HomeMy WebLinkAboutGoodman & Mehlenbacher - Shuman Waterline Extension Change Order #1 (CP7WT9A1801)CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 1
Project No: CP7-WT-9A-18-01 Project Title: Schuman Waterline Extension
Contractor: Goodman & Mehlenbacher Ent., Inc.
Description of Change: New 4' chainlink fence
Detail as Appropriate: Install 4' school rated chainlink fence
Contract Bid Amount:
SALES TAX @ 8.6%:
Total:
$ 61,438.00
$ 5,283.67
$ 66,721.67
PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER
Subtotal Subtotal $ 25,187.84
Sales tax @ 8 .6% $ -Sales tax @ 8.6% $ 2,166.15
Total $ -Total $ 27,353.99
Total Change Orders To Date $ 27,353.99
New Contract Amount $ 94,075.66
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract T ime Prior to this Change Order ............................... .. 20
Modification to Contract time by this Change Order .................. ..
revised Total Contract Time .................................................. .. 20
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of t he previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED: APPROVED :
co~
10/30/2019
Date
// ,.,,,,i/41~ 10/B/t t:t
~JECT MANAGER Date '
APPROVED :
NO.
1
2
3
4
CO_l (New 4' Chain link fence)
Mr. Kent Mccue
Date: 08/26/2019
DESCRIPTION
Mobilization
Labor
Equipment
Subcontractor
GAm
QTY
1
1
1
1
Sub Total $25,187.84
Tax $2,166.15
Total $27,353.99
Summary Of Work
Excavate and haul off trench material for mow strip, set posts, pouring 12" x 6" mow strip, install 4' tall school rated
chain link fence (Black).
WA#GOODMME006BJ I OR_CC B#l 49 669 I LEVEL U FSCC
#BID NUMBER P.O. BOX S94 9 KENNEW ICK, WA 99337 I ph.(509)582-5570 fx.(509)582-5770 8/26/2019@4:02 PM
Memo
To: Dan Ford , P.E., City Engineer
From:
Date:
Re:
Kent McCue, Construction Manager /~
September 10, 2019
Change Order for Schuman Lane Waterline
Public Works Department
Engineering Division
The change order is necessary to replace the old, existing 3 wire fence along Chiawana
Park that had to be removed to install the new waterline at the request of the Parks
Department.