HomeMy WebLinkAbout4054 Resolution - PWRF CO NOs. 2-4 & 6 for IPSRESOLUTION NO. 4054
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
AUTHORIZING THE CITY MANAGER TO SIGN AND EXECUTE A SIXTH
CHANGE ORDER TO THE CONSTRUCTION CONTRACT WITH APOLLO,
INC. FOR THE PROCESS WATER REUSE FACILITY (PWRF) IRRIGATION
PUMP STATION (IPS) PROJECT AND RATIFYING APPROVAL FOR
PREVIOUS CHANGE ORDER NOS. 2,3 AND 4.
WHEREAS, the City and Apollo, Inc. entered into a Construction Contract on 11/12/2019
to provide Improvements to the PWRF Irrigation Pump Station Project; and
WHEREAS, the City and Apollo, Inc. has executed five Change Orders to the
Construction Contract; and
WHEREAS, Change Order No. I and No. 5 to the contract were authorized under the
authority provided to the City Manager and Public Works Director; and
WHEREAS, Change Orders No. 2, 3 and 4 require Council ratification to maintain
consistency with Administrative Order No. 470 "Purchasing Policies and Procedures 2.0"; and
WHEREAS, a corrective and preventative action plan is being developed to address proper
processing practices for change order approvals; and
WHEREAS, Change Order No. 6 in the amount of $54,660.85 exceeds the City Manager's
authority and thus requires Council approval.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PASCO, WASHINGTON:
Section 1. The City Manager of the City of Pasco, Washington, is hereby authorized,
empowered, and directed to sign and execute Change Order No. 6 a copy of which is attached
hereto, and incorporated herein by this reference as Exhibit A, on behalf of the City of Pasco.
Section 2. That Change Orders No. 2, 3 and 4 to Apollo, Inc. are hereby ratified by City
Council.
Resolution — Sixth Change Order
Contract with Apollo - 1
PASSED by the City Council of the City of Pasco, Washington, this 19th day of April,
2021.
Saul Martinez
Mayor
ATTEST:
Debra Barham, CMC
City Clerk
Resolution — Sixth Change Order
Contract with Apollo - 2
APPROVED AS TO FORM:
Ke LLC
City Attorney
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.6
Project No: CP7-SR-1 R-18-00 Project Title: Irrigation Pump Station
Contractor: ADOIIO.Inc.
Description of Change
COP 008-012 Electrical Revisions
EXHIBIT A
Detail as Appropriate: COP 008: PUD required change ($8,415.21); COP 009: Rev. to pump
emergency stop; ($16,119.04); COP 010: Additional breakers and power
for slidegate ($16,781.92); COP 011: Relocate 125V circuit to CU -1
($1,318.84); COP 012: Replace control wiring to pumps 1-3 ($7,976.89)
Contract Bid Amount:
SALES TAX @ 8.0%:
Total:
$ 7,452,422.00
$ 596,193.76
$ 8,048,615.76
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 503,461.64
Subtotal $ 50,611.90
Sales tax @ 8.0% $ 40,276.93
Sales tax @ 8.0% $ 4,048.95
Total $ 543,738.57
Total $ 54,660.85
Total Change Orders To Date $ 598,399.42
New Contract Amount $ 8,647,015.18
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
r—Y--ES-1 NO
Additional 20 Days
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
CONTRACTOR Date
APPROVED:
APPROVED:
PROJECT MANAGER Date
APPROVED:
CONST. MANAGER Date CIP MANAGER Date PUBLIC WORKS Date
DIRECTOR
Memo
To: Steve Worley, PE. Public Works Director
oe
From: Maria Serra, PE. CIP Manager
Date: 4/7/2021
Re: PWRF Irrigation Pump Station (IPS)
Change Order History
Pasco
A construction contact with Apollo Inc. for the construction of the PWRF Irrigation Pump Station (IPS) project
was executed on 11. 12.2019 in the amount of $8,048,615.76.
The following Change Orders were negotiated and routed for approval:
Change Order No. 1: High Performance wetwell Coating: A protective coating of the
wetwell was not included in the original specifications. A protective
coating of the wetwell is required to maintain integrity of the concrete
which is exposed to caustic conditions from the industrial wastewater.
Amount of $171,135.42.
Approved/Signed by City Manager.
Change Order No. 2: Additional grading of 115 million gallon pond: With the new IPS
the outflow (or low point) of the 115 million gallon pond needed to be
changed from the east side of the pond to the southwest corner, closer to
the new IPS. Due to a discrepancy in the as -built survey of the existing
115 million gallon pond, it was necessary to remove an additional
significant amount of native material to accommodate the new low point.
Amount of $176,952.58.
Approved/Signed by City Manager.
Change Order No. 3: Changes in boring: A new discharge pipe from the 115 million gallon
pond to the IPS was designed to be installed via directional boring
underneath the pond embankment to the inside bottom of the pond. A
steel casing is required within the embankment and then the actual
discharge (or carrier) pipe is installed through the casing. A change was
necessary to decrease the steel casing diameter and change the carrier
piping material from PVC to HDPE. This resolved a conflict between the
30" PVC piping being too large for installation in the specified steel
casing.
Amount of $236,966.74.
Approved/Signed by City Manager.
Page 1 of 2
Change Order No. 4: Replacement ballast tubes in the 115 million gallon pond: The
installation of ballast tubes on the replaced liner area in the 115 million
gallon pond was not included in the original bid. Ballast tubes are required
in lined ponds to weigh down the liner. In this facility these ballast tubes
are critical, since the ponds remain empty for extended periods of time.
This change order added 1,300LF of ballast tubes installation.
Amount of $63,177.27.
Approved/Signed by City Manager.
Change Order No. 5: Manhole value engineering concept: A value engineering concept
during the construction was to delete a 72" manhole, reroute a 12" PVC
and drop piping to the wetwell and install stubs with mechanical joint caps
on the future manhole locations. This alternative layout preserves the
design intent and allows maintenance operations to be performed, without
the need for the deep 72" manholes structures as originally proposed.
Amount of ($104,493.43). This Change Order was a credit.
Approved/Signed by Public Works Director.
Proposed Change Order No. 6: Electrical revisions: This Change Order (No.6) is for
Electrical Revisions that are being required by Franklin PUD along with
modifications to the electrical system associated with the pumps that was
identified by Operations Staff (revision to the pump emergency stop
button location, additional breakers and power for slide gate, relocate
125V circuit and replace control wiring to pumps). The cost of Change
Order No. 6 is $54,660.85. Should Change Order No. 6 be approved, the
total Construction Contract cost would increase to $8,647,015.18.
The following table provides a summary of change orders and running total:
Change Order
No.
Approval Date
Amount
Running Total
1
6/8/2020
171,135.42
171,135.42
2
8/21/2020
176,952.58
348,088.00
3
8/21/2020
_ 236,966.74
585,054.74
4
9_/8/2020
63,177.27
648,232.01
5
_
11/30/2020
(104,493.43
543,738.58
6
ro osed
54,660.85
598,399.43 j
As shown in the table above, Council Approval should have been sought for change orders 2
through 4. This procedural error was identified as Change Order No. 6 was being prepared.
Council approval is needed for Change Order No. 6 along with ratification of change orders 2
through 4.
A corrective and preventative action plan is being developed to prevent this procedural error
from occurring in the future.
Page 2 of 2