HomeMy WebLinkAboutTCA Architecture Planning, Inc - Fire Station 81, Fire Station 82 Training Rehab Center - Amendment No. 2 (CP5FR9A2081, CP5FR232000, CP5FR9A2082)AMENDMENT NUMBER "2" to
PROFESSIONAL SERVICES AGREEMENT
Station 81 (Oregon Avenue), Station 82 (Airport) and Training Center Restroom Schematic
Design through Contract Closeout Project
PROJECTS: CP5FR232000, CP5FR9A2081 and CP5FR9A2082
WHEREAS, the City and TCA Architecture Planning, Inc. (TCA) entered into a
Professional Services Agreement on 9/4/2019 to provide architecture and engineering services
with respect to the Station 81, Station 82 and Training Center Restroom projects.
NOW, THEREFORE, this agreement is amended to allow TCA to provide additional
engineering services for sewer line extension at the Training Center as described on Exhibit A.
I . Scope of Work:
See Exhibit A
2. Fee:
The compensation for the work is based on a Time and Materials Basis not to exceed
the amount of $3,560 for a total authorization amount of $304,702.
3. Time of performance:
The services shall be complete for the project on or before 9/4/2021.
DATED THIS ' DAY OF � Y(,� `2020.
CITY OF PASCO:
/;JaK��
i P o
Dave Zabell, City Manager
Amendment No. 2 to Professional Services Agreement
TCA Architecture Planning
Training Center Restroom
CONSULTANT"
TCA Architecture Planning, Inc.
Brian Harris, Principal
Page 1
DAC/'f% 12akn , Ckakar - Can Wnrkchaat (RPV. 41 Exhibit A February 25, 2020
REHAB SHELTER
_-..--- --_-_____. I --- - _ _ ---
MTGS HRS TCA FEE -
TASK 1- As
Builds FIXED
Coordinate Existing Conditions
6
35
Develop New CAD Backgrounds (site plan &floor plan)
Confirm Existing Condition on Site3
P
^�T
U pdate Drawin s Per Site Visit
4
SUB TOTAL
0 48
AS -BUILD TOTAL $6A80
MTGS HRS TCA FEE
-- ----- -
TASK 2 -:Schematic Desi
n FIXED
Initial Site Visit (already occurred) 1 2
1- Design Meetings (Part of all projects combined on same visit)
Develop Project Schedule 2
Develop Schematic Design Drawings 40
Coordinate Septic System 6
Coordinate Site Reports
Develop Project Cost Estimate 6
General Consultant Coordination 2
SUB TOTAL 21 67
SCHEMATIC DESIGN TOTAL
$9,045
�MTGS
HRS
TCA FEE
TASK 3 - Design
Development FIXED
1 -Meetings (Part of all projects combined)
1 4
60
U date Project Schedule
Develop Desi n Development Drawings
_
Project Cost Estimate +Total Budget
10
'Develop
Develo Outline Specifications
10
General Consultant Coordination
4
SUB TOTAL
1 90
__.
DESIGN DEVELOPMENT TOTAL
$12,150
MTGS
HRS
TCA FEE
TASK 4 - Construction Documents FIXED
1 -Meeting (Part of all projects combined) 14
Update Project Schedule _
2
DevelopPermit Drawings
70
Finalize Project Specifications
30
Respond to City Comments
B
Develo Bid Documents
35
General Co ulting Coordination
6
SUBTOTAL 1
155
CONSTRUCTION DOCUMENTS TOTAL
20925
TPOW
DESIGN DOCUMENTS TOTAL - TCA
$48,600
Page 1 of 3
CACIV% Onkmk Cheltor - rap Wnrkchaat (RPV. 41
February 25, 2020
Page 2 of 3
MTGS
and Ne otiation
1 -Bid Coordination Meeting -Teleconference 1
HRS TCA FEE
HOURLY T&M
1.5
Prepare Documents for Bidding
Assist Owner with Bid Advertisement
4
2
�sr
Issue Addenda as Needed
Assist Owner in Evaluation of Bids
_ 2 -
Assist Owner with Owner/Contractor Agreement
4
SUB TOTAL1
TASK 6 - Construction Administration & Closeout
Participate in Pre -Construction Meeting 1
19.5
HOURLY
8
32
16
20,
B
8
$2,633
T&M
Attend on Progress Meetings 4
Respond to Contractors Questions During Const. (RFI's)
Review Submittals, and Shop Drawings
Process Supplementary Instructions, Proposal Requests, -�
Change Orders, Change Directives
Coordinate Consultants to Address Questions During Const.
Review and Process Monthly Certificates for Payment
8
TASK 7 - Project
SUB TOTAL 51
Closeo '
Provide Punch Lists 1
104
12
$14,040
T&M
Issue a Certificates of Substantial Completion
4
Provide Final Inspections
1
12
Coordinate Final Punch Lists
4
_.
Assist Owner in Closing Out the Contract
4
SUB TOTAL 2
36
$4,860
-
CONSTRUCTION ALLOWANCE BUDGET TOTAL - T
BILLED TIME AND MATERIALS AGAINST ALLOWANCE
$21 533
CONSULTANTS
STRUCTURAL ENGINEERING
_
$5,900
(CONSTRUCTION ADMIN. BILLED AT HOURLY RATES) TCA Mark-Up
10%
$590
..,.._,._�.-...
..._,_.._.-..
MECHANCIAL ENGINEER
10%
$ 9,000
TCA Mark -U
$900
ELECTRICAL ENGINEER _ ._.�., -.
$3,800
TCA Mark-Up
10%
10%
$380
CIVIL ENGINEER (INCLUDES SEPTIC) _
$8,800
(CONSTRUCTION ADMIN. BILLED AGAINST $2,500 NTE TCA Mark -U 3
$880
FOR ALL THREE PROJECTS)
COST ESTIMATOR
$4,000
TCA Mark -U 10%
PROJECT TOTAL - CONSULTANTS
$400
$34,650
Page 2 of 3
PASO Rehab Shelter - Fee Worksheet (Rev. 4)
February 25, 2020
Page 3 of 3
MECHANCIAL ENGINEER _
TCA Mark -U 3 10%
0
ADDED MECHANICAL SCOPE OF WORK
1. MECHANICAL ENGINEER WILL PERFORM MECHANCIAL AND PLUMBING COST
ESTIMATES AT A SAVINGS IN LIEU OF COST ESTIMATOR. COST ESTIMATOR BUDGET
HAS BEEN
REDUCED FOR ALL THREE PROJECTS.
REIMBURSABLES - ALLOWANCE $9,000
-
TRAVEL -ALLOWANCE 6,000
COMBINED PROJECT TOTAL $114,663
Sewer extension to Ainsworth OTAL ADD FEE ADD
A.
ADMENQN
Scope of Work Description:
New gravity sewer main from north property line.
CIVIL ENGINEER Additional Service
$2,500
TCA Mark-Up
1096 250
Total Sewer Line Extension $2,750
Civil Total - Add 2 $2,750
TCA__ �__ .._._... �......
Additional drawing, meeting, HRS TCA FEE
(coordination and management. 1 6 $810
COMBINED PROJECT TOTAL - ADD 1&2 $120,441