate breakdown for this work is
outlined in the table below. Consultant will manage the work identified to the aggregate
authorized budget amount which shall not be exceeded without prior written authorization from
the City.
Task
Task 1- Project Management
Amount
Change
Final
$230,475
$230,475
$0
Task 2 — Project Definition
$171,445
-$120
$171,325
Task 3 — Schematic Design
$248,233
-$1,6-96
$246,537
Task 4 — Design Development
$314,948
-$50,910
$264,038
Task 5 — Contract Document
Development (90%)
$669,558
-$1,215
$668,343
Task 5 — Contract Document
Development (Final)
$156,351
+$172,996
$329,347
Task 6 — Cost Opinions
$125,124
-$39,345
$85,779
Task 7 — Design Reviews
$138,749
-$1,890
$136,859
Task 8 — Special Activities &
Investigations
$225,105
-$193,105
$32,000
Task 9 — Bid -Phase Assistance
$41,579
+$115,285
$156,864
TOTAL
$2,321,567
$0
$2,321,567
City of Pasco MURRAYSMITH WWTP Improvements, Phase 1
January 2021 Page 3
Project Schedule
Assuming a Notice to Proceed by the second week of January 2020, the work provided under this
scope of work is anticipated to be completed per the milestone dates provided in the table below.
Consultant will make every effort to complete the work in a timely manner; however, it is agreed
that consultant can not be responsible for delays occasioned by factors beyond its control, nor by
factors that could not reasonably have been foreseen at the time this scope was executed.
Task 2 —
Task
Project Definition
Completion Date
3/3/2020
Task 3 —
Schematic Design
4/30/2020
Task 4 —
Design Development
6/23/2020
Task 5 —
Contract Document Development (90%)
9/24/2020
Task 5 —
Contract Document Development (Final)
12/15/2020
Task 9 — Bid -Phase Assistance
3/31/2021
City of Pasco MURRAYSMITH WWTP Improvements, Phase 1
January 2021 Page 4