HomeMy WebLinkAboutJackson Contractor Group, Inc. - Fire Station 84 Construction Contract (CP5FR231984--�JDAIA Document A101 - 2017 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the nineteenth day of June in the year Two Thousand and Twenty (In words, indicate day, month and year.) ADDITIONS AND DELETIONS: The author of this document has BETWEEN the Owner: added Information needed for its (Name, legal status, address and other information) completion. The author may also have revised the text of the original City of Pasco AIA standard form. An Additions and 525 North 31d Ave Deletions Report that notes added Pasco, WA 99301 information as well as revisions to the standard form text is available from the author and should be reviewed. A and the Contractor: vertical line in the left margin of this (Name, legal status, address and other information) document indicates where the author has added necessary Information and where the author has added to or Jackson Contractor Group, Inc. deleted from the original AIA text, 1220 W Poplar St. Walla Walla, WA 99362 This document has Important legal consequences. Consultation with an for the following Project: attorney is encouraged with respect (Name, location and detailed description) to Its completion or modification. The parties should complete Headquarters Fire Station 84 Al010--2017, Exhibit A, Insurance 4920 W Court Street and Bonds, contemporaneously with Pasco, WA 99301 this Agreement. AIA Document A2010--2007, General Conditions of The Architect: the Contract for Construction, is (Name, legal status, address and other information) adopted In this document by reference. Do not use with other TGA Architecture Planning Inc. general conditions unless this 6211 Roosevelt Way NE document Is modified, Seattle, WA 98115 The Owner and Contractor agree as follows. Init. AIA Document A101®- 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects," "AIA,' the AIA Logo, "A101," and "AIA Contract Documents* are registered trademarks and may not be used without permission. This document was produced by AIA software at 16:12:58 ET on 0 611 8/2 02 0 under ®Mer t No.6895345522 which expires on 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documentse Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (1968256337) TABLE OF ARTICLES 1 THE CONTRACT DOCUMENTS 2 THE WORK OF THIS CONTRACT 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION 4 CONTRACT SUM PAYMENTS DISPUTE RESOLUTION TERMINATION OR SUSPENSION MISCELLANEOUS PROVISIONS ENUMERATION OF CONTRACT DOCUMENTS EXHIBIT A INSURANCE AND BONDS ARTICLE 1 THE CONTRACT DOCUMENTS The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary, and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9. (Paragraphs deleted) ARTICLE 2 THE WORK OF THIS ENTIRE CONTRACT The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others. ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be as follows: (Paragraph deleted) The date of commencement will be fixed in a notice to proceed issued by the Owner. (Paragraphs deleted) § 3.2 The Contract Time shall be measured from the date of commencement. § 3.3 Substantial Completion § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work: (Check one of the following boxes and complete the necessary information.) [ X ] Substantial Completion shall be not later than four hundred and twenty-six (426) calendar days from the date of commencement of the work. Final completion shall be not later than forty-five (45) calendar days from the date of substantial completion. [ ] By the following date: (Table deleted) (Paragraph deleted) Init. AIA Document A1016- 2o17. Copyright 0 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects,' "AIA," the AIA Logo, "A101," and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document was produced by AIA software at 15:12:58 ET on 06/1812020 under Order I No,6895345522 which expires on 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documentse Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (1968256337) § 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5. ARTICLE 4 CONTRACT SUM § 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the Contract. The Contract Sum includes the Base Bid, Alternate 1, and Alternate 2. The Contract Sum shall be six million, nine hundred and nineteen thousand, eight hundred dollars ($ 6,919,800.00 ), subject to additions and deductions as provided in the Contract Documents. § 4.2 Alternates § 4.2.1 Alternates, if any, included in the Contract Sum: Item Price Alternate 1: Additional Bay at Storage $179,700.00 Building Alternate 2: Utility Extensions Along $104,500.00 Future Marie Street § 4.2.2 Subject to the conditions noted below, the following alternates may be accepted by the Owner following execution of this Agreement. Upon acceptance, the Owner shall issue a Modification to this Agreement. (Insert below each alternate and the conditions that must be met for the Owner to accept the alternate) Item Price Conditions for Acceptance NONE § 4.3 Allowances, if any, included in the Contract Sum: (Identify each allowance) Item Price Allowance No. 1: Exterior Signage $1,500.00 Allowance No. 2 Interior Signage $3,500.00 § 4.4 Unit prices, if any: (Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable) Item Unit Price 1: Units and Limitations Price per Unit ($0.00) Unsuitable Soils $_42—/bank cubic yard § 4.5 Liquidated damages, if any: (Insert terms and conditions for liquidated damages, if any.) Liquidated damages shall be in the amount of $2,500.00 per calendar day beyond the allowed contract time that substantial completion is not attained. § 4.6 Other: (Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum) (Paragraphs deleted) ARTICLE 6 DISPUTE RESOLUTION § 6.1 Initial Decision Maker The Architect will serve as the Initial Decision Maker pursuant to Article 15 of AIA Document A201-2007, unless the parties appoint below another individual, not a party to this Agreement, to serve as the Initial Decision Maker, Init. AIA Document A101®- 2017. Copyright 0 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects," "AIA," the AIA Logo, "A101," and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document was produced by AIA software at 15:12:58 ET on 06/1812020 under Order I No.6895345522 which expires an 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used In accordance with the AIA Contract Doeumentse Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (1988258397) (If the parties mutually agree, insert the name, address and other contact information of the Initial Decision rltaker, if other than the Architect.) § 6.2 Binding Dispute Resolution For any Claim subject to, but not resolved by, mediation pursuant to Article 15 of AIA Document A201-2007, the method of binding dispute resolution shall be as follows: (Check the appropriate box.) [ X ] Arbitration pursuant to Section 15.4 of AIA Document A201-2007 [ J Litigation in a court of competent jurisdiction [ ] Other (Spec) If the Owner and Contractor do not select a method of binding dispute resolution, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be resolved by litigation in a court of competent jurisdiction. (Paragraphs deleted) § 8.2 The Owner's representative: (Name, address, email address, and other information) Owner's Contact: Fire Chief Bob Gear Address: 1011 E Aidsworth St Pasco, WA 99301 Owner's Representative: Strategic Construction Management, Inc. 5426 N. Rd. 68, Suite D Box #246 Pasco, WA 99301. Contact: David L. Robison Phone: 509-378-5044 § 8.3 The Contractor's representative: (Name, address, email address, and other information) Matt Brossman Jackson Contractor Group, Inc. P.O. Box 2029 Walla Walla, WA 99362 § 8.4 Neither the Owner's nor the Contractor's representative shall be changed without ten days' prior notice to the other party. (Paragraphs deleted) § 8.7 Other provisions: None AIA Document A101®- 2017. Copyright O 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The Init. American Institute of Architects. All rights reserved. The "American Institute of Architects," "AIA," the AIA Logo, "A101," and "AIA Contract Documents" are 4 registered trademarks and may not be used without permission. This document was produced by AIA software at 15:12:58 ET on 06/18/2020 under Order I No.6895345522 which expires on 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents" Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (1968256337) ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS § 9.1 This Agreement is comprised of the following documents: .1 AIA Document AJO1TM-2017, Standard Form of Agreement Between Owner and Contractor ,2 AIA Document A201 Tm-2007, General Conditions of the Contract for Construction (Paragraph deleted) .3 The other Conditions of the Contract are those contained in the latest version of the Project Manual for Headquarter Fire Station 84 all documents reference therein together with all Addenda issued prior to the Bid Date. .5 Drawings (Row deleted) Title of Drawings Exhibit: Drawings as issued for Bid or modified by subsequent addenda. Refer to the sheet index on Drawing T1.1 issued forbid. .6 Specifications Specifications The Specifications are those contained in the Project Manual as described in Section 9.1.3 and below: Title of Specifications Exhibit: Specification Divisions 01 through 33 as included in the Project Manual issued for Bid or as modified by subsequent addenda. Refer to the Table of Contents found in the Project Manual issued for Bid. .7 Addenda, if any: Number Date Pages Addendum 1 05/18/2020 92 Addendum 2 05/22/2020 2 Addendum 3 05/29/2020 57 Addendum 4 06/03/2020 34 Addendum 5 05/05/2020 42 Portions of Addenda relating to bidding or proposal requirements are not part of the Contract Documents unless the bidding or proposal requirements are also enumerated in this Article 9. .8 Other Exhibits: (Check all boxes that apply and include appropriate information identifying the exhibit where required.) (Table deleted) (Paragraphs deleted) (Paragraphs deleted).9 Other documents, if any, listed below: (List here any additional documents that are intended to form part of the Contract Documents, AIA Document A201 Tm-2007 provides that the advertisement or invitation to bid, Instructions to Bidders, sample forms, the Contractor's bid or proposal, portions of Addenda relating to bidding or proposal requirements, and other information furnished by the Owner in anticipation of receiving bids or proposals, are not part of the Contract Documents unless enumerated in this Agreement. Any such documents should be listed here only if intended to be part of the Contract Documents) This Agreement entered into as of the day and year first written above. Init AIA Document A1010- 2017. Copyright@ 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects," "AIA," the AIA Logo, "A101," and "AIA Contract Documents" are 5 registered trademarks and may not be used without permission. This document was produced by AIA software at 15:12:58 ET on 06/18/2020 under Order No.8895345522 which expires on 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (1988258337) e*--- _,,e //,/ OWNER (Signature) (Printed name and title) CONTRACTOR (Signature) (Printed name and title) Inst. AIA Document A1010- 2017. Copyright 01915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects," "AIA," the AIA Logo, "A101," and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document was produced by AIA software at 15:12:58 ET on 06/1 812 02 0 under Order No.6895345522 which expires on 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Doeumentse Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (1968288337) - Document A101 2017 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the nineteenth day of June in the year Two Thousand and Twenty (In words, indicate day, month and year.) ADDITIONS AND DELETIONS: The author of this document has BETWEEN the Owner: added information needed for Its (Name, legal status, address and other information) completion. The author may also have revised the text of the original City of Pasco AIA standard form. An Additions and 525 North 3rd Ave Deletions Report that notes added Pasco, WA 99301 information as well as revisions to the standard form text Is available from the author and should be reviewed, A and the Contractor: vertical line in the left margin of this (Name, legal status, address and other information) document indicates where the author has added necessary Information Jackson Contractor Group, Inc. and where the author has added to or deleted from the original AIA text. 1220 W Poplar St, Walla Walla, WA 99362 This document has important legal consequences. Consultation with an for the following Project: attorney is encouraged with respect (Name, location and detailed description) to its completion or modification. The parties should complete Headquarters Fire Station 84 Al 01&-2017, Exhibit A, Insurance 4920 W Court Street and Bonds, contemporaneously with Pasco, WA 99301 this Agreement. AIA Document A20104007, General Conditions of The Architect: the Contract for Construction, Is (Name, legal status, address and other information) adopted In this document by reference. Do not use with other TCA Architecture Planning Inc. general conditions unless this 6211 Roosevelt Way NE document Is modified. Seattle, WA 98115 The Owner and Contractor agree as follows. Init. AIA Document A101®- 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects," "AIA," the AIA Logo, "A101," and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document was produced by AIA software at 15:12:58 ET on 06/18/2020 under Order l No.6895345522 which expires on 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used In accordance with the AIA Contract Documentse Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (1988256337) TABLE OF ARTICLES 1 THE CONTRACT DOCUMENTS 2 THE WORK OF THIS CONTRACT 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION 4 CONTRACT SUM 5 PAYMENTS 6 DISPUTE RESOLUTION 7 TERMINATION OR SUSPENSION 8 MISCELLANEOUS PROVISIONS 9 ENUMERATION OF CONTRACT DOCUMENTS EXHIBIT A INSURANCE AND BONDS ARTICLE 1 THE CONTRACT DOCUMENTS The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary, and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9, (Paragraphs deleted) ARTICLE 2 THE WORK OF THIS ENTIRE CONTRACT The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others. ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be as follows: (Paragraph deleted) The date of commencement will be fixed in a notice to proceed issued by the Owner. (Paragraphs deleted) § 3.2 The Contract Time shall be measured from the date of commencement. § 3.3 Substantial Completion § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work: (Check one of the following boxes and complete the necessary information.) [ X ] Substantial Completion shall be not later than four hundred and twenty-six (426) calendar days from the date of commencement of the work. Final completion shall be not later than forty-five (45) calendar days from the date of substantial completion. By the following date: (Table deleted) (Paragraph deleted) Init. AIA Document A10118- 2017. Copyright 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects," "AIA," the AIA Logo, "A101," and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document was produced by AIA software at 15:12:58 ET on 08/18/2020 under Order t No.8895345522 which expires on 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents" Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (1968258337) § 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5. ARTICLE 4 CONTRACT SUM § 4,1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the Contract. The Contract Sum includes the Base Bid, Alternate 1, and Alternate 2. The Contract Sum shall be six million, nine hundred and nineteen thousand, eight hundred dollars ($ 6,919,800.00 ), subject to additions and deductions as provided in the Contract Documents. § 4,2 Alternates § 4.2.1 Alternates, if any, included in the Contract Sum: Item Price Alternate 1: Additional Bay at Storage $179,700.00 Building Alternate 2: Utility Extensions Along $104,500.00 Future Marie Street § 4.2.2 Subject to the conditions noted below, the following alternates may be accepted by the Owner following execution of this Agreement. Upon acceptance, the Owner shall issue a Modification to this Agreement. (Insert below each alternate and the conditions that must be met for the Owner to accept the alternate.) Item Price Conditions for Acceptance NONE § 4.3 Allowances, if any, included in the Contract Sum: (Ident fy each allowance.) Item Price Allowance No. 1: Exterior Signage $1,500.00 Allowance No. 2 Interior Signage $3,500.00 § 4.4 Unit prices, if any: (Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.) Item Unit Price 1: Units and Limitations Price per Unit ($0.00) Unsuitable Soils $-42—/bank cubic yard § 4.5 Liquidated damages, if any: (Insert terms and conditions for liquidated damages, if any.) Liquidated damages shall be in the amount of $2,500.00 per calendar day beyond the allowed contract time that substantial completion is not attained. § 4.6 Other: (Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum.) (Paragraphs deleted) ARTICLE 6 DISPUTE RESOLUTION § 6.1 Initial Decision Maker The Architect will serve as the Initial Decision Maker pursuant to Article 15 of AIA Document A201-2007, unless the parties appoint below another individual, not a party to this Agreement, to serve as the Initial Decision Maker. Init. AIA Document A11018- 2017. Copyright® 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects," "AIA," the AIA Logo, "A101," and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document was produced by AIA software at 15:12:58 ET on 06/18/2020 under Order I No,6895345522 which expires on 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Doeumentse Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (1968258337) (If the parties mutually agree, insert the name, address and other contact information of the Initial Decision /Maker, if other than the Architect.) § 6.2 Binding Dispute Resolution For any Claim subject to, but not resolved by, mediation pursuant to Article 15 of AIA Document A201--2007, the method of binding dispute resolution shall be as follows: (Check the appropriate box.) X ] Arbitration pursuant to Section 15.4 of AIA Document A201.-2007 [ ] Litigation in a court of competent jurisdiction [ ] Other (Specify) If the Owner and Contractor do not select a method of binding dispute resolution, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be resolved by litigation in a court of competent jurisdiction. (Paragraphs deleted) § 8.2 The Owner's representative: (Name, address, email address, and other information) Owner's Contact: Fire Chief Bob Gear Address: 1011 E Aidsworth St Pasco, WA 99301 Owner's Representative: Strategic Construction Management, Inc. 5426 N. Rd. 68, Suite D Box #246 Pasco, WA 99301 Contact: David L. Robison Phone: 509-378-5044 § 8.3 The Contractor's representative: (Name, address, email address, and other information) Matt Brossman Jackson Contractor Group, Inc. P,O. Box 2029 Walla Walla, WA 99362 § 8.4 Neither the Owner's nor the Contractor's representative shall be changed without ten days' prior notice to the other party. (Paragraphs deleted) § 8.7 Other provisions: None AIA Document A101®- 2017. Copyright(D 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1897, 2007.and 2017 by The Init. American Institute of Architects. All rights reserved. The "American Institute of Architects," "AIA," the AIA Logo, "A101," and "AIA Contract Documents" are 4 registered trademarks and may not be used without permission. This document was produced by AIA software at 15:12:58 ET on 06/18/2020 under Order I No,6895345522 which expires on 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used In accordance with the AIA Contract DoeumentsO Terms of Service. To report copyright violations, e-mail copyright@aia.org. Ussr Notes: (1968256337) ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS § 9.1 This Agreement is comprised of the following documents: .1 ALA Document Al01TM-2017, Standard Form of Agreement Between Owner and Contractor .2 AIA Document A201Tm-2007, General Conditions of the Contract for Construction (Paragraph deleted) .3 The other Conditions of the Contract are those contained in the latest version of the Project Manual for Headquarter Fire Station 84 all documents reference therein together with all Addenda issued prior to the Bid Date. .5 Drawings (Row deleted) Title of Drawings Exhibit: Drawings as issued for Bid or modified by subsequent addenda. Refer to the sheet index on Drawing T1.1 issued forbid. .6 Specifications Specifications The Specifications are those contained in the Project Manual as described in Section 9.1.3 and below: Title of Specifications Exhibit: Specification Divisions 01 through 33 as included in the Project Manual issued for Bid or as modified by subsequent addenda. Refer to the Table of Contents found in the Project Manual issued for Bid. .7 Addenda, if any: Number Date Pages Addendum 1 05/18/2020 92 Addendum 2 05/22/2020 2 Addendum 3 05/29/2020 57 Addendum 4 06/03/2020 34 Addendum 5 05/05/2020 42 Portions of Addenda relating to bidding or proposal requirements are not part of the Contract Documents unless the bidding or proposal requirements are also enumerated in this Article 9. .8 Other Exhibits: (Check all boxes that apply and include appropriate information identifying the exhibit where required.) (Table deleted) (Paragraphs deleted) (Paragraphs deleted).9 Other documents, if any, listed below: (List here any additional documents that are intended to form part of the Contract Documents. AIA ,Document A201 T" X2007 provides that the advertisement or invitation to bid, Instructions to Bidders, sample forms, the Contractor's bid or proposal, portions ofAddenda relating to bidding or proposal requirements, and other information furnished by the Owner in anticipation of receiving bids or proposals, are not part of the Contract Documents unless enumerated in this Agreement, Any such documents should be listed here only if intended to be part of the Contract Documents.) This Agreement entered into as of the day and year first written above. Init. AIA Document A1019- 2017. Copyright ® 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects," "AIA," the AIA Logo, "A101," and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document was produced by AIA software at 15:12:58 ET on 06/18/2020 under Order t No.8895345522 which expires on 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract DocumentsO Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (1968258337) OWNEW(Signatzz ) lx�t�bc1� (Printed name and title) CONTRACTOR (Signature) /497I (Printed name and title) 11111. AIA Document A101®- 2017. Copyright ©1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. The "American Institute of Architects,' AIA," the AIA Logo, "A101," and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document was produced by AIA software at 15:12:68 ET on 08/1812020 under Order I No.6895345522 which expires on 10/03/2020, is not for resale, is licensed for one-time use only, and may only be used in accordance with the ALA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (1 9682 56 337)