Change Order
Project:
20-71 COP Fire Station 83
7510 Sandifur Parkway
Pasco, WA 99301
Chervenell Construction Company
7511 W Arrowhead Ave, Suite 8
Kennewick, WA 99336
Ph : 509-735-3377
To Contractor:
Chervenell Construction Company
7511 W Arrowhead Ave, Suite B
Kennewick, WA 99336
The Contract Is changed as follows:
CR -002 PR -01
CR -003 PR -02 -Door Changes
Change Order: 1
Date: 5/13/2020
Architects Project: 20-71
$-3,402.81
$5,033.93
Total: $1,631.12
The original Contract Amount was
$4,349,184.00
Net change by previously authorized Change Orders
$0.00
The Contract Amount prior to this Change Order was
$4,349,184.00
The Contract will be increased by this Change Order in the amount of
$1,631.12
The new Contract Amount including this Change Order will be
$4,350,815.12
The date of Substantial Completion as of the date of this Change Order therefore is
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACT AND OWNER.
TCAArchdecture Planning Chervenell Construction Company
City of Pasco
ARCHITECT CONTRACTOR
OWNER
6211 Roosevelt Way NE 7511 W Arrowhead Ave, Suite B
525 N Third Ave
Seattleā WA 98115 Kennewick, WA 99336
Pasco, WA 99301
(SionArure) (Signature) M gnature)
Sarah Elley Brandon GadishBy
5/28/2020 By 06/09/2020 By 6 -to - zo
Date Date Date