HomeMy WebLinkAboutIndustrial Construction of Washington - Water Main Replacement - Wehe Contract Book (19073)
CONTRACT DOCUMENTS
WATER MAIN REPLACEMENT – ALLEY EAST
OF WEHE
CONTRACT NO. 19073
COPY_1___
CONTRACT DOCUMENTS
WATER MAIN REPLACEMENT –
ALLEY EAST OF WEHE
PROJECT CERTIFICATION
The technical material and data contained in this report was prepared by the City of Pasco,
under the supervision of the below listed individuals. Those responsible staff members who are
registered professional engineers are licensed in the State of Washington.
Jonathan A. Padvorac, P.E.
CONTRACT NO. 19073
TOC
TABLE OF CONTENTS
WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE
CONTRACT NO. 19073
INVITATION FOR BIDS .................................................................................................................................... AD-1
INFORMATION FOR BIDDERS:
Standard Specifications ........................................................................................................................... IB-1 Qualification of Bidders .......................................................................................................................... IB-1 Explanation of Contract Documents and Work Site ................................................................................ IB-1 Qualification of Bidders ........................................................................................................................... IB-1 Water ....................................................................................................................................................... IB-1 Right Of Way ............................................................................................................................................ IB-2 Submission of Bid Proposal ..................................................................................................................... IB-2 Schedule of Events .................................................................................................................................. IB-3 Award of Contract.................................................................................................................................... IB-3 Prevailing Wage Requirements ................................................................................................................ IB-3 Bid Opening Procedures .......................................................................................................................... IB-4
PROPOSAL:
Bid Proposal .......................................................................................................................................P-1, P-2
Subcontract Disclosure ........................................................................................................................... SD-1
Bid Bond ................................................................................................................................................. BB-1
Non-Collusion Declaration ..................................................................................................................... NC-1
Prevailing Wage Rate Reference ......................................................................................................... PWR-1
CONTRACT REGULATIONS:
Contract ................................................................................................................................................. CO-1 Performance Bond .................................................................................................................................. PB-1 Payment Bond ...................................................................................................................................... PAB-1
SPECIAL PROVISIONS
City of Pasco Special Provisions .............................................................................................................. SP-1
PLANS ................................................................................................................................................... SHEET NO. 1
AD-1
ATTENTION CONTRACTORS
INVITATION TO BID
WATER M AIN REPLACEMENT – ALLEY EAST OF WEHE
CONTRACT NO. 19073
The City of Pasco, Washington is inviting and requesting bid proposals for the WATER MAIN
REPLACEMENT – ALLEY EAST OF WEHE project, Contract No. 19073 via the Municipal Research and
Services Center (MRSC) Small Works Roster. The work addressed in this project consists of a new 8” water
main (approximately 500 linear feet), as replacement of the existing water main, located in the broadly
described alley East of South Wehe Avenue, between East Alton Street and East Helena Street. Also
included is installation of a fire hydrant and appurtenances, pavement restoration along the alley way, and
other related work. This is a Small Works Project; all bidders shall be on the Municipal Research and
Services Center (MRSC) Small Works Roster.
Bids shall be submitted electronically via email to Dustin Wittman at wittmand@pasco-wa.gov, and
addressed to the CITY OF PASCO ENGINEERING DEPARTMENT (19073 – WATER MAIN
REPLACEMENT – ALLEY EAST OF WEHE).
All proposals will be due no later than WEDNESDAY, OCTOBER 28, 2020 at 2:00 PM. Following the
end-time of bid acceptance the bids will be opened and recorded and the apparent low will be
announced via e-mail.
Bids are to be submitted only on forms provided in the specifications.
A bid bond (surety bond) is not required for this project but a performance bond will be and retainage will
be withheld at 5%.
Technical questions regarding the scope of this project should be put in writing via e-mail and directed to
Jon Padvorac, PE, Project Manager, City of Pasco, Public Works, 525 N. 3rd Avenue, PO Box 293,
Pasco, WA 99301, Email: padvoracj@pasco-wa.gov.
Bids will only be accepted from Contractors who are eligible to perform services as governed
by PMC 14.15 and who are on the MRSC Small Works Roster.
All work performed on the project will be subject to State of Washington prevailing wage rates.
The City of Pasco is an equal opportunity and affirmative action employer. Small, minority-and women-
owned businesses are encouraged to submit bids. All work performed on the project will be subject to
the prevailing state wage rates.
The City reserves the right to reject any and all bids and to waive technicalities or irregularities, and
after l consideration of all bids and factors involved make the award to best serve the interests of the City
of Pasco.
DATED: October 12, 2020
_________________________________________
Jonathan Padvorac, PE
Project Manager – Public Works Engineering
Information for Bidders
Standard Specifications ........................................................................................................................... IB-1 Qualification of Bidders .......................................................................................................................... IB-1 Explanation of Contract Documents and Work Site ................................................................................ IB-1 Qualification of Bidders ........................................................................................................................... IB-1 Water ....................................................................................................................................................... IB-1 Submission of Bid Proposal ..................................................................................................................... IB-2 Schedule of Events .................................................................................................................................. IB-3 Award of Contract.................................................................................................................................... IB-3 Prevailing Wage Requirements ................................................................................................................ IB-3 Bid Opening Procedures ......................................................................................................................... IB-4
IB 1 of 4
INFORMATION FOR BIDDERS
STANDARD SPECIFICATIONS
The Standard Specifications for the municipal Public Works Construction, as
prepared by the Washington Department of Transportation 2020 Standard
Specifications for Road, Bridge, and Municipal Construction hereinafter referred
to as “Standard Specifications,” hereby references are made a part of this
contract as amended by the WSDOT and the APWA general special provisions
as indicated and supplemented by the “Special Provisions.” Copies of the
Standard Specifications are available for review and inspection at the office of
the Engineer. Copies of the Standard Specifications may be purchased from:
Washington State Department of Transportation (WSDOT)
Engineering Publications
Post Office Box 47408
Olympia, WA. 98504-7408
Any reference to the 20XX Standard Specifications for Road, Bridge and
Municipal Construction shall read 2020 Standard Specifications for Road, Bridge
and Municipal Construction.
EXPLANATION OF CONTRACT DOCUMENTS AND WORK SITE
Bidders should carefully examine the Contract Documents and work site to fully
acquaint themselves with all the conditions and matters, which can in any way
affect the work or the cost thereof. Any explanation regarding the meaning or
interpretation of the Contract Documents must be requested in writing, with
sufficient allowance of time for receipt of reply before the time of the bid opening.
Any such explanations or interpretations shall be made in the form of addenda to
the documents and shall be furnished to all bidders, who shall submit all addenda
with their bids. Oral explanations and interpretations made prior to the bid
opening shall not be binding.
QUALIFICATION OF BIDDERS
All bidders must be qualified in accordance with Pasco Municipal Code Chapter
(PMC) 14.15 ‘Qualification for Public Works Construction’ and who are on the
Municipal Research and Services Center (MRSC) Small Works Roster. The City
reserves the right to reject any bid of such bidder who is not eligible to perform
services as governed by PMC 14.15 and is not on the MRSC Small Works
Roster.
WATER
If City water is used for any work related to this project, a Fire Hydrant Meter and
Gate Valve will be furnished by the City of Pasco to be used specifically for this
project. The Contractor shall be charged an $800 return deposit plus a $50 non-
refundable handling and processing fee for the meter and valve. The City will
charge the Contractor for any water used in the construction of the project. Any
IB 2 of 4
water used for this project shall be considered incidental to construction and will
be paid per WSDOT Standard Specification 2-07.5. The Contractor shall not
operate the hydrant as a gate valve, nor shall the Contractor be allowed to
operate any other City owned valve. The Contractor shall provide the necessary
back flow prevention device when connecting to the water service. The Fire
Hydrant Meter requirements and the Fire Hydrant Meter Application are available
at the Customer Service Window and the Engineering Department.
Fire Hydrant Meters shall be read daily and submitted to the City Engineer
weekly. There shall be no specific measurement and payment for the use of
water. All payments necessary to meet the requirements of this provision shall
be considered incidental to the work and included in the Contract price.
SUBMISSION OF BID PROPOSAL
The City of Pasco (herein called the City and/or Owner) invites Bidders (herein
called the Contractor) to submit bids on the proposal forms (Sec. 1-02.13) (bid
package) to be provided to those Bidders pre-qualified in accordance with PMC
14.15 (Sec. 1-02.1).
In an effort to provide proper social distancing to Contractors and City Staff, the
City of Pasco has opted to conduct the bidding of this project through an online
bidding process.
Bids shall be submitted electronically, via email, to Dustin Wittman at
wittmand@pasco.wa.gov, and addressed to the City of Pasco Public Works
Capital Projects Group (19073 WATER MAIN REPLACEMENT – ALLEY
EAST OF WEHE).
The proposal forms to be completed for the bid package include:
The Proposal (Sec. 1-02.6), the Non-Collusion Declaration (Sec. 1-02.8(1)), the
Subcontractor Disclosure (Sec. 1-02.6), and Acknowledgement of any Addenda
(Sec. 1-02.6). All blank spaces for bid prices shall be completed either in ink or
be type written and shall contain the appropriate amounts in figures (Sec. 1-
02.6).
A bid bond (surety bond) is not required for this project but a performance bond
will be and retainage will be withheld at 5%.
Any bid may be withdrawn prior to the scheduled time for the opening of bids or
authorized postponement thereof (Sec. 1-02.10). Any bid received after the time
and date specified shall not be considered (Sec. 1-02.9). No bidder may
withdraw a bid within sixty (60) days after the actual date of the opening thereof
(Sec. 1-03.2).
IB 3 of 4
Bids will be accepted from Contractors who are eligible to perform services as
governed by PMC 14.15 and who obtained original bid documents from Dustin
Wittman via the MRSC Small Works Roster notification.
SCHEDULE OF EVENTS
Once the lowest responsible bidder has been determined and the City Council
has authorized award of the Contract, the City will mail or otherwise transmit to
the Contractor the necessary Contract Documents for execution. The Contractor
will have a maximum of ten (10) calendar days from the date of award in which to
complete and return the Contract Documents along with the Performance Bond
and Certificate of Insurance (Sec. 1-03.3). Once all the contract documents have
been returned, a Pre-Construction Conference will be held and the Notice to
Proceed will be issued (Sec. 1-08.4). If requested by the Contractor, the City
would be willing to delay notice-to-proceed until early spring in 2021. The City
will issue the notice-to-proceed within six months from the date of contract
award.
AWARD OF CONTRACT
The award of the contract is contingent upon approval by the Pasco City Council.
It is the intent of the City to award a contract to the lowest responsible bidder
provided the bid has been submitted in accordance with the requirements of the
bidding documents and does not exceed the funds available.
The City reserves the right to (Sec 1-03.1):
• Waive any informality in bids received when such waiver is in the best
interest of the City.
• Accept Alternates in any order or combination, unless otherwise
specifically provided in the bidding documents, and to determine the low
bidder on the basis of the sum of the Base Bid and the Alternates
accepted.
• Reject any and all bids.
• Republish the invitation for bids.
PREVAILING WAGE REQUIREMENTS
Because this is a Public Works contract, the Contractor and all sub-contractors
must follow the State’s Prevailing Wage requirements. The Contractor must
submit the Intent and Affidavit forms, approved by the Department of Labor and
Industries. Intent forms must be filed prior to the start of work, if possible.
Affidavits are filed after completion of the work. The City may not make any
payments where the Contractor and all sub-contractors have not submitted the
approved Intent form; nor may not release retainage until the Contractor and all
sub-contractors have submitted the approved Affidavit forms. As this job
The City requests that certified payroll for the Contractor and all sub-contractors
be provided on a weekly basis.
IB 4 of 4
BID OPENING PROCEDURE
Bid Opening for this project will occur at 2:00pm on October 28, 2020 in the
Public Works – Capital Project office, whereas, in accordance to Resolution No.
3950, on March 23, 2020, City Hall and other certain City of Pasco public
facilities are temporarily closed. These orders will remain in effect for the duration
of Proclamation No. 20-25, requiring the aforementioned temporary closure
ordered by the Office of the Governor, as amended, unless extended or
terminated by separate written order.
Immediately following the bid-opening a preliminary Bid-Tab will be sent out to
Contractors whom bid on the project. Upon finalization of documents and award
a Final Bid-Tab will be posted to the City of Pasco Website.
Proposal
Bid Proposal .....................................................................................................................................P-1 & P-2
Subcontract Disclosure ........................................................................................................................... SD-1
Bid Bond ................................................................................................................................................. BB-1
Non-Collusion Declaration ..................................................................................................................... NC-1
Prevailing Wage Rate Reference ......................................................................................................... PWR-1
BID PROPOSAL
WATER MAIN REPLACEMENT - ALLEY EAST OF WEHE
CONTRACT NO. 19073
SS=STANDARD SPEC SP=SPECIAL PROVISION
ITEM PAY ITEM QUANTITY UNIT DESCRIPTION Unit Price Total Price
1 SS 1-09.7 1 LS MOBILIZATION AND DEMOBILIZATION
2 SS 1-10.4 1 LS PROJECT TEMPORARY TRAFFIC CONTROL, MIN. BID $1,000
3 SS 1-07.15 1 LS SPCC PLAN, MIN. BID $1,000
4 SP 8-01.5 1 LS EROSION/WATER POLLUTION CONTROL, MIN BID $1,000
5 SP 1-05.3(3) 1 LS RECORD DRAWINGS, MIN. BID $1,000
6 SP 7-09.5 500 LF SHORING OR EXTRA EXCAVATION
7 SP 2-02.5 1 LS REMOVAL OF STRUCTURES AND OBSTRUCTIONS
8 SP 7-09.5 6 EA DIG AND VERIFY
9 SP 2-02.5 70 LF SAWCUTTING PAVEMENT
10 SP 7-09.5 140 CY ROADWAY AND TRENCH EXCAVATION INCL. HAUL
11 SP 4-04.5 490 SY 2" CRUSHED SURFACE TOP COARSE (CSTC)
12 SP 4-04.5 490 SY 6" CRUSHED SURFACE BASE COARSE (CSBC)
13 SP 4-04.5 20 SY 10" CRUSHED SURFACE BASE COARSE (CSBC)
14 SP 5-05.5 4.5 TON 3" HMA, CL. 3/8", PG 64S-28 FOR ASPHALT REPAIR
15 SP 5-05.5 60 TON 2" HMA, CL. 3/8", PG 64S-28 FOR ASPHALT ALLEY PAVEMENT
16 SP 2-09.5 140 CY TRENCH BACKFILL
17 SP 8-02.5 1 LS LANDSCAPE RESTORATION
18 SP 7-08.5 10 EA UTILITY CROSSING
19 SP 7-09.5 1 EA BLOW OFF ASSEMBLY
20 SP 7-09.5 500 LF WATER MAIN INSTALLATION AND COMISSIONING
21 SP 7-09.5 1 EA CONNECT TO EXISTING WATERMAINS
22 SP 7-12.5 1 EA DUCTILE IRON GATE VALVE, 8-IN.
23 SP 7-09.5 7 EA SERVICE CONNECTIONS, COPPER PIPE, 1 IN. DIAM (WITH WATER METER BOXES)
24 SP 7-09.5 3 EA SERVICE CONNECTIONS, COPPER PIPE, 1 IN. DIAM (WITHOUT WATER METER BOXES)
25 SP 7-14.5 1 EA HYDRANT ASSEMBLY WITH VALVE
26 SS 8-14.5 40 SF DETECTABLE WARNING SURFACE
27 SP 8-04.5 60 LF CEMENT CONC. TRAFFIC CURB AND GUTTER
28 SP 8-14.5 20 SY CEMENT CONC. SIDEWALK
29 SP 8-14.5 2 EA CEMENT CONCRETE CURB RAMP TYPE 2 COMMERCIAL
Subtotal:
Sales Tax @ 8.6%:
GRAND TOTAL:
HONORABLE MAYOR AND CITY COUNCIL
City Hall
Pasco, Washington 99301
Council Members:
The undersigned declares that he has carefully examined the site at:
The broadly described alley East of South Wehe Avenue, between East Alton Street and East Helena Street, located in Pasco, WA
And has carefully examined specifications, plans, laws, and ordinances covering:
The improvement of approximately 500 linear feet (LF) of a new water main, as replacement of the existing water main, installation of a fire hydrant and
appurtenances, pavement restoration along the alley way, and other work, all in accordance with the attached Contract Plans, these Contract Provisions,
and the Standard Specifications.
In accordance with the terms, provisions, and requirements of the foregoing, the following prices are tendered as an offer to furnish the equipment,
materials, appurtenances and guarantees, where required, and to perform the work in place and in good working order.
SCHEDULE OF PRICES
Unit prices for all items, all extensions, and total amount of bid must be shown.
ALL ENTRIES SHALL BE IN INK OR TYPED TO VALIDATE BID.
P-1
SIGNED: ____________________________________ TITLE:_____________________________________________
PRINTED NAME: ________________________________________________________________________
TELEPHONE: _________________________________________________________________________
STATE CONTRACTOR'S LICENSE NO.: _____________________________________________________
BID PROPOSAL
WATER MAIN REPLACEMENT - ALLEY EAST OF WEHE
CONTRACT NO. 19073
The Proposal Form, Bid Bond, Noncollusion Declaration, Subcontract Disclosure and Acknowledgement of all Addenda shall be submitted as a complete
integral bid package.
The undersigned hereby agrees that the City Engineer for the City of Pasco shall determine the actual amount of quantities and materials to be paid under
the Contract for which this Proposal is made and that all material furnished and all work performed shall be strictly in accordance with the plans and
specifications.
The undersigned agrees that if awarded the contract, he will commence work on the date indicated on the written Notice to proceed and that all work
should be completed within 20 working days. The undersigned further agrees to pay as liquidated damage for each consecutive working day thereafter as
provided in the current Standard Specification for road, bridge, and Municipal Construction Section 1-08.9.
The undersigned Bidder hereby certifies that, within the three-year period immediately preceding the bid solicitation date for this Project, the bidder is not a
“willful” violator, as defined in RCW 49.48.082, of any provision of chapters 49.46, 49.48, or 49.52 RCW, as determined by a final and binding citation and
notice of assessment issued by the Department of Labor and Industries or through a civil judgment entered by a court of limited or general jurisdiction.
Accompanying this Proposal is a certified check, cashier's check or bid bond, payable to the City of Pasco being an amount not less than 5% of the total bid
based upon the estimate of quantities at the above prices according to the conditions of the Information for Bidders. If this proposal is accepted by the City
of Pasco, and the undersigned shall fail to execute a satisfactory contract and bonds, as stated in the Instructions For Bidders hereto attached, within ten
(10) calendar days from the date of notice of award, then the City may, at its option, determine that the undersigned has abandoned the contract and
thereupon this proposal shall be null and void and the certified check or bid bond accompanying this proposal shall be forfeited to and become the property
of the City of Pasco. Otherwise, the certified check, cashier's check or bid bond accompanying this proposal shall be returned to the undersigned.
Receipt is hereby acknowledged of addendum(s) No.(s) __________, __________ & _________
DATED AT ________________ THIS _______ DAY OF___________________, ________.
NAME OF COMPANY: ___________________________________________________________________
ADDRESS: _____________________________________________________________________________
P-2
SD-1
SUBCONTRACT DISCLOSURE
All Subcontractors must be qualified in accordance with Pasco Municipal Code 14.15, at the time of bid
submittal. Bidder acknowledges that work performed by a non-qualified subcontractor will not be
accepted by the City of Pasco.
We, the undersigned, intend to employ the following subcontractors, in order to fully perform the work
outlined in these specifications, as required by RCW 39.30.060. Further, we acknowledge that
qualification of subcontractors must be in place no later than when subcontractors are required to
perform any work on the project.
We intend to employ the firm(s) of:
NAME ADDRESS UBI # List Item Number
1)____________________________________________________________________________
(Electrical)
2)____________________________________________________________________________
(Plumbing)
3)____________________________________________________________________________
(HVAC)
4)____________________________________________________________________________
(Structural Steel Installation)
5)____________________________________________________________________________
(Rebar Installation)
6)____________________________________________________________________________
7)____________________________________________________________________________
and represent and warrant that the work will be performed by said subcontractors in a good and
workmanlike manner and under our direct supervision. We further represent and warrant that the
work to be performed by them constitutes approximately percent of the total dollar value of
said contract.
Description of work to be performed by Prime Contractor:
FIRM:
NAME:
ADDRESS:
TELEPHONE:
EMAIL: _
BB-1
BID BOND
Bid Bond is NOT required for this project
NC-1
NON-COLLUSION DECLARATION
I, by signing the proposal, hereby declare, under penalty of perjury under the laws of the
United States that the following statements are true and correct:
1. That the undersigned person(s), firm association or corporation has (have) not,
either directly or indirectly, entered into any agreement, participated in any
collusion, or otherwise taken any action in restraint of free competitive bidding in
connection with the project for which this proposal is submitted.
2. That by signing the signature page of this proposal, I am deemed to have signed
and to have agreed to the provisions of this Declaration.
SIGNATURE DATE
PWR-1
PREVAILING WAGE RATE REFERENCE
The State of Washington prevailing wage rates applicable for this public works
project, which is located in Franklin County, may be found at the following website
address of the Department of Labor & Industries:
https://secure.lni.wa.gov/wagelookup/
Based on the bid submittal deadline for this project, the applicable effective date
for prevailing wages for this project is September 2, 2020, and subsequent
corrections effective on September 10, 2020. A copy of the applicable prevailing
wage rates are also available for viewing at the office of the Public Works Director,
located at 525 North 3rd, Pasco, Washington. Upon request, the City will mail a hard
copy of the applicable prevailing wages for this project. Please forward your request
in writing to the address above, or by calling (509) 545-3444.
Contract Regulations
Contract ................................................................................................................................................. CO-1 Performance Bond .................................................................................................................................. PB-1 Payment Bond ...................................................................................................................................... PAB-1
CO-1
CONTRACT
WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE
CONTRACT NO. 19073
STATE OF WASHINGTON ) ) ss COUNTY OF FRANKLIN )
This agreement and contract made and entered into in triplicate this ________ day of
_________________, 2020, by and between the City of Pasco, a municipal corporation,
hereinafter called the City and
hereinafter called the Contractor.
WITNESSETH:
That whereas, the City has caused to be prepared certain plans and specifications for
improvements in and for the City of Pasco and the Contractor did on the ______ day of
_______________, 2020 file with the Office of the City Clerk of the City of Pasco, Washington, a
Proposal to furnish all equipment, labor, materials and appurtenances and to pay for the same,
and agreed to accept for and in full consideration of the sums fully stated and set forth in said
Proposal as full compensation for the completed work.
WHEREAS, the said plans, specifications and proposal fully and accurately described the terms
and conditions upon which the contractor proposes to furnish said equipment, labor, tools,
materials and appurtenances and perform work, together with the manner and time of
furnishing the same.
It is therefore agreed, first that a copy of said specifications, plans and proposal, filed as
aforesaid on the _____ day of ____________________, 2020 be attached hereto and the same
are hereby made the items and conditions of this agreement by and between the City and
Contractor in all matters and things therein set forth and described; and further that the City
and the Contractor accept and agree to the terms and conditions of said plans, specifications
and proposal as filed as completely as if said terms and conditions and plans are herein set out
in full.
In witness whereof the parties hereto have caused this agreement to be executed the day and
year herein above written this day of , 2020.
CITY OF PASCO
BY:
Dave Zabell, City Manager Contractor Signature
ATTEST:
Debra C. Barham, City Clerk By: Printed Name
Approved as to form:
City Attorney
PB-1
PERFORMANCE BOND
BOND TO THE CITY OF PASCO
KNOW ALL MEN BY THESE PRESENTS:
That we, the undersigned,
as principal, and a corporation
organized and existing under the laws of the State of Washington, as a surety corporation, and
qualified under the laws of the State of Washington to become surety upon bonds of
contractors with Municipal Corporations, as surety, are jointly and severally held and firmly
bound to the City of Pasco in the penal sum of for the payment of
which sum on demand we bind ourselves and our successors, heirs, administrators or personal
representatives as the case may be.
This obligation is entered into a pursuance of the statutes of the State of Washington, and
ordinances of the City of Pasco.
Dated at , Washington, this day of , 2020.
Nevertheless, the conditions of the above obligation are such that:
WHEREAS, pursuant to action taken by the City Council of the City on ______________, 2020,
the Mayor and City Clerk of the City of Pasco have let or are about to let to the said
___________________________, the above bounden principal, a certain contract, the same
contract being numbered 19073 and providing for WATER MAIN REPLACEMENT – ALLEY EAST
OF WEHE (which contract is referred to herein and is made a part hereof as though attached
hereto.)
WHEREAS, the said principal has accepted, or is about to accept the said contract, and
undertake to perform the work wherein provided for in the manner and within the time set
forth.
NOW, THEREFORE, if the said ________________________________ shall faithfully perform all
of the provisions of said contract in the manner and within the time therein set forth, or within
such extensions of the time as may be granted under the contract, and shall pay all laborers,
mechanics, subcontractors, and material men, and all persons who shall supply said principal or
subcontractors with provisions and supplies for the carrying on of said work, and shall
indemnify and hold said City of Pasco harmless from any loss or damage occasioned to any
person or property by reason of any carelessness or negligence on the part of said principal, or
any subcontractor in the performance of said work, and shall indemnify and hold the City of
Pasco harmless from any damage or expense by reason or failure of performance as specified in
said contract or from defects appearing or developing in the material or workmanship provided
or performed under said contract after its acceptance thereof by the City of Pasco, then and in
that event this obligations shall be void; but otherwise it shall be and remain in full force and
effect.
Approved as to Form:
Surety Contractor
PAB-1
PAYMENT BOND
TO THE CITY OF PASCO
Bond No. _________
The City of Pasco, Washington, City has awarded to (Principal), a
contract for the construction of the project designated as WATER MAIN REPLACEMENT –
ALLEY EAST OF WEHE Contract No. 19073 in Pasco, Washington (Contract), and said Principal
is required under the terms of that Contract to furnish a payment bond in accord with Title 39.08
Revised Code of Washington (RCW).
The principal, and (Surety), a corporation organized under
the laws of the State of and licensed to do business in the State
of Washington as surety and named in the current list of “Surety Companies Acceptable in
Federal Bonds” as published in the Federal Register by the Audit Staff Bureau of Accounts, U.S.
Treasury Dept., are jointly and severally held and firmly bound to the City, in the sum of
US Dollars,
($ ) Total Contract Amount, subject to the provisions herein.
This statutory payment bond shall become null and void, if and when the Principal, its heirs,
executors, administrators, successors, or assigns shall pay all persons in accordance with RCW
Titles 39.08, and 39.12 including all workers, laborers, mechanics, subcontractors, and material
suppliers for the carrying on of such work, and all taxes incurred on said Contract under Title 50
and 51 RCW an all taxes imposed on the Principal under Title 82 RCW; and if such payment
obligations have not been fulfilled, this bond shall remain in full force and effect.
The Surety for value received agrees that no change, extension of time, alteration or addition to
the terms of the Contract, the specifications accompanying the Contract, or to the work to be
performed under the Contract shall in any way affect its obligation on this bond, except as
provided herein, and waives notice of any change, extension of time, alteration or addition to the
terms of the Contract or the work performed. The Surety agrees that modifications and changes
to the terms and conditions of the Contract that increase the total amount to be paid the Principal
shall automatically increase the obligation of the Surety on this bond and notice to Surety is not
required for such increased obligation.
This bond may be executed in two (2) original counterparts, and shall be signed by the parties’
duly authorized officers. This bond will only be accepted if it is accompanied by a fully executed
and original power of attorney for the officer executing on behalf of the surety.
PRINCIPAL SURETY
Principal Signature Date Surety Signature Date
Printed Name Printed Name
Title Title
Name, address, and telephone of local office/agent of Surety Company is:
Approved as to form:
___
Signature Title Date
Special Provisions
City of Pasco Special Provisions .............................................................................................................. SP-1
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-1
INTRODUCTION TO THE SPECIAL PROVISIONS 1
2
(August 14, 2013 APWA GSP) 3
4
The work on this project shall be accomplished in accordance with the Standard Specifications 5
for Road, Bridge and Municipal Construction, 2020 edition, as issued by the Washington State 6
Department of Transportation (WSDOT) and the American Public Works Association (APWA), 7
Washington State Chapter (hereafter “Standard Specifications”). The Standard Specifications, 8
as modified or supplemented by the Amendments to the Standard Specifications and these 9
Special Provisions, all of which are made a part of the Contract Documents, shall govern all of 10
the Work. 11
12
These Special Provisions are made up of both General Special Provisions (GSPs) from various 13
sources, which may have project-specific fill-ins; and project-specific Special Provisions. Each 14
Provision either supplements, modifies, or replaces the comparable Standard Specification, or is 15
a new Provision. The deletion, amendment, alteration, or addition to any subsection or portion 16
of the Standard Specifications is meant to pertain only to that particular portion of the section, 17
and in no way should it be interpreted that the balance of the section does not apply. 18
19
The project-specific Special Provisions are not labeled as such. The GSPs are labeled under 20
the headers of each GSP, with the effective date of the GSP and its source. For example: 21
22
(March 8, 2013 APWA GSP) 23
(April 1, 2013 WSDOT GSP) 24
(******) Project Specific Special Provisions 25
(June 26, 2020 COP GSP) 26
27
Also incorporated into the Contract Documents by reference are: 28
• Manual on Uniform Traffic Control Devices for Streets and Highways, currently adopted 29
edition, with Washington State modifications, if any 30
• Standard Plans for Road, Bridge and Municipal Construction, WSDOT/APWA, current 31
edition 32
• Pasco Municipal Code (PMC), A Codification of the General Ordinances 33
of the City of Pasco, Washington 34
35
Contractor shall obtain copies of these publications, at Contractor’s own expense. 36
37
DESCRIPTION OF WORK 38
(******) 39
40
This Contract provides for the improvement of a new water main, as replacement of the existing 41
water main, located in the broadly described alley East of South Wehe Avenue, between East 42
Alton Street and East Helena Street, installation of a fire hydrant and appurtenances, pavement 43
restoration along the alley way, and other work, all in accordance with the attached Contract 44
Plans, these Contract Provisions, and the Standard Specifications. 45
46
47
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-2
DIVISION 1 1
GENERAL REQUIREMENTS 2
3
1-01 Definitions and Terms 4
5
Definitions 6
(January 4, 2016 APWA GSP) 7
8
Delete the heading Completion Dates and the three paragraphs that follow it, and replace them 9
with the following: 10
11
Dates 12
Bid Opening Date 13
The date on which the City publicly opens and reads the Bids. 14
Award Date 15
The date of the formal decision of the City to accept the lowest responsible and 16
responsive Bidder for the Work. 17
Contract Execution Date 18
The date the City officially binds the Agency to the Contract. 19
Notice to Proceed Date 20
The date stated in the Notice to Proceed on which the Contract time begins. 21
Substantial Completion Date 22
The day the Engineer determines the City has full and unrestricted use and benefit of the 23
facilities, both from the operational and safety standpoint, any remaining traffic 24
disruptions will be rare and brief, and only minor incidental work, replacement of 25
temporary substitute facilities, plant establishment periods, or correction or repair 26
remains for the Physical Completion of the total Contract. 27
Physical Completion Date 28
The day all of the Work is physically completed on the project. All documentation 29
required by the Contract and required by law does not necessarily need to be furnished 30
by the Contractor by this date. 31
Completion Date 32
The day all the Work specified in the Contract is completed and all the obligations of the 33
Contractor under the contract are fulfilled by the Contractor. All documentation required 34
by the Contract and required by law must be furnished by the Contractor before 35
establishment of this date. 36
Final Acceptance Date 37
The date on which the City accepts the Work as complete. 38
39
(******) 40
Supplement this Section with the following: 41
42
All references in the Standard Specifications, Amendments, or WSDOT General Special 43
Provisions, to the terms “Department of Transportation”, “Washington State Transportation 44
Commission”, “Commission”, “Secretary of Transportation”, “Secretary”, “Headquarters”, and 45
“State Treasurer” shall be revised to read “City”. 46
47
All references to the terms “State” or “state” shall be revised to read “City” unless the 48
reference is to an administrative agency of the State of Washington, a State statute or 49
regulation, or the context reasonably indicates otherwise. 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-3
1
All references to “State Materials Laboratory” shall be revised to read “City designated 2
location”. 3
4
All references to “certification of completed public improvements” shall be interpreted to 5
mean the City form(s) by which final acceptance is granted. Public improvements shall be 6
deemed accepted by the City one year from the date of certification. 7
8
Additive 9
A supplemental unit of work or group of bid items, identified separately in the Bid Proposal, 10
which may, at the discretion of the City, be awarded in addition to the base bid. 11
12
Altern ate 13
One of two or more units of work or groups of bid items, identified separately in the Bid 14
Proposal, from which the City may make a choice between different methods or material of 15
construction for performing the same work. 16
17
Business Day 18
A business day is any day from Monday through Friday except holidays as listed in Section 19
1-08.5. 20
21
City 22
Means the City of Pasco, a municipal corporation, as represented by its authorized officials, 23
employees or agents, who is responsible for the execution and administration of the 24
Contract. 25
26
Contract Bond 27
The definition in the Standard Specifications for “Contract Bond” applies to whatever bond 28
form(s) are required by the Contract Documents, which may be a combination of a Payment 29
Bond and a Performance Bond. 30
31
Contract Time 32
The period of time established by the terms and conditions of the Contract within which the 33
Work must be physically completed. 34
35
Contractor 36
The individual, partnership, firm, corporation, or joint venture under contract with the City, 37
including but not limited to their employees, representatives, consultants, authorized 38
officials, or agents, to perform the construction of the public works improvements, and any 39
engineers hired by the before stated entity. 40
41
City Inspector 42
The Engineer’s representative who is responsible for inspecting the Contractor’s 43
performance in detail. Unless otherwise authorized by the City, the Inspector is not 44
responsible for the execution and administration of the Contract. 45
46
Notice of Award 47
The written notice from the City to the successful Bidder signifying the City’s acceptance of 48
the Bid Proposal. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-4
Notice to Proceed 1
The written notice from the City to the Contractor authorizing and directing the Contractor to 2
proceed with the Work and establishing the date on which the Contract time begins. 3
4
Standard Specifications 5
The latest edition of Standard Specifications for Road, Bridge, and Municipal Construction 6
prepared by the Washington State Department of Transportation, and amendments, and the 7
APWA GSP's for Division One that are, by this reference, made part of the Contract. Except 8
as may be amended, modified, or supplemented hereinafter, each section of the Standard 9
Specifications shall be considered part of the Contract. 10
11
Special Provisions 12
The Special Provisions supplement or modify the Standard Specifications and supersede 13
any conflicting provisions of the Standard Specifications for Road, Bridge, and Municipal 14
Construction and the appended amendments to the Standard Specifications and are made a 15
part the Contract. 16
17
Traffic 18
Both vehicular and non-vehicular traffic, such as pedestrians, bicyclists, wheelchairs, and 19
equestrian traffic. 20
21
1-02 BID PROCEDURES AND CONDITIONS 22
23
Prequalification of Bidders 24
25
Delete this section and replace it with the following: 26
27
1-02.1 Qualifications of Bidder 28
(January 24, 2011 APWA GSP) 29
30
Before award of a public works contract, a bidder must meet at least the minimum 31
qualifications of RCW 39.04.350(1) to be considered a responsible bidder and qualified 32
to be awarded a public works project. 33
34
Plans and Specifications 35
(******) 36
37
Delete this section and replace it with the following: 38
39
Information as to where Bid Documents can be obtained or reviewed can be found in the 40
Call for Bids (Advertisement for Bids) for the work. 41
42
After award of the contract, plans and specifications will be issued to the Contractor at no 43
cost as detailed below: 44
45
To Prime Contractor No. of Sets Basis of Distribution
Reduced plans (11" x 17") 2 Furnished automatically
upon award.
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-5
Contract Provisions
2 Furnished automatically
upon award.
Large plans (e.g., 22" x
34")
0 Furnished only upon
request.
1
Additional plans and Contract Provisions may be obtained by the Contractor from the source 2
stated in the Call for Bids, at the Contractor’s own expense. 3
4
1-02.4(1) General 5
(******) 6
7
The first sentence of the fourth to last paragraph is revised to read: 8
9
Any prospective Bidder desiring an explanation or interpretation of the Bid Documents, 10
shall request the explanation or interpretation in writing by close of business 3 business 11
days preceding the bid opening to allow a written reply to reach all prospective Bidders 12
before the submission of their Bids. 13
14
The second sentence of the fourth to last paragraph is revised to read: 15
16
Explanations, interpretations, or instructions given by anyone before the Award of a 17
Contract that are not in the form of an Addendum will not be binding on the City. 18
19
1-02.4(2) Subsurface Information 20
(March 8, 2013 APWA GSP) 21
22
The second sentence in the first paragraph is revised to read: 23
24
The Summary of Geotechnical Conditions and the boring logs, if and when included as 25
an appendix to the Special Provisions, shall be considered as part of the Contract. 26
27
Proposal Forms 28
(July 31, 2017 APWA GSP) 29
30
Delete this section and replace it with the following: 31
32
The Proposal Form will identify the project and its location and describe the work. It will also 33
list estimated quantities, units of measurement, the items of work, and the materials to be 34
furnished at the unit bid prices. The bidder shall complete spaces on the proposal form that 35
call for, but are not limited to, unit prices; extensions; summations; the total bid amount; 36
signatures; date; and, where applicable, retail sales taxes and acknowledgment of addenda; 37
the bidder’s name, address, telephone number, and signature; the bidder’s 38
UDBE/DBE/M/WBE commitment, if applicable; a State of Washington Contractor’s 39
Registration Number; and a Business License Number, if applicable. Bids shall be 40
completed by typing or shall be printed in ink by hand, preferably in black ink. The required 41
certifications are included as part of the Proposal Form. 42
43
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-6
The City reserves the right to arrange the proposal forms with alternates and additives, if 1
such be to the advantage of the City. The bidder shall bid on all alternates and additives set 2
forth in the Proposal Form unless otherwise specified. 3
4
Preparation of Proposal 5
(******) 6
7
Supplement the second paragraph with the following: 8
4. If a minimum bid amount has been established for any item, the unit or lump sum price 9
must equal or exceed the minimum amount stated. 10
5. Any correction to a bid made by interlineation, alteration, or erasure, shall be initialed by 11
the signer of the bid. 12
13
Delete the last three paragraphs, and replace them with the following: 14
15
If no Subcontractor is listed, the Bidder acknowledges that it does not intend to use any 16
Subcontractor to perform those items of work. 17
18
If provided by the City in the bid documents, the Bidder shall submit the Certification of 19
Wage Law Compliance form with their Proposal. If required, failure to return this certification 20
as part of the Bid Proposal will make their Bid Nonresponsive and ineligible for Award. 21
22
The Bidder shall make no stipulation on the Bid Proposal, nor qualify the bid in any manner. 23
24
A bid by a corporation shall be executed in the corporate name, by the president or a vice 25
president (or other corporate officer accompanied by evidence of authority to sign). 26
27
A bid by a partnership shall be executed in the partnership name, and signed by a partner. 28
A copy of the partnership agreement shall be submitted with the Bid Proposal if any UDBE 29
requirements are to be satisfied through such an agreement. 30
31
A bid by a joint venture shall be executed in the joint venture name and signed by a member 32
of the joint venture. A copy of the joint venture agreement shall be submitted with their Bid 33
Proposal if any UDBE requirements are to be satisfied through such an agreement. 34
35
Bid Deposit 36
(March 8, 2013 APWA GSP) 37
38
Supplement this section with the following: 39
40
Bid bonds shall contain the following: 41
1. City-assigned number for the project; 42
2. Name of the project; 43
3. The City named as obligee; 44
4. The amount of the bid bond stated either as a dollar figure or as a percentage which 45
represents five percent of the maximum bid amount that could be awarded; 46
5. Signature of the bidder’s officer empowered to sign official statements. The 47
signature of the person authorized to submit the bid should agree with the signature 48
on the bond, and the title of the person must accompany the said signature; 49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-7
6. The signature of the surety’s officer empowered to sign the bond and the power of 1
attorney. 2
3
If so stated in the Contract Provisions, bidder must use the bond form included in the 4
Contract Provisions. 5
6
If so stated in the Contract Provisions, cash will not be accepted for a bid deposit. 7
8
Delivery of Proposal 9
(December 19, 2019 APWA GSP, Option A) 10
11
Delete this section and replace it with the following: 12
13
Each Proposal shall be submitted in a sealed envelope, with the Project Name and Project 14
Number as stated in the Call for Bids clearly marked on the outside of the envelope, or as 15
otherwise required in the Bid Documents, to ensure proper handling and delivery. 16
17
To be considered responsive on a FHWA-funded project, the Bidder may be required to 18
submit the following items, as required by Section 1-02.6: 19
20
• UDBE Written Confirmation Document from each UDBE firm listed on the Bidder’s 21
completed UDBE Utilization Certification (WSDOT 272-056U) 22
• Good Faith Effort (GFE) Documentation 23
• UDBE Bid Item Breakdown (WSDOT 272-054) 24
• UDBE Trucking Credit Form (WSDOT 272-058) 25
26
These documents, if applicable, shall be received either with the Bid Proposal or as a 27
supplement to the Bid. These documents shall be received no later than 48 hours (not 28
including Saturdays, Sundays and Holidays) after the time for delivery of the Bid Proposal. 29
30
If submitted after the Bid Proposal is due, the document(s) must be submitted in a sealed 31
envelope labeled the same as for the Proposal, with “Supplemental Information” added. All 32
other information required to be submitted with the Bid Proposal must be submitted with the 33
Bid Proposal itself, at the time stated in the Call for Bids. 34
35
Proposals that are received as required will be publicly opened and read as specified in 36
Section 1-02.12. The City will not open or consider any Bid Proposal that is received after 37
the time specified in the Call for Bids for receipt of Bid Proposals, or received in a location 38
other than that specified in the Call for Bids. The City will not open or consider any 39
“Supplemental Information” (UDBE confirmations, or GFE documentation) that is received 40
after the time specified above, or received in a location other than that specified in the Call 41
for Bids. 42
43
If an emergency or unanticipated event interrupts normal work processes of the City so that 44
Proposals cannot be received at the office designated for receipt of bids as specified in 45
Section 1-02.12 the time specified for receipt of the Proposal will be deemed to be extended 46
to the same time of day specified in the solicitation on the first work day on which the normal 47
work processes of the City resume. 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-8
Withdrawing, Revising, or Supplementing Proposal 1
(July 23, 2015 APWA GSP) 2
3
Delete this section, and replace it with the following: 4
5
After submitting a physical Bid Proposal to the City, the Bidder may withdraw, revise, or 6
supplement it if: 7
8
1. The Bidder submits a written request signed by an authorized person and physically 9
delivers it to the place designated for receipt of Bid Proposals, and 10
2. The City receives the request before the time set for receipt of Bid Proposals, and 11
3. The revised or supplemented Bid Proposal (if any) is received by the City before the 12
time set for receipt of Bid Proposals. 13
14
If the Bidder’s request to withdraw, revise, or supplement its Bid Proposal is received 15
before the time set for receipt of Bid Proposals, the City will return the unopened Proposal 16
package to the Bidder. The Bidder must then submit the revised or supplemented package 17
in its entirety. If the Bidder does not submit a revised or supplemented package, then its 18
bid shall be considered withdrawn. 19
20
Late revised or supplemented Bid Proposals or late withdrawal requests will be date 21
recorded by the City and returned unopened. Mailed, emailed, or faxed requests to 22
withdraw, revise, or supplement a Bid Proposal are not acceptable. 23
24
Irregular Proposals 25
(December 19, 2019 APWA GSP) 26
27
Delete this section and replace it with the following: 28
29
1. A Proposal will be considered irregular and will be rejected if: 30
a. The Bidder is not prequalified when so required; 31
b. The authorized Proposal form furnished by the City is not used or is altered; 32
c. The completed Proposal form contains any unauthorized additions, deletions, 33
alternate Bids, or conditions; 34
d. The Bidder adds provisions reserving the right to reject or accept the award, or 35
enter into the Contract; 36
e. A price per unit cannot be determined from the Bid Proposal; 37
f. The Proposal form is not properly executed; 38
g. The Bidder fails to submit or properly complete a Subcontractor list, if applicable, 39
as required in Section 1-02.6; 40
h. The Bidder fails to submit or properly complete an Underutilized Disadvantaged 41
Business Enterprise Certification, if applicable, as required in Section 1-02.6; 42
i. The Bidder fails to submit written confirmation from each UDBE firm listed on the 43
Bidder’s completed UDBE Utilization Certification that they are in agreement with 44
the bidder’s UDBE participation commitment, if applicable, as required in Section 45
1-02.6, or if the written confirmation that is submitted fails to meet the 46
requirements of the Special Provisions; 47
j The Bidder fails to submit UDBE Good Faith Effort documentation, if applicable, 48
as required in Section 1-02.6, or if the documentation that is submitted fails to 49
demonstrate that a Good Faith Effort to meet the Condition of Award was made; 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-9
k. The Bidder fails to submit a UDBE Bid Item Breakdown form, if applicable, as 1
required in Section 1-02.6, or if the documentation that is submitted fails to meet 2
the requirements of the Special Provisions; 3
l. The Bidder fails to submit UDBE Trucking Credit Forms, if applicable, as required 4
in Section 1-02.6, or if the documentation that is submitted fails to meet the 5
requirements of the Special Provisions; 6
m. The Bid Proposal does not constitute a definite and unqualified offer to meet the 7
material terms of the Bid invitation; or 8
n. More than one Proposal is submitted for the same project from a Bidder under 9
the same or different names. 10
11
2. A Proposal may be considered irregular and may be rejected if: 12
a. The Proposal does not include a unit price for every Bid item; 13
b. Any of the unit prices are excessively unbalanced (either above or below the 14
amount of a reasonable Bid) to the potential detriment of the City; 15
c. Receipt of Addenda is not acknowledged; 16
d. A member of a joint venture or partnership and the joint venture or partnership 17
submit Proposals for the same project (in such an instance, both Bids may be 18
rejected); or 19
e. If Proposal form entries are not made in ink. 20
21
Disqualification of Bidders 22
(May 17, 2018 APWA GSP, Option A) 23
24
Delete this section and replace it with the following: 25
26
A Bidder will be deemed not responsible if the Bidder does not meet the mandatory bidder 27
responsibility criteria in RCW 39.04.350(1), as amended. 28
29
The City will verify that the Bidder meets the mandatory bidder responsibility criteria in RCW 30
39.04.350(1). To assess bidder responsibility, the City reserves the right to request 31
documentation as needed from the Bidder and third parties concerning the Bidder’s 32
compliance with the mandatory bidder responsibility criteria. 33
34
If the City determines the Bidder does not meet the mandatory bidder responsibility criteria 35
in RCW 39.04.350(1) and is therefore not a responsible Bidder, the City shall notify the 36
Bidder in writing, with the reasons for its determination. If the Bidder disagrees with this 37
determination, it may appeal the determination within two (2) business days of the City’s 38
determination by presenting its appeal and any additional information to the City. The City 39
will consider the appeal and any additional information before issuing its final determination. 40
If the final determination affirms that the Bidder is not responsible, the City will not execute a 41
contract with any other Bidder until at least two business days after the Bidder determined to 42
be not responsible has received the City’s final determination. 43
44
Pre Award Information 45
(August 14, 2013 APWA GSP) 46
47
Revise this section to read: 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-10
Before awarding any contract, the City may require one or more of these items or actions of 1
the apparent lowest responsible bidder: 2
1. A complete statement of the origin, composition, and manufacture of any or all 3
materials to be used, 4
2. Samples of these materials for quality and fitness tests, 5
3. A progress schedule (in a form the City requires) showing the order of and time 6
required for the various phases of the work, 7
4. A breakdown of costs assigned to any bid item, 8
5. Attendance at a conference with the Engineer or representatives of the Engineer, 9
6. Obtain, and furnish a copy of, a business license to do business in the city or county 10
where the work is located. 11
7. Any other information or action taken that is deemed necessary to ensure that the 12
bidder is the lowest responsible bidder. 13
14
1-03 AWARD AND EXECUTION OF CONTRACT 15
16
Consideration of Bids 17
(January 23, 2006 APWA GSP) 18
19
Revise the first paragraph to read: 20
21
After opening and reading proposals, the City will check them for correctness of extensions 22
of the prices per unit and the total price. If a discrepancy exists between the price per unit 23
and the extended amount of any bid item, the price per unit will control. If a minimum bid 24
amount has been established for any item and the bidder’s unit or lump sum price is less 25
than the minimum specified amount, the City will unilaterally revise the unit or lump sum 26
price, to the minimum specified amount and recalculate the extension. The total of 27
extensions, corrected where necessary, including sales taxes where applicable and such 28
additives and/or alternates as selected by the City, will be used by the City for award 29
purposes and to fix the Awarded Contract Price amount and the amount of the contract 30
bond. 31
32
Execution of Contract 33
(October 1, 2005 APWA GSP) 34
35
Revise this section to read: 36
37
Copies of the Contract Provisions, including the unsigned Form of Contract, will be available 38
for signature by the successful bidder on the first business day following award. The 39
number of copies to be executed by the Contractor will be determined by the City. 40
41
Within 10 calendar days after the award date, the successful bidder shall return the signed 42
City-prepared contract, an insurance certification as required by Section 1-07.18, and a 43
satisfactory bond as required by law and Section 1-03.4. Before execution of the contract 44
by the City, the successful bidder shall provide any pre-award information the City may 45
require under Section 1-02.15. 46
47
Until the City executes a contract, no proposal shall bind the City nor shall any work begin 48
within the project limits or within City-furnished sites. The Contractor shall bear all risks for 49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-11
any work begun outside such areas and for any materials ordered before the contract is 1
executed by the City. 2
3
If the bidder experiences circumstances beyond their control that prevents return of the 4
contract documents within the calendar days after the award date stated above, the City 5
may grant up to a maximum of 5 additional calendar days for return of the documents, 6
provided the City deems the circumstances warrant it. 7
8
Contract Bond 9
(July 23, 2015 APWA GSP) 10
11
Delete the first paragraph and replace it with the following: 12
13
The successful bidder shall provide executed payment and performance bond(s) for the full 14
contract amount. The bond may be a combined payment and performance bond; or be 15
separate payment and performance bonds. In the case of separate payment and 16
performance bonds, each shall be for the full contract amount. The bond(s) shall: 17
1. Be on City-furnished form(s); 18
2. Be signed by an approved surety (or sureties) that: 19
a. Is registered with the Washington State Insurance Commissioner, and 20
b. Appears on the current Authorized Insurance List in the State of Washington 21
published by the Office of the Insurance Commissioner, 22
3. Guarantee that the Contractor will perform and comply with all obligations, duties, and 23
conditions under the Contract, including but not limited to the duty and obligation to 24
indemnify, defend, and protect the City against all losses and claims related directly or 25
indirectly from any failure: 26
a. Of the Contractor (or any of the employees, Subcontractors, or lower tier 27
Subcontractors of the Contractor) to faithfully perform and comply with all contract 28
obligations, conditions, and duties, or 29
b. Of the Contractor (or the Subcontractors or lower tier Subcontractors of the 30
Contractor) to pay all laborers, mechanics, Subcontractors, lower tier 31
Subcontractors, material person, or any other person who provides supplies or 32
provisions for carrying out the work; 33
4. Be conditioned upon the payment of taxes, increases, and penalties incurred on the 34
project under titles 50, 51, and 82 RCW; and 35
5. Be accompanied by a power of attorney for the Surety’s officer empowered to sign the 36
bond; and 37
6. Be signed by an officer of the Contractor empowered to sign official statements (sole 38
proprietor or partner). If the Contractor is a corporation, the bond(s) must be signed by 39
the president or vice president, unless accompanied by written proof of the authority of 40
the individual signing the bond(s) to bind the corporation (i.e., corporate resolution, 41
power of attorney, or a letter to such effect signed by the president or vice president). 42
43
Judicial Review 44
(November 30, 2018 APWA GSP) 45
46
Revise this section to read: 47
48
Any decision made by the City regarding the Award and execution of the Contract or Bid 49
rejection shall be conclusive subject to the scope of judicial review permitted under 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-12
Washington Law. Such review, if any, shall be timely filed in the Superior Court of the 1
county where the City headquarters is located, provided that where an action is asserted 2
against a county, RCW 36.01.050 shall control venue and jurisdiction. 3
4
1-04 SCOPE OF THE WORK 5
6
Coordination of Contract Documents, Plans, Special Provisions, Specifications 7
and Addenda 8
(******) 9
10
Revise the second paragraph to read: 11
12
Any inconsistency in the parts of the contract shall be resolved by following this order of 13
precedence (e.g., 1 presiding over 2, 2 over 3, 3 over 4, and so forth): 14
15
1. Addenda, 16
2. Proposal Form, 17
3. Special Provisions, 18
4. Contract Plans, 19
5. Amendments to the Standard Specifications, 20
6. Standard Specifications, 21
7. WSDOT Standard Plans for Road, Bridge, and Municipal Construction. 22
23
Changes 24
(******) 25
26
Supplement this section with the following: 27
28
The Contractor is responsible for determining all work, scheduling and costs impacts caused 29
by changes, and shall include such when proposing the price and time for the change. No 30
subsequent requests for compensation or time will be accepted once the change has been 31
approved or the protest period [Section 1-04.5] expires. 32
33
No changes in the work covered by the approved Contract shall be made without having 34
prior written approval of the City. Note that submittal review does not constitute approval of 35
a change order. Changes shown on shop drawings or submittals only will not satisfy this 36
requirement. Work performed before a change is approved is at the Contractor’s risk, and at 37
the discretion of the City at the contractor’s expense. 38
39
Variation in Estimated Quantities 40
(******) 41
42
Supplement this section with the following: 43
44
The quantities listed in the unit price Bid Proposal are estimates for bidding purposes only. 45
There will be no adjustments in price due to increases or decreases in quantities regardless 46
of the magnitude. The 25 percent provisions of this Section 1-04.6 shall not apply to: All 47
Bid Items. Payment will be made at the unit contract price for actual quantities of work 48
completed. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-13
Differing Site Conditions (Changed Conditions) 1
(******) 2
3
Supplement this section with the following: 4
5
Depths are approximate and provided for informational purposes only. Contractor shall 6
verify the actual depths. Variation between the actual depth and the depth indicated on the 7
construction plans shall not constitute a changed condition. 8
9
The pipe diameters provided on the construction plans are the nominal pipe diameters. 10
Contractor shall measure all actual pipe diameters and lengths prior to ordering any 11
material. If a nominal pipe diameter is encountered that is different from the nominal 12
diameter shown on the construction plans, payment shall be per the unit price established 13
for the actual nominal pipe diameter. If no unit price is established for a given nominal pipe 14
diameter, payment shall be per section 1-04.4. 15
16
Final Cleanup 17
(June 26, 2020 COP GSP) 18
19
Delete this section and replace it with the following: 20
21
The Contractor shall perform final cleanup as provided in this section to the City’s 22
satisfaction. The date of acceptance will not be established until this is done. The material 23
sites and all ground the Contractor occupied to do the work shall be left neat and 24
presentable. The Contractor shall: 25
26
1. Remove all rubbish, surplus materials, discarded materials, falsework, temporary 27
structures, equipment, and debris, and 28
29
2. Deposit in embankments, or remove from the project, all unneeded, oversized rock 30
left from grading, surfacing, or paving. 31
32
Partial cleanup shall be done by the Contractor when they feel it is necessary or when, in 33
the opinion of the City, partial clean-up should be done prior to either major cleanup or final 34
inspection. 35
36
(June 26, 2020 COP GSP) 37
Add the following new section: 38
39
Waste Site 40
41
Where there is additional waste excavation in excess of that needed for the project and 42
in excess of that needed for compliance with requests of the City, the Contractor shall 43
secure and operate their own waste site at their own expense. The Contractor shall 44
also be required to secure and operate their own waste site at their own expense for 45
the disposal of all unsuitable material, asphalt, concrete, debris, or waste material, and 46
any other objectionable material which is directed to waste. 47
48
The Contractor shall comply with the State of Washington's regulations regarding 49
disposal of waste material as outlined in WAC 173-304, Subchapter 461. 50
51
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-14
1-05 CONTROL OF WORK 1
2
Authority of the Engineer 3
(June 26, 2020 COP GSP) 4
5
Supplement this section with the following: 6
7
Unless otherwise provided in the approved Contract, the means and methods of 8
construction shall be such as the Contractor may choose; subject, however, to the City’s 9
right to reject the means and methods proposed by the Contractor which (1) will constitute 10
or create a hazard to the work, or to persons or property; or (2) in the City’s opinion will not 11
produce finished work in accordance with the terms of the Contract. Approval of the 12
Contractor's means and methods of construction or their failure to exercise their right to 13
reject such means or methods shall not relieve the Contractor of the obligation to 14
accomplish the result intended by the Contract; nor shall the exercise of such right to reject 15
create a cause for action for damages. 16
17
(******) 18
Add the following new section: 19
20
1-05.3(1) Project Record Drawings 21
22
The Contractor shall maintain a neatly marked and legible red-lined set of plans and 23
specifications, which shall be updated at a minimum on a weekly basis, with all field 24
instruction, change orders, and construction adjustments. The Contractor’s red-lined 25
drawings/specifications shall be subject to the inspection of the City at all times. The 26
red-lined set of plans shall include all as-built survey information required in the 27
Contract. 28
29
The responsibility of preparing and maintaining Record Drawings shall be performed or 30
overseen by an experienced, and qualified individual. The quality of the Record 31
Drawings, in terms of accuracy, clarity, and completeness, is to be adequate to allow 32
the City to modify the computer-aided drafting (CAD) Contract Drawings to produce a 33
complete set of Record Drawings for the Contracting Agency without further 34
investigative effort by the Contracting Agency. 35
36
The Record Drawing markups shall document all changes in the Work, both concealed 37
and visible. Items that must be shown on the markups include but are not limited to: 38
39
• Actual Dimensions, arrangement, and materials used when different than shown 40
in the Plans. 41
• Changes made by Change Order or Field Order. 42
• Changes made by the Contractor. 43
• Accurate locations, both horizontally and vertically, of storm sewer, sanitary 44
sewer, water mains and other water appurtenances, structures, conduits, light 45
standards, vaults, width of roadways, sidewalks, landscaping area, building 46
footprints, channelization and pavement markings, etc. Include pipe invert 47
elevations, top of castings (manholes, inlets, etc.). 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-15
Drawings shall be subject to the inspection by the City at all times. Prior to acceptance 1
of the work, the Contractor shall deliver to the City one set of neatly marked record 2
drawings showing the information required above. Requests for partial payment will not 3
be approved if the marked-up prints are not kept current, and request for final payment 4
will not be approved until the fully complete marked-up prints are delivered to and 5
accepted by the City. 6
7
(******) 8
Add the following new section: 9
10
1-05.3(2) Measurement 11
12
The Bid item “RECORD DRAWINGS, MIN. BID $1,000.00” shall be measured as lump 13
sum (LS). 14
15
(******) 16
Add the following new section: 17
18
1-05.3(3) Payment 19
20
Payment will be made for each of the following Bid items that are included in the Proposal: 21
“RECORD DRAWINGS”, lump sum (LS). 22
23
The lump sum (LS) Contract price for “RECORD DRAWINGS, MIN. BID $1,000.00” shall 24
be for the full compensation of materials, equipment, and labor necessary to complete a 25
full set of Record Drawings as described in Section 1-05.3(1) of these Special Provisions, 26
except for those costs included in other items which are included in this Subsection and 27
which are included in the Proposal. 28
29
Conformity With and Deviations from Plans and Stakes 30
(******) 31
32
Supplement this section with the following: 33
34
Contractor Surveying - Roadway 35
36
The Contractor shall be responsible for setting, maintaining, and resetting all primary 37
survey control, alignment stakes, slope stakes, and grades necessary for the construction 38
of the roadbed, drainage, surfacing, paving, channelization and pavement marking, 39
illumination and signals, guardrails and barriers, and signing. Calculations, surveying, and 40
measuring required for setting and maintaining the necessary lines and grades shall be the 41
Contractor's responsibility. 42
43
The Contractor shall inform the Engineer when monuments are discovered that were not 44
identified in the Plans and construction activity may disturb or damage the monuments. All 45
monuments shall be protected throughout the length of the project or be replaced at the 46
Contractors expense. 47
48
Detailed survey records shall be maintained by the Contractor, including a description of 49
the work performed on each shift, the methods utilized, and the control points used. The 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-16
record shall be adequate to allow the survey to be reproduced. A copy of each day's record 1
shall be provided to the Engineer within three working days after the end of the shift. 2
3
The meaning of words and terms used in this provision shall be as listed in "Definitions of 4
Surveying and Associated Terms" current edition, published by the American Congress on 5
Surveying and Mapping and the American Society of Civil Engineers. 6
7
The survey work shall include but not be limited to the following: 8
9
1. Establish the primary horizontal and vertical control, and expand into secondary 10
control by adding stakes and hubs as well as additional survey control needed for 11
the project. Provide descriptions of secondary control to the Contracting Agency. 12
The description shall include coordinates and elevations of all secondary control 13
points. 14
15
2. Establish, the centerlines of all alignments, by placing hubs, stakes, or marks on 16
centerline or on offsets to centerline at all curve points (PCs, PTs, and PIs) and at 17
points on the alignments spaced no further than 50 feet. 18
19
3. Establish clearing limits, placing stakes at all angle points and at intermediate 20
points not more than 50 feet apart. The clearing and grubbing limits shall be 5 21
feet beyond the toe of a fill and 10 feet beyond the top of a cut unless otherwise 22
shown in the Plans. 23
24
4. Establish grading limits, placing slope stakes at centerline increments not more 25
than 50 feet apart. Establish offset reference to all slope stakes. If Global 26
Positioning Satellite (GPS) Machine Controls are used to provide grade control, 27
then slope stakes may be omitted at the discretion of the Contractor 28
29
5. Establish the horizontal and vertical location of all drainage features, placing offset 30
stakes to all drainage structures and to pipes at a horizontal interval not greater 31
than 25 feet. 32
33
6. Establish roadbed and surfacing elevations by placing stakes at the top of 34
subgrade and at the top of each course of surfacing. Subgrade and surfacing 35
stakes shall be set at horizontal intervals not greater than 50 feet in tangent 36
sections, 25 feet in curve sections with a radius less than 300 feet, and at 10-foot 37
intervals in intersection radii with a radius less than 10 feet. Transversely, stakes 38
shall be placed at all locations where the roadway slope changes and at additional 39
points such that the transverse spacing of stakes is not more than 12 feet. If GPS 40
Machine Controls are used to provide grade control, then roadbed and surfacing 41
stakes may be omitted at the discretion of the Contractor. 42
43
7. Establish intermediate elevation benchmarks as needed to check work throughout 44
the project. 45
46
8. Provide references for paving pins at 25-foot intervals or provide simultaneous 47
surveying to establish location and elevation of paving pins as they are being 48
placed. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-17
9. For all other types of construction included in this provision, (including but not 1
limited to channelization and pavement marking, illumination and signals, 2
guardrails and barriers, and signing) provide staking and layout as necessary to 3
adequately locate, construct, and check the specific construction activity. 4
5
10. Contractor shall determine if changes are needed to the profiles or roadway 6
sections shown in the Contract Plans in order to achieve proper smoothness and 7
drainage where matching into existing features, such as a smooth transition from 8
new pavement to existing pavement. The Contractor shall submit these changes 9
to the Engineer for review and approval 10 days prior to the beginning of work. 10
11
The Contractor shall provide the Contracting Agency copies of any calculations and staking 12
data when requested by the Engineer. 13
14
The Contractor shall ensure a surveying accuracy within the following tolerances: 15
16
Vertical Horizontal 17
Slope stakes ±0.10 feet ±0.10 feet 18
Subgrade grade stakes set 19
0.04 feet below grade ±0.01 feet ±0.5 feet 20
(parallel to alignment) 21
±0.1 feet 22
(normal to alignment) 23
24
Stationing on roadway N/A ±0.1 feet 25
Alignment on roadway N/A ±0.04 feet 26
Surfacing grade stakes ±0.01 feet ±0.5 feet 27
(parallel to alignment) 28
±0.1 feet 29
(normal to alignment) 30
31
Roadway paving pins for 32
surfacing or paving ±0.01 feet ±0.2 feet 33
(parallel to alignment) 34
±0.1 feet 35
(normal to alignment) 36
37
The Contracting Agency may spot-check the Contractor's surveying. These spot-checks 38
will not change the requirements for normal checking by the Contractor. 39
40
When staking roadway alignment and stationing, the Contractor shall perform independent 41
checks from different secondary control to ensure that the points staked are within the 42
specified survey accuracy tolerances. 43
44
The Contractor shall calculate coordinates for the alignment. The Contracting Agency will 45
verify these coordinates prior to issuing approval to the Contractor for commencing with the 46
work. The Contracting Agency will require up to seven calendar days from the date the 47
data is received. 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-18
Contract work to be performed using contractor-provided stakes shall not begin until the 1
stakes are approved by the Contracting Agency. Such approval shall not relieve the 2
Contractor of responsibility for the accuracy of the stakes. 3
4
Stakes shall be marked in accordance with Standard Plan A10.10. When stakes are 5
needed that are not described in the Plans, then those stakes shall be marked, at no 6
additional cost to the Contracting Agency as ordered by the Engineer. 7
8
GPS systems may be used by the Contractor, but physical reference points shall be 9
available for City Inspectors. 10
11
Payment 12
13
No separate payment will be Payment will be made for Roadway Surveying. All costs 14
associated with Roadway Surveying" will be considered incidental to other bid items. 15
16
17
Inspections of Work and Materials 18
(June 26, 2020 COP GSP) 19
20
Supplement this section with the following: 21
22
The City may not be on the job site full-time. The Contractor shall follow the approved 23
construction plans and specifications, schedule, and request inspections and testing at the 24
appropriate times as required herein. The Contractor shall provide a minimum two (2) 25
business days of notice to the City to request inspections and/or testing, but in no case 26
shall there be more than three (3) business days of notice. The request shall state the date 27
and approximate time the inspection and/or test is requested. Should the Contractor 28
request inspection and/or testing on short notice, the City will make every effort to 29
accommodate the Contractor’s request but no guarantees shall apply. The Contractor shall 30
prepare a project schedule and submit it to the City for review. The approved project 31
schedule shall also be used as a guide for the Contractor to schedule inspections. 32
33
The Contractor shall be prepared for Contractor-scheduled inspections. If over the 34
duration of the Contract the Contractor fails more than twice to be prepared for Contractor-35
scheduled inspections or tests, all subsequent costs associated with re-mobilizing 36
inspectors shall be borne by the Contractor. 37
38
At the beginning of the project, or each applicable construction activity, the Contractor shall 39
meet with City and establish a minimum 100 feet of product, in the field, which meets the 40
specifications. This work includes: Survey staking and control, pavement cuts, utility 41
trenches, trench bedding, pipe installation, backfill, patches, curb and gutter alignment, 42
grade and finish, sidewalk finish, paving finish, and any other activities determined by the 43
City to be important to the project. No major amount of work shall proceed until this is 44
established. This does not waive the Contractor’s requirements in the specifications for 45
quality control or materials used. 46
47
Inspections and testing are mandatory for acceptance of backfilling any utility trenches; 48
placing base course and top course for streets; paving; placing sidewalks, curbs and 49
gutters; storm, sewer and water line installation. 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-19
1
Removal of Defective and Unauthorized Work 2
(******) 3
4
Supplement this section with the following: 5
6
If the Contractor fails to remedy defective or unauthorized work within the time specified in a 7
written notice from the City, or fails to perform any part of the work required by the Contract 8
Documents, the City may correct and remedy such work as may be identified in the written 9
notice, with City forces or by such other means as the City may deem necessary. 10
11
If the Contractor fails to comply with a written order to remedy what the City determines to 12
be an emergency situation, the City may have the defective and unauthorized work 13
corrected immediately, have the rejected work removed and replaced, or have work the 14
Contractor refuses to perform completed by using City or other forces. An emergency 15
situation is any situation when, in the opinion of the City, a delay in its remedy could be 16
potentially unsafe, or might cause serious risk of loss or damage to the public. 17
18
Direct or indirect costs incurred by the City attributable to correcting and remedying 19
defective or unauthorized work, or work the Contractor failed or refused to perform, shall be 20
paid by the Contractor. Payment will be deducted by the City from monies due, or to 21
become due to the City by the Contractor. Such direct and indirect costs shall include in 22
particular, but without limitation, compensation for additional professional services required, 23
and costs for repair and replacement of work of others destroyed or damaged by correction, 24
removal, or replacement of the Contractor’s unauthorized work. 25
26
No adjustment in contract time or compensation will be allowed because of the delay in the 27
performance of the work attributable to the exercise of the City’s rights provided by this 28
Section. 29
30
The rights exercised under the provisions of this section shall not diminish the City’s right to 31
pursue any other avenue for additional remedy or damages with respect to the Contractor’s 32
failure to perform the work as required. 33
34
Supplement this section with the following: 35
(June 26, 2020 COP GSP) 36
37
For new roadway/street construction and overlays, HMA work rejected shall require the 38
replacement of the entire road or street width from block to block or as approved in writing 39
from the City. For trench patching, HMA work rejected shall require the replacement of the 40
entire patch width from block to block or as approved in writing from the Engineer. 41
42
(June 26, 2020 COP GSP) 43
Add the following new section: 44
45
Means and Methods 46
47
Unless otherwise provided in the Contract, the means and methods of construction 48
shall be such as the Contractor may choose; subject, however, to the City’s right to 49
reject means and methods proposed by the Contractor which (1) will constitute or 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-20
create a hazard to the work, or to persons or property; or (2) will not produce finished 1
work in accordance with the terms of the Contract. The Consultant's or City’s approval 2
of the Contractor's means and methods of construction or their failure to exercise their 3
right to reject such means or methods shall not relieve the Contractor of the obligation 4
to accomplish the result intended by the Contract; nor shall the exercise of such right to 5
reject create a cause for action for damages. 6
7
Guarantees 8
(June 26, 2020 COP GSP) 9
10
Delete this section and replace it with the following: 11
12
If defective and unauthorized materials or work is discovered within the guarantee timeframe 13
after the certification of completed public improvements date, the Contractor shall promptly, 14
upon written request, return and in accordance with the instructions either correct such 15
work, or if such work has been rejected, remove it from the Project Site and replace it with 16
non-defective and authorized work, all without cost to the City. If the Contractor does not 17
promptly comply with the written request to correct defective and unauthorized work, or if an 18
emergency exists, the City reserves the right to have defective and unauthorized work 19
corrected or rejected, removed, and replaced pursuant to the provisions of Section 1-05.7 of 20
the Standard Specifications. 21
22
Final Acceptance 23
24
Delete this section and replace it with the following: 25
26
1-05.11 Final Inspections and Operational Testing 27
(October 1, 2005 APWA GSP) 28
29
1-05.11(1) Substantial Completion Date 30
31
When the Contractor considers the work to be substantially complete, the Contractor shall 32
so notify the Engineer and request the Engineer establish the Substantial Completion Date. 33
The Contractor’s request shall list the specific items of work that remain to be completed in 34
order to reach physical completion. The Engineer will schedule an inspection of the work 35
with the Contractor to determine the status of completion. The Engineer may also establish 36
the Substantial Completion Date unilaterally. 37
38
If, after this inspection, the Engineer concurs with the Contractor that the work is 39
substantially complete and ready for its intended use, the Engineer, by written notice to the 40
Contractor, will set the Substantial Completion Date. If, after this inspection the Engineer 41
does not consider the work substantially complete and ready for its intended use, the 42
Engineer will, by written notice, so notify the Contractor giving the reasons therefor. 43
44
Upon receipt of written notice concurring in or denying substantial completion, whichever is 45
applicable, the Contractor shall pursue vigorously, diligently and without unauthorized 46
interruption, the work necessary to reach Substantial and Physical Completion. The 47
Contractor shall provide the Engineer with a revised schedule indicating when the 48
Contractor expects to reach substantial and physical completion of the work. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-21
The above process shall be repeated until the Engineer establishes the Substantial 1
Completion Date and the Contractor considers the work physically complete and ready for 2
final inspection. 3
4
1-05.11(2) Final Inspection and Physical Completion Date 5
6
When the Contractor considers the work physically complete and ready for final inspection, 7
the Contractor by written notice, shall request the Engineer to schedule a final inspection. 8
The Engineer will set a date for final inspection. The Engineer and the Contractor will then 9
make a final inspection and the Engineer will notify the Contractor in writing of all particulars 10
in which the final inspection reveals the work incomplete or unacceptable. The Contractor 11
shall immediately take such corrective measures as are necessary to remedy the listed 12
deficiencies. Corrective work shall be pursued vigorously, diligently, and without interruption 13
until physical completion of the listed deficiencies. This process will continue until the 14
Engineer is satisfied the listed deficiencies have been corrected. 15
16
If action to correct the listed deficiencies is not initiated within 7 days after receipt of the 17
written notice listing the deficiencies, the Engineer may, upon written notice to the 18
Contractor, take whatever steps are necessary to correct those deficiencies pursuant to 19
Section 1-05.7. 20
21
The Contractor will not be allowed an extension of contract time because of a delay in the 22
performance of the work attributable to the exercise of the Engineer’s right hereunder. 23
24
Upon correction of all deficiencies, the Engineer will notify the Contractor and the City, in 25
writing, of the date upon which the work was considered physically complete. That date 26
shall constitute the Physical Completion Date of the contract, but shall not imply acceptance 27
of the work or that all the obligations of the Contractor under the contract have been fulfilled. 28
29
1-05.11(3) Operational Testing 30
31
It is the intent of the City to have at the Physical Completion Date a complete and operable 32
system. Therefore when the work involves the installation of machinery or other mechanical 33
equipment; street lighting, electrical distribution or signal systems; irrigation systems; 34
buildings; or other similar work it may be desirable for the Engineer to have the Contractor 35
operate and test the work for a period of time after final inspection but prior to the physical 36
completion date. Whenever items of work are listed in the Contract Provisions for 37
operational testing they shall be fully tested under operating conditions for the time period 38
specified to ensure their acceptability prior to the Physical Completion Date. During and 39
following the test period, the Contractor shall correct any items of workmanship, materials, 40
or equipment which prove faulty, or that are not in first class operating condition. 41
Equipment, electrical controls, meters, or other devices and equipment to be tested during 42
this period shall be tested under the observation of the Engineer, so that the Engineer may 43
determine their suitability for the purpose for which they were installed. The Physical 44
Completion Date cannot be established until testing and corrections have been completed to 45
the satisfaction of the Engineer. 46
47
The costs for power, gas, labor, material, supplies, and everything else needed to 48
successfully complete operational testing, shall be included in the unit contract prices 49
related to the system being tested, unless specifically set forth otherwise in the proposal. 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-22
Operational and test periods, when required by the Engineer, shall not affect a 1
manufacturer’s guaranties or warranties furnished under the terms of the contract. 2
3
Add the following new section: 4
5
1-05.12(1) Warranty 6
(******) 7
8
The Contractor shall guarantee the work for a period of one year from the date of 9
acceptance against defects in the work as described in the construction drawings and 10
project specifications and otherwise set forth in the contract documents. Contractor shall 11
start work to remedy such defects within seven (7) days of mailing notice of discovery 12
thereof by the City and shall complete such work within a reasonable time. In 13
emergencies where damage may result from delay or where loss of service may result, 14
such corrections may be made by the City, in which case the cost shall be borne by 15
Contractor. In the event Contractor does not accomplish corrections at the time 16
specified, the work will be otherwise accomplished and the cost of same shall be paid by 17
Contractor. 18
19
The Contractor shall be liable for any costs, losses, expenses or damages including 20
consequential damages suffered by the City resulting from defects in the Contractor’s 21
work. This includes, but is not limited to the cost of Engineering, inspection, and 22
supervision by the City. The Contractor shall hold the City harmless from any and all 23
claims which may be made against the City as a result of any defective work and the 24
Contractor shall defend any such claims at their own expense. 25
26
Warranty does not cover damage due to misuse by the City or conditions outside of the 27
City or Contractor’s control or exceptional events (force majeure) including war, strikes, 28
floods (water exceeding normal high water mark), rainfall in excess of 100 year storm 29
event, fire, earthquakes, high winds (over 85 mph for 3 seconds peak gust), freezes 30
below minus 10 degrees Fahrenheit (Eastern Washington), governmental restrictions, 31
vandalism, and power failures or surges. The Contractor has control over workmanship, 32
third party subcontractors and parts and materials used to complete the project. 33
34
35
Superintendents, Labor, and Equipment of Contractor 36
(August 14, 2013 APWA GSP) 37
38
Delete the sixth and seventh paragraphs of this section. 39
40
Cooperation with Other Contractors 41
(June 26, 2020 COP GSP) 42
43
Supplement this section with the following: 44
45
No additional compensation will be given to the Contractor for any coordination or delays 46
caused by other nearby construction projects. 47
48
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-23
Method of Serving Notices 1
(March 25, 2009 APWA GSP) 2
3
Revise the second paragraph to read: 4
5
All correspondence from the Contractor shall be directed to the Project Engineer. All 6
correspondence from the Contractor constituting any notification, notice of protest, notice of 7
dispute, or other correspondence constituting notification required to be furnished under the 8
Contract, must be in paper format, hand delivered or sent via mail delivery service to the 9
Project Engineer's office. Electronic copies such as e-mails or electronically delivered 10
copies of correspondence will not constitute such notice and will not comply with the 11
requirements of the Contract. 12
13
(******) 14
Add the following new section: 15
Water and Power 16
17
Water Supply: The Contractor shall make necessary arrangements, and shall bear the 18
costs for water necessary for the performance of the work. Water for use on the projects 19
may be purchased from the City of Pasco, and the Contractor shall arrange for and 20
convey the water from the nearest convenient hydrant or other source at their own 21
expense. The hydrants shall be used in accordance with the City of Pasco Water 22
Department regulations. 23
24
If City water is used for any work related to a project, a fire hydrant meter and gate valve 25
will need to be obtained from the City of Pasco to be used specifically for this project. 26
The City will charge the Contractor for any water used during construction. The 27
Contractor shall not operate the hydrant as a gate valve, nor shall the Contractor be 28
allowed to operate any other City owned valve. The Contractor shall provide the 29
necessary back flow prevention device when connecting to the water service. The Fire 30
Hydrant Meter requirements and the Fire Hydrant Meter Application are available at the 31
Customer Service Window and the Engineering Department. 32
33
The City reserves the right to deny the use of fire hydrants where deemed inappropriate 34
by the City. 35
36
Power Supply: The Contractor shall make necessary arrangements, and shall bear the 37
costs for power necessary for the performance of the work. 38
39
(June 26, 2020 COP GSP) 40
Add the following new section: 41
42
Oral Agreements 43
44
The following new section shall be added to the Standard Specifications: 45
46
No oral agreement or conversation with any officer, agent, or employee of the City, either 47
before or after construction, shall affect or modify any of the terms or obligations 48
contained in any of the City-approved documents. Such oral agreement or 49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-24
conversation shall be considered as unofficial information and in no way binding upon 1
the City, unless subsequently put in writing and signed by the City. 2
3
1-06 CONTROL OF MATERIAL 4
5
Approval of Materials Prior to Use 6
(******) 7
8
Revise the first paragraph to read: 9
10
Product substitution requests shall be submitted by the Contractor to the City in advance of 11
associated submittals. 12
13
Prior to purchasing any materials for use, the Contractor shall submit documentation to the 14
City of all proposed material. The Contractor shall use the Request for Approval of Material 15
(RAM) form, WSDOT Form 350-071, which shall be provided to the City as a submittal. 16
Materials included in the WSDOT Qualified Products List (QPL) but not in the City’s 17
Construction Standards will be taken under consideration by use of the RAM form. 18
19
Submittal review is only for general conformance with the design concept and the 20
information given in the Contract Documents. Submittal review and the associated 21
comments do not constitute a complete verification of the submittal, and do not relieve the 22
Contractor from compliance with the Contract Documents. Review and approval of a 23
specific item shall not constitute review and approval of the associated assembly of which 24
the item is a component. The Contractor is responsible for compatibility of assembly 25
components. The Contractor is additionally responsible for: dimensions to be confirmed 26
and coordinated at the jobsite; information that pertains solely to the fabrication process or 27
to the means, methods, techniques, sequences and procedures of construction; 28
coordination of the work with that of all other trades, and performing all work safely and 29
with good workmanship. Any deviation from the Contract Documents by the Contractor 30
shall be clearly noted. Any such deviation not noted has not been reviewed. Any 31
fabrications or other work performed in advance of the receipt of approved submittals shall 32
be entirely at the Contractor’s risk and expense. 33
34
Submittal Process 35
36
Processing Time 37
38
Allow time for submittal review, including time for resubmittals, as follows. Time for review 39
shall commence on City’s receipt of submittal. No extension of the Contract time will be 40
authorized because of failure to transmit submittals enough in advance of the work to 41
permit processing, including resubmittals. 42
43
1. Initial Review : 44
Allow ten (10) working days for initial review of each submittal. Allow additional 45
time if coordination with subsequent submittals is required. City will advise 46
Contractor when a submittal being processed must be delayed for coordination. 47
2. Resubmittal Review: 48
Allow five (5) working days for review of each resubmittal. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-25
Submittal Response 1
2
The City will note the submittal status when responding to a submittal as follows: 3
4
1. Under Review 5
2. Approved: 6
If the review indicates that the submittal appears to be in conformance with the 7
Contract Documents, the submittal will be marked "APPROVED". The Contractor 8
may begin implementing the work method or incorporating the material or 9
equipment covered by the submittal. 10
3. Approved As Noted: 11
If the review indicates that the submittal is insufficient or that limited corrections are 12
required, the submittal will be marked "APPROVED AS NOTED". The Contractor 13
may begin implementing the work method or incorporating the material or 14
equipment covered by the submittal, in accordance with the noted corrections. 15
Where submittal information will be incorporated in operation and maintenance 16
plan, a corrected copy shall be provided within 30 days, otherwise no further action 17
will be required. 18
4. Revise & Resubmit: 19
If the review reveals that the submittal is substantially insufficient or contains 20
incorrect data to an extent that requires revision and re-review by the District prior 21
to proceeding with the associated work, the submittal will be marked "RESUBMIT" 22
and returned to the Contractor. This indicated that the Contractor should not 23
proceed with the relevant portion of work, at-risk or otherwise, until a revised 24
submittal has been submitted, reviewed, and accepted by the District as either 25
“APPROVED”, or “APPROVED AS NOTED.” 26
5. Rejected 27
6. N/A: 28
If the review reveals that the submittal is not required by the Contract Documents, 29
at the District’s discretion it may be returned by the District without action marked 30
“N/A” This does not constitute review of the submittal, and is only communicating 31
that District review of this submittal is not required by the Contract Documents. It is 32
the Contractor’s responsibility to follow up with the District if the Contractor needs 33
approval of information in a submittal that was marked “N/A.” 34
35
The Contract for the Work, as awarded, shall be on the basis of adhering to specifications 36
in the Contract Documents for Bid Items such as labor, materials, equipment, and/or 37
procedures. 38
39
Proposal by the Bidder for an “or-equal”, and/or “substitute”, to those items shall be 40
approved by the City and identified by an Addendum. 41
42
1-06.2(1) Samples and Tests for Acceptance 43
(******) 44
45
Supplement this section with the following: 46
47
The Contractor shall coordinate with the City and schedule all material and compaction 48
testing required by these special provisions, which will be paid for by the City. All costs 49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-26
associated with subsequent testing due to failure to meet acceptance criteria will be paid 1
by the Contractor. 2
3
Trench Backfill 4
5 The City will perform three (3) compaction tests, at varying depths, within the first one 6
hundred (100) feet of pipeline installed to establish compaction method. Once a 7
satisfactory method has been established by the Contractor, one test shall be performed 8
for each one hundred (100) linear feet of pipeline installed. Tests shall be taken at varying 9
depths along the trench. Compaction method shall be reestablished each time backfill 10
material, compaction equipment, or method of operation changes. 11
12
Roadway Subgrade 13
14
The City will perform two (2) compaction tests for the first ten thousand (10,000) square feet 15
and one (1) test for each additional ten thousand (10,000) square feet. 16
17
The City may request additional tests be performed at the Contractor's expense, if test 18
results do not meet the required subgrade densities. Subgrade compaction shall be as 19
specified for Roadway Embankment in Section 2-03.3(14)C, Method C. 20
21
Embankment 22
23 The City will perform two (2) compaction tests for the first one thousand (1,000) square feet 24
and one (1) test for each additional one thousand (1,000) square feet. Tests will be taken at 25
varying depths within the embankment. 26
27
The City may request additional tests be performed at the Contractor's expense, if test 28
results do not meet the required subgrade densities. Subgrade compaction shall be as 29
specified for Roadway Embankment in Section 2-03.3(14)C, Method C. 30
31
Ballast and Crushed Surfacing 32
33
The City will perform two (2) compaction tests for the first ten thousand (10,000) square feet 34
and one (1) test for each additional ten thousand (10,000) square feet. 35
36
The City may request additional tests be performed at the Contractor's expense, if test 37
results do not meet the required subgrade densities. Compaction of ballast and crushed 38
surfacing shall be as specified in Section 4-04.3(5). 39
40
Asphalt Pavement 41
42
Asphalt paving may not occur until successful compaction test results are achieved for 43
trench backfill, subgrade, embankment, ballast and crushed surfacing, as applicable. 44
45
The City may request additional tests be performed at the Contractor's/Developer’s 46
expense, if test results do not meet the required densities. Compaction of Hot Mix Asphalt 47
pavement shall be as specified in Section 5-04.3(10). 48
49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-27
Cement Concrete Curb, Gutter, and Sidewalk 1
2
A copy of the cement concrete design mix or certification from the concrete supplier that 3
the concrete provided has been prepared to the strength requirements in Section 8-04.3(1). 4
5
All testing procedures shall be conducted in accordance with applicable Sections of 6
Division 6-02 of the Standard Specifications and Sections 8-04 and 8-14 of these Special 7
Provisions. 8
9
1-06.2(2) Statistical Evaluations of Materials for Acceptance 10
(June 26, 2020 COP GSP) 11
12
Delete Section 1-06.2(2). 13
14
1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC 15
16
Laws to be Observed 17
(******) 18
19
Supplement this section with the following: 20
21
In cases of conflict between different safety regulations, the Contractor shall immediately 22
notify the City and proceed with subsequent direction given by the City. For bidding 23
purposes, assume the more stringent regulation shall apply. 24
25
The Washington State Department of Labor and Industries shall be the sole and 26
paramount administrative agency responsible for the administration of the provisions of the 27
Washington Industrial Safety and Health Act of 1973 (WISHA). 28
29
The Contractor shall be solely responsible for compliance with Occupational Safety and 30
Health Administration (OSHA) requirements on the jobsite. 31
32
The Contractor shall have sole responsibility for the safety, efficiency, and adequacy of the 33
Contractor’s plant, appliances, and methods, and for any damage or injury resulting from 34
their failure, or improper maintenance, use, or operation. The Contractor shall be solely 35
and completely responsible for the conditions of the project site, including safety for all 36
persons and property in the performance of the work. This requirement shall apply 37
continuously, and not be limited to normal working hours. The required or implied duty of 38
the City to conduct construction review of the Contractor’s performance does not, and shall 39
not, be intended to include review and adequacy of the Contractor’s safety measures in, 40
on, or near the project site. 41
42
The Contractor shall maintain at the project site office, or other well-known place at the 43
project site, all articles necessary for providing first aid to the injured. The Contractor shall 44
establish, publish, and make known to all employees, procedures for ensuring immediate 45
removal to a hospital, or doctor’s care, persons, including employees, who may have been 46
injured on the project site. Employees should not be permitted to work on the project site 47
before the Contractor has established and made known procedures for removal of injured 48
persons to a hospital or a doctor’s care. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-28
The Contractor shall comply with all applicable federal, state, and local laws and 1
requirements. 2
3
Amend the second sentence of the first paragraph to read: 4
5
The Contractor shall indemnify and save harmless the City of Pasco (including any agents, 6
officers, employees, and representatives) against any claims that may arise because the 7
Contractor (or any employee of the Contractor or Subcontractor or materialman) violated a 8
legal requirement. 9
10
(May 13, 2020 WSDOT GSP, Option 4) 11
Supplement this section with the following: 12
13
In response to COVID-19, the Contractor shall prepare a project specific COVID-19 health 14
and safety plan (CHSP) in conformance with Section 1-07.4(2) as supplemented in these 15
specifications, COVID-19 Health and Safety Plan (CHSP). 16
17
State Taxes 18
19
Delete this section, including its sub-sections, in its entirety and replace it with the following: 20
21
1-07.2 State Sales Tax 22
(June 27, 2011 APWA GSP) 23
24
The Washington State Department of Revenue has issued special rules on the State sales 25
tax. Sections 1-07.2(1) through 1-07.2(3) are meant to clarify those rules. The Contractor 26
should contact the Washington State Department of Revenue for answers to questions in 27
this area. The City will not adjust its payment if the Contractor bases a bid on a 28
misunderstood tax liability. 29
30
The Contractor shall include all Contractor-paid taxes in the unit bid prices or other contract 31
amounts. In some cases, however, state retail sales tax will not be included. Section 1-32
07.2(2) describes this exception. 33
34
The City will pay the retained percentage (or release the Contract Bond if a FHWA-funded 35
Project) only if the Contractor has obtained from the Washington State Department of 36
Revenue a certificate showing that all contract-related taxes have been paid (RCW 37
60.28.051). The City may deduct from its payments to the Contractor any amount the 38
Contractor may owe the Washington State Department of Revenue, whether the amount 39
owed relates to this contract or not. Any amount so deducted will be paid into the proper 40
State fund. 41
42
1-07.2(1) State Sales Tax — Rule 171 43
(June 27, 2011 APWA GSP) 44
45
WAC 458-20-171, and its related rules, apply to building, repairing, or improving streets, 46
roads, etc., which are owned by a municipal corporation, or political subdivision of the state, 47
or by the United States, and which are used primarily for foot or vehicular traffic. This 48
includes storm or combined sewer systems within and included as a part of the street or 49
road drainage system and power lines when such are part of the roadway lighting system. 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-29
For work performed in such cases, the Contractor shall include Washington State Retail 1
Sales Taxes in the various unit bid item prices, or other contract amounts, including those 2
that the Contractor pays on the purchase of the materials, equipment, or supplies used or 3
consumed in doing the work. 4
5
1-07.2(2) State Sales Tax — Rule 170 6
(June 27, 2011 APWA GSP) 7
8
WAC 458-20-170, and its related rules, apply to the constructing and repairing of new or 9
existing buildings, or other structures, upon real property. This includes, but is not limited to, 10
the construction of streets, roads, highways, etc., owned by the state of Washington; water 11
mains and their appurtenances; sanitary sewers and sewage disposal systems unless such 12
sewers and disposal systems are within, and a part of, a street or road drainage system; 13
telephone, telegraph, electrical power distribution lines, or other conduits or lines in or above 14
streets or roads, unless such power lines become a part of a street or road lighting system; 15
and installing or attaching of any article of tangible personal property in or to real property, 16
whether or not such personal property becomes a part of the realty by virtue of installation. 17
18
For work performed in such cases, the Contractor shall collect from the City, retail sales tax 19
on the full contract price. The City will automatically add this sales tax to each payment to 20
the Contractor. For this reason, the Contractor shall not include the retail sales tax in the 21
unit bid item prices, or in any other contract amount subject to Rule 170, with the following 22
exception. 23
24
Exception: The City will not add in sales tax for a payment the Contractor or a subContractor 25
makes on the purchase or rental of tools, machinery, equipment, or consumable supplies 26
not integrated into the project. Such sales taxes shall be included in the unit bid item prices 27
or in any other contract amount. 28
29
1-07.2(3) Services 30
(June 27, 2011 APWA GSP) 31
32
The Contractor shall not collect retail sales tax from the City on any contract wholly for 33
professional or other services (as defined in Washington State Department of Revenue 34
Rules 138 and 244). 35
36
Sanitation 37
38
1-07.4(2) Health Hazards 39
(******) 40
41
COVID-19 Health and Safety Plan (CHSP) 42
The Contractor shall prepare a project specific COVID-19 health and safety plan (CHSP). 43
The Contractor’s CHSP shall adhere to the most current State and Federal requirements 44
throughout the duration of the project. If the State and/or Federal requirements are revised, 45
the CHSP shall be updated as necessary to conform to the current requirements. The 46
CHSP shall be prepared by the Contractor prior to beginning physical Work and made 47
visible at the job site. 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-30
The Contractor shall update and resubmit the CHSP as the work progresses and new 1
activities appear on the look ahead schedule required under Section 1-08.3(2)D. If the 2
conditions change on the project, or a particular activity, the Contractor shall update and 3
resubmit the CHSP. Work on any activity shall cease if conditions prevent full compliance 4
with the CHSP. 5
6
The CHSP shall address the health and safety of all people associated with the project 7
including State workers in the field, Contractor personnel, consultants, project staff, 8
Subcontractors, suppliers and anyone on the project site, staging areas, or yards. The 9
CHSP shall: 10
11
1. Identify all standards, guidance, publications, and sources on which it is based. 12
Those standards may include references to the City’s current requirements, OSHA, 13
WISHA, and CDC publications that current at the time the CHSP is prepared. 14
15
2. Identify a responsible individual from the Contractor who is responsible for 16
implementation of the CHSP. The individual(s) contact information shall be listed in 17
the CHSP. 18
19
3. Identify the specific project for which it is applicable, and if applicable, shall address 20
project work areas outside the project limits such as staging areas and/or yards. 21
22
4. Identify the administrative and engineered controls necessary to maintain a safe site. 23
This includes, but is not limited to: personal protective equipment (PPE) needed to 24
protect workers from COVID-19, sanitation resources, screening stations, safety 25
briefings, and controlling access. 26
27
5. Identify measures for screening and managing workers or visitors to that enter and 28
leave the project site. The plan shall include procedures should a person exhibit 29
symptoms of COVID-19 at the project site. 30
31
6. Identify how the plan will be updated as new work activities are added with each two-32
week look-ahead schedule. The CHSP updates shall identify the number of workers, 33
crews, work tasks, and the degree of congestion or confinement workers will 34
experience for the work activities in the two-week look-ahead schedule. 35
36
7. Include how the Contractor will ensure everyone on the site has been trained on the 37
CHSP requirements. This includes Subcontractors, suppliers, and anyone on the 38
project site. 39
40
COVID-19 Health and Safety Plan (CHSP) Inspection 41
The Contractor shall grant full and unrestricted access to the City for CHSP Inspections. 42
The City will conduct periodic compliance inspections on the project site, staging areas, or 43
yards to verify that any ongoing work activity is following the CHSP plan. If the City 44
becomes aware of a noncompliance incident either through a site inspection or other 45
means, the Contractor will be notified immediately (within 1 hour). The Contractor shall 46
immediately remedy the noncompliance incident or suspend all or part of the associated 47
work activity. The Contractor shall satisfy the City that the noncompliance incident has been 48
corrected before the suspension will end. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-31
1
Environmental Regulations 2
3
1-07.5(1) General 4
(******) 5
6
Supplement this section with the following: 7
8
Dumping of material removed from catch basins and other storm drain structures into the 9
right of way, sanitary sewer or storm drain system is prohibited. 10
11
1-07.5(3) State Department of Ecology 12
(******) 13
14
Supplement this section with the following: 15
16
10. Comply with the requirements and special general conditions of the Construction 17
Stormwater General Permit issued by the Washington State Department of Ecology for 18
this project. 19
20
Contractor’s Responsibility for Work 21
22
1-07.13(1) General 23
(******) 24
25
Supplement this section with the following: 26
27
The Contractor is responsible for constructing and completing all work included in the 28
Contract in a professional manner with first-class workmanship. 29
30
The Contractor shall keep the City of Pasco informed in writing of the address to which 31
official correspondence is to be directed, the address and phone number of the person in 32
charge of their field personnel, and the address and telephone number of the Contractor's 33
representative who will be responsible and available outside of normal working hours for 34
emergency repairs and the maintenance of traffic control and safety devices. 35
36
1-07.16(1) Private/Public Property 37
(*****) 38
39
Supplement this section with the following: 40
41
Existing utilities and access to utilities may be located within easements on private property. 42
The City will assist the Contractor in gaining access to those existing utilities on private 43
property by notifying property owners of the intent to access the property. The Contractor 44
shall notify the City of any properties where access to an easement is required a minimum of 45
three (3) working days in advance of needing the access. The Contractor shall be 46
responsible to make arrangements for physical access and to remove or relocate any public 47
or private improvements impacting the project specific work. All improvements that are 48
removed or relocated shall be restored by the Contractor in accordance with this section. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-32
Utilities and Similar Facilities 1
(******) 2
3
Supplement this section with the following: 4
5
It shall be the Contractor’s responsibility to coordinate and schedule work with other local 6
utility companies where the work may impact their operations and/or existing infrastructure. 7
A list of contacts is provided below for informational purposes. Should any of the contacts 8
change throughout the duration of the project, the Contractor shall contact the City to 9
obtain alternate contact information. The Contractor is responsible for coordination in 10
advance of work with the contacts below to avoid delays. 11
12
Benton Franklin Transit
Richard Ciccone
ciccone@bft.org
1000 Columbia Park Trail
Richland, WA 99352
(509) 735-4131
(509) 735-1800 Fx
Big Bend Electric Cooperative
Duane Johnson
admin@bbec.org
PO Box 348
Ritzville, WA 99169
(866) 844-2363
(509) 659-1700
(509) 659-1404 Fx
BNRR
Jim Breene, Superintendent
PO Box 1309
Pasco, WA 99301
Bonneville Power Admin.
Stephanie Lorenz, Realty Specialist
selorenz@bpa.gov
Real Property Field Services
2211 N. Commercial Ave
Pasco, WA 99301
(509) 544-4748
Cascade Natural Gas
Arnie Garza
arnie.garza@cngc.com
8311 W. Grandridge Blvd.
Kennewick, WA 99336
(509) 735-7333
(509) 735-9141 Fx
Century Link
Tobias Mears
tobias.mears@centurylink.com
Sunnyside, WA
(509) 839-6651 - Office
(509) 305-7503 - Cell
Charter Communications
Antonio "Tony" Campos
Antonio.Campos@charter.com
639 N. Kellogg
Kennewick, WA 99336
(509) 572-0537 cell
Corps of Engineers
(509) 547-2048
(509) 547-6720 Fx
Chiawana Park Reservations for Pavillion
Janet
(509) 547-2048 #8
Ice Harbor
Lanelle Adams
(509) 543-6060
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-33
Dept. of Natural Resources
Mark Bonet
2211 Airport Rd.
Ellensburg, WA 98926
FCID-Franklin County Irrigation District
John Burns
fcid1@owt.com
jburn@pocketinet.com
PO Box 3907
Pasco, WA 99302
(509) 547-4912
(509) 545-1160 Fx
Fire Department (Pasco)
Chief Bob Gear
GEARB@pasco-wa.gov
509-543-5701
Franklin County Engineering Dept.
Craig Erdman, County Engineer
publicworks@co.franklin.wa.us
3416 Stearman Ave.
Pasco, WA 99301
(509) 545-3514
(509) 545-2133 Fx
Franklin County PUD
Aaron Gonzalez
agonzalez@franklinpud.com
PO Box 2407
Pasco, WA 99302
(509) 547-5591
(509) 547-4116 Fx
Williams Pipeline
Paul Fincher
paul.m.fincher@williams.com
606 S. Oregon Ave.
Pasco, WA 99301
(509) 544-9216
(509) 544-0866 Fx
1
It shall be the Contractor's responsibility to investigate and verify the presence and location of 2
all utilities prior to construction. 3
4
The Contractor shall call for field location, no sooner than 5 business days before the 5
scheduled date for commencement of excavation which may affect underground utility 6
facilities, unless otherwise agreed upon by the parties involved. A business day is defined 7
as any day other than Saturday, Sunday, or a legal local, state, or federal holiday. The 8
phone number for the Northwest Utility Notification Center for Pasco is 1-800-424-5555 (or 9
811). If no one-number locator service is available, notice shall be provided individually by 10
the Contractor to those owners known to or suspected of having underground facilities 11
within the area of proposed excavation. 12
13
The Contractor is alerted to the existence of Chapter 19.122 RCW, a law relating to 14
underground utilities. Any cost to the Contractor incurred as a result of this law shall be at 15
the Contractor's expense. 16
17
No excavation shall begin until all known facilities, in the vicinity of the excavation area, 18
have been located and marked. 19
20
In addition to the requirements of RCW 19.122, the Contractor shall use surface features 21
and other evidence in determining the approximate utility location prior to excavation. The 22
Contractor shall hand dig to expose known utilities. 23
24
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-34
Where the location of the work is in proximity to overhead wires and power lines, the 1
Contractor shall coordinate all work with the utility and shall provide for such measures as 2
may be necessary for the protection of workmen. 3
4
Only City personnel shall operate water system valves. 5
6
Public Liability and Property Damage Insurance 7
8
Delete this section in its entirety, and replace it with the following: 9
10
1-07.18 Insurance 11
(January 4, 2016 APWA GSP) 12
13
1-07.18(1) General Requirements 14
15
A. The Contractor shall procure and maintain the insurance described in all subsections of 16
section 1-07.18 of these Special Provisions, from insurers with a current A. M. Best 17
rating of not less than A-: VII and licensed to do business in the State of Washington. 18
The City reserves the right to approve or reject the insurance provided, based on the 19
insurer’s financial condition. 20
21
B. The Contractor shall keep this insurance in force without interruption from the 22
commencement of the Contractor’s Work through the term of the Contract and for thirty 23
(30) days after the Physical Completion date, unless otherwise indicated below. 24
25
C. If any insurance policy is written on a claims made form, its retroactive date, and that of 26
all subsequent renewals, shall be no later than the effective date of this Contract. The 27
policy shall state that coverage is claims made, and state the retroactive date. Claims-28
made form coverage shall be maintained by the Contractor for a minimum of 36 months 29
following the Completion Date or earlier termination of this Contract, and the Contractor 30
shall annually provide the City with proof of renewal. If renewal of the claims made form 31
of coverage becomes unavailable, or economically prohibitive, the Contractor shall 32
purchase an extended reporting period (“tail”) or execute another form of guarantee 33
acceptable to the City to assure financial responsibility for liability for services performed. 34
35
D. The Contractor’s Automobile Liability, Commercial General Liability and Excess or 36
Umbrella Liability insurance policies shall be primary and non-contributory insurance as 37
respects the City’s insurance, self-insurance, or self-insured pool coverage. Any 38
insurance, self-insurance, or self-insured pool coverage maintained by the City shall be 39
excess of the Contractor’s insurance and shall not contribute with it. 40
41
E. The Contractor shall provide the City and all additional insureds with written notice of 42
any policy cancellation, within two business days of their receipt of such notice. 43
44
F. The Contractor shall not begin work under the Contract until the required insurance has 45
been obtained and approved by the City 46
47
G. Failure on the part of the Contractor to maintain the insurance as required shall 48
constitute a material breach of contract, upon which the City may, after giving five 49
business days’ notice to the Contractor to correct the breach, immediately terminate the 50
Contract or, at its discretion, procure or renew such insurance and pay any and all 51
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-35
premiums in connection therewith, with any sums so expended to be repaid to the City 1
on demand, or at the sole discretion of the City, offset against funds due the Contractor 2
from the City. 3
4
H. All costs for insurance shall be incidental to and included in the unit or lump sum prices 5
of the Contract and no additional payment will be made. 6
7
(June 26, 2020 COP GSP) 8
Supplement this section with the following: 9
10
I. The Contractor shall obtain and maintain in full force and effect during the duration of 11
the work public liability and property damage insurance in accordance with this section 12
and as modified herein. 13
14
J. Prior to start of construction, the Contractor shall furnish the City of Pasco a Certificate 15
of Insurance and the additional insured endorsements as evidence of compliance with 16
these requirements. This certificate shall name the City of Pasco, its employees, 17
agents, elected and appointed officials, consultants, and all Subcontractors as 18
“additional insureds” and shall stipulate that the policies named thereon cannot be 19
canceled unless at least forty-five (45) days written notice has been given to the City of 20
Pasco. The certificate shall not contain the following or similar wording regarding 21
cancellation notification: “Failure to mail such notice shall impose no obligation or liability 22
of any kind upon the company, its agents, or representatives.” 23
24
1-07.18(2) Additional Insured 25
26
All insurance policies, with the exception of Workers Compensation, and of Professional 27
Liability and Builder’s Risk (if required by this Contract) shall name the following listed 28
entities as additional insured(s) using the forms or endorsements required herein: 29
the City and its officers, elected officials, employees, agents, and volunteers 30
City’s hired independent testing agency 31
32
The above-listed entities shall be additional insured(s) for the full available limits of liability 33
maintained by the Contractor, irrespective of whether such limits maintained by the 34
Contractor are greater than those required by this Contract, and irrespective of whether the 35
Certificate of Insurance provided by the Contractor pursuant to 1-07.18(4) describes limits 36
lower than those maintained by the Contractor. 37
38
For Commercial General Liability insurance coverage, the required additional insured 39
endorsements shall be at least as broad as ISO forms CG 20 10 10 01 for ongoing 40
operations and CG 20 37 10 01 for completed operations. 41
42
1-07.18(3) SubContractors 43
The Contractor shall cause each SubContractor of every tier to provide insurance coverage 44
that complies with all applicable requirements of the Contractor-provided insurance as set 45
forth herein, except the Contractor shall have sole responsibility for determining the limits of 46
coverage required to be obtained by SubContractors. 47
48
The Contractor shall ensure that all SubContractors of every tier add all entities listed in 49
1-07.18(2) as additional insureds, and provide proof of such on the policies as required by 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-36
that section as detailed in 1-07.18(2) using an endorsement as least as broad as ISO CG 1
20 10 10 01 for ongoing operations and CG 20 37 10 01 for completed operations. 2
3
Upon request by the City, the Contractor shall forward to the City evidence of insurance and 4
copies of the additional insured endorsements of each SubContractor of every tier as 5
required in 1-07.18(4) Verification of Coverage. 6
7
1-07.18(4) Verification of Coverage 8
The Contractor shall deliver to the City a Certificate(s) of Insurance and endorsements for 9
each policy of insurance meeting the requirements set forth herein when the Contractor 10
delivers the signed Contract for the work. Failure of City to demand such verification of 11
coverage with these insurance requirements or failure of City to identify a deficiency from 12
the insurance documentation provided shall not be construed as a waiver of Contractor’s 13
obligation to maintain such insurance. 14
15
Verification of coverage shall include: 16
1. An ACORD certificate or a form determined by the City to be equivalent. 17
2. Copies of all endorsements naming City and all other entities listed in 1-07.18(2) as 18
additional insured(s), showing the policy number. The Contractor may submit a copy of any 19
blanket additional insured clause from its policies instead of a separate endorsement. 20
3. Any other amendatory endorsements to show the coverage required herein. 21
4. A notation of coverage enhancements on the Certificate of Insurance shall not satisfy 22
these requirements – actual endorsements must be submitted. 23
24
Upon request by the City, the Contractor shall forward to the City a full and certified copy of 25
the insurance policy(s). If Builders Risk insurance is required on this Project, a full and 26
certified copy of that policy is required when the Contractor delivers the signed Contract for 27
the work. 28
29
1-07.18(5) Coverages and Limits 30
The insurance shall provide the minimum coverages and limits set forth below. Contractor’s 31
maintenance of insurance, its scope of coverage, and limits as required herein shall not be 32
construed to limit the liability of the Contractor to the coverage provided by such insurance, 33
or otherwise limit the City’s recourse to any remedy available at law or in equity. 34
35
All deductibles and self-insured retentions must be disclosed and are subject to approval by 36
the City. The cost of any claim payments falling within the deductible or self-insured 37
retention shall be the responsibility of the Contractor. In the event an additional insured 38
incurs a liability subject to any policy’s deductibles or self-insured retention, said deductibles 39
or self-insured retention shall be the responsibility of the Contractor. 40
41
1-07.18(5)A Commercial General Liability 42
Commercial General Liability insurance shall be written on coverage forms at least as broad 43
as ISO occurrence form CG 00 01, including but not limited to liability arising from premises, 44
operations, stop gap liability, independent Contractors, products-completed operations, 45
personal and advertising injury, and liability assumed under an insured contract. There shall 46
be no exclusion for liability arising from explosion, collapse or underground property 47
damage. 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-37
The Commercial General Liability insurance shall be endorsed to provide a per project 1
general aggregate limit, using ISO form CG 25 03 05 09 or an equivalent endorsement. 2
3
Contractor shall maintain Commercial General Liability Insurance arising out of the 4
Contractor’s completed operations for at least three years following Substantial Completion 5
of the Work. 6
7
Such policy must provide the following minimum limits: 8
$2,000,000 Each Occurrence 9
$2,000,000 General Aggregate 10
$2,000,000 Products & Completed Operations Aggregate 11
$1,000,000 Personal & Advertising Injury each offence 12
$1,000,000 Stop Gap / Employers’ Liability each accident 13
14
1-07.18(5)B Automobile Liability 15
Automobile Liability shall cover owned, non-owned, hired, and leased vehicles; and shall be 16
written on a coverage form at least as broad as ISO form CA 00 01. If the work involves the 17
transport of pollutants, the automobile liability policy shall include MCS 90 and CA 99 48 18
endorsements. 19
20
Such policy must provide the following minimum limit: 21
$1,000,000 Combined single limit each accident 22
23
1-07.18(5)C Workers’ Compensation 24
The Contractor shall comply with Workers’ Compensation coverage as required by the 25
Industrial Insurance laws of the State of Washington. 26
27
Public Convenience and Safety 28
(******) 29
30
Supplement this section with the following: 31
32
All work shall be carried out with due regard for public safety. For any open trenches, the 33
Contractor shall provide proper barricades and adequate night-time illumination. 34
35
At access points to public and private properties access shall be provided by the 36
Contractor throughout the duration of construction unless otherwise approved by the City. 37
38
The Contractor shall contact all resident, tenants, and property owners in the immediate 39
vicinity of the scheduled work via door hanger or a mailing a minimum of seven (7) calendar 40
days in advance of beginning work in the area. The door hanger or mailing shall be printed 41
in both English and Spanish and shall contain the following information at a minimum: 42
43
• Project Name 44
• Description of the work being performed 45
• Exact area to be affected by the work 46
• Date work is to commence 47
• Date work will be completed 48
• Company name, contact person & phone number 49
• Contractors local contact person name & local phone number 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-38
• Contractors superintendent name & phone number (if different) 1
• Services that may be impacted 2
• Restrictions during work (such as advising against water usage) 3
4
In addition, 24 hours in advance of a utility shut-down, the Contractor shall informing the 5
resident or tenant of the time period of the possible interruption to the utility service and 6
advise against water usage during this period. The notice shall be in the form of a door 7
hanger printed in both English and Spanish. 8
9
The Contractor shall submit both the 7-day notice and the 24-hour notice to the City for 10
review prior to delivering any notice to a resident, tenant, or property owner. 11
12
The Contractor shall be responsible to coordinate all construction efforts with the following 13
entities: 14
15
• Benton-Franklin Health District 16
• Benton-Franklin Transit 17
• Pasco School District 18
• Pasco Fire Department 19
• Pasco Police Department and all other law enforcement divisions 20
• United States Postal Service 21
• Basin Disposal Incorporated 22
• City of Pasco Public Works and all other Utility owners/operators 23
24
The Contractor must notify an affected property owner or occupant and the City 25
immediately upon the accidental disruption of any public or private service. The disrupted 26
service shall be restored the same day as the disruption occurred. 27
28
1-07.23(1) Construction Under Traffic 29
(February 3, 2020 WSDOT GSP) 30
31
Supplement this section with the following: 32
33
Work Zone Clear Zone 34
35
The Work Zone Clear Zone (WZCZ) applies during working and nonworking hours. The 36
WZCZ applies only to temporary roadside objects introduced by the Contractor’s operations 37
and does not apply to preexisting conditions or permanent Work. Those work operations 38
that are actively in progress shall be in accordance with adopted and approved Traffic 39
Control Plans, and other contract requirements. 40
41
During nonworking hours equipment or materials shall not be within the WZCZ unless they 42
are protected by permanent guardrail or temporary concrete barrier. The use of temporary 43
concrete barrier shall be permitted only if the Engineer approves the installation and 44
location. 45
46
During actual hours of work, unless protected as described above, only materials absolutely 47
necessary to construction shall be within the WZCZ and only construction vehicles 48
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-39
absolutely necessary to construction shall be allowed within the WZCZ or allowed to stop or 1
park on the shoulder of the roadway. 2
3
The Contractor's nonessential vehicles and employees private vehicles shall not be 4
permitted to park within the WZCZ at any time unless protected as described above. 5
6
Deviation from the above requirements shall not occur unless the Contractor has requested 7
the deviation in writing and the Engineer has provided written approval. 8
9
Minimum WZCZ distances are measured from the edge of traveled way and will be 10
determined as follows: 11
12
Regulatory
Posted Speed
Distance From
Traveled Way
(Feet)
35 mph or less 10
40 mph 15
45 to 50 mph 10
55 to 60 mph 30
65 mph or greater 35
13
Minimum Work Zone Clear Zone Distance 14
15
Rights of Way 16
(******) 17
18
Delete this section and replace it with the following: 19
20
Street Right of Way lines, limits of easements, and limits of construction permits are 21
indicated in the Plans. The Contractor’s construction activities shall be confined within these 22
limits, unless arrangements for use of private property are made. 23
24
The City has obtained all rights of way and easements deemed necessary for the completed 25
facility and direct construction work. 26
27
Whenever any of the work is accomplished on or through property other than public Right of 28
Way, the Contractor shall meet and fulfill all covenants and stipulations of any easement 29
agreement obtained by the City from the owner of the private property. Copies of the 30
easement agreements may be included in the Contract Provisions or made available to the 31
Contractor as soon as practical after they have been obtained by the City. 32
33
Whenever easements or rights of entry have not been acquired prior to advertising, these 34
areas are so noted in the Plans. The Contractor shall not proceed with any portion of the 35
work in areas where right of way, easements or rights of entry have not been acquired until 36
the City certifies to the Contractor that the right of way or easement is available or that the 37
right of entry has been received. If the Contractor is delayed due to acts of omission on the 38
part of the City in obtaining easements, rights of entry or right of way, the Contractor will be 39
entitled to an extension of time. The Contractor agrees that such delay shall not be a 40
breach of contract. 41
42
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-40
The Contractor shall notify each property owner two (2) business days prior to entry. This 1
includes entry onto easements and private property where private improvements must be 2
adjusted. 3
4
Rights of way and easements obtained by the City are not guaranteed to include the amount or location of land 5
desired by the Contractor to support all of the Contractor’s activities. The Contractor shall be 6
responsible for providing, without expense or liability to the City, any additional land and 7
access thereto that the Contractor may desire for temporary construction facilities, storage 8
of materials, or other Contractor needs. However, before using any private property, 9
whether adjoining the work or not, the Contractor shall file with the City a written permission 10
of the private property owner, and, upon vacating the premises, a written release from the 11
property owner of each property disturbed or otherwise interfered with by reasons of 12
construction pursued under this contract. The statement shall be signed by the private 13
property owner, or proper authority acting for the owner of the private property affected, 14
stating that permission has been granted to use the property and all necessary permits have 15
been obtained or, in the case of a release, that the restoration of the property has been 16
satisfactorily accomplished. The statement shall include the parcel number, address, and 17
date of signature. Written releases must be filed with the City before the Completion Date 18
will be established. 19
20
(June 26, 2020 COP GSP) 21
Add the following new section: 22
23
Safety Standards 24
25
All work shall be performed in accordance with all applicable local, state, and federal 26
health and safety codes, standards, regulations, and/or accepted industry standards. It 27
shall be the responsibility of the Contractor to ensure that their work force, the City, and 28
the public are adequately protected against any hazards. 29
30
The City shall have the authority at all times to issue a stop work order at no penalty if, in 31
their opinion, working conditions present an undue hazard to the public, property, or the 32
work force. Such authority shall not, however, relieve the Contractor of responsibility for 33
the maintenance of safe working conditions or assess any responsibility to the City or 34
Contractor for the identification of any or all unsafe conditions. 35
36
(******) 37
Add the following new section: 38
39
Notifying Property Owners 40
41
When construction activities cause there to be temporary or modified ingress and/or 42
egress to a property along the project alignment, the Contractor shall be responsible for 43
notifying the occupant(s) of the property three (3) business days prior to the work. If the 44
Contractor is unable to contact the occupant(s), the Contractor shall leave written 45
notification at least one (1) business day prior to the work. A copy of all notifications 46
shall be provided to the City. 47
48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-41
1-08 PROSECUTION AND PROGRESS 1
2
Add the following new section: 3
4
Preliminary Matters 5
(May 25, 2006 APWA GSP) 6
7
Add the following new section: 8
9
1-08.0(1) Preconstruction Conference 10
(******) 11
12
Prior to the commencement of any work, a preconstruction conference shall be held. The 13
Contractor shall contact the City and set a date and time for the meeting. It shall be the 14
responsibility of the Contractor to notify and invite all parties having an interest in the 15
project to the meeting, including the City, major subcontractors, Irrigation Districts, and all 16
applicable private utilities. The Contractor shall ensure they understand all provisions and 17
intentions of the work. 18
19
The purpose of the preconstruction conference will be: 20
1. Overall scope 21
2. Order and coordination of work 22
3. Long lead time items 23
4. Means and methods of construction 24
5. Inspection and reporting procedures 25
6. To review the initial schedule; 26
7. To establish a working understanding among the various parties associated or 27
affected by the work; 28
8. To establish and review procedures for progress payment, notifications, approvals, 29
submittals, etc.; 30
9. To establish normal working hours for the work; 31
10. To review safety standards and traffic control; and 32
11. To discuss such other related items as may be pertinent to the work. 33
12. To walk the project site and confirm which if any objects are to be removed and 34
replaced. 35
13. Protection of features to remain in place for the duration of construction. 36
14. Dust control equipment and procedures. 37
38
The Contractor shall prepare and submit at least five (5) business days prior to the 39
preconstruction conference the following: 40
1. A breakdown of all lump sum items; 41
2. A preliminary schedule of working drawing submittals; and 42
3. A list of material sources for approval if applicable. 43
44
Any proposed road or sidewalk closures shall be presented to the City at the 45
preconstruction conference for consideration, including duration of closure. If approved, 46
closures shall not extend beyond permitted duration. Should closures extend beyond the 47
duration, road user delay costs shall be assessed to the Contractor and paid to the City of 48
Pasco. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-42
Add the following new section: 1
2
1-08.0(2) Hours of Work 3
(December 8, 2014 APWA GSP) 4
5
Except in the case of emergency or unless otherwise approved by the Engineer, the normal 6
working hours for the Contract shall be any consecutive 8-hour period between 7:00 a.m. 7
and 6:00 p.m. Monday through Friday, exclusive of a lunch break. If the Contractor desires 8
different than the normal working hours stated above, the request must be submitted in 9
writing prior to the preconstruction conference, subject to the provisions below. The working 10
hours for the Contract shall be established at or prior to the preconstruction conference. 11
12
All working hours and days are also subject to local permit and ordinance conditions (such 13
as noise ordinances). 14
15
If the Contractor wishes to deviate from the established working hours, the Contractor shall 16
submit a written request to the City for consideration. This request shall state what hours 17
are being requested, and why. Requests shall be submitted for review no later than 5 18
business days prior to the day(s) the Contractor is requesting to change the hours. 19
20
If the City approves such a deviation, such approval may be subject to certain other 21
conditions, which will be detailed in writing. For example: 22
1. On non-Federal aid projects, requiring the Contractor to reimburse the City for the 23
costs in excess of straight-time costs for City representatives who worked during 24
such times. (The Engineer may require designated representatives to be present 25
during the work. Representatives who may be deemed necessary by the Engineer 26
include, but are not limited to: survey crews; personnel from the City’s material 27
testing lab; inspectors; and other City employees or third party consultants when, in 28
the opinion of the Engineer, such work necessitates their presence.) 29
2. Considering the work performed on Saturdays, Sundays, and holidays as working 30
days with regard to the contract time. 31
3. Considering multiple work shifts as multiple working days with respect to contract 32
time even though the multiple shifts occur in a single 24-hour period. 33
4. If Davis Bacon wage rates apply to this Contract, all requirements must be met and 34
recorded properly on certified payroll. 35
36
(******) 37
Add the following new section: 38
39
1-08.0(3) Days of Work 40
41
No work will be allowed on the following days unless pre-approval is obtained from the City: 42
43
• New Years Day, Martin Luther King Jr., President’s Day, Memorial Day, July 4th, 44
• Labor Day, Veteran’s Day, Thanksgiving and the day after, Christmas and the day 45
after. 46
• If any of the above days falls on a Saturday, the preceding Friday. If any of the 47
above days falls on a Sunday, the following Monday. 48
• All Saturdays and Sundays. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-43
Requests to work on any of the days listed above must be made in writing by the Contractor 1
to the City for review no less than two weeks prior to the event and include the reason for 2
the request. Approval of any such request is not guaranteed. If approval is given, each day 3
may be counted as a working day at the discretion of the City. 4
5
Subcontracting 6
(May 30, 2019 APWA GSP, Option B) 7
8
Delete the ninth paragraph, beginning with “On all projects, the Contractor shall certify…”. 9
10
1-08.3(1) General Requirements 11
(******) 12
13
Supplement this section with the following: 14
15
Items in the schedule shall be arranged in the order and sequence in which they will be 16
performed. The schedule shall be drawn to a time scale, using an appropriate 17
measurement per day with weekends and holidays indicated. The schedule shall be 18
continuously updated and, if necessary, redrawn upon the first working day of each month 19
or upon issuance of any change order which substantially affects the schedule. Copies (2 20
prints or 1 reproducible) of newly updated schedules shall be provided to the City. 21
22
When the Contract Work has progressed to Substantial Completion as defined in the 23
Contract, the City may determine that the work is Substantially Complete. The City will 24
notify the Contractor in writing of the Substantial Completion Date. 25
26
The Contractor shall complete the remaining Work as promptly as possible. Upon request 27
by the City, the Contractor shall furnish a written schedule for completing the physical Work 28
on the Contract. 29
30
1-08.3(2)A Type A Progress Schedule 31
(March 13, 2012 APWA GSP) 32
33
Revise this section to read: 34
35
The Contractor shall submit 2 copies of a Type A Progress Schedule to the City no later than 36
5 business days prior to the preconstruction conference, or some other mutually agreed 37
upon time. The schedule shall be in a format acceptable to the City. The City may at their 38
discretion allow a critical path method (CPM) schedule, bar chart, or other standard 39
schedule format. Regardless of which format used, the schedule shall identify the critical 40
path. The Engineer will evaluate the Type A Progress Schedule and approve or return the 41
schedule for corrections within 15 calendar days of receiving the submittal. 42
43
1-08.3(2)D Weekly Look-Ahead Schedule 44
(******) 45
46
Supplement this section with the following: 47
48
At the discretion of the City, a weekly meeting between representatives of the City (e.g. 49
inspector and/or engineer) and Contractor (foreman, supervisor, and/or project manager) 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-44
shall be held at the project site or at City Hall at a pre-determined time. The Contractor shall 1
present an update on project status, project schedule, and any problems that have arisen. 2
3
Prosecution of Work 4
5
Delete this section and replace it with the following: 6
7
1-08.4 Notice to Proceed and Prosecution of Work 8
(July 23, 2015 APWA GSP) 9
10
Notice to Proceed will be given after the contract has been executed and the contract bond 11
and evidence of insurance have been approved and filed by the City. The Contractor shall 12
not commence with the work until the Notice to Proceed has been given by the Engineer. 13
The Contractor shall commence construction activities on the project site within ten days of 14
the Notice to Proceed Date, unless otherwise approved in writing. The Contractor shall 15
diligently pursue the work to the physical completion date within the time specified in the 16
contract. Voluntary shutdown or slowing of operations by the Contractor shall not relieve the 17
Contractor of the responsibility to complete the work within the time(s) specified in the 18
contract. 19
20
When shown in the Plans, the first order of work shall be the installation of high visibility 21
fencing to delineate all areas for protection or restoration, as described in the Contract. 22
Installation of high visibility fencing adjacent to the roadway shall occur after the placement 23
of all necessary signs and traffic control devices in accordance with 1-10.1(2). Upon 24
construction of the fencing, the Contractor shall request the City to inspect the fence. No 25
other work shall be performed on the site until the City has accepted the installation of high 26
visibility fencing, as described in the Contract. 27
28
Time for Completion 29
30
Supplement this section with the following: 31
32
(March 13, 1995 WSDOT GSP) 33
This project shall be physically completed within 20 working days. Substantial completion 34
does not stop contract time. 35
36
(November 30, 2018 APWA GSP, Option A) 37
38
Revise the third and fourth paragraphs to read: 39
40
Contract time shall begin on the first working day following the Notice to Proceed Date. 41
42
Each working day shall be charged to the contract as it occurs, until the contract work is 43
physically complete. If substantial completion has been granted and all the authorized 44
working days have been used, charging of working days will cease. Each week the 45
Engineer will provide the Contractor a statement that shows the number of working days: (1) 46
charged to the contract the week before; (2) specified for the physical completion of the 47
contract; and (3) remaining for the physical completion of the contract. The statement will 48
also show the nonworking days and any partial or whole day the City declares as 49
unworkable. Within 10 calendar days after the date of each statement, the Contractor shall 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-45
file a written protest of any alleged discrepancies in it. To be considered by the City, the 1
protest shall be in sufficient detail to enable the Engineer to ascertain the basis and amount 2
of time disputed. By not filing such detailed protest in that period, the Contractor shall be 3
deemed as having accepted the statement as correct. If the Contractor is approved to work 4
10 hours a day and 4 days a week (a 4-10 schedule) and the fifth day of the week in which a 5
4-10 shift is worked would ordinarily be charged as a working day then the fifth day of that 6
week will be charged as a working day whether or not the Contractor works on that day 7
unless otherwise approved by the City in writing. 8
9
Revise the sixth paragraph to read: 10
11
The Engineer will give the Contractor written notice of the completion date of the contract 12
after all the Contractor’s obligations under the contract have been performed by the 13
Contractor. The following events must occur before the Completion Date can be 14
established: 15
16
1. The physical work on the project must be complete; and 17
2. The Contractor must furnish all documentation required by the contract and required by 18
law, to allow the City to process final acceptance of the contract. The following 19
documents must be received by the Project Engineer prior to establishing a completion 20
date: 21
a. Certified Payrolls (per Section 1-07.9(5)). 22
b. Material Acceptance Certification Documents 23
c. Monthly Reports of Amounts Credited as DBE Participation, as required by 24
the Contract Provisions. 25
d. Final Contract Voucher Certification 26
e. Copies of the approved “Affidavit of Prevailing Wages Paid” for the Contractor 27
and all Subcontractors 28
f. A copy of the Notice of Termination sent to the Washington State Department 29
of Ecology (Ecology); the elapse of 30 calendar days from the date of receipt 30
of the Notice of Termination by Ecology; and no rejection of the Notice of 31
Termination by Ecology. This requirement will not apply if the Construction 32
Stormwater General Permit is transferred back to the City in accordance with 33
Section 8-01.3(16). 34
g. Property owner releases per Section 1-07.24 35
36
1-09 MEASUREMENT AND PAYMENT 37
38
1-09.2(5) Measurement 39
(May 2, 2017 APWA GSP) 40
41
Revise the first paragraph to read: 42
43
Scale Verification Checks – At the Engineer’s discretion, the Engineer may perform 44
verification checks on the accuracy of each batch, hopper, or platform scale used in 45
weighing contract items of Work. 46
47
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-46
Payments 1
(March 13, 2012 APWA GSP) 2
3
Delete the first four paragraphs and replace them with the following: 4
5
The basis of payment will be the actual quantities of Work performed according to the 6
Contract and as specified for payment. 7
8
The Contractor shall submit a breakdown of the cost of lump sum bid items at the 9
Preconstruction Conference, to enable the Project Engineer to determine the Work 10
performed on a monthly basis. A breakdown is not required for lump sum items that include 11
a basis for incremental payments as part of the respective Specification. Absent a lump 12
sum breakdown, the Project Engineer will make a determination based on information 13
available. The Project Engineer’s determination of the cost of work shall be final. 14
15
Progress payments for completed work and material on hand will be based upon progress 16
estimates prepared by the Engineer. A progress estimate cutoff date will be established at 17
the preconstruction conference. 18
19
The initial progress estimate will be made not later than 30 days after the Contractor 20
commences the work, and successive progress estimates will be made every month 21
thereafter until the Completion Date. Progress estimates made during progress of the work 22
are tentative, and made only for the purpose of determining progress payments. The 23
progress estimates are subject to change at any time prior to the calculation of the final 24
payment. 25
26
The value of the progress estimate will be the sum of the following: 27
1. Unit Price Items in the Bid Form — the approximate quantity of acceptable units of 28
work completed multiplied by the unit price. 29
2. Lump Sum Items in the Bid Form — based on the approved Contractor’s lump sum 30
breakdown for that item, or absent such a breakdown, based on the Engineer’s 31
determination. 32
3. Materials on Hand — 100 percent of invoiced cost of material delivered to Job site or 33
other storage area approved by the Engineer. 34
4. Change Orders — entitlement for approved extra cost or completed extra work as 35
determined by the Engineer. 36
37
Progress payments will be made in accordance with the progress estimate less: 38
1. Retainage per Section 1-09.9(1), on non FHWA-funded projects; 39
2. The amount of progress payments previously made; and 40
3. Funds withheld by the City for disbursement in accordance with the Contract 41
Documents. 42
43
Progress payments for work performed shall not be evidence of acceptable performance or 44
an admission by the City that any work has been satisfactorily completed. The 45
determination of payments under the contract will be final in accordance with Section 1-05.1. 46
47
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-47
1-09.11(3) Time Limitation and Jurisdiction 1
(November 30, 2018 APWA GSP) 2
3
Revise this section to read: 4
5
For the convenience of the parties to the Contract it is mutually agreed by the parties that 6
any claims or causes of action which the Contractor has against the City arising from the 7
Contract shall be brought within 180 calendar days from the date of final acceptance 8
(Section 1-05.12) of the Contract by the City; and it is further agreed that any such claims or 9
causes of action shall be brought only in the Superior Court of the county where the City 10
headquarters is located, provided that where an action is asserted against a county, RCW 11
36.01.050 shall control venue and jurisdiction. The parties understand and agree that the 12
Contractor’s failure to bring suit within the time period provided, shall be a complete bar to 13
any such claims or causes of action. It is further mutually agreed by the parties that when 14
any claims or causes of action which the Contractor asserts against the City arising from the 15
Contract are filed with the City or initiated in court, the Contractor shall permit the City to 16
have timely access to any records deemed necessary by the City to assist in evaluating the 17
claims or action. 18
19
1-09.13(3) Claims $250,000 or Less 20
(October 1, 2005 APWA GSP) 21
22
Delete this section and replace it with the following: 23
24
The Contractor and the City mutually agree that those claims that total $250,000 or less, 25
submitted in accordance with Section 1-09.11 and not resolved by nonbinding ADR 26
processes, shall be resolved through litigation unless the parties mutually agree in writing to 27
resolve the claim through binding arbitration. 28
29
1-10 TEMPORARY TRAFFIC CONTROL 30
(******) 31
32
Supplement this section with the following: 33
34
The provisions of the latest edition of the Manual on Uniform Traffic Control Devices 35
(MUTCD) for Streets and Highways and corresponding amendments published by the U.S. 36
Department of Transportation, Federal Highway Administration, and WSDOT by this 37
reference are made a part of these Contract Documents. 38
39
General 40
(******) 41
42
Supplement this section with the following: 43
44
The alley and access from the alley to private property shall be accessible at the end of 45
each working day to vehicle and pedestrian traffic. The Contractor shall inform the City 46
and residents on each side of the alley a minimum of 2 days before the start of 47
construction. The notification shall include the times and extents of alley closure. The 48
Contractor shall coordinate with Basin Disposal and shall ensure that garbage service to 49
residents on each side of the alley is not disrupted for the full duration of construction. 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-48
1-10.1(2) Description 1
(******) 2
3
Supplement this section with the following: 4
5
All signs, barricades, traffic control devices, and labor for traffic control required for 6
construction activities shall be supplied, placed, and maintained by the Contractor. This 7
shall apply to detours and traffic control both within and outside the limits of the project. 8
9
The Contractor shall prepare and submit a Traffic Control Plan (TCP) to the City for review. 10
The TCP shall include mention of any trenches to remain open overnight and the 11
Contractor’s plan to maintain access to public and private property throughout construction. 12
The TCP shall minimize interruption and inconvenience to pedestrian and vehicular traffic. 13
The Contractor shall make all arrangements to implement the TCP, and shall implement the 14
TCP at the Contractor’s expense. 15
16
If the Contractor fails implement their approved TCP, the City may notify the Contractor. If 17
this notification occurs, the Contractor shall immediately remedy the non-conformance. If 18
the Contractor fails to do this, the City shall be at liberty to remedy the non-conformance 19
without assuming liability and without further notice to the Contractor. Liability for 20
implementation of the TCP is the sole responsibility of the Contractor. The costs 21
associated with the City implementing the Contractor’s TCP may be deducted by the City 22
from monies due to the Contractor, or the City may request payment from the Contractor. 23
24
Any traffic restriction must have prior approval of the City of Pasco Engineering Division. 25
Appropriate traffic control measures and signage are required during temporary road 26
closures. 27
28
It shall be the responsibility of the Contractor to secure the City’s approval for any desired 29
road closure and associated traffic control plan including detours. Following approval, the 30
Contractor shall notify the City of Pasco, and the Police and Fire Departments, Pasco School 31
District, Basin Disposal, and Benton Franklin Transit at least 1 business day prior to closing 32
any street. When the street is re-opened, it shall again be the responsibility of the 33
Contractor to notify the above named departments and persons. 34
35
Traffic Control Management 36
37
1-10.2(1) General 38
(January 3, 2017 WSDOT GSP) 39
40
Supplement this section with the following: 41
42
Only training with WSDOT TCS card and WSDOT training curriculum is recognized in the 43
State of Washington. The Traffic Control Supervisor shall be certified by one of the 44
following: 45
46
The Northwest Laborers-Employers Training Trust 47
27055 Ohio Ave. 48
Kingston, WA 98346 49
(360) 297-3035 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-49
Evergreen Safety Council 1
12545 135th Ave. NE 2
Kirkland, WA 98034-8709 3
1-800-521-0778 4
5
The American Traffic Safety Services Association 6
15 Riverside Parkway, Suite 100 7
Fredericksburg, Virginia 22406-1022 8
Training Dept. Toll Free (877) 642-4637 9
Phone: (540) 368-1701 10
11
1-10.2(1)B Traffic Control Supervisor 12
(******) 13
14
The last paragraph is revised to read: 15
16
The TCS may perform the Work described in Section 1-10.3(1)A Flaggers or in Section 1-17
10.3(1)B Other Traffic Control Labor, however, all compensation shall be included in the 18
lump sum bid price for Project Temporary Traffic Control. If TCS duties are not being 19
performed to the satisfaction of the Engineer, this provision will be revoked. 20
21
1-10.2(2) Traffic Control Plans 22
(******) 23
24
Delete the entire section and replace with the following: 25
26
The Contractor shall prepare a signing plan showing the necessary Class A and B 27
construction signing, barricades, and traffic control devices required for the project and 28
submit it to the City, no later than the preconstruction conference date. When the Class B 29
signing for a particular area will be provided as detailed on one or more of the figures 30
included in the MUTCD without modification, the Contractor may reference the applicable 31
MUTCD figure at the appropriate location on the Plan. When this procedure is used, 32
variable distances such as minimum length of taper must be specified by the Contractor. 33
34
The signing plan prepared by the Contractor shall provide for adequate warning within the 35
limits of the project and on all streets, alleys, and driveways entering the project so that 36
approaching traffic may turn left or right onto existing undisturbed streets before reaching 37
the project. The Plan shall be prepared to create a minimum of inconvenience for 38
pedestrian and vehicle traffic. 39
40
All modifications to the accepted signing plans shall be reviewed by the City. 41
42
1-10.3(3)A Construction Signs 43
(******) 44
45
The first sentence of the first paragraph is revised to read: 46
47
All signs, barricades, flashers, cones, traffic safety drums, barricades, and other traffic 48
control devices required by the approved traffic control plan(s), as well as any other 49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-50
appropriate signs prescribed by the City or County, shall be furnished and maintained by 1
the Contractor. 2
3
Open trenches shall be provided with proper barricades and at night they shall be distinctly 4
indicated by adequately spaced lights. 5
6
7
END DIVISION 1 8
9
10
11
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-51
DIVISION 2 1
EARTHWORK 2
3
2-01 CLEARING, GRUBBING, AND ROADSIDE CLEANUP 4
5
Description 6
(******) 7
8
Supplement this section with the following: 9
10
The Contractor shall perform the minimum amount of clearing and grubbing within the 11
construction limits that is necessary to perform the work. The limits of clearing and grubbing 12
shall be staked and flagged by the Contractor for approval by the City prior to construction. 13
14
(******) 15
16
Supplement this section with the following: 17
18
All work beyond the right-of -way line shall be coordinated with affected property owner(s) 19
per Section 1-07.24 Rights of Way. 20
21
If any work is to be performed outside of the right-of-way and outside of the work areas 22
designated in the Contract, the Contractor shall receive written permission from the City 23
prior to proceeding. 24
25
For work outside of the right-of-way requiring temporary removal of obstructions, the 26
following shall apply: 27
28
Should any existing objects impede the Contractor’s work, the Contractor may request 29
permission from the City to remove them. Once permission is obtained, the Contractor 30
shall temporarily remove and later replace to its original condition or relocate nearby as 31
directed eg. mail boxes, fences, small trees, shrubs, street signs and posts, culverts, 32
irrigation facilities, concrete or rock walls, or other similar obstructions which lie in or near 33
the line of work and are not intended for removal. Should any damage be incurred, the 34
cost of replacement or repair shall be borne by the Contractor. 35
36
Construction Requirements 37
38
2-01.3(1) Clearing 39
(******) 40
41
Supplement this section with the following: 42
43
Removal of trees for utility trenching shall include removal of the stump and root ball within 3 44
feet of the pipe on all sides. 45
46
Removal of tree roots for utility trenching shall include removal of any large tree roots within 47
the confines of the trench. Roots over 4 inches in diameter will require City approval to 48
remove. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-52
Move any existing materials stockpiled in the work zone as necessary to perform the work. 1
Do not dispose without written permission of the owner of said materials. Return materials 2
back to their approximate original locations at completion of construction unless an alternate 3
location is approved by both the owner of the material and the City. 4
5
Payment 6
(******) 7
8
Supplement this section with the following: 9
10
All costs for clearing and grubbing shall be incidental to the water main installation. No 11
separate payment will be made. 12
13
All costs for removal and resetting of existing fencing in Section 2-01.3(5) shall be incidental 14
to the water installation. No separate payment will be made. 15
16
2-02 REMOVAL OF STRUCTURES AND OBSTRUCTIONS 17
18
Description 19
(******) 20
21
Supplement this section with the following: 22
23
The primary work components shall include the decommissioning of the existing 2 inch DI 24
water main and 2 inch water valve. The primary work components shall also include all 25
necessary saw cutting of existing aggregate, asphalt and concrete pavements. 26
27
Construction Requirements 28
(******) 29
30
Supplement this section with the following: 31
32
This work shall consist of removing and disposing of, or salvaging various existing 33
improvements within the construction limits shown on the plans including, but not limited to: 34
35
1. Removal of asphalt surfacing, including saw cutting. 36
2. Removal of concrete curb, gutter, and sidewalk. 37
38
2-02.3(3) Removal of Pavement, Sidewalks, Curbs, and Gutters 39
(June 26, 2020 COP GSP) 40
41
Supplement this section with the following: 42
43
In those areas where asphalt pavement removal is required, the Contractor shall, prior to 44
excavation, score the edge of the asphalt concrete pavement with an approved pavement 45
cutter such as a concrete saw. During the course of the work, the Contractor shall take 46
precautions to preserve the integrity of this neat, clean pavement edge. Should the 47
pavement edge be damaged prior to asphalt concrete paving activities, the Contractor shall 48
be required to trim the edge with an approved pavement cutter as directed by the City 49
immediately prior to paving. Sidewalk and/or curb and gutter removal shall be from 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-53
construction joint to joint. No partial sidewalk panels or curb and gutter sections will be 1
allowed. 2
3
Measurement 4
(******) 5
6
Supplement this section with the following: 7
8
The Bid item “SAW CUTTING PAVEMENT” shall be measured by the linear foot (LF). 9
10
The Bid item “REMOVAL OF STRUCTURES AND OBSTRUCTIONS” shall be measured as 11
lump sum (LS), and includes the following work: 12
13
• Remove 60 linear foot of existing concrete curb and gutter. 14
• Remove 60 linear foot of existing concrete sidewalk. 15
• Remove 2 concrete ramps. 16
• Perform clearing and grubbing as needed. 17
18
Payment 19
(******) 20
21
Supplement this section with the following: 22
23
24
Payment will be made for each of the following Bid items that are included in the Proposal: 25
26
“SAW CUTTING PAVEMENT”, per linear foot (LF). 27
28
“REMOVAL OF STRUCTURES AND OBSTRUCTIONS”, lump sum (LS). 29
30
The unit Contract price per linear foot (LF) for “SAW CUTTING PAVEMENT” shall be full 31
compensation for all costs, including materials, equipment, and labor, incurred to carry out 32
the requirements of Section 2-02 except for those costs included in other items which are 33
included in this Subsection and which are included in the Proposal. 34
35
The lump sum (LS) Contract price for “REMOVAL OF STRUCTURES AND 36
OBSTRUCTIONS” shall be full compensation for all costs, including materials, equipment, 37
and labor, incurred to carry out the requirements of Section 2-02 and its Special Provisions 38
except for those costs included in other items which are included in this Subsection and 39
which are included in the Proposal. 40
41
2-03 ROADWAY EXCAVATION AND EMBANKMENT 42
43
Description 44
(******) 45
46
Supplement this section with the following: 47
48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-54
Street excavation shall consist of removing the existing material of whatever nature 1
encountered to the subgrade elevation and shaping the subgrade to conform to the cross- 2
section shown on the Plans or as staked in the field. 3
4
The Contractor shall use caution while performing roadway excavation. Heavy, rubber- tired 5
equipment, particularly front end loaders, shall limit their travel over a single area as much 6
as possible. Trucks shall observe a 10 mph speed limit when traveling over exposed 7
subgrade areas. Track mounted equipment may only be used with permission from the City, 8
and in areas where their use will not be detrimental to the project. 9
10
The City may reference known existing monuments or markers relating to subdivisions, 11
plats, roads, street centerline intersections, etc. The Contractor is responsible for field-locating 12
all existing monuments and markers. The Contractor shall take special care to protect these 13
monuments or markers and also the reference points. In the event the Contractor is 14
negligent in preserving such monuments and markers, the points will be reset by a licensed 15
surveyor at the Contractor's expense. 16
17
Construction Requirements 18
19
2-03.3(3) Excavation Below Subgrade 20
(June 26, 2020 COP GSP) 21
22
Supplement this section with the following: 23
24
At the direction of the Engineer, at the City’s expense, areas within the street subgrade which 25
exhibit instability due to high moisture content shall be: 26
27
1. Aerated and allowed to dry, 28
29
2. Over-excavated and backfilled with ballast, or crushed surfacing base course. The 30
Contractor may be instructed to install construction geotextile for soil stabilization in the 31
excavation, 32
33
3. Or a combination of any of the above. 34
35
2-03.3(14)D Compaction and Moisture Control Tests 36
(June 26, 2020 COP GSP) 37
38
Supplement this section with the following: 39
40
Compaction of placed fill shall be 95% of maximum density as determined by ASTM D 698 41
(Standard Proctor). The Contractor shall notify the City when ready for in-place subgrade 42
density tests. Placement of courses of aggregate shall not proceed until density 43
requirements are met. The Contractor shall be responsible for scheduling all testing. All 44
initial testing costs are the responsibility of the City. All costs associated with failed 45
tests/testing shall be the responsibility of the Contractor. 46
47
If the product fails any test, the City may require additional testing to determine the extent 48
of the failure and more frequent tests may be required on additional work. Testing shall be 49
in accordance with Section 1-06.2(1).7. 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-55
1
Measurement 2
(******) 3
4
Supplement this section with the following: 5
6
The Bid item “ROADWAY AND TRENCH EXCAVATION INCL. HAUL” shall be measured by 7
the cubic yard (CY). All excavated material will be measured in the position it occupied 8
before the excavation was performed. 9
10
For roadway excavation, original ground measurement will be taken and compared with the 11
planned finished section shown in the Plans. Slope/ground intercept points defining the 12
limits of the measurement shall be as staked. 13
14
For trench excavation, the depth shall be the actual depth removed for the changed line or 15
grade. The width shall be the actual width removed for the changed line or grade, but in no 16
case shall the measured width exceed the allowable widths specified in the Contract 17
Documents. 18
19
Payment 20
(******) 21
22
Supplement this section with the following: 23
24
Payment will be made for each of the following Bid items that are included in the proposal: 25
26
“ROADWAY AND TRENCH EXCAVATION INCL. HAUL”, per cubic yard (CY). 27
28
The unit Contract price per (CY) for “ROADWAY AND TRENCH EXCAVATION INCL. HAUL” 29
shall be full compensation for all costs, including materials, equipment, and labor, incurred to 30
carry out the requirements of Section 2-03 and its Special Provisions except for those costs 31
included in other items which are included in this Subsection and which are included in the 32
Proposal. No additional payment will be made to store native material that has been 33
excavated and the City determines may be used for trench backfill. 34
35
No separate payment will be made for roadway surveying. All costs associated with 36
roadway surveying will be considered incidental to other bid items. 37
38
2-07 WATERING 39
40
Description 41
(******) 42
43
Supplement this section with the following: 44
45
The Contractor shall be solely responsible for dust control and shall protect motoring 46
public, adjacent homes and businesses, orchards, crops, and school yards from damage 47
due to dust, by the most appropriate means necessary. The Contractor shall be 48
responsible for any claims for damages and shall protect and defend the City from any and all 49
such claims. 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-56
1
When directed by the City, the Contractor shall provide dust control within two hours of 2
such order and have equipment and manpower available at all times including weekends 3
and holidays to respond to orders for dust control measures. 4
5
The Contractor shall take special precautions to control dust at all times throughout the 6
entire project. This also includes watering on weekends and holidays. Watering, or other 7
approved dust control measures will be required whenever dust conditions are present on 8
the roadway, on adjacent streets when dust results from construction activities, and on cut 9
and fill slopes as determined by the City. The Contractor shall obtain their own source of 10
water at their expense unless otherwise indicated in the bid documents. No separate 11
payment will be made for dust control. 12
13
(******) 14
Add the following new section: 15
16
Watering for Compaction 17
18
Contractor shall provide watering as necessary to achieve optimal moisture content for 19
compaction. Cost for watering shall be incidental to the contract. The Contractor shall 20
coordinate with the water purveyor to provide a meter setup for construction water, if a 21
source is available. The maximum flow rate allowed from this meter may be restricted at 22
the purveyor’s discretion. The Contractor is responsible for protection of the meter 23
assembly from theft, vandalism, damage, and freezing. 24
25
Measurement 26
(******) 27
28
Supplement this section with the following: 29
30
There will be no separate measurement for dust control (dewatering) and watering (e.g. 31
compaction) operations by the Contractor. 32
33
Payment 34
(******) 35
36
Supplement this section with the following: 37
38
All costs for dust control (dewatering) and watering (e.g. compaction) operations shall be 39
incidental to other Bid items. 40
41
2-09 STRUCTURE EXCAVATION 42
43
Description 44
(******) 45
46
Supplement this section with the following: 47
48
The work shall include all necessary trench shoring and safety measures necessary for the 49
installation of the proposed water mains as shown in the Contract Plans. 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-57
1
Measurement 2
(******) 3
4
Supplement this section with the following: 5
6
The Bid item “TRENCH BACKFILL” shall be measured by the cubic yard (SY) of material 7
placed to the specified depth and compaction. Should the City determine to use native 8
trench material previously excavated and stored for trench backfill, no additional 9
measurement or payment will be made for excess new backfill material. 10
11
The Bid item “SHORING OR EXTRA EXCAVATION” shall be measured by the linear foot 12
(LF) along the proposed utility service alignment. 13
14
Payment 15
(******) 16
17
Supplement this section with the following: 18
19
Payment will be made for each of the following Bid items that are included in the Proposal: 20
21
“TRENCH BACKFILL”, per cubic yard (CY). 22
“SHORING OR EXTRA EXCAVATION”, per linear foot (LF). 23
24
The unit Contract price per cubic yard (CY) for “TRENCH BACKFILL” shall be full 25
compensation for all costs, including materials, equipment, and labor, incurred to carry out 26
the requirements of Section 2-09 and its Special Provisions except for those costs included 27
in other items which are included in this Subsection and which are included in the Proposal. 28
29
The unit Contract price per linear foot (LF) for “SHORING OR EXTRA EXCAVATION” shall 30
be full compensation for all materials, equipment, and labor required to construct the 31
shoring, including excavation, installation, and removal of the specified shoring, backfilling, 32
and compaction. When extra excavation is used by the Contractor in lieu of constructing the 33
shoring, the unit price bid shall be full pay for all additional excavation, backfill, compaction 34
and other work required. If select material is required within the limits of the trench 35
excavation, it shall also be required as backfill material for the extra excavation at the 36
Contractor’s expense. 37
38
2-11 TRIMMING AND CLEANUP 39
40
Construction Requirements 41
(June 26, 2020 COP GSP) 42
43
Supplement this section with the following: 44
45
7. Restore all grass area affected by construction with sod and in accordance with the 46
City of Pasco Construction Standards. 47
8. Restore all landscaping rock, mulch, and bark with the same materials as existed prior to 48
construction. Where the same materials are not readily available, the Contractor shall 49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-58
coordinate with the City prior to removing said materials to determine if said materials 1
should be salvaged for reuse, or if new similar materials should be provided. 2
9. Restore the site and offsite areas damaged by the work to their original condition or 3
better and to the satisfaction of the City and the adjoining homeowners. 4
5
6
END DIVISION 2 7
8
9
10
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-59
DIVISION 4 1
BASES 2
3
4-04 BALLAST AND CRUSHED SURFACING 4
5
Construction Requirements 6
7
4-04.3(5) Shaping and Compaction 8
(June 26, 2020 COP GSP) 9
10
Supplement this section with the following: 11
12
The Contractor shall notify the City when they are ready for in-place ballast, base course, 13
or top course density tests. Placement of successive courses of aggregate or asphalt 14
concrete shall not proceed until density requirements are met. All costs associated with 15
failed tests/testing shall be the responsibility of the Contractor. 16
17
Measurement 18
(******) 19
20
Supplement this section with the following: 21
22
The Bid items “2" CRUSHED SURFACE TOP COARSE (CSTC)”, “6" CRUSHED SURFACE 23
BASE COARSE (CSBC)”, and “10" CRUSHED SURFACE BASE COARSE (CSBC)” shall be 24
measured by the square yard (SY) of material placed to the specified depth and compaction, 25
except where used underneath concrete sidewalk, apron, curb, and gutter, in which case it is 26
incidental to other bid items and no separate payment for this item shall be made. 27
28
Payment 29
(******) 30
31
Supplement this section with the following: 32
33
Payment will be made for each of the following Bid items that are included in the Proposal: 34
35
“2" CRUSHED SURFACE TOP COARSE (CSTC)”, per square yard (SY). 36
“6" CRUSHED SURFACE BASE COARSE (CSBC)”, per square yard (SY). 37
“10" CRUSHED SURFACE BASE COARSE (CSBC)”, per square yard (SY). 38
39
The unit Contract price per square yard (CY) for “2" CRUSHED SURFACE TOP COARSE 40
(CSTC)”, “6" CRUSHED SURFACE BASE COARSE (CSBC)”, and “10" CRUSHED 41
SURFACE BASE COARSE (CSBC)” shall be full compensation for all costs, including 42
materials, equipment, and labor, incurred to carry out the requirements of Section 2-04 except 43
for those costs included in other items which are included in this Subsection and which are 44
included in the Proposal. 45
46
47
48
END DIVISION 4 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-60
DIVISION 5 1
SURFACE TREATMENTS AND PAVEMENTS 2
3
5-04 HOT MIX ASPHALT 4
(July 18, 2018 APWA GSP, Unless Otherwise Noted) 5
6
Delete Section 5-04 and amendments, Hot Mix Asphalt and replace it with the following: 7
8
Description 9
10
This Work shall consist of providing and placing one or more layers of plant-mixed hot mix 11
asphalt (HMA) on a prepared foundation or base in accordance with these Specifications 12
and the lines, grades, thicknesses, and typical cross-sections shown in the Plans. The 13
manufacture of HMA may include warm mix asphalt (WMA) processes in accordance with 14
these Specifications. WMA processes include organic additives, chemical additives, and 15
foaming. 16
17
HMA shall be composed of asphalt binder and mineral materials as may be required, mixed 18
in the proportions specified to provide a homogeneous, stable, and workable mixture. 19
20
Materials 21
22
Materials shall meet the requirements of the following sections: 23
Asphalt Binder 9-02.1(4) 24
Cationic Emulsified Asphalt 9-02.1(6) 25
Anti-Stripping Additive 9-02.4 26
HMA Additive 9-02.5 27
Aggregates 9-03.8 28
Recycled Asphalt Pavement 9-03.8(3)B 29
Mineral Filler 9-03.8(5) 30
Recycled Material 9-03.21 31
Portland Cement 9-01 32
Sand 9-03.1(2) 33
(As noted in 5-04.3(5)C for crack sealing) 34
Joint Sealant 9-04.2 35
Foam Backer Rod 9-04.2(3)A 36
37
The Contract Documents may establish that the various mineral materials required for the 38
manufacture of HMA will be furnished in whole or in part by the City. If the documents do 39
not establish the furnishing of any of these mineral materials by the City, the Contractor shall 40
be required to furnish such materials in the amounts required for the designated mix. 41
Mineral materials include coarse and fine aggregates, and mineral filler. 42
43
The Contractor may choose to utilize recycled asphalt pavement (RAP) in the production of 44
HMA. The RAP may be from pavements removed under the Contract, if any, or pavement 45
material from an existing stockpile. 46
47
The Contractor may use up to 20 percent RAP by total weight of HMA with no additional 48
sampling or testing of the RAP. The RAP shall be sampled and tested at a frequency of one 49
sample for every 1,000 tons produced and not less than ten samples per project. The 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-61
asphalt content and gradation test data shall be reported to the City when submitting the mix 1
design for approval on the QPL. The Contractor shall include the RAP as part of the mix 2
design as defined in these Specifications. 3
4
The grade of asphalt binder shall be as required by the Contract. Blending of asphalt binder 5
from different sources is not permitted. 6
7
The Contractor may only use warm mix asphalt (WMA) processes in the production of HMA 8
with 20 percent or less RAP by total weight of HMA. The Contractor shall submit to the 9
Engineer for approval the process that is proposed and how it will be used in the 10
manufacture of HMA. 11
12
Production of aggregates shall comply with the requirements of Section 3-01. 13
14
Preparation of stockpile site, the stockpiling of aggregates, and the removal of aggregates 15
from stockpiles shall comply with the requirements of Section 3-02. 16
17
5-04.2(1) How to Get an HMA Mix Design on the QPL 18
If the Contractor wishes to submit a mix design for inclusion in the Qualified Products List 19
(QPL), please follow the WSDOT process outlined in Standard Specification 5-04.2(1). 20
21
5-04.2(1)A Vacant 22
23
5-04.2(2) Mix Design – Obtaining Project Approval 24
No paving shall begin prior to the approval of the mix design by the Engineer. 25
26
Nonstatistical evaluation will be used for all HMA not designated as Commercial HMA in 27
the contract documents. 28
29
Commercial evaluation will be used for Commercial HMA and for other classes of HMA in 30
the following applications: sidewalks, road approaches, ditches, slopes, paths, trails, gores, 31
prelevel, and pavement repair. Other nonstructural applications of HMA accepted by 32
commercial evaluation shall be as approved by the Project Engineer. Sampling and testing 33
of HMA accepted by commercial evaluation will be at the option of the Project Engineer. 34
The Proposal quantity of HMA that is accepted by commercial evaluation will be excluded 35
from the quantities used in the determination of nonstatistical evaluation. 36
37
Nonstatistical Mix Design. Fifteen days prior to the first day of paving the Contractor shall 38
provide one of the following mix design verification certifications for City review; 39
40
• The WSDOT Mix Design Evaluation Report from the current WSDOT QPL, or one of 41
the mix design verification certifications listed below. 42
• The proposed HMA mix design on WSDOT Form 350-042 with the seal and 43
certification (stamp & sig-nature) of a valid licensed Washington State Professional 44
Engineer. 45
• The Mix Design Report for the proposed HMA mix design developed by a qualified 46
City or County laboratory that is within one year of the approval date.** 47
48
The mix design shall be performed by a lab accredited by a national authority such as 49
Laboratory Accreditation Bureau, L-A-B for Construction Materials Testing, The Construction 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-62
Materials Engineering Council (CMEC’s) ISO 17025 or AASHTO Accreditation Program 1
(AAP) and shall supply evidence of participation in the AASHTO: resource proficiency 2
sample program. 3
4
Mix designs for HMA accepted by Nonstatistical evaluation shall; 5
6
• Have the aggregate structure and asphalt binder content determined in accordance 7
with WSDOT Standard Operating Procedure 732 and meet the requirements of 8
Sections 9-03.8(2), except that Hamburg testing for ruts and stripping are at the 9
discretion of the Engineer, and 9-03.8(6). 10
• Have anti-strip requirements, if any, for the proposed mix design determined in 11
accordance with AASHTO T 283 or T 324, or based on historic anti-strip and 12
aggregate source compatibility from previous WSDOT lab testing. 13
14
At the discretion of the Engineer, agencies may accept verified mix designs older than 12 15
months from the original verification date with a certification from the Contractor that the 16
materials and sources are the same as those shown on the original mix design. 17
18
Commercial Evaluation Approval of a mix design for “Commercial Evaluation” will be based 19
on a review of the Contractor’s submittal of WSDOT Form 350-042 (For commercial mixes, 20
AASHTO T 324 evaluation is not required) or a Mix Design from the current WSDOT QPL or 21
from one of the processes allowed by this section. Testing of the HMA by the City for mix 22
design approval is not required. 23
24
For the Bid Item Commercial HMA, the Contractor shall select a class of HMA and design 25
level of Equivalent Single Axle Loads (ESAL’s) appropriate for the required use. 26
27
5-04.2(2)B Using Warm Mix Asphalt Processes 28
The Contractor may elect to use additives that reduce the optimum mixing temperature or 29
serve as a compaction aid for producing HMA. Additives include organic additives, chemical 30
additives and foaming processes. The use of Additives is subject to the following: 31
32
• Do not use additives that reduce the mixing temperature more than allowed in Section 33
5-04.3(6) in the production of mixtures. 34
• Before using additives, obtain the Engineer’s approval using WSDOT Form 350-076 35
to describe the proposed additive and process. 36
37
Construction Requirements 38
39
5-04.3(1) Weather Limitations 40
(June 26, 2020 COP GSP) 41
42
Revise this entire section from the APWA GSP and replace it with the following: 43
44
HMA shall not be placed on any traveled way beginning October 1st through March 31st of 45
the following year without written approval from the City. 46
47
Asphalt for prime coat shall not be applied when the ground temperature is lower than 50°F 48
without written approval of the City. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-63
HMA shall not be placed on any wet surface, or when the average surface temperatures 1
are less than those specified in the following table, or when weather conditions otherwise 2
prevent the proper handling or finishing of the bituminous mixtures. Any exceptions to the 3
above and following limitations will not be allowed without the written approval of the City. 4
5
Wind (mph) Ambient
0F
Surface 0F
(Minimum)
Precipitation
0-5 45° 40° Not Measurable
5-10 50° 40° Not Measurable
10-15 55° 40° Not Measurable
15+ 60° 45° Not Measurable
1. If the weather criteria are met, the Contractor shall complete the entire panel 6
or lane with no transverse joints. 7
2. If meteorological conditions change after starting, construction shall be 8
monitored by the City and require their approval. 9
3. HMA shall not be placed on ground that is frozen. 10
11
The weather guide shall be the “National Weather Service” zone forecast for the Lower 12
Columbia Basin, Washington at www.wrh.noaa.gov/. The wind speed shall be the current 13
conditions at the Tri-Cities Airport, available at the website above. 14
15
5-04.3(2) Paving Under Traffic 16
When the Roadway being paved is open to traffic, the requirements of this Section 17
shall apply. 18
19
The Contractor shall keep intersections open to traffic at all times except when paving the 20
intersection or paving across the intersection. During such time, and provided that there has 21
been an advance warning to the public, the intersection may be closed for the minimum time 22
required to place and compact the mixture. In hot weather, the Engineer may require the 23
application of water to the pavement to accelerate the finish rolling of the pavement and to 24
shorten the time required before reopening to traffic. 25
26
Before closing an intersection, advance warning signs shall be placed and signs shall also 27
be placed marking the detour or alternate route. 28
29
During paving operations, temporary pavement markings shall be maintained throughout the 30
project. Temporary pavement markings shall be installed on the Roadway prior to opening 31
to traffic. Temporary pavement markings shall be in accordance with Section 8-23. 32
33
All costs in connection with performing the Work in accordance with these requirements, 34
except the cost of temporary pavement markings, shall be included in the unit Contract 35
prices for the various Bid items involved in the Contract. 36
37
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-64
5-04.3(3) Equipment 1
2
5-04.3(3)A Mixing Plant 3
Plants used for the preparation of HMA shall conform to the following requirements: 4
5
1. Equipment for Preparation of Asphalt Binder – Tanks for the storage of asphalt 6
binder shall be equipped to heat and hold the material at the required temperatures. 7
The heating shall be accomplished by steam coils, electricity, or other approved 8
means so that no flame shall be in contact with the storage tank. The circulating 9
system for the asphalt binder shall be designed to ensure proper and continuous 10
circulation during the operating period. A valve for the purpose of sampling the 11
asphalt binder shall be placed in either the storage tank or in the supply line to the 12
mixer. 13
2. Thermometric Equipment – An armored thermometer, capable of detecting 14
temperature ranges expected in the HMA mix, shall be fixed in the asphalt binder 15
feed line at a location near the charging valve at the mixer unit. The thermometer 16
location shall be convenient and safe for access by Inspectors. The plant shall also 17
be equipped with an approved dial-scale thermometer, a mercury actuated 18
thermometer, an electric pyrometer, or another approved thermometric instrument 19
placed at the discharge chute of the drier to automatically register or indicate the 20
temperature of the heated aggregates. This device shall be in full view of the plant 21
operator. 22
3. Heating of Asphalt Binder – The temperature of the asphalt binder shall not exceed 23
the maximum recommended by the asphalt binder manufacturer nor shall it be below 24
the minimum temperature required to maintain the asphalt binder in a homogeneous 25
state. The asphalt binder shall be heated in a manner that will avoid local variations 26
in heating. The heating method shall provide a continuous supply of asphalt binder 27
to the mixer at a uniform average temperature with no individual variations exceeding 28
25°F. Also, when a WMA additive is included in the asphalt binder, the temperature 29
of the asphalt binder shall not exceed the maximum recommended by the 30
manufacturer of the WMA additive. 31
4. Sampling and Testing of Mineral Materials – The HMA plant shall be equipped 32
with a mechanical sampler for the sampling of the mineral materials. The 33
mechanical sampler shall meet the requirements of Section 1-05.6 for the crushing 34
and screening operation. The Contractor shall provide for the setup and operation of 35
the field testing facilities of the City as provided for in Section 3-01.2(2). 36
5. Sampling HMA – The HMA plant shall provide for sampling HMA by one of the 37
following methods: 38
a. A mechanical sampling device attached to the HMA plant. 39
b. Platforms or devices to enable sampling from the hauling vehicle without 40
entering the hauling vehicle. 41
42
5-04.3(3)B Hauling Equipment 43
Trucks used for hauling HMA shall have tight, clean, smooth metal beds and shall have a 44
cover of canvas or other suitable material of sufficient size to protect the mixture from 45
adverse weather. Whenever the weather conditions during the work shift include, or are 46
forecast to include, precipitation or an air temperature less than 45°F or when time from 47
loading to unloading exceeds 30 minutes, the cover shall be securely attached to protect the 48
HMA. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-65
The Contractor shall provide an environmentally benign means to prevent the HMA mixture 1
from adhering to the hauling equipment. Excess release agent shall be drained prior to 2
filling hauling equipment with HMA. Petroleum derivatives or other coating material that 3
contaminate or alter the characteristics of the HMA shall not be used. For live bed trucks, 4
the conveyer shall be in operation during the process of applying the release agent. 5
6
(June 26, 2020 COP GSP) 7
Supplement this section with the following: 8
9
Sufficient numbers of trucks shall be provided by the Contractor to assure a continuous 10
paving operation at proper HMA mix temperatures. Paving operations shall not proceed 11
until hauling equipment sufficient to assure continuous operations is provided. 12
13
5-04.3(3)C Pavers 14
HMA pavers shall be self-contained, power-propelled units, provided with an internally 15
heated vibratory screed and shall be capable of spreading and finishing courses of HMA 16
plant mix material in lane widths required by the paving section shown in the Plans. 17
18
The HMA paver shall be in good condition and shall have the most current equipment 19
available from the manufacturer for the prevention of segregation of the HMA mixture 20
installed, in good condition, and in working order. The equipment certification shall list the 21
make, model, and year of the paver and any equipment that has been retrofitted. 22
23
The screed shall be operated in accordance with the manufacturer’s recommendations and 24
shall effectively produce a finished surface of the required evenness and texture without 25
tearing, shoving, segregating, or gouging the mixture. A copy of the manufacturer’s 26
recommendations shall be provided upon request by the City. Extensions will be allowed 27
provided they produce the same results, including ride, density, and surface texture as 28
obtained by the primary screed. Extensions without augers and an internally heated 29
vibratory screed shall not be used in the Traveled Way. 30
31
When specified in the Contract, reference lines for vertical control will be required. Lines 32
shall be placed on both outer edges of the Traveled Way of each Roadway. Horizontal 33
control utilizing the reference line will be permitted. The grade and slope for intermediate 34
lanes shall be controlled automatically from reference lines or by means of a mat 35
referencing device and a slope control device. When the finish of the grade prepared for 36
paving is superior to the established tolerances and when, in the opinion of the Engineer, 37
further improvement to the line, grade, cross-section, and smoothness can best be achieved 38
without the use of the reference line, a mat referencing device may be substituted for the 39
reference line. Substitution of the device will be subject to the continued approval of the 40
Engineer. A joint matcher may be used subject to the approval of the Engineer. The 41
reference line may be removed after the completion of the first course of HMA when 42
approved by the Engineer. Whenever the Engineer determines that any of these methods 43
are failing to provide the necessary vertical control, the reference lines will be reinstalled by 44
the Contractor. 45
46
The Contractor shall furnish and install all pins, brackets, tensioning devices, wire, and 47
accessories necessary for satisfactory operation of the automatic control equipment. 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-66
If the paving machine in use is not providing the required finish, the Engineer may suspend 1
Work as allowed by Section 1-08.6. Any cleaning or solvent type liquids spilled on the 2
pavement shall be thoroughly removed before paving proceeds. 3
4
5-04.3(3)D Material Transfer Device or Material Transfer Vehicle 5
A Material Transfer Device/Vehicle (MTD/V) shall only be used with the Engineer’s approval, 6
unless other-wise required by the contract. 7
8
Where an MTD/V is required by the contract, the Engineer may approve paving without an 9
MTD/V, at the request of the Contractor. The Engineer will determine if an equitable 10
adjustment in cost or time is due. 11
12
When used, the MTD/V shall mix the HMA after delivery by the hauling equipment and prior 13
to laydown by the paving machine. Mixing of the HMA shall be sufficient to obtain a uniform 14
temperature throughout the mixture. If a windrow elevator is used, the length of the windrow 15
may be limited in urban areas or through intersections, at the discretion of the Engineer. 16
17
To be approved for use, an MTV: 18
19
1. Shall be self-propelled vehicle, separate from the hauling vehicle or paver. 20
2. Shall not be connected to the hauling vehicle or paver. 21
3. May accept HMA directly from the haul vehicle or pick up HMA from a windrow. 22
4. Shall mix the HMA after delivery by the hauling equipment and prior to placement 23
into the paving machine. 24
5. Shall mix the HMA sufficiently to obtain a uniform temperature throughout the 25
mixture. 26
27
To be approved for use, an MTD: 28
29
1. Shall be positively connected to the paver. 30
2. May accept HMA directly from the haul vehicle or pick up HMA from a windrow. 31
3. Shall mix the HMA after delivery by the hauling equipment and prior to placement 32
into the paving machine. 33
4. Shall mix the HMA sufficiently to obtain a uniform temperature throughout the 34
mixture. 35
36
5-04.3(3)E Rollers 37
Rollers shall be of the steel wheel, vibratory, oscillatory, or pneumatic tire type, in good 38
condition and capable of reversing without backlash. Operation of the roller shall be in 39
accordance with the manufacturer’s recommendations. When ordered by the Engineer for 40
any roller planned for use on the project, the Contractor shall provide a copy of the 41
manufacturer’s recommendation for the use of that roller for compaction of HMA. The 42
number and weight of rollers shall be sufficient to compact the mixture in compliance with 43
the requirements of Section 5-04.3(10). The use of equipment that results in crushing of the 44
aggregate will not be permitted. Rollers producing pickup, washboard, uneven compaction 45
of the surface, displacement of the mixture or other undesirable results shall not be used. 46
47
5-04.3(4) Preparation of Existing Paved Surfaces 48
When the surface of the existing pavement or old base is irregular, the Contractor shall bring 49
it to a uniform grade and cross-section as shown on the Plans or approved by the Engineer. 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-67
1
Preleveling of uneven or broken surfaces over which HMA is to be placed may be 2
accomplished by using an asphalt paver, a motor patrol grader, or by hand raking, as 3
approved by the Engineer. 4
5
Compaction of preleveling HMA shall be to the satisfaction of the Engineer and may require 6
the use of small steel wheel rollers, plate compactors, or pneumatic rollers to avoid bridging 7
across preleveled areas by the compaction equipment. Equipment used for the compaction 8
of preleveling HMA shall be approved by the Engineer. 9
10
Before construction of HMA on an existing paved surface, the entire surface of the 11
pavement shall be clean. All fatty asphalt patches, grease drippings, and other 12
objectionable matter shall be entirely removed from the existing pavement. All pavements 13
or bituminous surfaces shall be thoroughly cleaned of dust, soil, pavement grindings, and 14
other foreign matter. All holes and small depressions shall be filled with an appropriate 15
class of HMA. The surface of the patched area shall be leveled and compacted thoroughly. 16
Prior to the application of tack coat, or paving, the condition of the surface shall be approved 17
by the Engineer. 18
19
A tack coat of asphalt shall be applied to all paved surfaces on which any course of HMA is 20
to be placed or abutted; except that tack coat may be omitted from clean, newly paved 21
surfaces at the discretion of the Engineer. Tack coat shall be uniformly applied to cover the 22
existing pavement with a thin film of residual asphalt free of streaks and bare spots at a rate 23
between 0.02 and 0.10 gallons per square yard of retained asphalt. The rate of application 24
shall be approved by the Engineer. A heavy application of tack coat shall be applied to all 25
joints. For Roadways open to traffic, the application of tack coat shall be limited to surfaces 26
that will be paved during the same working shift. The spreading equipment shall be 27
equipped with a thermometer to indicate the temperature of the tack coat material. 28
29
Equipment shall not operate on tacked surfaces until the tack has broken and cured. If the 30
Contractor’s operation damages the tack coat it shall be repaired prior to placement of the 31
HMA. 32
33
The tack coat shall be CSS-1, or CSS-1h emulsified asphalt. The CSS-1 and CSS-1h 34
emulsified asphalt may be diluted once with water at a rate not to exceed one part water to 35
one part emulsified asphalt. The tack coat shall have sufficient temperature such that it may 36
be applied uniformly at the specified rate of application and shall not exceed the maximum 37
temperature recommended by the emulsified asphalt manufacturer. 38
39
(June 26, 2020 COP GSP) 40
Supplement this section with the following: 41
42
Overlays and Utility Patches 43
44 Edges of asphalt and curb edge shall be tack coated. 45
46
Prior to paving utility trenches, the edges of the trenches shall be saw-cut parallel to the 47
center of the street leaving long straight edges. Should any undermining occur on existing 48
adjacent pavement, the Contractor shall neatly cut the pavement 6 inches beyond the 49
undermined area. The City may waive all or a portion of the saw cutting requirement if the 50
original street cut is straight and not damaged. 51
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-68
5-04.3(4)A Crack Sealing 1
2
5-04.3(4)A1 General 3
When the Proposal includes a pay item for crack sealing, seal all cracks ¼ inch in width and 4
greater. 5
6
Cleaning: Ensure that cracks are thoroughly clean, dry and free of all loose and foreign 7
material when filling with crack sealant material. Use a hot compressed air lance to dry and 8
warm the pavement surfaces within the crack immediately prior to filling a crack with the 9
sealant material. Do not overheat pavement. Do not use direct flame dryers. Routing 10
cracks is not required. 11
12
Sand Slurry: For cracks that are to be filled with sand slurry, thoroughly mix the 13
components and pour the mixture into the cracks until full. Add additional CSS-1 cationic 14
emulsified asphalt to the sand slurry as needed for workability to ensure the mixture will 15
completely fill the cracks. Strike off the sand slurry flush with the existing pavement surface 16
and allow the mixture to cure. Top off cracks that were not completely filled with additional 17
sand slurry. Do not place the HMA overlay until the slurry has fully cured. 18
19
The sand slurry shall consist of approximately 20 percent CSS-1 emulsified asphalt, 20
approximately 2 percent portland cement, water (if required), and the remainder clean Class 21
1 or 2 fine aggregate per section 9-03.1(2). The components shall be thoroughly mixed and 22
then poured into the cracks and joints until full. The following day, any cracks or joints that 23
are not completely filled shall be topped off with additional sand slurry. After the sand slurry 24
is placed, the filler shall be struck off flush with the existing pavement surface and allowed to 25
cure. The HMA overlay shall not be placed until the slurry has fully cured. The 26
requirements of Section 1-06 will not apply to the portland cement and sand used in the 27
sand slurry. 28
29
In areas where HMA will be placed, use sand slurry to fill the cracks. 30
31
In areas where HMA will not be placed, fill the cracks as follows: 32
33
1. Cracks ¼ inch to 1 inch in width - fill with hot poured sealant. 34
2. Cracks greater than 1 inch in width – fill with sand slurry. 35
36
Hot Poured Sealant: For cracks that are to be filled with hot poured sealant, apply the 37
material in accordance with these requirements and the manufacturer’s recommendations. 38
Furnish a Type 1 Working Drawing of the manufacturer’s product information and 39
recommendations to the Engineer prior to the start of work, including the manufacturer’s 40
recommended heating time and temperatures, allowable storage time and temperatures 41
after initial heating, allowable reheating criteria, and application temperature range. Confine 42
hot poured sealant material within the crack. Clean any overflow of sealant from the 43
pavement surface. If, in the opinion of the Engineer, the Contractor’s method of sealing the 44
cracks with hot poured sealant results in an excessive amount of material on the pavement 45
surface, stop and correct the operation to eliminate the excess material. 46
47
5-04.3(4)A2 Crack Sealing Areas Prior to Paving 48
In areas where HMA will be placed, use sand slurry to fill the cracks. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-69
5-04.3(4)A3 Crack Sealing Areas Not to be Paved 1
In areas where HMA will not be placed, fill the cracks as follows: 2
3
A. Cracks ¼ inch to 1 inch in width - fill with hot poured sealant. 4
B. Cracks greater than 1 inch in width – fill with sand slurry. 5
6
(June 26, 2020 COP GSP) 7
Add the following new section: 8
9
5-04.3(4)B Soil Residual Herbicide 10
The Contractor shall apply one application of an approved soil residual herbicide on areas 11
where hot mix asphalt is applied. The requirements of Section 8-02.3(2)A shall apply to this 12
application. The application of herbicide shall precede paving by no more than 24 hours. 13
14
5-04.3(4)C Pavement Repair 15
The Contractor shall excavate pavement repair areas and shall backfill these with HMA in 16
accordance with the details shown in the Plans and as marked in the field. The Contractor 17
shall conduct the excavation operations in a manner that will protect the pavement that is to 18
remain. Pavement not designated to be removed that is damaged as a result of the 19
Contractor’s operations shall be repaired by the Contractor to the City’s satisfaction. All 20
costs associated with that pavement repair shall be at the expense of the Contractor. 21
22
The Contractor shall excavate only within one lane at a time unless approved otherwise by 23
the Engineer. The Contractor shall not excavate more area than can be completely finished 24
during the same shift, unless approved by the City 25
26
Unless otherwise shown in the Plans or determined by the City, excavate to a depth of 1.0 27
feet. The City will make the final determination of the excavation depth required. The 28
minimum width of any pavement repair area shall be 40 inches unless shown otherwise in 29
the Plans. Before any excavation, the existing pavement shall be sawcut or shall be 30
removed by a pavement grinder. Excavated materials will become the property of the 31
Contractor and shall be disposed of in a Contractor-provided site off the Right of Way or 32
used in accordance with Sections 2-02.3(3) or 9-03.21. 33
34
Asphalt for tack coat shall be required as specified in Section 5-04.3(4). A heavy application 35
of tack coat shall be applied to all surfaces of existing pavement in the pavement repair 36
area. 37
38
Placement of the HMA backfill shall be accomplished in lifts not to exceed 0.35-foot 39
compacted depth. Lifts that exceed 0.35-foot of compacted depth may be accomplished 40
with the approval of the City. Each lift shall be thoroughly compacted by a mechanical 41
tamper or a roller. 42
43
(June 26, 2020 COP GSP) 44
Supplement this section with the following: 45
46
After the completion of trench and patch repairs, the Contractor shall seal all joints with 47
CSS-1 and dry paving sand. 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-70
5-04.3(5) Producing/Stockpiling Aggregates and RAP 1
Aggregates and RAP shall be stockpiled according to the requirements of Section 3-02. 2
Sufficient storage space shall be provided for each size of aggregate and RAP. Materials 3
shall be removed from stockpile(s) in a manner to ensure minimal segregation when being 4
moved to the HMA plant for processing into the final mixture. Different aggregate sizes shall 5
be kept separated until they have been delivered to the HMA plant. 6
7
5-04.3(5)A Vacant 8
9
5-04.3(6) Mixing 10
After the required amount of mineral materials, asphalt binder, recycling agent and anti-11
stripping additives have been introduced into the mixer the HMA shall be mixed until 12
complete and uniform coating of the particles and thorough distribution of the asphalt binder 13
throughout the mineral materials is ensured. 14
15
When discharged, the temperature of the HMA shall not exceed the optimum mixing 16
temperature by more than 25°F as shown on the reference mix design report or as approved 17
by the Engineer. Also, when a WMA additive is included in the manufacture of HMA, the 18
discharge temperature of the HMA shall not exceed the maximum recommended by the 19
manufacturer of the WMA additive. A maximum water content of 2 percent in the mix, at 20
discharge, will be allowed providing the water causes no problems with handling, stripping, 21
or flushing. If the water in the HMA causes any of these problems, the moisture content 22
shall be reduced as directed by the Engineer. 23
24
Storing or holding of the HMA in approved storage facilities will be permitted with approval of 25
the Engineer, but in no event shall the HMA be held for more than 24 hours. HMA held for 26
more than 24 hours after mixing shall be rejected. Rejected HMA shall be disposed of by 27
the Contractor at no expense to the City. The storage facility shall have an accessible 28
device located at the top of the cone or about the third point. The device shall indicate the 29
amount of material in storage. No HMA shall be accepted from the storage facility when the 30
HMA in storage is below the top of the cone of the storage facility, except as the storage 31
facility is being emptied at the end of the working shift. 32
33
Recycled asphalt pavement (RAP) utilized in the production of HMA shall be sized prior to 34
entering the mixer so that a uniform and thoroughly mixed HMA is produced. If there is 35
evidence of the recycled asphalt pavement not breaking down during the heating and mixing 36
of the HMA, the Contractor shall immediately suspend the use of the RAP until changes 37
have been approved by the Engineer. After the required amount of mineral materials, RAP, 38
new asphalt binder and asphalt rejuvenator have been introduced into the mixer the HMA 39
shall be mixed until complete and uniform coating of the particles and thorough distribution 40
of the asphalt binder throughout the mineral materials, and RAP is ensured. 41
42
5-04.3(7) Spreading and Finishing 43
The mixture shall be laid upon an approved surface, spread, and struck off to the grade and 44
elevation established. HMA pavers complying with Section 5-04.3(3) shall be used to 45
distribute the mixture. Unless otherwise directed by the Engineer, the nominal compacted 46
depth of any layer of any course shall not exceed 0.30 feet. 47
48
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-71
On areas where irregularities or unavoidable obstacles make the use of mechanical 1
spreading and finishing equipment impractical, the paving may be done with other 2
equipment or by hand. 3
4
When more than one JMF is being utilized to produce HMA, the material produced for each 5
JMF shall be placed by separate spreading and compacting equipment. The intermingling 6
of HMA produced from more than one JMF is prohibited. Each strip of HMA placed during a 7
work shift shall conform to a single JMF established for the class of HMA specified unless 8
there is a need to make an adjustment in the JMF. 9
10
5-04.3(8) Aggregate Acceptance Prior to Incorporation in HMA 11
For HMA accepted by nonstatistical evaluation the aggregate properties of sand equivalent, 12
uncompacted void content and fracture will be evaluated in accordance with Section 3-04. 13
Sampling and testing of aggregates for HMA accepted by commercial evaluation will be at 14
the option of the Engineer. 15
16
5-04.3(9) HMA Mixture Acceptance 17
Acceptance of HMA shall be as provided under nonstatistical, or commercial evaluation. 18
19
Nonstatistical evaluation will be used for the acceptance of HMA unless Commercial 20
Evaluation is specified. 21
22
Commercial evaluation will be used for Commercial HMA and for other classes of HMA in 23
the following applications: sidewalks, road approaches, ditches, slopes, paths, trails, gores, 24
prelevel, temporary pavement, and pavement repair. Other nonstructural applications of 25
HMA accepted by commercial evaluation shall be as approved by the Engineer. Sampling 26
and testing of HMA accepted by commercial evaluation will be at the option of the Engineer. 27
28
The mix design will be the initial JMF for the class of HMA. The Contractor may request a 29
change in the JMF. Any adjustments to the JMF will require the approval of the Engineer 30
and may be made in accordance with this section. 31
32
HMA Tolerances and Adjustments 33
1. Job Mix Formula Tolerances – The constituents of the mixture at the time of 34
acceptance shall be within tolerance. The tolerance limits will be established as 35
follows: 36
For Asphalt Binder and Air Voids (Va), the acceptance limits are determined by 37
adding the tolerances below to the approved JMF values. These values will 38
also be the Upper Specification Limit (USL) and Lower Specification Limit (LSL) 39
required in Section 1-06.2(2)D2 40
Property Non-Statistical Evaluation Commercial Evaluation
Asphalt Binder +/- 0.5% +/- 0.7%
Air Voids, Va 2.5% min. and 5.5% max N/A
41
42
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-72
For Aggregates in the mixture: 1
a. First, determine preliminary upper and lower acceptance limits by applying the 2
following tolerances to the approved JMF. 3
Aggregate Percent
Passing
Non-Statistical
Evaluation
Commercial
Evaluation
1”, ¾”, ½”, and 3/8” sieves +/- 6% +/- 8%
No. 4 sieve +/-6% +/- 8%
No. 8 Sieve +/- 6% +/-8%
No. 200 sieve +/- 2.0% +/- 3.0%
b. Second, adjust the preliminary upper and lower acceptance limits determined from 4
step (a) the minimum amount necessary so that none of the aggregate properties 5
are outside the control points in Section 9-03.8(6). The resulting values will be the 6
upper and lower acceptance limits for aggregates, as well as the USL and LSL 7
required in Section 1-06.2(2)D2. 8
2. Job Mix Formula Adjustments – An adjustment to the aggregate gradation or asphalt 9
binder content of the JMF requires approval of the Engineer. Adjustments to the 10
JMF will only be considered if the change produces material of equal or better quality 11
and may require the development of a new mix design if the adjustment exceeds the 12
amounts listed below. 13
a. Aggregates –2 percent for the aggregate passing the 1½″, 1″, ¾″, ½″, ⅜″, and the 14
No. 4 sieves, 1 percent for aggregate passing the No. 8 sieve, and 0.5 percent 15
for the aggregate passing the No. 200 sieve. The adjusted JMF shall be within 16
the range of the control points in Section 9-03.8(6). 17
b. Asphalt Binder Content – The Engineer may order or approve changes to 18
asphalt binder content. The maximum adjustment from the approved mix design 19
for the asphalt binder content shall be 0.3 percent 20
21
5-04.3(9)A Vacant 22
23
5-04.3(9)B Vacant 24
25
5-04.3(9)C Mixture Acceptance – Nonstatistical Evaluation 26
HMA mixture which is accepted by Nonstatistical Evaluation will be evaluated by the City by 27
dividing the HMA tonnage into lots. 28
29
5-04.3(9)C1 Mixture Nonstatistical Evaluation – Lots and Sublots 30
A lot is represented by randomly selected samples of the same mix design that will be 31
tested for acceptance. A lot is defined as the total quantity of material or work produced for 32
each Job Mix Formula placed. Only one lot per JMF is expected. A sublot shall be equal to 33
one day’s production or 800 tons, whichever is less except that the final sublot will be a 34
minimum of 400 tons and may be increased to 1200 tons. 35
36
All of the test results obtained from the acceptance samples from a given lot shall be 37
evaluated collectively. If the Contractor requests a change to the JMF that is approved, the 38
material produced after the change will be evaluated on the basis of the new JMF for the 39
remaining sublots in the current lot and for acceptance of subsequent lots. For a lot in 40
progress with a CPF less than 0.75, a new lot will begin at the Contractor’s request after the 41
Engineer is satisfied that material conforming to the Specifications can be produced. 42
43
Sampling and testing for evaluation shall be performed on the frequency of one sample per 44
sublot. 45
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-73
1
5-04.3(9)C2 Mixture Nonstatistical Evaluation Sampling 2
Samples for acceptance testing shall be obtained by the Contractor when ordered by the 3
Engineer. The Contractor shall sample the HMA mixture in the presence of the Engineer 4
and in accordance with AASH-TO T 168. A minimum of three samples should be taken for 5
each class of HMA placed on a project. 6
7
5-04.3(9)C3 Mixture Nonstatistical Evaluation – Acceptance Testing 8
Testing of HMA for compliance of Va will at the option of the City. If tested, compliance of Va 9
will use WSDOT SOP 731. 10
11
Testing for compliance of asphalt binder content will be by WSDOT FOP for AASHTO T 12
308. 13
14
Testing for compliance of gradation will be by FOP for WAQTC T 27/T 11. 15
16
5-04.3(9)C4 Mixture Nonstatistical Evaluation – Pay Factors 17
For each lot of material falling outside the tolerance limits in 5-04.3(9), the City will 18
determine a Composite Pay Factor (CPF) using the following price adjustment factors: 19
20
Table of Price Adjustment Factors
Constituent Factor
“f”
All aggregate passing: 1½″, 1″, ¾″, ½″, ⅜″ and
No.4 sieves
2
All aggregate passing No. 8 sieve 15
All aggregate passing No. 200 sieve 20
Asphalt binder 40
Air Voids (Va) (where applicable) 20
21
Each lot of HMA produced under Nonstatistical Evaluation and having all constituents falling 22
within the tolerance limits of the job mix formula shall be accepted at the unit Contract price 23
with no further evaluation. When one or more constituents fall outside the nonstatistical 24
tolerance limits in the Job Mix Formula shown in Table of Price Adjustment Factors, the lot 25
shall be evaluated in accordance with Section 1-06.2 to determine the appropriate CPF. 26
The nonstatistical tolerance limits will be used in the calculation of the CPF and the 27
maximum CPF shall be 1.00. When less than three sublots exist, backup samples of the 28
existing sublots or samples from the Roadway shall be tested to provide a minimum of three 29
sets of results for evaluation. 30
31
5-04.3(9)C5 Vacant 32
33
5-04.3(9)C6 Mixture Nonstatistical Evaluation – Price Adju stments 34
For each lot of HMA mix produced under Nonstatistical Evaluation when the calculated CPF 35
is less than 1.00, a Nonconforming Mix Factor (NCMF) will be determined. The NCMF 36
equals the algebraic difference of CPF minus 1.00 multiplied by 60 percent. The total job 37
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-74
mix compliance price adjustment will be calculated as the product of the NCMF, the quantity 1
of HMA in the lot in tons, and the unit Contract price per ton of mix. 2
3
If a constituent is not measured in accordance with these Specifications, its individual pay 4
factor will be considered 1.00 in calculating the Composite Pay Factor (CPF). 5
6
5-04.3(9)C7 Mixture Nonstatistical Evaluation - Retests 7
The Contractor may request a sublot be retested. To request a retest, the Contractor shall 8
submit a written request within 7 calendar days after the specific test results have been 9
received. A split of the original acceptance sample will be retested. The split of the sample 10
will not be tested with the same tester that ran the original acceptance test. The sample will 11
be tested for a complete gradation analysis, asphalt binder content, and, at the option of the 12
agency, Va. The results of the retest will be used for the acceptance of the HMA in place of 13
the original sublot sample test results. The cost of testing will be deducted from any monies 14
due or that may come due the Contractor under the Contract at the rate of $500 per sample. 15
16
5-04.3(9)D Mixture Acceptance – Commercial Evaluation 17
If sampled and tested, HMA produced under Commercial Evaluation and having all 18
constituents falling within the tolerance limits of the job mix formula shall be accepted at the 19
unit Contract price with no further evaluation. When one or more constituents fall outside 20
the commercial tolerance limits in the Job Mix Formula shown in 5-04.3(9), the lot shall be 21
evaluated in accordance with Section 1-06.2 to determine the appropriate CPF. The 22
commercial tolerance limits will be used in the calculation of the CPF and the maximum CPF 23
shall be 1.00. When less than three sublots exist, backup samples of the existing sublots or 24
samples from the street shall be tested to provide a minimum of three sets of results for 25
evaluation. 26
27
For each lot of HMA mix produced and tested under Commercial Evaluation when the 28
calculated CPF is less than 1.00, a Nonconforming Mix Factor (NCMF) will be determined. 29
The NCMF equals the algebraic difference of CPF minus 1.00 multiplied by 60 percent. The 30
Job Mix Compliance Price Adjustment will be calculated as the product of the NCMF, the 31
quantity of HMA in the lot in tons, and the unit Contract price per ton of mix. 32
33
If a constituent is not measured in accordance with these Specifications, its individual pay 34
factor will be considered 1.00 in calculating the Composite Pay Factor (CPF). 35
36
5-04.3(10) HMA Compaction Acceptance 37
HMA mixture accepted by nonstatistical evaluation that is used in traffic lanes, including 38
lanes for intersections, ramps, truck climbing, weaving, and speed change, and having a 39
specified compacted course thickness greater than 0.10-foot, shall be compacted to a 40
specified level of relative density. The specified level of relative density shall be a 41
Composite Pay Factor (CPF) of not less than 0.75 when evaluated in accordance with 42
Section 1-06.2, using a LSL of 92.0 (minimum of 92 percent of the maximum density). The 43
maximum density shall be determined by WSDOT FOP for AASHTO T 729. The specified 44
level of density attained will be determined by the evaluation of the density of the pavement. 45
The density of the pavement shall be determined in accordance with WSDOT FOP for 46
WAQTC TM 8, except that gauge correlation will be at the discretion of the Engineer, when 47
using the nuclear density gauge and WSDOT SOP 736 when using cores to determine 48
density. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-75
Tests for the determination of the pavement density will be taken in accordance with the 1
required procedures for measurement by a nuclear density gauge or roadway cores after 2
completion of the finish rolling. 3
4
(June 26, 2020 COP GSP) 5
Supplement this section with the following: 6
7
The test procedures FOP for WAQTC TM 8 and WSDOT SOP T 729 will be used on the day 8
the mix is placed and prior to opening to traffic. 9
10
Two (2) density tests shall be taken within the first one hundred (100) tons of asphalt 11
delivered to the site each day and one (1) every 100 tons thereafter for the remainder of the 12
day. If the asphalt fails any test, the City will require additional testing to determine the 13
extent of the failure and more frequent tests may be required on additional asphalt. Testing 14
and samples shall be in accordance with Section 1-06.2(1). 15
16
In addition to randomly selected density test locations, the City may also isolate any area 17
that is suspected of being defective in relative density, and may require additional testing at 18
the Contractor’s expense. 19
20
HMA for preleveling shall be thoroughly compacted. HMA that is used for preleveling wheel 21
rutting shall be compacted with a pneumatic tire roller unless otherwise approved by the 22
City. 23
24
(June 26, 2020 COP GSP) 25
Revise this section from the APWA GSP and replace it with the following: 26
27
Test Results 28
HMA testing shall be pre-arranged and oil content results reported within two (2) hours of 29
sampling. Initial reports may be by phone, subsequent written documents shall be 30
submitted to the City prior to the next day’s paving shift. 31
32
5-04.3(10)A HMA Compaction – General Compaction Requirements 33
Compaction shall take place when the mixture is in the proper condition so that no undue 34
displacement, cracking, or shoving occurs. Areas inaccessible to large compaction 35
equipment shall be compacted by other mechanical means. Any HMA that becomes loose, 36
broken, contaminated, shows an excess or deficiency of asphalt, or is in any way defective, 37
shall be removed and replaced with new hot mix that shall be immediately compacted to 38
conform to the surrounding area. 39
40
The type of rollers to be used and their relative position in the compaction sequence shall 41
generally be the Contractor’s option, provided the specified densities are attained. Unless 42
the Engineer has approved otherwise, rollers shall only be operated in the static mode when 43
the internal temperature of the mix is less than 175°F. Regardless of mix temperature, a 44
roller shall not be operated in a mode that results in checking or cracking of the mat. Rollers 45
shall only be operated in static mode on bridge decks. 46
47
5-04.3(10)B HMA Compaction – Cyclic Density 48
(******) 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-76
Low cyclic density areas are defined as spots or streaks in the pavement that are less than 1
90 percent of the theoretical maximum density. The City may evaluate the HMA pavement 2
for low cyclic density at their discretion, and when doing so will follow WSDOT SOP 733. 3
Should the City accept a section of pavement with low cyclic density areas, a Cyclic Density 4
Price Adjustment may be assessed at the discretion of the City. 5
6
5-04.3(10)C Vacant 7
8
5-04.3(10)D HMA Nonstatistical Compaction 9
10
5-04.3(10)D1 HMA Nonstatistical Compaction – Lots and Sublots 11
HMA compaction which is accepted by nonstatistical evaluation will be based on acceptance 12
testing performed by the City dividing the project into compaction lots. 13
14
A lot is represented by randomly selected samples of the same mix design that will be 15
tested for acceptance. A lot is defined as the total quantity of material or work produced for 16
each Job Mix Formula placed. Only one lot per JMF is expected. A sublot shall be equal to 17
one day’s production or 400 tons, whichever is less except that the final sublot will be a 18
minimum of 200 tons and may be increased to 800 tons. Testing for compaction will be at 19
the rate of 5 tests per sublot per WSDOT T 738. 20
21
The sublot locations within each density lot will be determined by the Engineer. For a lot in 22
progress with a CPF less than 0.75, a new lot will begin at the Contractor’s request after the 23
Engineer is satisfied that material conforming to the Specifications can be produced. 24
25
HMA mixture accepted by commercial evaluation and HMA constructed under conditions 26
other than those listed above shall be compacted on the basis of a test point evaluation of 27
the compaction train. The test point evaluation shall be performed in accordance with 28
instructions from the Engineer. The number of passes with an approved compaction train, 29
required to attain the maximum test point density, shall be used on all subsequent paving. 30
31
HMA for preleveling shall be thoroughly compacted. HMA that is used to prelevel wheel ruts 32
shall be compacted with a pneumatic tire roller unless otherwise approved by the Engineer. 33
34
5-04.3(10)D2 HMA Compaction Nonstatistical Evaluation – Acceptance Testing 35
The location of the HMA compaction acceptance tests will be randomly selected by the 36
Engineer from within each sublot, with one test per sublot. 37
38
5-04.3(10)D3 HMA Nonstatistical Compaction – Price Adjustments 39
For each compaction lot with one or two sublots, having all sublots attain a relative density 40
that is 92 percent of the reference maximum density the HMA shall be accepted at the unit 41
Contract price with no further evaluation. When a sublot does not attain a relative density 42
that is 92 percent of the reference maximum density, the lot shall be evaluated in 43
accordance with Section 1-06.2 to determine the appropriate CPF. The maximum CPF shall 44
be 1.00, however, lots with a calculated CPF in excess of 1.00 will be used to offset lots with 45
CPF values below 1.00 but greater than 0.90. Lots with CPF lower than 0.90 will be 46
evaluated for compliance per 5-04.3(11). Additional testing by either a nuclear moisture-47
density gauge or cores will be completed as required to provide a minimum of three tests for 48
evaluation. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-77
For compaction below the required 92% a Non-Conforming Compaction Factor (NCCF) will 1
be determined. The NCCF equals the algebraic difference of CPF minus 1.00 multiplied by 2
40 percent. The Compaction Price Adjustment will be calculated as the product of CPF, the 3
quantity of HMA in the compaction control lot in tons, and the unit Contract price per ton of 4
mix. 5
6
5-04.3(11) Reject Work 7
8
5-04.3(11)A Reject Work General 9
Work that is defective or does not conform to Contract requirements shall be rejected. The 10
Contractor may propose, in writing, alternatives to removal and replacement of rejected 11
material. Acceptability of such alternative proposals will be determined at the sole discretion 12
of the Engineer. HMA that has been rejected is subject to the requirements in Section 1-13
06.2(2) and this specification, and the Contractor shall submit a corrective action proposal to 14
the Engineer for approval. 15
16
5-04.3(11)B Rejection by Contractor 17
The Contractor may, prior to sampling, elect to remove any defective material and replace it 18
with new material. Any such new material will be sampled, tested, and evaluated for 19
acceptance. 20
21
5-04.3(11)C Rejection Without Testing (Mixture or Compaction) 22
The Engineer may, without sampling, reject any batch, load, or section of Roadway that 23
appears defective. Material rejected before placement shall not be incorporated into the 24
pavement. Any rejected section of Roadway shall be removed. 25
26
No payment will be made for the rejected materials or the removal of the materials unless 27
the Contractor requests that the rejected material be tested. If the Contractor elects to have 28
the rejected material tested, a minimum of three representative samples will be obtained 29
and tested. Acceptance of rejected material will be based on conformance with the 30
nonstatistical acceptance Specification. If the CPF for the rejected material is less than 31
0.75, no payment will be made for the rejected material; in addition, the cost of sampling and 32
testing shall be borne by the Contractor. If the CPF is greater than or equal to 0.75, the cost 33
of sampling and testing will be borne by the City. If the material is rejected before 34
placement and the CPF is greater than or equal to 0.75, compensation for the rejected 35
material will be at a CPF of 0.75. If rejection occurs after placement and the CPF is greater 36
than or equal to 0.75, compensation for the rejected material will be at the calculated CPF 37
with an addition of 25 percent of the unit Contract price added for the cost of removal and 38
disposal. 39
40
5-04.3(11)D Rejection - A Partial Sublot 41
In addition to the random acceptance sampling and testing, the Engineer may also isolate 42
from a normal sublot any material that is suspected of being defective in relative density, 43
gradation or asphalt binder content. Such isolated material will not include an original 44
sample location. A minimum of three random samples of the suspect material will be 45
obtained and tested. The material will then be statistically evaluated as an independent lot 46
in accordance with Section 1-06.2(2). 47
48
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-78
5-04.3(11)E Rejection - An Entire Sublot 1
An entire sublot that is suspected of being defective may be rejected. When a sublot is 2
rejected a minimum of two additional random samples from this sublot will be obtained. 3
These additional samples and the original sublot will be evaluated as an independent lot in 4
accordance with Section 1-06.2(2). 5
6
5-04.3(11)F Rejection - A Lot in Progress 7
The Contractor shall shut down operations and shall not resume HMA placement until such 8
time as the Engineer is satisfied that material conforming to the Specifications can be 9
produced: 10
11
1. When the Composite Pay Factor (CPF) of a lot in progress drops below 1.00 and the 12
Contractor is taking no corrective action, or 13
2. When the Pay Factor (PF) for any constituent of a lot in progress drops below 0.95 14
and the Contractor is taking no corrective action, or 15
3. When either the PFi for any constituent or the CPF of a lot in progress is less than 16
0.75. 17
18
5-04.3(11)G Rejection - An Entire Lot (Mixture or Compaction) 19
20
An entire lot with a CPF of less than 0.75 will be rejected. 21
22
5-04.3(12) Joints 23
24
5-04.3(12)A HMA Joints 25
26
5-04.3(12)A1 Transverse Joints 27
The Contractor shall conduct operations such that the placing of the top or wearing course is 28
a continuous operation or as close to continuous as possible. Unscheduled transverse 29
joints will be allowed and the roller may pass over the unprotected end of the freshly laid 30
mixture only when the placement of the course must be discontinued for such a length of 31
time that the mixture will cool below compaction temperature. When the Work is resumed, 32
the previously compacted mixture shall be cut back to produce a slightly beveled edge for 33
the full thickness of the course. 34
35
A temporary wedge of HMA constructed on a 20H:1V shall be constructed where a 36
transverse joint as a result of paving or planing is open to traffic. The HMA in the temporary 37
wedge shall be separated from the permanent HMA by strips of heavy wrapping paper or 38
other methods approved by the Engineer. The wrapping paper shall be removed and the 39
joint trimmed to a slightly beveled edge for the full thickness of the course prior to 40
resumption of paving. 41
42
The material that is cut away shall be wasted and new mix shall be laid against the cut. 43
Rollers or tamping irons shall be used to seal the joint. 44
45
46
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-79
5-04.3(12)A2 Longitudinal Joints 1
The longitudinal joint in any one course shall be offset from the course immediately below by 2
not more than 6 inches nor less than 2 inches. All longitudinal joints constructed in the 3
wearing course shall be located at a lane line or an edge line of the Traveled Way. A 4
notched wedge joint shall be constructed along all longitudinal joints in the wearing surface 5
of new HMA unless otherwise approved by the Engineer. The notched wedge joint shall 6
have a vertical edge of not less than the maximum aggregate size or more than ½ of the 7
compacted lift thickness and then taper down on a slope not steeper than 4H:1V. The 8
sloped portion of the HMA notched wedge joint shall be uniformly compacted. 9
10
(June 26, 2020 COP GSP) 11
Supplement this section with the following: 12
13
All joints shall be hand raked prior to rolling. The final joint shall be straight, level with the 14
abutting edge, free of coarse material at the surface, and neat in appearance. The 15
Contractor shall use panel widths that minimize longitudinal pavement joints. 16
17
5-04.3(12)B2 Paved Panel Joint Seal 18
Construct the paved panel joint seal in accordance with the requirements specified in 19
section 5-04.3(12)B1 and the following requirement: 20
21
1. Clean and seal the existing joint between concrete panels in accordance with Section 22
5-01.3(8) and the details shown in the Standard Plans. 23
24
5-04.3(13) Surface Smoothness 25
The completed surface of all courses shall be of uniform texture, smooth, uniform as to 26
crown and grade, and free from defects of all kinds. The completed surface of the wearing 27
course shall not vary more than ⅛ inch from the lower edge of a 10-foot straightedge placed 28
on the surface parallel to the centerline. The transverse slope of the completed surface of 29
the wearing course shall vary not more than ¼ inch in 10 feet from the rate of transverse 30
slope shown in the Plans. 31
32
When deviations in excess of the above tolerances are found that result from a high place in 33
the HMA, the pavement surface shall be corrected by one of the following methods: 34
35
1. Removal of material from high places by grinding with an approved grinding machine, 36
or 37
2. Removal and replacement of the wearing course of HMA, or 38
3. By other method approved by the Engineer. 39
40
Correction of defects shall be carried out until there are no deviations anywhere greater than 41
the allowable tolerances. 42
43
Deviations in excess of the above tolerances that result from a low place in the HMA and 44
deviations resulting from a high place where corrective action, in the opinion of the 45
Engineer, will not produce satisfactory results will be accepted with a price adjustment. The 46
Engineer shall deduct from monies due or that may become due to the Contractor the sum 47
of $500.00 for each and every section of single traffic lane 100 feet in length in which any 48
excessive deviations described above are found. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-80
When utility appurtenances such as manhole covers and valve boxes are located in the 1
traveled way, the utility appurtenances shall be adjusted to the finished grade prior to 2
paving. This requirement may be waived when requested by the Contractor, at the 3
discretion of the Engineer or when the adjustment details provided in the project plan or 4
specifications call for utility appurtenance adjustments after the completion of paving. 5
6
Utility appurtenance adjustment discussions will be included in the Pre-Paving planning (5-7
04.3(14)B3). Submit a written request to waive this requirement to the Engineer prior to the 8
start of paving. 9
10
5-04.3(14)B Paving and Planing Under Traffic 11
12
5-04.3(14)B1 General 13
In addition the requirements of Section 1-07.23 and the traffic controls required in Section 1-14
10, and unless the Contract specifies otherwise or the Engineer approves, the Contractor 15
must comply with the following: 16
17
1. Intersections: 18
a. Keep intersections open to traffic at all times, except when paving or planing 19
operations through an intersection requires closure. Such closure must be kept to 20
the minimum time required to place and compact the HMA mixture, or plane as 21
appropriate. For paving, schedule such closure to individual lanes or portions 22
thereof that allows the traffic volumes and schedule of traffic volumes required in 23
the approved traffic control plan. Schedule work so that adjacent intersections are 24
not impacted at the same time and comply with the traffic control restrictions 25
required by the Traffic Engineer. Each individual intersection closure or partial 26
closure, must be addressed in the traffic control plan, which must be submitted to 27
and accepted by the Engineer, see Section 1-10.2(2). 28
b. When planing or paving and related construction must occur in an intersection, 29
consider scheduling and sequencing such work into quarters of the intersection, or 30
half or more of an intersection with side street detours. Be prepared to sequence 31
the work to individual lanes or portions thereof. 32
c. Should closure of the intersection in its entirety be necessary, and no trolley 33
service is impacted, keep such closure to the minimum time required to place and 34
compact the HMA mixture, plane, remove asphalt, tack coat, and as needed. 35
d. Any work in an intersection requires advance warning in both signage and a 36
number of Working Days advance notice as determined by the Engineer, to alert 37
traffic and emergency services of the intersection closure or partial closure. 38
e. Allow new compacted HMA asphalt to cool to ambient temperature before any 39
traffic is allowed on it. Traffic is not allowed on newly placed asphalt until approval 40
has been obtained from the Engineer. 41
2. Temporary centerline marking, post-paving temporary marking, temporary stop 42
bars, and maintaining temporary pavement marking must comply with Section 8-43
23. 44
3. Permanent pavement marking must comply with Section 8-22. 45
46
47
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-81
5-04.3(14)B2 Submittals –HMA Paving Plan 1
The Contractor must submit a separate paving plan to the Engineer at least 5 Working Days 2
in advance of each operation’s activity start date. This plan must show how the moving 3
operation and traffic control are coordinated, as they will be discussed at the pre-paving 4
briefing. When requested by the Engineer, the Contractor must provide each operation’s 5
traffic control plan on 24 x 36 inch or larger size Shop Drawings with a scale showing both 6
the area of operation and sufficient detail of traffic beyond the area of operation where 7
detour traffic may be required. The scale on the Shop Drawings is 1 inch = 20 feet, which 8
may be changed if the Engineer agrees sufficient detail is shown. 9
10
The paving operation include, but are not limited to, metal detection, removal of asphalt and 11
temporary asphalt of any kind, tack coat and drying, staging of supply trucks, paving trains, 12
rolling, scheduling, and as may be discussed at the briefing. 13
14
When intersections will be partially or totally blocked, provide adequately sized and 15
noticeable signage alerting traffic of closures to come, a minimum 2 Working Days in 16
advance. The traffic control plan must show where police officers will be stationed when 17
signalization is or may be, countermanded, and show areas where flaggers are proposed. 18
19
At a minimum, the paving plan must include: 20
21
1. A copy of the accepted traffic control plan, see Section 1-10.2(2), detailing each 22
day’s traffic control as it relates to the specific requirements of that day’s paving. 23
Briefly describe the sequencing of traffic control consistent with the proposed paving 24
sequence, and scheduling of placement of temporary pavement markings and 25
channelizing devices after each day’s paving. 26
2. A copy of each intersection’s traffic control plan. 27
3. Haul routes from Supplier facilities, and locations of temporary parking and staging 28
areas, including return routes. Describe the complete round trip as it relates to the 29
sequencing of paving operations. 30
4. Names and locations of HMA Supplier facilities to be used. 31
5. List of all equipment to be used for paving. 32
6. List of personnel and associated job classification assigned to each piece of paving 33
equipment. 34
7. Description (geometric or narrative) of the scheduled sequence of paving, and 35
intended area of paving for each day’s work, must include the directions of proposed 36
paving, sequence of adjacent lane paving, sequence of skipped lane paving, 37
intersection planing and paving scheduling and sequencing, and proposed 38
notifications and coordinations to be timely made. The plan must show HMA joints 39
relative to the final pavement marking lane lines. 40
8. Names, job titles, and contact information for field, office, and plant supervisory 41
personnel. 42
9. A copy of the approved Mix Designs. 43
10. Tonnage of HMA to be placed each day. 44
11. Approximate times and days for starting and ending daily operations. 45
46
5-04.3(14)B3 Pre-Paving and Pre-Planing Briefing 47
At least 2 Working Days before the first paving operation and the first planing operation, or 48
as scheduled by the Engineer for future paving and planing operations to ensure the 49
Contractor has adequately prepared for notifying and coordinating as required in the 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-82
Contract, the Contractor must be prepared to discuss that day’s operations as they relate to 1
other entities and to public safety and convenience, including driveway and business 2
access, garbage truck operations, Metro transit operations and working around energized 3
overhead wires, school and nursing home and hospital and other accesses, other 4
Contractors who may be operating in the area, pedestrian and bicycle traffic, and 5
emergency services. The Contractor, and Subcontractors that may be part of that day’s 6
operations, must meet with the Engineer and discuss the proposed operation as it relates to 7
the submitted planing plan and paving plan, approved traffic control plan, and public 8
convenience and safety. Such discussion includes, but is not limited to: 9
10
1. General for Paving Plan: 11
a. The actual times of starting and ending daily operations. 12
b. In intersections, how to break up the intersection, and address traffic control 13
and signalization for that operation, including use of peace officers. 14
c. The sequencing and scheduling of paving operations, as applicable, as it 15
relates to traffic control, to public convenience and safety, and to other con-16
tractors who may operate in the Project Site. 17
d. Notifications required of Contractor activities, and coordinating with other 18
entities and the public as necessary. 19
e. Description of the sequencing of installation and types of temporary 20
pavement markings as it relates to planning and to paving. 21
f. Description of the sequencing of installation of, and the removal of, temporary 22
pavement patch material around exposed castings and as may be needed 23
g. Description of procedures and equipment to identify hidden metal in the 24
pavement, such as survey monumentation, monitoring wells, street car rail, 25
and castings, before planning, see Section 5-04.3(14)B2. 26
h. Description of how flaggers will be coordinated with the paving, and related 27
operations. 28
i. Description of sequencing of traffic controls for the process of rigid pavement 29
base repairs. 30
j. Other items the Engineer deems necessary to address. 31
2. Paving – additional topics: 32
a. When to start applying tack and coordinating with paving. 33
b. Types of equipment and numbers of each type equipment to be used. If 34
more pieces of equipment than personnel are proposed, describe the 35
sequencing of the personnel operating the types of equipment. Discuss the 36
continuance of operator personnel for each type equipment as it relates to 37
meeting Specification requirements. 38
c. Number of JMFs to be placed, and if more than one JMF how the Contractor 39
will ensure different JMFs are distinguished, how pavers and MTVs are 40
distinguished if more than one JMF is being placed at the time, and how 41
pavers and MTVs are cleaned so that one JMF does not adversely influence 42
the other JMF. 43
d. Description of contingency plans for that day’s operations such as equipment 44
breakdown, rain out, and Supplier shutdown of operations. 45
e. Number of sublots to be placed, sequencing of density testing, and other 46
sampling and testing. 47
48
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-83
5-04.3(15) Sealing Pavement Surfaces 1
Apply a fog seal to any areas where HMA pavement has been ground to correct the surface 2
elevation/finish. Construct the fog seal in accordance with Section 5-02.3. Unless 3
otherwise approved by the Engineer, apply the fog seal prior to opening to traffic. 4
5
5-04.3(16) HMA Road Approaches 6
HMA approaches shall be constructed at the locations shown in the Plans or where staked 7
by the Engineer. The Work shall be performed in accordance with Section 5-04. 8
9
Measurement 10
(******) 11
12
Revise this section to read: 13
14
The Bid Item “3" HMA, CL. 3/8", PG 64S-28 FOR ASPHALT REPAIR” and “2" HMA, CL. 15
3/8", PG 64S-28 FOR ASPHALT ALLEY PAVEMENT” will be measured by the ton in 16
accordance with Section 1-09.2, with no deduction being made for the weight of asphalt 17
binder, mineral filler, or any other component of the mixture. If the Contractor elects to 18
remove and replace mix as allowed by Section 5-04.3(11), the material removed will not be 19
measured. 20
21
Preparation of Existing Paved Surfaces will be measured by the linear foot. 22
23
Soil residual herbicide will be not be measured, it will be considered incidental to other 24
payment items and separate payment will not be made. 25
26
There will be no separate measurement for dust control (dewatering) and watering (e.g. 27
compaction) operations by the Contractor. 28
29
Payment 30
Payment will be made for each of the following Bid items that are included in the Proposal: 31
32
33
The unit contract price per ton for “3" HMA, CL. 3/8", PG 64S-28 FOR ASPHALT REPAIR”, 34
shall be full compensation for all costs, including materials, equipment, and labor, incurred 35
to carry out the requirements of Section 5-04 and its Special Provisions except for those 36
costs included in other items which are included in this Subsection and which are included in 37
the Proposal. This includes, but is not limited to, all costs necessary to prepare existing 38
paved surfaces, apply anti-stripping additive, apply soil residual herbicide, and provide dust 39
control. 40
41
The unit contract price per ton for “2" HMA, CL. 3/8", PG 64S-28 FOR ASPHALT ALLEY 42
PAVEMENT ”, shall be full compensation for all costs, including materials, equipment, and 43
labor, incurred to carry out the requirements of Section 5-04 and its Special Provisions 44
except for those costs included in other items which are included in this Subsection and 45
which are included in the Proposal. This includes, but is not limited to, all costs necessary 46
to prepare existing paved surfaces, apply anti-stripping additive, apply soil residual 47
herbicide, and provide dust control. 48
49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-84
If the Proposal does not include a Bid item for “Preparation of Untreated Roadway”, the 1
Roadway shall be prepared with herbicide as specified, but the Work shall be included in the 2
Contract prices of the other items of Work. 3
4
END DIVISION 5 5
6
7
8
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-85
1
DIVISION 6 2
STRUCTURES 3
4
6-02 CONCRETE STRUCTURES 5
6
6-02.3(14) Finishing Concrete Surfaces 7
(June 26, 2020 COP GSP) 8
9
Supplement this section with the following: 10
11
The completed surface shall be of uniform texture, smooth, uniform as to grade, and free 12
from defects of all kinds. The completed surface shall not vary more than 1/8-inch from the 13
lower edge of a 10-foot straightedge placed on the surface parallel to the centerline. 14
15
The finish shall be a light broom finish, or as noted in the Plans, or as approved by the City. 16
A non-uniform finish, an overworked finish, a finish where a cement layer has formed, 17
discolored, is spalling, or a finish damaged by the weather, will not be accepted, and shall 18
be replaced at the Contractor’s expense. 19
20
21
END DIVISION 6 22
23
24
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-86
DIVISION 7 1
DRAINAGE STRUCTURES, STORM SEWERS, SANITARY 2
SEWERS, WATER MAINS, AND CONDUITS 3
4
7-08 GENERAL PIPE INSTALLATION REQUIREMENTS 5
6
General 7
(******) 8
9
Supplement this section with the following 10
11
All construction work shall be inspected by the City Inspector prior to backfilling. At least 12
48 hours of notice shall be given to the City prior to backfilling. 13
14
The Contractor shall notify the Utility Notification Center (One Call Center) at least 48 hours 15
prior to start of excavation so that underground utilities may be marked. Telephone number 16
is 1-800-424-5555. An onsite meeting with Cascade Natural Gas will be performed to 17
review the existing gas line location prior to excavation in accordance with these Special 18
Provisions. 19
20
7-08.3(1)A Trenches 21
(June 26, 2020 COP GSP) 22
23
Supplement this section with the following: 24
25
Existing pavement shall be neatly saw-cut on both sides of the trench using parallel cuts 26
consistent with the dimensions presented on the Trench Surfacing Repair standard detail. 27
Sawcutting shall be performed prior to surface repair. 28
29
7-08.3(1)C Bedding the Pipe 30
(June 26, 2020 COP GSP) 31
32
Supplement this section with the following: 33
34
Gravel Backfill for Pipe Zone (including Bedding): Pipe zone material shall be Crushed 35
Surfacing Top Course meeting the requirements of section 9-03.9(3), and shall be placed 36
and compacted in layers as designated by the City. With prior approval by the City, 37
suitable native material may be an acceptable alternate for pipe zone bedding above the 38
bottom of the pipe. 39
40
Trench Backfill: All longitudinal pipeline trenches (parallel to curb) may be backfilled full 41
depth above the pipe zone with native material (free of organic material, wood, rocks, or 42
pavement chunks larger than 6-inches in maximum dimension), unless otherwise directed 43
by the City. Street crossings, transverse trenches, and other locations as directed by the 44
City may be required to be backfilled full depth with imported select backfill. Imported 45
select backfill shall be crushed surfacing top course or crushed surfacing base course 46
meeting the requirements of section 9-03.9(3), placed and compacted in layers. 47
48
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-87
7-08.3(2)B Pipe Laying – General 1
(June 26, 2020 COP GSP) 2
3
Supplement this section with the following: 4
5
Potable domestic water mains shall maintain a 10-foot horizontal and 18-inch vertical 6
separation above non-potable pipelines (sewer, irrigation, and storm) consistent with the 7
Department of Health Water System Design Manual. 8
9
When parallel to existing utilities, new domestic water mains shall be installed a minimum of 10
10 feet horizontally (outside pipe wall to outside pipe wall, typical) and 18 inches vertically 11
above other non-potable pipelines. Where this is not possible at the discretion of the City, 12
a water main may be installed a minimum of five feet horizontally and 18 inches vertically 13
above other non-potable pipelines, as long as the water main is placed in a separate trench 14
and on a bench of undisturbed earth. 15
16
When crossing existing utilities, new domestic water mains shall be installed a minimum of 17
18 inches vertically above non-potable pipelines. Where this is not possible, or the water 18
main passes under a non-potable pipeline, the water main shall be installed in a pressure 19
rated pipe casing extending 10 feet each side of the crossing. In addition, where the water 20
main passes under an existing non-potable pipeline, support shall be provided for the non-21
potable pipeline by backfilling the non-potable pipeline trench with controlled density 22
backfill or other approved methods. A minimum of 6 inches of separation between the 23
crossing pipelines must be maintained in all cases. 24
25
When parallel to existing potable water mains, new non-potable pipelines shall be installed a 26
minimum of 10 feet horizontally and 18 inches vertically below existing water mains. 27
Where this is not possible at the discretion of the Engineer, a non-potable pipeline may be 28
installed a minimum of five feet horizontally from an existing water main, as long as the 29
non-potable pipeline is installed a minimum of 18 inches vertically below the water main 30
and the non-potable pipeline is placed in a separate trench. If the vertical separation 31
cannot be met, then the non-potable pipeline shall be constructed of or encased in 32
materials equal to water main standards with a minimum pressure rating of 165psi (C900 33
PVC DR 25, ductile iron, etc.). 34
35
When crossing existing potable water mains, new non-potable pipelines shall be installed a 36
minimum of 18 inches vertically below existing water mains. Due to difficulties in 37
compacting under existing utilities, controlled density backfill or other City approved 38
materials shall be placed as backfill at the crossing locations, to a depth of the water main 39
spring line. Where the minimum clearance is not possible, or the non-potable pipeline 40
passes above a water main, a full length of non-potable pipeline shall be centered at the 41
crossing. In addition, the non-potable pipeline shall either be installed in a pressure rated 42
pipe casing extending 10 feet each side of the crossing, or be constructed of one standard 43
length of pipe material equal to waterline standards with a minimum pressure rating of 44
165psi (C900 PVC DR 25, ductile iron, etc.). A minimum of 6 inches of separation between 45
the crossing pipelines must be maintained in all cases. 46
47
Magnetic detectable marking tape shall be installed above the pipe. The tape shall be 48
placed approximately two feet above the top of the pipe and shall extend its full length. 49
The horizontal location of the tape shall vary no more than one foot from the centerline 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-88
alignment of the pipe. Detectable marking tape shall meet the requirements of Section 9-1
15.18 of the Standard Specifications. Tape width shall be a minimum of 3 inches wide, or 2
wider as recommended by the manufacturer for the installation depth. 3
4
Revise the third paragraph of this section to read: 5
6
Pipe shall be laid to a true line and grade at the invert of the pipe and the Contractor shall 7
exercise care in matching pipe joints for concentricity and compatibility. In no case shall 8
two pipes be joined together with ends having the maximum manufacturer’s tolerance. The 9
invert line may vary from the true line and grade within the limits stated to develop 10
uniformity, concentricity, and uniform compression of jointing material provided such 11
variance does not result in a reverse sloping invert. The limit of variance at the invert 12
elevation of the pipe shall be plus or minus ¾-inch for a completed, backfilled pipe. 13
Checking of the invert elevation of the pipe shall be done by remote operated CCTV 14
camera utilizing a ¾-inch measuring device (lead ball). 15
16
7-08.3(3) Backfilling 17
(June 26, 2020 COP GSP) 18
19
Revise the second paragraph of this section to read: 20
21
Gravel Backfill for Pipe Zone (including Bedding): Pipe zone material shall be Crushed 22
Surfacing Top Course meeting the requirements of section 9-03.9(3), and shall be placed 23
and compacted in layers as designated by the City. With prior approval by the City, 24
suitable native material may be an acceptable alternate for pipe zone bedding above the 25
bottom of the pipe. 26
27
Trench Backfill: All longitudinal pipeline trenches (parallel to curb) may be backfilled full 28
depth above the pipe zone with native material if approved by the City (free of organic 29
material, wood, rocks, or pavement chunks larger than 6-inches in maximum dimension). 30
Street crossings, transverse trenches, and other locations as directed by the City may be 31
required to be backfilled full depth with imported select backfill. Imported select backfill 32
shall be crushed surfacing top course or crushed surfacing base course meeting the 33
requirements of section 9-03.9(3), placed and compacted in layers. 34
35
Supplement this section with the following: 36
37
The City may require the use of Controlled Density Fill (CDF) for trench backfill in certain 38
circumstances. The requirements for CDF are set forth in CHAPTER 8, Section 8-30 of 39
these Special Provisions. 40
41
Backfill above pipe zone shall be placed in horizontal lifts not exceeding 6 inches in depth. 42
43
The Contractor shall be responsible for scheduling all testing required. 44
45
46
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-89
Measurement 1
(******) 2
3
Supplement this section with the following: 4
5
The Bid item “UTILITY CROSSING” shall be measured by each (EA) location where 6
placement of new domestic water pipe may require unforeseen field routing to maintain 7
specified minimum clearance with existing utilities. 8
9
Payment 10
(******) 11
12
Supplement this section with the following: 13
14
The unit Contract price per each (EA) for “UTILITY CROSSING” shall be full compensation 15
for all costs, including materials, equipment, and labor, incurred to carry out the 16
requirements of Section 7-08 and its Special Provisions except for those costs included in 17
other items which are included in this Subsection and which are included in the Proposal. 18
19
7-09 WATER MAINS 20
21
Construction 22
23
7-09.3(5) Grade and Alignment 24
(June 26, 2020 COP GSP) 25
26
Replace the first sentence of the third paragraph with the following: 27
28
The depth of trenching for water mains shall be such to provide a minimum cover of 42 29
inches and a maximum cover of 72 inches, unless otherwise approved by the City. 30
31
7-09.3(7) Trench Excavation 32
(June 26, 2020 COP GSP) 33
34
Supplement this section with the following: 35
36
The Contractor shall neatly sawcut all areas of existing pavement within the trench 37
excavation area, then remove and haul all waste materials from the project and dispose of 38
at an approved site provided by the Contractor. Should any undermining occur on adjacent 39
pavement, the Contractor shall neatly cut the pavement six (6) inches beyond the 40
undermined area. 41
42
All trench excavations shall have adequate safety systems for the trench excavation that 43
meet the requirements of the Washington Industrial Safety and Health Act, Chapter 49.17 44
RCW. The Contractor shall be responsible for providing the necessary back sloping, 45
cribbing, trench boxes, etc., as required to meet the specified safety requirements for the 46
trench. When City crews will be making the main line taps or other work in the trench, the 47
Contractor shall provide all trench safety measures, prior to City personnel entering the 48
trench. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-90
7-09.3(9) Bedding the Pipe 1
(******) 2
3
Supplement this section with the following: 4
5
All construction work shall be inspected by the City before pipe installation and backfilling. 6
7
7-09.3(11) Compaction of Backfill 8
(June 26, 2020 COP GSP) 9
10
Delete the first paragraph and supplement this section with the following: 11
12
Mechanical compaction shall be required for all trenches. The Contractor shall be 13
responsible for scheduling and paying for all testing required. 14
15
The density of the compacted material shall be at least 95% of the maximum density as 16
determined by ASTM D 698 Tests (Standard Proctor). Density tests shall be taken at 17
various depths in the trench. All costs associated with testing shall be the responsibility of 18
the Contractor. Placement of courses of aggregate shall not proceed until density 19
requirements have been met. 20
21
The first 500 feet of trench backfill operations shall be considered a test section for the 22
Contractor to demonstrate their backfilling and compaction techniques. The Contractor 23
shall notify the City at least 3 working days prior to beginning trench excavation and backfill 24
operations. The Contractor shall arrange for in-place density tests to be taken on the 25
completed test section in accordance with the above requirements. No further trenching 26
will be allowed until the specified density is achieved in the test section. Passing in-place 27
density tests in the test section will not relieve the Contractor from achieving the specified 28
densities throughout the project. 29
30
7-09.3(15)A Ductile Iron Pipe 31
(******) 32
33
Revise the first paragraph of this section to read: 34
35
Long radius curves, either horizontal or vertical, may be accomplished using standard pipe 36
lengths by deflecting the joints. If the pipe is shown curved on the Plans and no special 37
fittings are shown, the Contractor can assume that the curves can be made by deflecting the 38
joints with standard lengths of pipe. If shorter lengths are required, the Contractor shall 39
submit a proposed maximum length to the City for review. The amount of deflection at each 40
pipe joint when pipe is laid on a horizontal or vertical curve shall not exceed one-half (1/2) of 41
the manufacturer’s printed recommended deflections. If the deflection required to maintain 42
the line shown on the approved construction drawings exceeds 1/2 of the manufacturer’s 43
printed recommended deflection then the Contractor shall utilize fittings to maintain the 44
approved line. Additional labor and materials will be at the developer’s expense. 45
46
7-09.3(19)A Connections to Existing Mains 47
(June 26, 2020 COP GSP) 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-91
Delete the third paragraph of Section 7-09.3(19)A in its entirety. Supplement this section with 1
the following: 2
3
Requests for water line shut downs and water taps shall utilize the City’s Procedure for 4
Scheduling Water Crews, Performing Taps, and Placing New Water Lines in Service. New 5
water mains shall be tested, flushed, and disinfected per Section 7-09.3(23) and 7- 09.3(24) 6
with passing results, prior to making connection to existing main and being placed into 7
operation. 8
9
No existing line valves shall be closed without permission by the City. In no case shall any 10
existing water main valve be closed for a period of greater than eight (8) hours. 11
12
The anticipated schedule for the connections shall be discussed and scheduled at the 13
preconstruction conference, and indicated on the weekly schedule. The City reserves the 14
right to adjust the schedule of the connections, as required, subject to a minimum of 1 15
working day notice of schedule change to the Contractor. No connections will be scheduled 16
for the first working day after a weekend or holiday. 17
18
7-09.3(20) Detectable Marking Tape 19
(June 26, 2020 COP GSP) 20
21
Delete this section and replace it with the following: 22
23
7-09.3(20) Detectable Marking Tape and Tracer Wire 24
25
Detectable marking tape and tracer wire shall be installed over all water lines, including 26
service lines. The tape shall be placed approximately 2-feet above the top of the line and 27
shall extend its full length. The tracer wire shall be fastened to the top of the pipe with duct 28
tape at 6-foot intervals and shall be routed up into valve boxes with adequate length for 29
connection to location equipment. 30
31
7-09.3(21) Concrete Thrust Blocking 32
(******) 33
Supplement this section with the following: 34
35
Thrust blocks shall be formed and placed in conformance with the Contract Documents for 36
the appropriate pipe size and fitting type. 37
38
7-09.3(22) Blow -off Assemblies 39
(June 26, 2020 COP GSP) 40
41
Supplement this section with the following: 42
43
Even if not shown in the Plans, all permanent dead-end lines must end with a blow-off, 44
unless there is a hydrant connection within the last 30 feet of the water main. 45
46
7-09.3(23) Hydrostatic Pressure Test 47
(******) 48
49
Delete this section and replace it with the following: 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-92
1
Water main appurtenances and service connections to the meter setter shall be tested in 2
sections of convenient length under a hydrostatic pressure equal to 150-psig. Pumps, 3
gauges, plugs, saddles, corporation stops, miscellaneous hose and piping, and measuring 4
equipment necessary for performing the test shall be furnished and operated by the 5
Contractor. 6
7
Sections to be tested shall normally be limited to 1,500 feet. The City may require that the 8
first section of pipe, not less than 1,000 feet in length, installed by each of the Contractor’s 9
crews, be tested in order to qualify the crew and the materials. Pipe laying shall not be 10
continued more than an additional 1,000 feet until the first section has been tested 11
successfully. 12
13
The pipeline shall be backfilled sufficiently to prevent movement of the pipe under pressure. 14
Mechanical restraints and/or thrust blocks shall be in place and time allowed for the 15
concrete to cure before testing. Where permanent blocking is not required, the Contractor 16
shall furnish and install temporary blocking and remove it after testing. 17
18
The mains shall be filled with water and allowed to stand under pressure a sufficient length 19
of time to allow the escape of air and allow the lining of the pipe to absorb water. The City 20
will furnish the water necessary to fill the pipelines for testing purposes at a time of day 21
when sufficient quantities of water are available for normal system operation. 22
23
The test shall be accomplished by pumping the main up to the required pressure and 24
stopping the pump and holding pressure for one (1) hour. During the test, the section being 25
tested shall be observed to detect any visible leakage. 26
27
There shall not be a loss in pressure during the one-hour test period. 28
29
Pressure gauges used in the test shall be in good working condition and have a zero- 30
pressure reading prior to use. Erroneous or damaged gauges may be rejected at the 31
discretion of the City, and shall be replaced with new gauges at the Contractor’s expense. 32
The Contractor shall submit a current calibration certificate for any pressure gage to be 33
used. 34
35
Any visible leakage detected shall be corrected by the Contractor. Should the tested section 36
fail to meet the pressure test successfully as specified, the Contractor shall, at no additional 37
expense to the City, locate and repair the defects and then retest the pipeline. 38
39
Tests shall be made with the hydrant auxiliary gate valves open and pressure against the 40
hydrant valve. Each valve shall be tested by closing each in turn and relieving the pressure 41
beyond. This test of the valve will be acceptable if there is no immediate loss of pressure on 42
the gauge when the pressure comes against the valve being checked. The Contractor shall 43
verify that the pressure differential across the valve does not exceed the rated working 44
pressure of the valve. 45
46
Prior to calling out the City Inspector to witness the pressure test, the Contractor shall have 47
all equipment set up completely ready for operation and shall have successfully performed 48
the test to ensure that the pipe is in satisfactory condition. 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-93
Defective materials or workmanship, discovered as a result of hydrostatic field test, shall be 1
replaced by the Contractor at no expense to the City. Whenever it is necessary to replace 2
defective material or correct the workmanship, the hydrostatic test shall be re-run at the 3
Contractor’s expense until a satisfactory test is obtained. 4
5
7-09.3(24) Disinfection of Water Mains 6
(June 26, 2020 COP GSP) 7
8
Supplement this section with the following: 9
10
AWWA Standard C651 shall be used as a guideline for disinfecting water mains. 11
12
7-09.3(24)J Preventing Reverse Flow 13
(June 26, 2020 COP GSP) 14
15
Supplement this section with the following: 16
17
All water lines shall be pressure tested and sanitized with a satisfactory report received from 18
the Washington State Department of Health prior to the backflow assembly installation. 19
Backflow preventers shall NOT be pressure tested against. 20
21
7-09.3(24)K Retention Period 22
(June 26, 2020 COP GSP) 23
24
Revise this section to read: 25
26
Treated water shall be retained in the pipe at least 24 hours but not more than 28 hours. 27
After the 24-hour period, the chlorine residual at pipe extremities and at other representative 28
points shall be at least 25 mg/l. 29
30
Measurement 31
(******) 32
33
Section 7-09.4 is supplemented with the following: 34
35
There will be no separate measurement for dust control (dewatering) and watering (e.g. 36
compaction) operations by the Contractor. 37
38
The Bid item “SHORING OR EXTRA EXCAVATION” shall be measured by the linear foot 39
(LF). 40
41
The Bid item “DIG AND VERIFY” shall be measured by each (EA) location of utility 42
connection points and crossings verified by the Contractor prior to commencement of the 43
work. 44
45
The Bid item “BLOW OFF ASSEMBLY” shall be measured by each (EA). The assembly 46
includes, but is not limited to, the following components as specified in the Plans (see Detail 47
W-5): Ductile Iron Gate Valve, 8-in., Mechanical Restraints, Valve Box, Galvanized Elbow, 48
Galvanized Pipe, 2”, Ductile Iron Pipe, 8”, Pipe Bedding, and Thrust Block(s). 49
50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-94
The Bid item “WATER MAIN INSTALLATION AND COMISSIONING” shall be measured by 1
the linear foot (LF). 2
3
The Bid item “CONNECT TO EXISTING WATERMAINS” shall be measured by each (EA) 4
tapping sleeve location. 5
6
The Bid item “SERVICE CONNECTIONS, COPPER PIPE, 1 IN. DIAM (WITH WATER 7
METER BOXES)” shall be measured by each (EA) service connection with new water meter 8
boxes as shown in the Plans. 9
10
The Bid item “SERVICE CONNECTIONS, COPPER PIPE, 1 IN. DIAM (WITHOUT WATER 11
METER BOXES)” shall be measured by each (EA) service connection to existing water 12
meter boxes as shown in the Plans. 13
14
Payment 15
(******) 16
17
Section 7-09.5 is supplemented with the following: 18
19
Payment will be made for each of the following Bid items that are included in the Proposal: 20
21
“DIG AND VERIFY”, each (EA). 22
“BLOW OFF ASSEMBLY”, each (EA). 23
“WATER MAIN INSTALLATION AND COMISSIONING”, per linear foot (LF). 24
“CONNECT TO EXISTING WATERMAINS”, each (EA). 25
“SERVICE CONNECTIONS, COPPER PIPE, 1 IN. DIAM (WITH WATER METER BOXES)”, 26
each (EA). 27
“SERVICE CONNECTIONS, COPPER PIPE, 1 IN. DIAM (WITHOUT WATER METER 28
BOXES)”, each (EA). 29
30
All costs for dust control (dewatering) and watering (e.g. compaction) operations shall be 31
incidental to other Bid items. 32
33
The unit Contract price per each (EA) for “DIG AND VERIFY” shall be full compensation for 34
all costs, including materials, equipment, and labor, incurred to carry out the requirements of 35
Section 7-09 and its Special Provisions except for those costs included in other items which 36
are included in this Subsection and which are included in the Proposal. 37
38
The unit Contract price per each (EA) for “BLOW OFF ASSEMBLY” shall be full 39
compensation for all costs, including materials, equipment, and labor incurred to furnish, 40
install, and commission the assembly with the requirements of Section 7-09 and its Special 41
Provisions except for those costs included in other items which are included in this 42
Subsection and which are included in the Proposal. 43
44
The unit Contract price per linear foot (LF) for “WATER MAIN INSTALLATION AND 45
COMISSIONING” shall be full compensation for all materials, equipment, and labor to carry 46
out the requirements of Section 7-09 and its Special Provisions except for those costs 47
included in other items which are included in this Subsection and which are included in the 48
Proposal. This includes, but is not limited to, all costs necessary to furnish and install water 49
main pipe and fittings as shown on the Plans, including, but not limited to bedding, imported 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-95
pipe bedding material in the pipe zone, laying and jointing the pipe and fittings, ductile iron 1
pipe and fittings, locating wire, detectable marking tape, concrete thrust blocking, 2
disinfecting the pipeline, flushing, dechlorination of water used for flushing, and cleanup. 3
4
The unit Contract price per each (EA) for “CONNECT TO EXISTING WATERMAINS” shall 5
be full compensation for all costs, including materials, equipment, and labor incurred to 6
furnish, install, and commission the tapping sleeve(s) with the requirements of Section 7-09 7
and its Special Provisions except for those costs included in other items which are included 8
in this Subsection and which are included in the Proposal. 9
10
The unit Contract price per each (EA) for “SERVICE CONNECTIONS, COPPER PIPE, 1 IN. 11
DIAM (WITH WATER METER BOXES)” shall be full compensation for all costs, including 12
materials, equipment, and labor incurred to furnish, install, and commission the service 13
connection and a new water meter box with the requirements of Section 7-09 and its Special 14
Provisions except for those costs included in other items which are included in this 15
Subsection and which are included in the Proposal. 16
17
The unit Contract price per each (EA) for “SERVICE CONNECTIONS, COPPER PIPE, 1 IN. 18
DIAM (WITHOUT WATER METER BOXES)” shall be full compensation for all costs, 19
including materials, equipment, and labor incurred to furnish, install, and commission the 20
service connection to an existing water meter box with the requirements of Section 7-09 and 21
its Special Provisions except for those costs included in other items which are included in 22
this Subsection and which are included in the Proposal. 23
24
7-12 VALVES FOR WATER MAINS 25
26
Construction Requirements 27
(June 26, 2020 COP GSP) 28
29
Supplement this section with the following: 30
31
Tapping Sleeve and Valve Assemblies: City of Pasco Public Works will perform all taps for 32
tapping sleeve and valve assemblies up to 12-inch diameter, sleeve and valve to be 33
installed by the Contractor. For taps greater than 12-inch diameter, the Contractor or 34
Subcontractor completing the work shall have at least five (5) years’ experience with a 35
minimum of ten (10) water main taps of pipes with diameters equal to or larger than that 36
specified. Contractor shall notify City at least 72 hours prior to proposed taps and provide 37
work experience references if requested. Work to complete the tap shall not commence 38
without City’s written approval. If the Contractor or Subcontractor does not have sufficient 39
experience in the sole opinion of the City, a qualified Subcontractor as approved by the City, 40
shall be used to complete the tap at no cost to the City. 41
42
Valves: Upon completion of all work, the Developer/Contractor shall contact the City of 43
Pasco Public Works for opening water valves. Valves shall only be operated by City Public 44
Works staff. 45
46
Valves shall not be installed in Sidewalks, Pedestrian Curb Ramps, Driveway Approaches or 47
any other exposed concrete surface. 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-96
Valve Boxes: Valve boxes should be set to position during backfilling operations so they will 1
be in a vertically centered alignment to the valve operating stem. The top of the box will be 2
at final grade. 3
4
The Contractor shall adjust all water valve boxes to the final grade of the surrounding area 5
including new concrete sidewalk, asphalt paving, gravel surfacing, or topsoil surfacing, in 6
accordance with the details shown on the Drawings. 7
8
The Contractor shall keep the valve boxes free from debris caused by the construction 9
activities. All valve boxes will be inspected during final walk-thru to verify that the valve box 10
is plumb and that the valve wrench can be placed on the operating nut. Misaligned valve 11
boxes shall be excavated, plumbed, and backfilled at the Contractor's expense. 12
13
Measurement 14
(******) 15
16
Supplement this section with the following: 17
18
The Bid item “DUCTILE IRON GATE VALVE, 8-IN.” shall be measured by each (EA), unless 19
otherwise specified as part of an assembly. 20
21
Payment 22
(******) 23
24
Payment will be made for each of the following Bid items that are included in the Proposal: 25
26
“DUCTILE IRON GATE VALVE, 8-IN.”, each (EA). 27
28
The unit Contract price per each (EA) for “DUCTILE IRON GATE VALVE, 8-IN.” shall be full 29
compensation for all costs, including materials, equipment, and labor incurred to furnish, 30
install, and commission the valve with the requirements of Section 7-09 and its Special 31
Provisions except for those costs included in other items which are included in this 32
Subsection and which are included in the Proposal. 33
34
7-14 HYDRANTS 35
36
7-14.3(1) Setting Hydrants 37
(June 26, 2020 COP GSP) 38
39
Delete the first and second paragraphs and replace with the following: 40
41
The hydrant shoe shall be set to the correct elevation on a concrete block base, which has 42
been placed on undisturbed earth. Around the base of the hydrant and weep hole, the 43
Contractor shall place washed drain rock, to allow free drainage of the hydrant. The drain 44
rock shall be completely surrounded with construction geotextile filter fabric. 45
46
The Contractor shall set all hydrants plumb and nozzles parallel with, or at right angles to, 47
the curb, with the pumper nozzle facing the curb. Hydrants shall be set so that the flange is 48
2”-8” above the back of curb, sidewalk, or finished grade to clear nuts and bolts. Hydrants 49
shall be ordered with the bury depth required to meet the flange elevation requirements. 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-97
The Contractor shall be responsible for verifying the hydrant flange elevations and no 1
extensions will be allowed. 2
3
Fire hydrants shall be painted with two coats of high visibility yellow paint. 4
5
Fire hydrants shall be located 1-foot behind the back of sidewalk to the face of hydrant 6
where the sidewalk is adjacent to the curb and 7-feet behind the back of curb where the 7
sidewalk is not adjacent to the curb. Hydrants adjacent to roadside swales shall be located 8
1-foot behind the swale on the property line side. 9
10
No bends are allowed in fire hydrant runs. If a bend cannot be avoided, the elbow fittings 11
shall be mechanically restrained with EBAA Megalugs or approved equal. 12
13
Hydrants installed outside of paved areas where there will not be maintained landscaping 14
shall install a 4’ x 4’ concrete pad around the hydrant. 15
16
7-14.3(2) Hydrant Connections 17
(June 26, 2020 COP GSP) 18
19
Replace this section with the following: 20
21
Hydrant runs of less than 50 feet shall be connected to the main with 6-inch minimum 22
diameter water main. Each hydrant lateral shall include an auxiliary gate valve and valve 23
box. 24
25
7-14.3(2)A Hydrant Restraints 26
(June 26, 2020 COP GSP) 27
28
Replace this section with the following: 29
30
All hydrants shall be securely connected to the water main as shown on drawings and each 31
joint shall be mechanically restrained. 32
33
7-14.3(2)C Hydrant Guard Posts 34
(June 26, 2020 COP GSP) 35
36
Replace this section with the following: 37
38
The City may determine that four (4) 6-inch diameter Sch. 40 steel guard posts shall be 39
installed at a hydrant location. Hydrant guard posts shall be painted the same color as the 40
hydrants. 41
42
Measurements 43
(******) 44
45
Supplement this section with the following: 46
47
48
The Bid item “HYDRANT ASSEMBLY WITH VALVE” shall be measured by each (EA). The 49
assembly includes, but is not limited to, the following components as specified in the Plans 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-98
(see Detail W-10): Ductile Iron Pipe, 8-in., Ductile Iron Gate Valve, 8-in., Mechanical 1
Restraints, Valve Box, Valve Box Extension, Galvanized Elbow, Galvanized Pipe, 2”, Ductile 2
Iron Pipe, 8”, Tracer Wire, Pipe Bedding, Concrete Base Block, Filter Fabric, and Thrust 3
Block(s). 4
5
Payment 6
(******) 7
8
Supplement this section with the following: 9
10
Payment will be made for each of the following Bid items that are included in the Proposal: 11
12
“HYDRANT ASSEMBLY WITH VALVE”, each (EA). 13
14
The unit Contract price per each (EA) for “HYDRANT ASSEMBLY WITH VALVE” shall be full 15
compensation for all costs, including materials, equipment, and labor incurred to furnish, 16
install, and commission the assembly with the requirements of Section 7-09 and its Special 17
Provisions except for those costs included in other items which are included in this Subsection 18
and which are included in the Proposal. 19
20
7-15 SERVICE CONNECTIONS 21
22
Description 23
(June 26, 2020 COP GSP) 24
25
Replace this section with the following: 26
27
All new water service lines shall be a minimum of 1-inch, for 3/4- and 1-inch meters, and 28
shall conform to the Contract. The Contractor shall furnish and install all water service 29
components (except hot tap and water meter) from the water main to the property line 30
including service saddle, corporation stop, service pipe, meter stop, meter check valve, 31
customer piping, and meter box, all at the Contractor’s expense. Only one meter shall be 32
served from each main tap. All service hot taps shall be performed by the City of Pasco 33
Public Works Crews. 34
35
Construction Requirements 36
(June 26, 2020 COP GSP) 37
38
Supplement this section with the following: 39
40
The Contractor shall set the water meter box to the finished grade of the area, typically flush 41
with the top back of sidewalk. The Contractor will be required to reset the meter box if it is 42
not at finished grade at the completion of the project. The completed water service shall be 43
tested at system operating pressure by the Contractor and must show no signs of leakage. 44
45
The location of water services at the property line or easement line shall be marked per the 46
Standard Detail. Fiberglass markers may be proposed for approval consideration by the 47
City Engineer. 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-99
The fresh concrete curb above all water service lines shall be stamped on the curb face with 1
a 2" high "W". 2
3
Service saddle shall not be placed within one (1) foot of pipe joint, couplings, or other 4
clamps without approval from the City. 5
6
No joints are allowed between the corporation stop and the angle meter stop. 7
8
9
END DIVISION 7 10
11
12
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-100
DIVISION 8 1
MISCELLANEOUS CONSTRUCTION 2
3
8-01 EROSION CONTROL AND WATER POLLUTION CONTROL 4
5
Construction Requirements 6
(******) 7
8
Supplement this section with the following: 9
10
The Contractor shall take all necessary precautions and utilize the Department of Ecology’s 11
(DOE) Best Management Practices to prevent sediment and fugitive dust from construction 12
activities from entering into storm water systems, natural waterways, or environmentally 13
sensitive areas and from otherwise being carried away from the construction area by storm 14
water or air. 15
16
Temporary erosion protection shall be furnished, installed, and maintained for the duration of 17
this Project to protect environmentally sensitive areas, sloped surfaces, adjacent areas 18
and/or water bodies or conveyance systems. Temporary erosion protection may include the 19
use of straw, jute matting, wattles, heavy plastic sheeting, or other forms of ground cover on 20
areas disturbed by construction and catch basin inserts for catch basins down-slope from 21
the construction. Sloped surfaces shall be restored and protected in such a manner that 22
surface runoff does not erode the embankments, slopes, or ground surfaces, nor create 23
surface channels, or ruts. 24
25
Measurement 26
(******) 27
28
Supplemented this section with the following: 29
30
The Bid item “EROSION/WATER POLLUTION CONTROL” shall be measured as lump sum 31
(LS). 32
33
Payment 34
(******) 35
36
Supplement this section with the following: 37
38
Payment will be made for each of the following Bid items that are included in the Proposal: 39
40
“EROSION/WATER POLLUTION CONTROL”, lump sum (LS). 41
42
The lump sum (LS) unit Contract price for “EROSION/WATER POLLUTION CONTROL” 43
shall be full compensation for all costs, including materials, equipment, and labor, incurred to 44
carry out the requirements of Section 8-01 and its Special Provisions except for those costs 45
included in other items which are included in this Subsection and which are included in the 46
Proposal. 47
48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-101
8-02 ROADSIDE RESTORATION 1
2
Measurement 3
(******) 4
5
Supplement this section with the following: 6
7
The Bid item “LANDSCAPE RESTORATION” shall be measured as lump sum (LS). 8
9
Payment 10
(******) 11
12
Supplement this section with the following: 13
14
Payment will be made for each of the following Bid items that are included in the Proposal: 15
16
“LANDSCAPE RESTORATION”, lump sum (LS). 17
18
The lump sum (LS) unit Contract price for “LANDSCAPE RESTORATION”, shall be full 19
compensation for all costs, including materials, equipment, and labor, incurred to carry out 20
the requirements of Section 8-02 except for those costs included in other items which are 21
included in this Subsection and which are included in the Proposal. 22
23
8-04 CURBS, GUTTERS, AND SPILLWAYS 24
25
Construction Requirements 26
(June 26, 2020 COP GSP) 27
28
Supplement this section with the following: 29
30
Testing requirements shall be as follows: 31
32
Project Quantity Test Requirement
Less than 5 CY None
5 CY – 10 CY 1 Slump, 4 Cylinders
10+ CY 2 Slump, 4 Cylinders per 25 CY
33
For project quantities above five (5) cubic yards, test requirements shall be based on 34
concrete placed during one (1) working day. If the concrete fails any test, the City will 35
require additional testing to determine the extent of the failure and more frequent tests may 36
be required on additional concrete being placed. Testing and samples shall be in 37
accordance with Section 1-06.2(1). 38
39
Regardless of quantity, a Certification of Compliance shall be provided for all concrete 40
delivered to the site in accordance with Section 6-02.3(5)B. 41
42
8-04.3(1) Cement Concrete Curbs, Gutters, and Spillways 43
(June 26, 2020 COP GSP) 44
45
Revise the fourth paragraph of this section to read: 46
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-102
1
Expansion joints in the curb or curb and gutter shall be spaced at 50-foot intervals, the 2
beginning and ends of curb returns, drainage structures, bridges, and cold joints with 3
existing curbs and gutters. The expansion joint shall be filled to full cross-section with ½- 4
inch premolded joint filler. When curb or curb and gutter is placed adjacent to Portland 5
Cement Concrete Pavement, a 3/8-inch thick, 6-inch deep premolded joint filler shall be 6
installed between the 2 vertical surfaces to prevent cracking. Joint material shall be set 7
flush or trimmed flush with the finished concrete surface. Construction joints shall be at 8
accurate ten (10) foot spacing and shall consist of a two (2) inch cut or slice into the 9
concrete pour, and an additional two (2) inch cut into the heel of the pour. Joints shall be 10
formed neatly and perpendicular to the line of the curb. 11
12
Supplement this section with the following: 13
14
Cement concrete traffic curb and gutter shall be as designated in these Special Provisions. 15
Full Height or “Type A” cement concrete traffic curb and gutter shall be used on the roadway. 16
Depressed or “Drop” cement concrete traffic curb and gutter shall be used at all driveway 17
entrances and sidewalk ramp locations and as directed in the field by the City. 18
19
Depressed “Type D” cement concrete traffic curb and gutter shall be used on cul-de-sacs 20
from curb return to curb return. Cement concrete curb and gutter which does not comply 21
with the City's details shall be removed and replaced at the Contractor's expense. 22
23
A template shall be required to be placed at the back of curb for construction of driveway 24
transitions from Type A to Type D curb and gutter. The template shall extend from the 25
bottom of curb to the top of the curb, and shall have a minimum length to provide a 26
maximum slope of 8.3%. 27
28
The new concrete curb and gutter shall be cured in accordance with Section 5-05.3(13)A of 29
the Standard Specifications. Application of the curing compound shall be in accordance with 30
the manufacturer's recommendations. 31
32
First-class workmanship and finish will be required on all portions of concrete curb and 33
gutter work. Quality of workmanship and finish will be evaluated continuously and will be 34
based solely upon the judgment of the City. The Contractor shall be required to construct a 35
minimum 20 linear foot section of curb and gutter which demonstrates quality which is 36
acceptable by the City. This “model” section will be referenced during construction for 37
comparison to newly poured curb. If at any time it is found that quality is unacceptable, work 38
shall be immediately stopped, and no additional curb and gutter shall be placed. Cement 39
concrete curb and gutter which does not comply with the section details on the Plans, or in 40
the City's opinion does not demonstrate first-class workmanship and finish, shall be 41
removed and replaced at the Contractor's expense. Should the Contractor's equipment or 42
methods be unable to produce curb and gutter meeting the requirements of the Contract, no 43
further curb and gutter construction will be allowed until corrections have been made to said 44
equipment or methods. 45
46
8-06 CEMENT CONCRETE DRIVEWAY ENTRANCES 47
48
Construction Requirements 49
(June 26, 2020 COP GSP) 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-103
1
Supplement this section with the following: 2
3
The concrete driveway entrance/sidewalk shall be six (6) inches in thickness. Both the curb 4
and gutter as well as the sidewalk portion must comply the requirement of 8-04.3(1). Class 5
4000 air entrained concrete conforming to the Section 6-02 shall be required. 6
7
8-13 MONUMENT CASES 8
9
Construction Requirements 10
(June 26, 2020 COP GSP) 11
12
Revise the last paragraph of this section to read: 13
14
The Contractor will be responsible for placing the concrete core and tack or wire inside the 15
pipe. 16
17
8-14 CEMENT CONCRETE SIDEWALKS 18
19
Construction Requirements 20
(June 26, 2020 COP GSP) 21
22
Supplement this section with the following: 23
24
Testing requirements shall be as follows: 25
26
Project Quantity Test Requirement
less than 5CY None
5CY - 10CY 1 Slump, 4 Cylinders
10+CY 2 Slump, 4 Cylinders per each 25CY
27
For project quantities above five (5) cubic yards, test requirements shall be based on 28
concrete placed during one (1) working day. If the concrete fails any test, the City will 29
require additional testing to determine the extent of the failure and more frequent tests may 30
be required on additional concrete being placed. Testing and samples shall be in 31
accordance with Section 1-06.2(1). 32
33
Regardless of quantity, a Certification of Compliance shall be provided for all concrete 34
delivered to the site in accordance with Section 6-02.3(5)B. 35
36
8-14.3(3) Placing and Finishing Concrete 37
(June 26, 2020 COP GSP) 38
39
Supplement this section with the following: 40
41
Expansion joints, using 1/2” thick pre-molded material (AASHTO M213) at full depth, shall 42
be perpendicular and provided at a maximum spacing of thirty (30) feet, at cold joints and at 43
each side of driveway. See WSDOT Standard Plans F-40 for joints at pedestrian ramps. 44
Sidewalk construction joints shall be provided at five (5) foot intervals, or as required to 45
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-104
match existing improvements. All work shall be perpendicular to the curb and straight. Joint 1
material shall be set flush or trimmed flush with the finished concrete surface. 2
3
Concrete finish shall be in accordance with Section 6-02.3(14). 4
5
All sidewalks not located in driveway entrance areas shall be four (4) inches in thickness. 6
All concrete approaches located behind a Type D curb and gutter section or at any driveway 7
location shall be six (6) inches in thickness. 8
9
Concrete sidewalk shall be cured in accordance with Section 5-05.3(13)A of the Standard 10
Specifications. Application of the curing compound shall be in accordance with the 11
manufacturer's recommendations. Failure to properly secure or seal the cement concrete 12
sidewalk will require the Contractor to remove and replace the sidewalk section at their 13
expense. 14
15
Sidewalk ramps shall be constructed as shown on the Plans in accordance with the 16
Contract. 17
18
First-class workmanship and finish will be required on all portions of cement concrete 19
sidewalk work. Quality of workmanship and finish will be evaluated continuously and will be 20
based solely upon the judgment of the City. If at any time it is found that quality is 21
unacceptable, work shall be immediately stopped, and no additional sidewalk shall be 22
placed. Cement concrete sidewalk which does not comply with the section details on the 23
Plans, or in the City's opinion does not demonstrate first-class workmanship and finish, shall 24
be removed and replaced at the Contractor's expense. Should the Contractor’s equipment 25
or methods be unable to produce sidewalk meeting the requirements of the Contract no 26
further sidewalk construction will be allowed until corrections have been made to said 27
equipment or methods. 28
29
Payment 30
(******) 31
32
Supplement this section with the following: 33
Gravel subgrade materials for cement concrete apron, sidewalk, curb, and gutter with be 34
incidental to those bid items, and separate payment for the gravel subgrade material will not be 35
made. 36
37
38
8-21 PERMANENT SIGNING 39
40
Construction Requirements 41
(June 26, 2020 COP GSP) 42
43
Supplement this section with the following: 44
45
Socket sleeves for sign posts shall be set in 12" diameter x 18" deep base of class 3000 46
cement concrete at finish grade so that erected signs will be plumb with roadway/sidewalk. 47
The Contractor shall correct any misaligned socket sleeves at their own expense. 48
49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-105
8-22 PAVEMENT MARKING 1
2
Description 3
(June 26, 2020 COP GSP) 4
5
Supplement this section with the following: 6
7
This work includes temporary pavement markings as designated in these Special 8
Provisions. 9
10
11
END DIVISION 8 12
13
14
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-106
9-03 AGGREGATES 1
2
9-03.12(3) Gravel Backfill for Pipe Zone Bedding 3
(June 26, 2020 COP GSP) 4
5
Revise this section to read: 6
7
Backfill shall be as follows: 8
9
Gravel Backfill for Pipe Zone (including Bedding): Pipe zone material shall be Crushed 10
Surfacing Top Course meeting the requirements of section 9-03.9(3), and shall be 11
placed and compacted in layers as designated by the City. With prior approval by the 12
City, suitable native material may be an acceptable alternate for pipe zone bedding 13
above the bottom of the pipe. 14
15
Trench Backfill: All longitudinal pipeline trenches (parallel to curb) may be backfilled full 16
depth above the pipe zone with native material (free of organic material, wood, rocks, or 17
pavement chunks larger than 6-inches in maximum dimension), unless otherwise 18
directed by the City of Pasco. Street crossings, transverse trenches, and other locations 19
as directed by the City of Pasco may be required to be backfilled full depth with imported 20
select backfill. Imported select backfill shall be crushed surfacing top course or crushed 21
surfacing base course meeting the requirements of section 9-03.9(3), placed and 22
compacted in layers. 23
24
9-22 MONUMENT CASES 25
26
Monument Cases, Covers, and Risers 27
(June 26, 2020 COP GSP) 28
29
Supplement this section to read: 30
31
The monument frame and cover shall be East Jordan Iron Works model 3680. 32
33
9-28 SIGNING MATERIALS AND FABRICATION 34
(June 26, 2020 COP GSP) 35
36
Revise this section to read: 37
38
Sign posts for permanent traffic control signing shall be 2"x2" 12-gauge perforated steel 39
tubing. Socket sleeves for the sign post shall be 2-1/4"x 2-1/4"x30" 12-gauge perforated steel 40
tubing. 41
42
Street name sign brackets shall be Zumar. 43
44
45
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-107
9-30 WATER DISTRIBUTION MATERIALS 1
2
Pipe 3
4
9-30.1(1) Ductile Iron Pipe 5
(June 26, 2020 COP GSP) 6
7
Revise this section to read: 8
9
Ductile Iron Pipe: Ductile iron pipe shall conform to the requirements of Section 9-30.1(1) of 10
the Standard Specifications, except that it shall be Standard Thickness Class 52. Joints 11
shall be rubber gasket, push-on type (Tyton Joint). Fittings shall be mechanical joint or 12
flanged, as shown on the Plans, and shall conform to Section 9-30.2(1) of the Standard 13
Specifications and NSF 61. 14
15
Tracer Wire: Tracer wire shall be 12-gauge heavy insulated (60 mil) copper wire with UF 16
insulation colored for the utility being installed in accordance with Section 9-15.18. Direct 17
bury splice kits shall be 3M DBY-6. 18
19
Fittings 20
21
9-30.2(1) Ductile Iron Pipe 22
(June 26, 2020 COP GSP) 23
24
Revise this section to read: 25
Fittings: Fittings shall be cement lined, ductile iron, rubber gaskets and glands, and bolts 26
meeting the requirements of AWWA C110, C111, or C153. Fittings shall comply with NSF 61 27
requirements. 28
29
Hardware: Bolts and studs shall be carbon steel, grade B meeting the requirements of 30
ASTM A307 and nuts meet the requirements of ASTM A563. 31
32
Lubricant: Lubricant shall be nontoxic and water-soluble. 33
34
Valves 35
(June 26, 2020 GSP) 36
37
Supplement this section with the following: 38
39
Valves shall be of the same size as the line on which they are located. 40
41
9-30.3(1) Gate Valves (3 to 16 inches) 42
(******) 43
44
Revise the title of Section 9-30.3(1): 45
46
9-30.3(1) Gate Valves 47
(June 26, 2020 COP GSP) 48
49
Supplement this section with the following: 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-108
1
All gate valves sizes 2-inch through 10-inch shall be resilient wedge gate valves with 2
ductile iron bodies and shall conform to the latest revision of AWWA Resilient Seated 3
Gate Valves Standard C515 and AWWA C104. 4
5
All gate valves shall have non-rising stems, open counterclockwise, and shall be 6
provided with a 2-inch square AWWA operating nut. 7
8
9-30.3(3) Butterfly Valves 9
(June 26, 2020 COP GSP) 10
11
Supplement this section with the following: 12
13
All butterfly valves sizes 12 inches and larger shall be butterfly valves suitable for direct 14
burial and shall be rubber seated and conform to the latest revision of AWWA Standard 15
C504 Class 150B and C104. All valves shall open counterclockwise and shall be provided 16
with a 2-inch square AWWA operating nut. 17
18
9-30.3(4) Valve Boxes 19
(June 26, 2020 COP GSP) 20
21
Supplement this section with the following: 22
23
Valve boxes shall be two-piece adjustable, Olympic Foundry model 931. 24
25
9-30.3(7) Combination Air/Release Air Vacuum Valves 26
(June 26, 2020 COP GSP) 27
28
Revise this section to read: 29
30
Combination air release/air vacuum valves shall be designed to operate with potable water 31
under pressure to permit discharging a surge of air from an empty line when filling and 32
relieve the vacuum when draining the system. The valves shall also release an 33
accumulation of air when the system is under pressure. 34
35
Valves shall meet the requirements of C512 and shall be APCO 140 Series or Val-Matic VM-36
200 Series. Seats shall be Buna N rubber. Internal parts shall be stainless steel or bronze. 37
38
9-30.3(8) Tapping Sleeve and Valve Assemblies 39
(June 26, 2020 COP GSP) 40
41
Revise this section to read: 42
43
Tapping sleeves shall be full circle stainless steel with ductile iron flanged outlet, conforming 44
to the latest AWWA Standard C223. Tapping gate valves shall meet the requirements for 45
Gate Valves in Section 9-30.1(1) of these Special Provisions. The following stainless steel 46
tapping sleeves are approved for use: Ford FAST style, Romac model SST, and Smith-Blair. 47
48
Hydrants 49
(June 26, 2020 COP GSP) 50
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-109
1
Supplement this section with the following: 2
3
All hydrants shall be dry-barrel, compression type, with a Main Valve Opening (MVO) of 5-4
1/4" and suitable for working pressures up to 150 psi meeting the requirements of C502. 5
Hydrants shall have a 1-1/2” pentagon operating nut, opening left. All hydrants shall include 6
a 5”x4-1/2” NH connector and cap, Storz HPHA50-45NH and HBC-50. Threads on all ports 7
shall be National Standard Thread. 8
9
Approved manufacturers include Mueller (Centurion), Clow (Medallion), and Waterous 10
(Pacer WB-67). 11
12
No bends are allowed in fire hydrant runs. If a bend cannot be avoided, the elbow fittings 13
shall be mechanically restrained with EBAA Megalugs or approved equal 14
15
(******) 16
Revise the title of Section 9-30.3(1) to read: 17
18
Water Service Connections 19
20
9-30.6(1) Saddles 21
(June 26, 2020 COP GSP) 22
23
Revise this section to read: 24
25
New service saddles less than 12” diameter shall meet the requirements of AWWA C800 26
and have CC threads. Approved manufacturers include Romac (202S, 101S), Mueller 27
DS2S, McDonald (384x, 382x), and Smith-Blair (315, 317). New service saddles 12” and 28
larger shall meet the requirements of AWWA C800 and have CC threads. Approved 29
manufacturers include Romac (305, 306). 30
31
9-30.6(2) Corporation Stops 32
(June 26, 2020 COP GSP) 33
34
New 1” corporation stops shall be Ford FB1000, Mueller B-25008N, B-20013N, or McDonald 35
74701B. New 2” corporation stops shall be Ford FB400(CC), FB500(IP), Mueller B-36
2996N(CC), H-2969(IP), or McDonald 74701B. 37
38
9-30.6(3) Service Pipes 39
40
9-30.6(3)A Copper Tubing 41
(June 26, 2020 COP GSP) 42
43
Supplement this section with the following: 44
45
New service pipe shall be copper tubing. Approved service pipe manufacturers include Cerro, 46
Muller, and Cambridge Lee. 47
48
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-110
9-30.6(3)B Polyethylene Tubing 1
(June 26, 2020 COP GSP) 2
3
Delete this section. 4
5
9-30.6(3)C PEX-a Tubing 6
(June 26, 2020 COP GSP) 7
8
Delete this section. 9
10
9-30.6(4) Service Fittings 11
(******) 12
13
Revise this section to read: 14
15
Fittings used for copper tubing shall be either compressions or flare type. 16
17
All fittings shall be lead free. 18
19
New copper to copper fittings shall be compression type Ford C- 44, Mueller H-15403, and 20
McDonald 4758-22. Grip fittings are not acceptable. 21
22
9-30.6(5) Meter Setters 23
(June 26, 2020 COP GSP) 24
25
Supplement this section with the following: 26
27
New 1” compression valve shall be Ford BA43, Mueller B-24258N, or McDonald 74602B. 28
New 2” threaded valves shall be Ford BFA13, Mueller B-24286N, or McDonald 74604B. All 29
angle meter valves shall be quarter turn. 30
31
9-30.6(7) Meter Boxes 32
(June 26, 2020 COP GSP) 33
34
Supplement this section with the following: 35
36
Meter Boxes (3/4” to 2” meters): New meter boxes shall be Raven RMB 1324-18 or Carson 37
HW Model 1324BCF-18 with 1324R reader lid (3/4” and 1” meters) and Raven RMB 1730-38
18 or Carson HW Model 1730BCF-18 with 1730R reader lid (1-1/2” and 2” meters). 39
40
(June 26, 2020 COP GSP) 41
Add the following new Section: 42
43
9-30.6(8) Locating Wire 44
45
Locate wire shall meet the requirements of Section 7-09.3(20) and be continuous from the 46
water main to the meter box. Locating wire shall be 12-gauge heavy insulated (60 mil) 47
copper wire with UF insulation colored for the utility being installed in accordance with 48
Section 9-15.18. Direct bury splice kits shall be 3M DBY-6. 49
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-111
1
(June 26, 2020 COP GSP) 2
Add the following new Section: 3
4
9-30.6(9) Meter 5
6
New 3/4” to 2” meters shall meet the requirements of AWWA C700. Approved meters shall 7
be any of the following: Badger (LP35, LP55, LP120), Neptune (T-10, Tru/Flo), and Sensus 8
(SRII, SRH). 9
10
(June 26, 2020 COP GSP) 11
Add the following new Section: 12
13
9-30.6(10) Meter Check Valve 14
15
New 1” compression valves shall be Ford HA34 or Mueller H-14269. New 1-1/2” and 2” 16
threaded valves shall be Ford HFA31. 17
18
(June 26, 2020 COP GSP) 19
Add the following new Section: 20
21
9-30.6(11) Thread Sealant 22
23
Thread sealant shall be used on all threaded pipe fittings. Approved manufacturers include 24
Spears Blue 75, Whitlam Blue Magic, and Teflon Tape. 25
26
27
(June 26, 2020 COP GSP) 28
Add the following new Section: 29
30
9-30.6(12) Backflow Assembly Box 31
32
Backflow Assembly Box (3/4” to 2”): New assembly box shall be Carson 1220 and 1324 33
(3/4” and 1”) and Carson 1730 (1-1/4” to 2”), meeting inside dimension tolerances specified 34
on Details. 35
36
(June 26, 2020 COP GSP) 37
Add the following new Section: 38
39
9-30.6(13) Meter Vault 40
41
New precast cement concrete vault shall be Oldcastle Precast or H2 Precast meeting inside 42
dimension tolerances specified on the Plans, and shall have diamond plate spring assisted 43
cover with locking latch inside (332P cover). 44
45
(June 26, 2020 COP GSP) 46
Add the following new Section: 47
48
City of Pasco
September 2020 19073 WATER MAIN REPLACEMENT – ALLEY EAST OF WEHE AVE
SP-112
9-30.6(14) Back Flow Assembly Vault 1
2
New precast cement concrete vault shall be Oldcastle Precast or H2 Precast meeting inside 3
dimension tolerances specified on Details, and shall have diamond plate spring assisted 4
cover with locking latch inside (332P for 2” to 3”, 2-322P for 4” to 6”, and 3-322P for 8” to 5
12”). Contractor shall provide to the City Inspector any factory tools, keys, or wrenches 6
required to open vault lid. 7
8
(June 26, 2020 COP GSP) 9
Add the following new Section: 10
11
9-30.6(15) Vault Ladder 12
13
Ladders installed in vaults shall include a Bilco LadderUp safety post, model LU-2, LU-3, or 14
LU-4. 15
16
(June 26, 2020 COP GSP) 17
Add the following new Section: 18
19
9-30.6(16) Pipe Bedding and Backfill 20
21
Pipe bedding and select backfill shall be utilized for trench backfill as directed by the City in 22
accordance with Section 7-09.2 of the Special Provisions. 23
24
25
END DIVISION 9 26
27
28
PLANS
LOCATION MAP
BASIN DISPOSAL VICTOR FLORES (509) 547-2476
CASCADE NATURAL GAS ARNIE GARZA (509) 735-5548
CENTURY LINK TOBIAS MEARS (509) 839-6651
CHARTER COMMUNICATION TROY CAMPOS (509) 222-2665
CITY OF PASCO, ENGINEERING KENT MCCUE (509) 545-3444
CITY OF PASCO, PUBLIC WORKS OPERATIONS KIM HOLST (509) 545-3084
CITY OF PASCO, OPERATIONS KIM HOLST (509)545-3463
FRANKLIN COUNTY IRRIGATION DISTRICT JOHN BURNS (509) 547-9391
FRANKLIN PUD NORM RUMMEL (509) 546-5965
PASCO SCHOOL DISTRICT, TRANSPORTATION SHAREN RATCLIFFE (509) 547-2510
SITE
SHEET
DRAWN BY:
DESIGN BY:
CHECKED BY:
HOR SCALE:
VER SCALE:
PROJECT NO:
CAD DWG:
DATE:REVBY APR.DATE(509) 545-3444REVISIONCITY OF PASCODESCRIPTIONPUBLIC WORKS - ENGINEERINGWATER MAIN REPLACEMENTALLEY EAST OF WEHE AVENUECOVER SHEETBID
19703
10-12-2020
DV/MA
JP
MS/KM
N/A
N/A
1
11
1
3 PLAN & PROFILE: STA 1+00 TO STA 2+00
R
Know what's below.
before you dig.Call
2
NTS
4
5
6
7
8
PLAN & PROFILE: STA 2+00 TO STA 3+00
PLAN & PROFILE: STA 3+00 TO STA 4+00
PLAN & PROFILE STA: 4+00 TO STA 5+00
PLAN & PROFILE STA: 5+00 TO STA: 6+00
VICINITY MAP
NTS
SITE
COVER SHEET
SHEET INDEX
SHEET TITLEREV NO.SHEET NO.
GENERAL NOTES
DETAILS
9
N
10
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
11
DETAILS
CITY OF PASCO
WATER MAIN REPLACEMENT
ALLEY EAST OF WEHE AVENUE
PROJECT NUMBER: 19073
CONTACTS BA49510S F
ETTAIN
OG
TNO WASH
R RETGIES DE IGE EENO RLNAP F
OR
SSE
I N
GENERAL NOTES
MISCELLANEOUS
UNDERGROUND UTILITIES
GARBAGE SERVICE
UNDERGROUND GAS UTILITIES
UNDERGROUND ELECTRIC UTILITIES
PAVING
POTABLE WATER
FIRE HYDRANT RESTRAINT
SURVEY
ALLEY ACCESS
WATER METER & METER BOX REPLACEMENT
ABBREVIATIONS
LEGEND
WATER EXISTING PROPOSED
NATURAL GAS
POWER
CENTURY LINK
ROAD
GENERAL
R
Know what's below.before you dig.Call
SHEET
DRAWN BY:
DESIGN BY:
CHECKED BY:
HOR SCALE:
VER SCALE:
PROJECT NO:
CAD DWG:
DATE:REVBY APR.DATE(509) 545-3444REVISIONCITY OF PASCODESCRIPTIONPUBLIC WORKS - ENGINEERINGWATER MAIN REPLACEMENTALLEY EAST OF WEHE AVE49510S FE
TTAIN
OG
TNO WASH
R RETGIES DE IGE EENO RLNAP F
OR
SSE
I N
2
11GENERAL NOTESBID
19703
10-12-2020
DV/MA
JP
MS/KM
N/A
N/A
KEY NOTESNMATCHLINE SHEET 4
RKnow what'sbelow.before you dig.CallSHEETDRAWN BY:DESIGN BY:CHECKED BY:HOR SCALE:VER SCALE:PROJECT NO:CAD DWG:DATE:REV BY APR.DATE
(509) 545-3444
REVISION
CITY OF PASCO
DESCRIPTION
PUBLIC WORKS - ENGINEERING
WATER MAIN REPLACEMENT
ALLEY EAST OF WEHE AVE
49510S
FE
T TA
INOGTNOWASHR RETGIESDE
IGE
EE
NO
RLNAP FORSSEIN113PLAN AND PROFILE
STA 1+00 TO STA 2+00SEE PLAN/PROFILESEE PLAN/PROFILE0510FEETUNDERGROUND GAS UTILITIESLOCATION OF GAS UTILITIES IS UNCERTAIN, SEEGENERAL NOTES FOR ADDITIONAL INFORMATION.UNDERGROUND ELECTRIC UTILITIESLOCATION OF ELECTRIC UTILITIES UNCERTAIN, SEEGENERAL NOTES FOR ADDITIONAL INFORMATION.MS/KMJPDV/MA10-12-202019703BID
NMATCHLINE SHEET 5
MATCHLINE SHEET 3
RKnow what'sbelow.before you dig.CallSHEETDRAWN BY:DESIGN BY:CHECKED BY:HOR SCALE:VER SCALE:PROJECT NO:CAD DWG:DATE:REV BY APR.DATE
(509) 545-3444
REVISION
CITY OF PASCO
DESCRIPTION
PUBLIC WORKS - ENGINEERING
WATER MAIN REPLACEMENT
ALLEY EAST OF WEHE AVE
49510S
FET TA
INOGTNOWASHR RETGIESDE
IGE
EE
NO
RLNAP FORSSEIN411PLAN & PROFILE
STA 2+00 TO STA 3+00 0510FEETUNDERGROUND GAS UTILITIESLOCATION OF GAS UTILITIES IS UNCERTAIN, SEEGENERAL NOTES FOR ADDITIONAL INFORMATION.UNDERGROUND ELECTRIC UTILITIESLOCATION OF ELECTRIC UTILITIES UNCERTAIN, SEEGENERAL NOTES FOR ADDITIONAL INFORMATION.KEY NOTESMS/KMJPDV/MA10-12-202019703BIDSEE PLAN/PROFILESEE PLAN/PROFILE
NMATCHLINE SHEET 6
MATCHLINE SHEET 4
RKnow what'sbelow.before you dig.CallSHEETDRAWN BY:DESIGN BY:CHECKED BY:HOR SCALE:VER SCALE:PROJECT NO:CAD DWG:DATE:REV BY APR.DATE
(509) 545-3444
REVISION
CITY OF PASCO
DESCRIPTION
PUBLIC WORKS - ENGINEERING
WATER MAIN REPLACEMENT
ALLEY EAST OF WEHE AVE
49510S
FE
T TA
INOGTNOWASHR RETGIESDE
IGE
EE
NO
RLNAP FORSSEIN511PLAN & PROFILE
STA 3+00 TO STA 4+00 0510FEETUNDERGROUND GAS UTILITIESLOCATION OF GAS UTILITIES IS UNCERTAIN, SEEGENERAL NOTES FOR ADDITIONAL INFORMATION.UNDERGROUND ELECTRIC UTILITIESLOCATION OF ELECTRIC UTILITIES UNCERTAIN, SEEGENERAL NOTES FOR ADDITIONAL INFORMATION.KEY NOTESMS/KMJPDV/MA10-12-202019703BIDSEE PLAN/PROFILESEE PLAN/PROFILE
VOLTSNMATCHLINE SHEET 7
MATCHLINE SHEET 5
RKnow what'sbelow.before you dig.CallSHEETDRAWN BY:DESIGN BY:CHECKED BY:HOR SCALE:VER SCALE:PROJECT NO:CAD DWG:DATE:REV BY APR.DATE
(509) 545-3444
REVISION
CITY OF PASCO
DESCRIPTION
PUBLIC WORKS - ENGINEERING
WATER MAIN REPLACEMENT
ALLEY EAST OF WEHE AVE
49510S
FET TA
INOGTNOWASHR RETGIESDE
IGE
EE
NO
RLNAP FORSSEIN611PLAN & PROFILE STA
4+00 TO STA 5+00 0510FEETUNDERGROUND GAS UTILITIESLOCATION OF GAS UTILITIES IS UNCERTAIN, SEEGENERAL NOTES FOR ADDITIONAL INFORMATION.UNDERGROUND ELECTRIC UTILITIESLOCATION OF ELECTRIC UTILITIES UNCERTAIN, SEEGENERAL NOTES FOR ADDITIONAL INFORMATION.KEY NOTESMS/KMJPDV/MA10-12-202019703BIDSEE PLAN/PROFILESEE PLAN/PROFILE
NMATCHLINE SHEET 6
RKnow what'sbelow.before you dig.CallSHEETDRAWN BY:DESIGN BY:CHECKED BY:HOR SCALE:VER SCALE:PROJECT NO:CAD DWG:DATE:REV BY APR.DATE
(509) 545-3444
REVISION
CITY OF PASCO
DESCRIPTION
PUBLIC WORKS - ENGINEERING
WATER MAIN REPLACEMENT
ALLEY EAST OF WEHE AVE
49510S
FET TA
INOGTNOWASHR RETGIESDE
IGE
EENORLNAP FORSSEIN711PLAN & PROFILE
STA: 5+00 TO STA: 6+00 0510FEETUNDERGROUND GAS UTILITIESLOCATION OF GAS UTILITIES IS UNCERTAIN, SEEGENERAL NOTES FOR ADDITIONAL INFORMATION.UNDERGROUND ELECTRIC UTILITIESLOCATION OF ELECTRIC UTILITIES UNCERTAIN, SEEGENERAL NOTES FOR ADDITIONAL INFORMATION.KEY NOTESMS/KMJPDV/MA10-12-202019703BIDSEE PLAN/PROFILESEE PLAN/PROFILE
HMA PAVEMENT REPAIR FOR STREETSNOTES:1. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL TRENCH SURFACE RESTORATION BEYOND THE LIMITS SHOWN,INCLUDING WIDER TRENCH SECTIONS RESULTING FROM LAYING BACK TRENCH SIDES AT THE CONTRACTORSOPTION.2. NO AREA REQUIRING ASPHALT CONCRETE SURFACING REPAIR SHALL REMAIN UNPAVED FOR MORE THAN FIVEWORKING DAYS FOLLOWING INITIAL EXCAVATION.3. ALL THICKNESSES ARE COMPACTED DEPTHS.(MIN)1'-6"1'-6"1'-6"HOT MIX ASPHALT PATCH LIMITSSYMMETRICALABOUT ℄ OF PIPECOMPACTEDBACKFILLSAWCUT PRIORTO REPAIREXISTING PAVEMENTSURFACING DEPTHVARIESEXCAVATIONLIMITSSAWCUT PRIORTO REPAIR3" HMA, CL. 1/2"PG 64S-28*10" CRUSHEDSURFACINGBASE COURSEALTERNATEBACKSLOPE ATCONTRACTORSOPTION* 4" HMA DEPTH ONTRUCK ROUTESHMA PAVEMENT FOR ALLEYHOT MIX ASPHALT PAVING LIMITSCOMPACTEDBACKFILL2" HMA, CL. 1/2"PG 64S-28*6" CRUSHEDSURFACINGBASE COURSECOMPACTEDBACKFILL2" CRUSHEDSURFACINGTOP COURSEBST SURFACETREATMENTAPPROXIMATELY 4" GRAVEL(CONTRACTOR TO FIELD VERIFY)EXISTING ALLEY SURFACE10' WIDE EXISTING ALLEY PAVEMENTNEW ASPHALT TOMATCH ADJACENTEXISTING GRADESNEW ASPHALT TOMATCH ADJACENTEXISTING GRADESCUT-IN TEE/CROSSTAPPING SLEEVE AND VALVEADDITIONAL VALVESMAY BE REQUIREDTHRUST BLOCK TO BE PERDWG. NO. W-8EXISTING WATER MAINFLANGED COUPLING ADAPTERSEE SPECIFICATIONSNEW WATER MAINFLANGE X MJ VALVERESILIENT SEATED GATE VALVESEE SPECIFICATIONSTHRUST BLOCK PER DWG. NO. W-8EXISTING WATER MAINRESILIENT SEATED GATE MJ X FL TAPPINGVALVE, SEE SPECIFICATIONSCOUPLING ADAPTER AS REQUIREDBY PIPE SIZE AND TYPETAPPING SLEEVESEE SPECIFICATIONS2' MIN.MINIMUM 10' LONGTRENCH TO ALLOW FORCITY TAPPING MACHINETRENCH LIMITNOTES:1. CONTRACTOR TO DIG & VERIFY PIPE SIZE AND MATERIAL PRIOR TO ORDERING MATERIALS.2. MATERIALS TO BE ON THE JOB PRIOR TO SCHEDULING SHUTDOWNS OR TAPS. UP TO 48 HOURS NOTICE SHALL BE REQUIRED TOSCHEDULE CITY CREWS FOR TAP.3. MAXIMUM TAP TO EXISTING LINE NOT TO EXCEED 50% OF MAIN DIAMETER ON A.C. OR P.V.C. PIPE, EXCEPT C900/905.4. FOR D.I., C.I. STEEL AND C-900/905 SIZE ON SIZE TAPPING TEES AND SADDLES ON MAINS SHALL BE TAPPED 1/2" UNDERSIZED.5. CONTRACTOR TO EXCAVATE, INSTALL TAPPING SLEEVE AND VALVE PRIOR TO CITY CREW ARRIVAL, CITY CREW WILL COMPLETETAP, TAP FEE MAY BE REQUIRED. CONTRACTOR SHALL SUPPLY PROPER SLOPING/SHORING, ALONG WITH TABULATED DATA, PRIORTO CITY CREW ARRIVAL.6. ONCE IN SERVICE, WATER SHALL NOT BE TURNED OFF WITHOUT APPROVAL FROM CITY ENGINEER OR CITY FIELD DIVISIONMANAGER.7. IF WATER MAIN IS LESS THAN 6" DIAMETER, A CUT-IN TEE SHALL BE USED.FINISH GRADENOTES:1. IF METER NOT INSTALLED, A PVC JUMPER CUT TO THE SIZE AND THREAD OF THE APPROPRIATE SERVICE SHALL BE PLACED BETWEEN ANGLE METER STOP AND METER CHECK VALVE. DRILL TWO 3/16" HOLES IN JUMPER.2. SEE DWG. W-20 FOR BEDDING.3. BOXES TO BE SET PERPENDICULAR TO THE STREET, TOP OF BOX LEVEL WITH TOP BACK OF SIDEWALK.4. ATTACH THE TWO BOX SECTIONS TOGETHER WITH #14 X 2-1/2" HEX WASHER HEAD ZINC COATED SELF TAPPING SCREW AT 2EQUALLY SPACED LOCATIONS ON THE LONG SIDE. SPREADER BAR TO BE BETWEEN THE TWO BOXES.5. ALL SERVICE CONNECTIONS TO WATER MAIN, EXCEPT TO DUCTILE IRON PIPE CLASS 52 OR STRONGER SHALL BE MADE USINGSADDLES AS SPECIFIED AND BE OF THE SIZE AND TYPE SUITABLE FOR USE WITH THE PIPE BEING INSTALLED.6. WATER SERVICE TAIL PIECE SHALL BE EXTENDED TO THE PROPERTY LINE OR EASEMENT LINE, WHICHEVER IS FURTHER, ANDMARKED WITH AN 8' TREATED 2x4 INSIDE AN 8' STEEL STUD, PAINTED BLUE, EXTENDING 36-48" ABOVE FINISHED GROUND SURFACE.MARKER BOARD TO BE CUT OFF FLUSH WITH THE GROUND IN ALREADY ESTABLISHED AREAS.7. WATER METER BOX TO HAVE 18" CLEARANCE FROM ANY CONCRETE OR ASPHALT DRIVEWAY, SIDEWALK, ETC.8. DO NOT BURY ANGLE METER STOP BEFORE INSTALLING METER BOX.9. NO COUPLINGS FROM MAIN TO ANGLE METER STOP OR FROM ANGLE METER CHECK TO TERMINATION AT EASEMENT LINE.10. COPPER SERVICE TO BE SET TO GRADE BEFORE WATER IS TURNED ON.11. BACKFLOW PREVENTION SHALL BE A REDUCED PRESSURE BACKFLOW ASSEMBLY FOR COMMERCIAL WATER SERVICES. THISREQUIREMENT MAY BE REDUCED OR WAIVED UPON WRITTEN REQUEST TO THE CITY ENGINEER. BACKFLOW ASSEMBLY ANDFITTINGS ARE TO BE LEAD FREE.12. PROPERTY OWNER RESPONSIBLE FOR ACCESS TO VALVE (VALVE BOX/CAN) AND FREEZE PROTECTION. SEE SPECIFICATIONS.13. THESE BACKFLOW PREVENTION ASSEMBLY INSTALLATION STANDARDS REFLECT MINIMUM REQUIREMENTS TO COMPLY WITHWASHINGTON DEPARTMENT OF HEALTH REGULATIONS (WAC 246-290-490) AND UNIFORM PLUMBING CODE. UNAPPROVED DEVIATIONMAY RESULT IN THE CITY REJECTING THE INSTALLATION AND THE CERTIFICATE OF OCCUPANCY AS WELL. ALL REQUESTS FORDEVIATION TO THESE STANDARDS MUST BE SUBMITTED IN WRITING AND APPROVED BY THE CITY'S CROSS CONNECTIONSPECIALIST.42" MIN.30° - 45°1" METER CHECK VALVE,SEE SPECIFICATIONSSEE NOTE 11" ANGLE METER STOP, SEE SPECIFICATIONSSEE NOTE 3SEE NOTE 4EXTEND PLAIN END TAIL PIPE.SEE NOTE 71" "K" TYPE COPPER PIPEMETER BOX, SEESPECIFICATIONSWATER MAINPVC TAP, WITHHORIZONTAL S-CURVESERVICE SADDLE,SEE SPECIFICATIONSCORPORATION STOP,SEE SPECIFICATIONSDUCTILE TAPONLY1" "K" TYPECOPPER PIPE12"36"42" MIN.6"WATER MAIN1" PVC JUMPERTO BUILDING1"x1" THxSLP3/16" HOLES2 EACH11"WHITE INTERNAL LINERSCREWSPREADER BAR11"WATER MAIN
SIDEWALK18"R/W LINE
CURB FACETO HOUSE/BUSINESSTO IRRIGATION SYSTEM(IF APPLICABLE)UTILITY ESMT.BACKFLOWPREVENTOR, LOCATEOUT OF R/W OR ESMT.IRRIGATION CONNECTION ONLY IF NOIRRIGATION SERVICE IS AVAILABLEAND SHALL BE LEAD FREE24"-36"36"R.S. VALVEWATER SERVICEMETER BOXWATER MAINWATERLID DETAILEXTENSION PIECE DETAILUNIMPROVEDIMPROVEDMATCH NEW HMA WITHEXISTING HMA(CONCRETE COLLAR INUNIMPROVED AREAS)SEE LID DETAILSEE EXTENSION PIECE DETAILVALVE OPERATING EXTENSIONSSHALL BE INSTALLED TO PROVIDEA 4 FOOT OPERATING DEPTHTRACER WIRE #12 GAUGECOPPER WIRE WITH UFINSULATOR COLOR BLUE2" GAPTIGHTLY WRAP WIRE 3 FULL TURNSBELOW VALVE OPERATOR FLANGE ONGATE VALVE AND AGAINST VALVE BODYON B.F. VALVES.ATTACH WIRE TO CENTER OF PIPEAT MIN. 6' INTERVALS AND ATBENDS WITH DUCT TAPEMARKED WITH RAISEDLETTERS ('WATER' OR'IRR', AS APPROPRIATE),SEE SPECIFICATIONSTRACING WIRE SPLICE KIT,SEE SPECIFICATIONS6"MIN.6"MIN.12"18"24"36"6" MIN.24"VARIESNOTES:1. BUTTERFLY VALVES SHALL BE ORIENTED SUCH THAT THE OPERATING NUT AND VALVE BOX SHALL BE NEAR THE CENTERLINE.2. SEE DWG. NO. W-20 FOR BEDDING.IRR2.5" COMMERCIAL HMA4" MIN. CONCRETE6" MIN.CLASS 3000 CONCRETE COLLAR WITHLIGHT BROOM FIINISH6" MIN.VERTICAL THRUST BLOCKSREBAR EMBEDMENT HOOKSIZE DEPTH SIZE# 411"6"# 514"7.5"# 617"9"# 822"12"SADDLE THRUST BLOCKSEE DWG. NO. W-9NOTES:1. THRUST BLOCKING TO BE STRUCTURAL CONCRETE PER SPECIFICATIONS. MAX. SLUMP OF 4".2. THE TABULATIONS ARE BASED UPON A MAXIMUM WATER PRESSURE OF 150 PSI AND A SAFE BEARING CAPACITY OF 2,000LBS. PER SQ. FOOT ADJUST FOR OTHER VALUES OF PRESSURE.3. KEEP CONCRETE CLEAR OF JOINTS AND ACCESSORIES.4. ALL THRUST BLOCKS MUST BE FORMED WITH PLYWOOD OR OSB AND INSPECTED. BY C.O.P. WATER DEPARTMENT.5. JOINTS TO BE WRAPPED POLYETHYLENE 3 MIL.6. MECHANICALLY RESTRAINED PIPE AND FITTINGS MAY BE USED IN LIEU OF THRUST BLOCKING, SEE SPECIAL PROVISIONS7-09.3(21).A(FT)B(FT) C(IN)6" & UNDER 211.5 88"211.5 810"21.51.5 1212"41.51.5 1216"421.5 1618"42.52 2020"632 2424"83.52 24TOP VIEWSIDE VIEWBC246915192434FUTURE WATERLINEEND CAP3/4" SHACKLE RODS,GALVANIZEDFUTURE WATERLINEEND CAPROD "L"SEE NOTE 13/8" REBARUNDISTURBED EARTH,TRENCH WIDTH VARIESREBAR CAGEPIPEDIAMETERSHACKLERODSREQUIREDBEARINGAREA(SF)DIMENSIONSMINIMUM BEARING AREA OF THRUST BLOCK IN SQ. FEET(BASED ON 2,000 P.S.F. SOIL BEARING CAP)AAAASECTION A - A10'NOTES:1. THE LENGTH OF RODS "L" SHALL BE 10 FEETMINIMUMOR AS DIRECTED BY THE CITY ENGINEER.2. CONCRETE SHALL BE PER THE SPECIFICATIONS.3. RESTRAINED JOINTS (MEGA-LUG AND/OR FIELD LOCGASKETS) MAY BE USED OR SHALL BE REQUESTEDTO BE USED AT THE DIRECTION AND PERMISSIONOF THECITY ENGINEER.BBBTRENCH SURFACING REPAIRST-3 (PROJECT SPECIFIC)CITY OF PASCO - STANDARD DETAILTAPPING WATER MAINW-1CITY OF PASCO - STANDARD DETAILRESIDENTIAL AND 1" COMMERCIAL WATER SERVICEW-2CITY OF PASCO - STANDARD DETAILCAST IRON VALVE BOXW-4CITY OF PASCO - STANDARD DETAILCONCRETE THRUST BLOCKINGW-8CITY OF PASCO - STANDARD DETAILSADDLE THRUST BLOCKINGW-9RKnow what'sbelow.before you dig.CallSHEETDRAWN BY:DESIGN BY:CHECKED BY:HOR SCALE:VER SCALE:PROJECT NO:CAD DWG:DATE:REV BY APR.DATE
(509) 545-3444
REVISION
CITY OF PASCO
DESCRIPTION
PUBLIC WORKS - ENGINEERING
WATER MAIN REPLACEMENT
ALLEY EAST OF WEHE AVE
49510S
FE
T TA
INOGTNOWASHR RETGIESDE
IGE
EE
NO
RLNAP FORSSEIN811DETAILSSEE PLAN/PROFILESEE PLAN/PROFILESEE PLAN/PROFILESEE PLAN/PROFILEBID1970310-12-2020DV/MAJPMS/KM
4" CRUSHED SURFACING TOP COURSE5' RESIDENTIAL7' COMMERCIALCROSS SLOPE 2% MAX. / 1% MIN.SEE DWG. NO. ST-6FOR CURB DETAILS4" CEMENT CONCRETENOTES:1. JOINTS ON SIDEWALKS EVERY 5' (FEET) OR AS REQUIRED TO MATCH EXISTING IMPROVEMENTS (CUT 3/4" MIN. DEEP FORAGGREGATE SEPARATION). THE JOINTS SHALL MATCH CURB JOINTS AND BE PERPENDICULAR TO THE CURB.2. SIDEWALK EXPANSION JOINTS USING 1/2" MASTIC ARE REQUIRED AT 30' SPACING, ALL CURB RETURNS, THE TOP AND BOTTOM OFALL DRIVEWAY TRANSITIONS, AND AT EXISTING CONCRETE.3. ALL 1/2" MASTIC TO BE FULL DEPTH PENETRATION AND FLUSH WITH THE FINISHED SURFACE.4. IF THE THREAT OF RAIN OR BLOWING SAND IS PRESENT, SURFACES SHALL BE COVERED WITH 6-MIL POLY SHEETING. IF THETHREAT OF FREEZING IS PRESENT, THE WORK SHALL BE COVERED WITH THERMAL CURING BLANKETS FOR A PERIOD OF SEVEN(7) DAYS.5. CRUSHED SURFACING TOP COURSE AND SUBGRADE SHALL BE COMPACTED TO A MINIMUM OF 95% OF ASTM D1557.6. HEADERBOARD BULKHEADS TO BE INSTALLED PRIOR TO FORM INSPECTION.7.SIDEWALKS BEHIND MOUNTABLE AND DEPRESSED CURB SHALL HAVE 6" THICK CONCRETE.8. SLOPE ALL SURFACES (I.E. LANDSCAPE WHERE DETACHED SIDEWALK) AT 2% FROM RIGHT OF WAY TO BACK OF CURB.WATER SERVICE6"WATER MAINSEE DWG. NO. ST-3FOR TRENCH SURFACING REPAIRDETECTABLEMARKING TAPETRENCH WALLTRACER WIREPIPE ZONE BEDDING PERSPECIFICATIONS, OR ASAPPROVED BY CITY ENGINEERWATER MAINTRENCH BACKFILL MATERIAL MUSTBE COMPACTED TO 95% OR MIN.(ASTM D698)2'TACK AROUNDEXISTING PAVEMENTPIPE BEDDING ALL AROUND MUST BECOMPACTED TO 95% MIN. (ASTM 698)CORPORATION STOPNOTES:1. THIS STANDARD IS ACCEPTABLE FOR DEPTHS UP TO 14 FEET. PIPES THAT EXCEED 14 FEET SHALL CONFORM TO MANUFACTURER'SRECOMMENDATIONS FOR BEDDING.2. TRENCH SHALL BE EXCAVATED TO ACCOMMODATE PIPE BELL.6"DUCTILE IRON TAPPVC TAPPIPEZONE6"TRENCH BEDDING MATERIAL MUSTBE COMPACTED TO 95% OR MIN.(ASTM D698)R/W LINENOTES:1. HYDRANTS SHALL BE PER THE SPECIFICATIONS.2. HUB & FLANGE CASTING. (SEE SPECIFICATIONS).3. HYDRANTS SHALL BE HOODED UNTIL OPERATIONAL.4. HYDRANTS SHALL FACE THE STREET UNLESS OTHERWISE APPROVED BY THE CITY ENGINEER.5. TRACER WIRE FROM MAIN TO FIRE HYDRANT. (BLUE INSULATION)6. USE OF HYDRANT EXTENSIONS MUST BE APPROVED IN WRITING BY THE CITY ENGINEER. NOT TO BE USED IN NEW INSTALLATIONS.7. SEE GUARD POST REQUIREMENTS DWG. NO. W-12.8. REMOVE CHAINS FROM CAPS. STORZ CABLE TO REMAIN.9. MECHANICAL RESTRAINT WILL BE PROVIDED IN LIEU OF THRUST BLOCKS CONTINUOUSLY FROM THE HYDRANT THROUGH THE6 INCH BRANCH OF THE TEE.HYDRANT - PAINTED OSHASAFETY YELLOW5" STORZ ADAPTER WITHCAP PER SPECIFICATIONSCOMPACTED BACK FILLTO 95% (ASTM D698)PLACE MINIMUM OF 2 C.F.OF 2" MINUS DRAIN ROCKFILTER FABRICSEPARATING DRAIN ROCKAND NATIVE SOILSCONCRETE BASE BLOCK 12"x12"x4"WEEP HOLE, DONOT COVER WITHCONCRETE BASE6" PIPE, ROMAC GRIPRINGS AT ALL JOINTS6" GATE VALVE MJxFLBOLT TO TEE ORTAPPING SLEEVEWATER MAINTHRUST BLOCK PER DWG. NO. W-8VARIABLETYPICAL SIDEWALKVALVE BOX EXTENSIONSEE DWG. NO. W-4TYPICAL CURBAND GUTTERVALVE BOX PERDWG. NO. W-4SEE NOTE 512"HYDRANT PLACEMENTWITHIN CITY R/W ORWITHIN UTILITYEASEMENT24"MAX.3' - 6" MIN.3-6" DIAMETER AROUNDHYDRANT MUST BE LEVELEXCAVATION LIMITS2"-8" ABOVE ADJACENTGROUND ELEVATIONROMAC GRIPRING MJACCESSORYKITROMAC GRIP RINGMJ ACCESSORY KITSEE NOTE 2NOTES:1. CURB & GUTTER, VALLEY GUTTER, & CONCRETE APPROACH SHALL BE SEPARATED BY 3/8" THICK EXPANSION JOINT MATERIAL.2. THIS DETAIL INDICATES GENERAL CONFIGURATION REQUIREMENTS FOR COMMERCIAL DRIVEWAY APPROACHES. STYLE AND LOCATIONOF HANDICAP RAMPS WILL DEPEND UPON SITE CONDITIONS AND SHALL BE CONSTRUCTED ACCORDING TO THE SPECIFIC PROJECT SITEPLAN APPROVED BY THE CITY ENGINEER.3. WSDOT CLASS 3000 CONCRETE WITH COARSE AGGREGATE GRADING NO. 5.4. DUE TO THE MINIMUM SIZE RADIUS OF 15', SPECIAL CONSIDERATIONS NEED TO BE MADE TO ALLOW FOR ADA PROVISIONS ON THE RAMPS.15' RADIUS DESIGNS MUST BE SUBMITTED AND APPROVED BY THE CITY ENGINEER PRIOR TO CONSTRUCTION.5. REGARDLESS OF QUANTITY, A CERTIFICATE OF COMPLIANCE SHALL BE PROVIDED FOR ALL CONCRETE DELIVERED TO THE SITE.2% MAX
.1% M
IN
.1/2 DRIVEWAY WIDTH(12' MINIMUM)6" CEMENT CONCRETE(INCLUDING APRON)MIN. 3" CSTC (COMPACTED DEPTH)(INCLUDING APRON)COMMERCIAL APPROACH - TYPE 2L5'
APRON
orTO R/W
L
INE(WHICHEVER
ISGREATER)RAMP RUNNING SLOPESSHALL BE 7.5% MAX.COLD JOINT (TYP)COLD JOINT (TYP)DETECTABLE WARNINGSURFACE, SEE WSDOTSTD. PLAN F-45.10.7.5%CNOTES:1. CONCRETE SHALL BE PER THE SPECIFICATIONS.2. CUT JOINTS SHALL BE 10'-0" O/C.3. EXPANSION MATERIAL (3/8" MASTIC) SHALL BE PLACED AT ALL CURB RETURNS.4. BONDING AGENT TO BE FOUR (4) PARTS PORTLAND CONCRETE SLURRY TO ONE (1) PART DAYTON SUPERIOR J-40,OR APPROVED EQUAL.5. MATCH ROADWAY SLOPE. MAXIMUM COUNTER SLOPE SHALL BE 5.0%.6. VALLEY GUTTER SHALL INCLUDE TWO (2) #4 REBAR.TYPE "A" BARRIER CURB AND GUTTERMATCH ROADWAY SLOPETYPE "D" DEPRESSED CURB AND GUTTER ATDRIVEWAY DROP AND ADA RAMPSVARIES2%1/2"R1/4"R6"18"5/8"6"SEE NOTE 512"5-1/2"1/2"18"6"1"R5/8"STAB MIN. 3" TYP. EVERY CUTJOINTCEMENT CONCRETE VALLEY GUTTER7"1/2" R1/2" R25"11"FLOWLINE9/16"7"12"7"36"TAPERTO ZEROEXPANSION JOINTCURB TERMINAL ENDREBAR, SEE NOTE 6FINISHED GRADESEE DWG. NO. W-4 FORVALVE BOX ADJUSTMENTS2" THREADED CAP(FINGER TIGHT)SEE DWG. NO. W-4 FORVALVE BOX ADJUSTMENTSSTD. PIPE THREADSCONCRETE THRUST BLOCKPER DWG. NO. W-8CAP WITH 2" I.P.THREADED TAPUNDISTURBED EARTHPIPE BEDDINGSADDLE THRUST BLOCKSEE DWG. NO. W-9VALVE BOX WITH COVERPER SPECIFICATIONS2" DIA. GALV. STEEL PIPE (APWA 72-2.06)42" MIN.COVER10' MIN.2"WATER MAIN ORIRRIGATION LINE1' MIN.NOTES:1. ON WATER MAINS WHICH WILL BE EXTENDED IN THE FUTURE, THE VALVE WHICH OPERATES THE BLOW-OFF ASSEMBLY SHALL BE THE SAME SIZE AS THE MAIN UNLESS OTHERWISEAPPROVED BY THE ENGINEER.2. THE THRUST BLOCK SHALL BE SIZED TO PROVIDE THRUST FOR THE MAIN WATER LINE.3. JOINT RESTRAINTS AND FIELD LOK GASKETS MAY BE REQUIRED IN PLACE OF A SADDLE THRUST BLOCK OR MAY BE USED WITH PERMISSION OF THE CITY ENGINEER.WATER MAIN VALVE1" HEX NUTWELDEDTO CAPRKnow what'sbelow.before you dig.CallCITY OF PASCO - STANDARD DETAILCEMENT CONCRETESIDEWALKST-4CITY OF PASCO - STANDARD DETAILCITY OF PASCO - STANDARD DETAILCEMENT CONCRETE CURBSST-6TYPICAL WATER TRENCH SECTIONW-20FIRE HYDRANT INSTALLATIONW-10 (PROJECT SPECIFIC)CEMENT CONCRETE CURBSST-5 (PROJECT SPECIFIC)RKnow what'sbelow.before you dig.CallSHEETDRAWN BY:DESIGN BY:CHECKED BY:HOR SCALE:VER SCALE:PROJECT NO:CAD DWG:DATE:REV BY APR.DATE
(509) 545-3444
REVISION
CITY OF PASCO
DESCRIPTION
PUBLIC WORKS - ENGINEERING
WATER MAIN REPLACEMENT
ALLEY EAST OF WEHE AVE
49510S
FE
T TA
INOGTNOWASHR RETGIESDE
IGE
EE
NO
RLNAP FORSSEIN911DETAILSCITY OF PASCO - STANDARD DETAILBLOW-OFF ASSEMBLYW-5SEE PLAN/PROFILESEE PLAN/PROFILEBID1970310-12-2020DV/MAJPMS/KM
RKnow what'sbelow.before you dig.CallSHEETDRAWN BY:DESIGN BY:CHECKED BY:HOR SCALE:VER SCALE:PROJECT NO:CAD DWG:DATE:REV BY APR.DATE
(509) 545-3444
REVISION
CITY OF PASCO
DESCRIPTION
PUBLIC WORKS - ENGINEERING
WATER MAIN REPLACEMENT
ALLEY EAST OF WEHE AVE
49510S
FET TA
INOGTNOWASHR RETGIESDE
IGE
EE
NO
RLNAP FORSSEIN1011SITE PHOTOGRAPHS SEE PLAN/PROFILESEE PLAN/PROFILEBID1970310-12-2020DV/MAJPMS/KM
RKnow what'sbelow.before you dig.CallSHEETDRAWN BY:DESIGN BY:CHECKED BY:HOR SCALE:VER SCALE:PROJECT NO:CAD DWG:DATE:REV BY APR.DATE
(509) 545-3444
REVISION
CITY OF PASCO
DESCRIPTION
PUBLIC WORKS - ENGINEERING
WATER MAIN REPLACEMENT
ALLEY EAST OF WEHE AVE
49510S
FE
T TA
INOGTNOWASHR RETGIESDE
IGE
EE
NO
RLNAP FORSSEINSITE PHOTOGRAPHS 1111SEE PLAN/PROFILESEE PLAN/PROFILEBID1970310-12-2020DV/MAJPMS/KM