Loading...
HomeMy WebLinkAboutPACE Engineers, Inc - PWRF Water Treatment Facility Plan Amendment 6 (Agreement No. 16016)AMENDMENT NUMBER 6 to PROFESSIONAL SERVICES AGREEMENT 16016 — PROCESS WATER TREATMENT FACILITY PLAN PROJECT PROJECT: MN9-ED-ST-18-01 WHEREAS, the City and PACE Engineers entered into a Professional Services Agreement on 9/7/2017 to provide engineering services with respect to the Process Water Treatment Facility Plan project. NOW, THEREFORE, this agreement is amended to allow PACE Engineers to provide additional engineering services as described on Exhibit A. 1. Scope of Work: For Full Scope of Work please see Exhibit A. In summary this amendment is to provide: - Respond to 2nd iteration of Ecology Review of Facility Plan - Additional Construction Engineering Services Not Anticipated - Additional Services for Attending Coordination Meetings - Additional Design Engineering and Revising IPS Construction Drawings 2. Fee: The compensation for the work is based on a Time and Materials Basis not to exceed the amount of $66,149.51 for a total contract amount of $1,239,702.36. See Exhibit B for the breakdown of hours. 3. Time of performance: No Change. The services within this amendment shall be complete for the project on or before 7/30/2020. DATED THIS 1 I DAY OF CITY OF PASCO: City of Pasco Dave Zabell, City Manager IIVI*.Z , 2020. Amendment No. 6 to Professional Services Agreement PACE Engineers Inc 16016 — Process Water Facility Plan Project CONSULTANT ACE Engineers, Inc. Robin Nelson, PE Page 1 PACE An Engineering Servioes Company City of Pasco, WA Amendment No. 6 Capital Facilities Plan and Engineering Report Project # MN9-ED-ST-18-01 Contract #18021 EXHIBIT A Engineers � Planners I Surveyors BACKGROUND: The City of Pasco authorized PACE to proceed with a professional services agreement, on September 7, 2017, to prepare a Capital Facilities Plan and Engineering Report. This work also included preparing bid documents for the Irrigation Pump Station. During the execution of the scope of services additional tasks and costs were encountered that exceeded our original level of effort estimates, please see below. • Initially, supplement #1 was approved extending the completion date of our agreement to July 31, 2019. This was a no cost supplement. • Supplement #2 was authorized to evaluate an alternate underground piping alignment to supply effluent from the 115 MG pond to the Irrigation Pump Station. This supplement was in the amount of $47,380.00. • Supplement #3 was authorized to captured out of scope services incurred in the design phase for the IPS Pump Station Improvements. • Supplement #4 extends the contract completion date to July 31, 2020. Supplement #5 included bid assistance and limited construction engineering support for the Irrigation Pump Station Replacement project. • Supplement #6 will capture out of scope services incurred to respond to a second iteration of Ecology review comments for the final Capital Facilities Plan/Engineering Report and an accelerated timeline to complete this work. This work included responding to additional Ecology review comments of the final Land Treatment System plan (Chapter 1 of the capital facilities plan), responding and reprinting the Hydrogeologic Study (Chapter 2 of the report in its entirety and submitting as a stand-alone report as requested by Ecology), and responding to additional Ecology review comments within Chapters 3 - 14 the remaining body of the report. • Supplement #6 will capture additional construction engineering services not anticipated in previous supplements. At request of the City this work included redesign 12- inch Forcemain from 8 MG Equalization Basin to new IPS and issue revised plans, redesign 30 — inch gravity piping from 115 MG Pond to new IPS and issue revised plans, and responding to Franklin County Building permit comments for energy code compliance and seeking variance from section C402.1.2 of the WEC code. • Supplement #6 will also capture additional services for attending coordination meetings not anticipated in our original scope of work at the request of City staff. These included monthly phone conference calls for PWRF coordination from October 2019 through February 2020. Also attending a coordination meeting at City Hall with City staff to discuss processor permit limits held on February 26, 2020. • Supplement #6 will also include additional design engineering and revising IPS PACE Engineers, Inc. 11255 Kirkland Way I Suite 300 Kirkland, Washington 98033-3417 p 425.827.2014 1 f 425.827.5043 www.vaceenars.com �� PACE M Engineering Services Company Engineers I Planners I Surveyors construction drawings to include extending the new 24 inch Forcemain from the proposed point of connection with the existing 18 inch process water supply and additional 200 feet extending the new 24 inch C900 PVC piping beyond the PWRF site fencing. JUSTIFICATION: PACE budgeted to respond to just one iteration of Ecology review comments for the Capital Facilities Plan/Engineering Report, see task 2.6 below. Task 2.6 — Response to Ecology Comments Work with the City to develop a response strategy to Ecology comments on the Capital Facilities Plan/Engineering Report and prepare responses to Ecology review comments on behalf of the City. This scope of work and budget only includes one iteration of responding to Ecology review comments for each submittal at the preliminary draft, hydrogeologic study, and final document. Further iterations of comments will be billed at a time and materials basis and covered under Task 7 budget. ORIGINAL SCOPE OF WORK: Preliminary Draft Reviews (Capital Facilities Plan, Land Treatment System Plan, and Hydrogeologic Study) PACE prepared and submitted individual technical memorandums representing each chapter of the proposed preliminary draft Capital Facilities Plan/Engineering Report to the City for review and comment. Upon completion of all technical memorandums, PACE assembled all technical memorandums into a final Capital Facilities Plan/Engineering Report. This document was made available to stakeholders for review and comment. Ecology was in attendance at this meeting however declined to comment on the report until it was formally submitted by the City. On August 6, 2018, stakeholders issue their responses to the final report which PACE, on behalf of the City, completed a review and responded to all comments along with associated edits to the final plan. Final Draft 1St Review (Capital Facilities Plan, Land Treatment System Plan, and Hydrogeologic Study) On October 3, 2018 the final plan was submitted to Ecology for review and approval. On March 13, 2019, Ecology issued their review comments to the City. The review comments included revisions to the Hydrogeologic Study, and remainder of the Capital Facilities Plan/Engineering report. PACE was instructed by the City to respond to these comments and resubmit the final document. On July 5, 2019, PACE submitted the final plan for approval incorporating all of Ecology's comments. SUPPLEMENT #6 — ADDITIONAL SCOPE OF WORK: Final Draft 2nd Review (Capital Facilities Plan, Land Treatment System, and Hydrogeologic Study) However, on November 12, 2019 the City received additional review comments from Ecology requesting an expedited response on or before November 29, 2019 of the Hydrogeologic Study, and remainder of the Capital Facilities Plan/Engineering Report. This short duration for preparing responses and editing this second submittal of the final document was to secure eligibility for a ECY planning loan to fund the design recommendations of the Capital Facilities Plan/Engineering report. In an email dated November 12, 2019, PACE notified the City that responding to these additional comments were not included in our original scope of work and requested an amendment for these 2 Engineers I Planners I Surveyors PACE An Engineering Services Company additional services. Further, we would reprioritize our schedules in an attempt to meet the Ecology imposed deadline. Per our original agreement, responding to this second iteration of comments would be billed at a time and materials basis. PACE proceeded as instructed to respond and revise the report. During this timeframe, (November 12, 2019 to November 29, 2019), the City received additional review comments from Ecology Hydrogeologist, Lyn Doremus, to the Hydrogeologic Study (Chapter 2 of the final document). On or about November 23, 2019, the City received the additional comments from Ecology's Hydrogeologist to include in the Capital Facilities Plan/Engineering Report but with one additional request to provide a stand alone Hydrogeologic Report separate from what was included in the Capital Facilities Plan. All this additional work associated with the second Ecology submittal was completed and the amended final document submitted to Ecology for approval. Please note, the City received approval of the final plan from Ecology on December 16, 2019 in time to secure the ECY $1.5M funding request. LEVEL OF EFFORT ESTIMATE AMENDMENT #6 The following summarizes the additional effort and cost to address the second iteration of Ecology comments discussed above. TASK #1 -ADDRESS 2ND ROUND OF ECOLOGY COMMENTS Capital Facilities Plan (CES $16,800) Chapter 1 - Prepare responses to Ecology comments on the Capital Facility Plan, Land Treatment System Assessment (Section 1) provided to CES, November 12, 2019, and provide the responses to PACE. Make update modifications to Section 1 based on our response to Ecology comments and provide the updated Section 1 to PACE in electronic form. The following limitations contained in the original scope of work were exceeded: • Updating Section 1 required significant rework of nutrient and water balances and related calculations, with large amounts of time conducting research to address Ecology's comments. Significant effort was required and CES discussed the nature and effort required with PACE to gain additional budget authorization. • Formal, extended meetings, via phone or in person, or additional follow-up responses were required. • The prepared responses and updated Section 1 were submitted electronically. Hydrogeologic Study (Jacobs $11,249.76) Chapter 2 — Responding to Ecology review comments for hydrogeologic study from both Diana Washington and Lyn Doremus. Comments were issued independently. This work included coordinating with Ecology reviewers, additional research and revisions to Chapter 2 delivered on December 9, 2019 and revisions to Chapter 2 and preparing independent Hydrogeologic study delivered on December 30, 2019. Capital Facilities Plan ($17,069.00) Chapter 3 through 14 - Additional services were provided to address 2nd round of Ecology review comments for the Capital Facilities Plan. Ecology issued 55 comments in their 2nd review. This work included preparing review response matrix, subconsultant coordination and oversight, preparing 3 Engineers I Planners I Surveyors PACE An Engineering Services Company detailed responses to Ecology reviewer comments, coordination with Ecology reviewer and City staff, updating final plan, submitting to City and Ecology. Deliverables: PACE provided the following deliverables: s Electronic Copy revised final draft of Capital Facilities Plan/Engineering Report Volumes 1 & 2. o Revised Land Treatment System Plan (Chapter 1) o Revised Hydrogeologic Study (Chapter 2) o Revised Capital Facilities Plan/Engineering Report (Chapters 3 —14) ® Electronic Copy of Reviewer Response Matrix TASK #2 - ADDITIONAL CONSTRUCTION SERVICES (PACE $12,490.75) 1. At request of the City redesign 12- inch Forcemain from 8 MG Equalization Basin to new IPS and issue revised plans. 2. At request of City redesign 30 — inch gravity piping from 115 MG Pond to new IPS and issue revised plans. 3. Address Franklin County Energy code review comments and applying for variance for building occupancy. Variance was granted on nearly all of Section C402.1.2 of the WEC code, thus, classifying the IPS building as an equipment building, and removing thermal envelope provisions. Variance was granted for: ® Maximum size (in sqft) to qualify as an equipment building ® Maximum installed equipment power consumption, per sqft - ® - Maximum heating system capacities TASK #3 - ADDITIONAL COORDINATION MEETINGS (PACE $4,042.50) PACE conducted monthly phone conference calls for PWRF coordination meetings from October 2019 through February 2020. This work includes preparing meeting agenda and facilitating the hour long meeting with City staff. PACE was requested to attend a City coordination meeting to discuss strategy to address the processors on pretreatment limits and discharge permit renewals. This meeting was held at City Hall on February 26, 2020. This cost includes travel time to and from the meeting at City Hall. TASK #4 - 24 INCH FORCEMAIN EXTENSION (PACE $4,497.50) Includes additional design engineering with modification to existing sheet C-9 and preparing a new plan and profile sheet C -9A extending the new 24 inch Forcemain from the current point of connection shown on sheet C-9. This work includes approximately 200 feet of 24 inch C900 piping and detailing for the connection to existing piping. Final stamped construction. drawings will be issued to the City including a revised sheet C-9 and new sheet C -9A. We do not anticipate additional survey needed to complete this work. However, the existing TIN for the surface model in CAD Civil 3D will need to be modified to include the additional alignment. As - built data will be revisited to document existing underground utilities. Base mapping will be prepared with the additional topographic data. A new base map will be created and serve as our basis for design. 4 PACE An Engineering Servlcas Company Budget Original Budget = $977,632.00 Amendment #1 = $0.00 Amendment #2 = $47,380.00 Amendment #3 = $61,432.65 Amendment #4 = $0.00 Amendment #5 = $87,108.20 Amendment #6 = $66,149.51 Revised Budget = $1,239,702.36 End Supplement #6 5 Engineers I Planners I Surveyors .i o - m M 0 d N N Cl! t17 m Obi O M N CD D) ai n d Ill 0 0. O O O r 00 _ N :. .. c0 c0 c0 Q. 0�OV ffl 6M9 6N9 �• ... C a0t6 C O M I ............. .::: ::.:. F Ku c�U .:.•:.•:•:.•::•:'.•.•:: N O m WCD o m ::. •::.M .•.. V N....................................................................... ........... -moo L Oma. d _ ... U E 10 Y d ............................................................................................................................ ........... d m Y ..... ..................................................................... ..... d O Q O................................................................................................................... m ofoi ' co•. o a o i v rn N.0 �, O O r. 1 C i N oD � � A R O F y O U) Q cc 3 U L•i:•:•: y m .......................................................................................................................m m ...... C co w N w O d N M O x 7 co c Lo o G n c V c J 55 = Z; rn N U 'n V M W U Cl) C 7 [6 W 7 .... J ..........:................... ...... ....... ......... ..... ..... ..... ...... ..... ..... ....... ..... ............ ..... ..... ...... ...........ct N -� N m O �n ami N rT O y M •:':N 'c CO CL 69 •E f1 :. C— aO Q p-p� v O• N N N O 7 N O m O) f.t3 c N : U C C W m:........ ........... ...... ....... ...... ...... ..... ..... ..... ..... ..... ....... .......... ....... ..... ..... ...... . ........ c U ti d r W M c"i e" ca d 419. ccc a .................................:......................... .... .................. . ... U) c LLO rn N co c .O E9 o O j 69 cd CO :. _........................................................................................... ........... G @ M LO N c0 ` N rn CV ai coN 3 to m Nil N ....... d E 44: t0 y cc V C O Y Z y y o F `p rn 76 i •0 N O .� W d N Uj co cL u' y o O o c6 N ca a U U E m ci cc m' 0 O 4: co co u- 22 o fy J fy- •:'. Z c C..) 0 L N d N N '" .1+ NCD N i6 C i N LL m19 o> E2N ca O C d `�y 0- cn U) 0 •:: Q F U F F F x J K tl . a f1 ' F