HomeMy WebLinkAboutC&E Trenching, LLC - Foster Wells Force Main - Change Orders 5 & 6 (CP7-SR-1A-19-00)Project No:
CP7-SR-1 A-19-00
CIN OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 5
Contractor: C&E Trenching, LLC
Project Title: Foster Wells Forcemain Improvements
Description of Change: RFC 06 - Extend HDPE DR 11 Pipe
Detail as Appropriate: RDC 06: Cost to extend 16" & 8" with DHPE R 11 pipe to reach the new
tie-in point per RFI 17.
Contract Bid Amount: $ 4,390,989.00
SALES TAX @ 8.6%: $ 377,625.05
Total: $ 4,768,614.05
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 94,911.92
Subtotal $ 14,123.94
Sales tax @ 8.6% $ 8,162.43
Sales tax @ 8.6% $ 1,214.66
Total $ 103,074.35
Total $ 15,338.60
Total Change Orders To Date $ 118,412.95
New Contract Amount $ 4,887,027.00
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
YES NO
128
2
130
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED: APPROVED:
Com= 12-31-19
CONTRACTOR Date P OJECT MANAGER Date
APPROVED:
t ✓. Z -/07
,MANAGER Dade
APPROVED:
Date Date
WREfrT6R
C&E Trenching LLC
PO Box 3788
Pasco, WA 99302
Phone: (509) 545-6940
Fax: (509) 545-8671
�iJ ziIJ:JZ Jr:1law
r
To: City of Pasco
PO Box 293
Pasco, WA 99301
Project: Foster Wells Forcemain Improv.
RFC No: 06
Date: 10/17/2019
Description: Cost to extend 16" & 8" with HDPE DR I 1 pipe to reach the new tie in
point per RFI 17.
SS pipe alone no welding, excavation, labor or equipment is $22,227.00
Plan to extend into ground off of manifold, 90 then flange SS, connect
HDPE via flange, extend to new location, flange back to SS via flange, SS
90 and flange to connect to valve. (S S 90 's is already fabbed) Update plan
may be to go HDPE all the way to the valve as we are short one SS
Flange.
Labor $ 3,619.85 Equipment 2,577.52 Material $5,743.68 Mark up
$2,577.52
Credit portion of RFI 17 coming seperate once we get paper work on the
credit from supplier. Need to get material ordered asap for this extension.
Please add 2 days to the contract for this change.
The above work is subject to the same conditions as specified in the original contract
unless otherwise stipulated.
Upon approval the sum of $14,123.94will be added to the contract price.
Original Contract $4,390,989.00
Other Approved Change Orders $80,404.67
Total Contract to Date $4,471,393.67
This Request $14,123.94
Other Pending Requests $0.00
Total Contract plus Pending RFCs $4,485,517.61
Project No
CP7-SR-1 A-19-00
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.6
Project Title: Foster Wells Forcemain Improvements
Contractor: C&E Trenching, LLC
Description of Change: RFC 09 - Heat Tape
Detail as Appropriate: RFC 09 - Add heat tape to Pump Station end above ground pipe &
PWRF 30" above ground pipe.
Contract Bid Amount: $ 4,390,989.00
SALES TAX @ 8.6%: $ 377,625.05
Total: $ 4,768,614.05
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 109,035.86
Subtotal $ 9,898.98
Sales tax @ 8.6% $ 9,377.08
Sales tax @ 8.6% $ 851.31
Total $ 118,412.94
Total $ 10,750.29
Total Change Orders To Date $ 129,163.23
New Contract Amount
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
$ 4,897,777.28
YES NO
130
0
130
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
(� (t) 12/31/19
CONTRACTOR 41 Date
APPROVED:
CONST. MANAGER
Date
APPROVED:
PROJECT MANAGER Date
Date
M4 -0U AAqEJ2—
C&E Trenching LLC
PO Box 3788
Pasco, WA 99302
Phone: (509) 545-6940
Fax: (509) 545-8671
J �� 4� i �-� �• r T r
r 1J
To: City of Pasco
PO Box 293
Pasco, WA 99301
Project: Foster Wells Forcemain Improv.
RFC No: 09
Date: 12/12/2019
Description: Cost to add heat tape to Foster Wells pump station end above ground pipe,
and PWRF 30" above ground pipe. See LBS quote for details.
Option cost of $1,400.00(with markup) to add Thermostats
Sub cost $8,425.20 Markup $1,473.78
The above work is subject to the same conditions as specified in the original contract
unless otherwise stipulated.
Upon approval the sum of $9,898.98will be added to the contract price.
Original Contract $4,390,989.00
Other Approved Change Orders $109,035.86
Total Contract to Date $4,500,024.86
This Request $9,898.98
Other Pending Requests $0.00
Total Contract plus Pending RFCs $4,509,923.84
Authorized Signature:
Authorized Signature:
C&E Trenching LLC
City of Pasco
Date:
Date: