HomeMy WebLinkAboutCentral Washington Asphalt - 20th Avenue Overlays Change Order #2 CP5-ST-3R-19-01CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 2
Project No: CP5-ST-3R-19-0· Project Title: 20th Ave Overlay (Court St to 1-182)
Contractor: Central Washington Asphalt
Description of Change: Concrete ADA Ramps ------~--------------------
De ta i I as Appropriate: Removal of additional curb, gutter & sidewalk to fit new ADA appurtenances.
Contract Bid Amount: $ 386,587.65
SALES TAX@8.6%: N/A
Total: $ 386,587.65
PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER
Subtotal $ 3 ,589.60 Subtotal $ 13,485.36
Sales tax @ 8 .6 % N/A Sales tax @ 8 .6 % N/A
Total $ 3,589.60 Total $ 13,485.36
Total Change Orders To Date $ 17,074.96
New Contract Amount $ 403,662.61
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ................................ . 50
Modification to Contract time by this Change Order .................. ..
revised Total Contract Time ................................................... . 50
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are)
being made and that the compensation for this Change Order is full and complete and is the only
compensation due or owing for this Change Order. Further, it is mutually agreed that this document will
supplement the present Contract Documents and that the provisions of the previously executed Contract
Documents shall apply to this Change Order.
ACCEPTED: APPROVED:
It> /tJj I '7
Oate Ji'fltlr:f:!J~e /0 / 8 Jr Of
SUBCONTRACTOR
RAY POLAND Qu anhty Unit Unit Price T otal
Concrete Removal 9 Each $ 166.00 $ 1,494.00
Ramp Prep 9 Each $ 141 .00 $ 1,269.00
4 .5' Concrete Sidewalk 62 LF $ 40.00 $ 2,480.00
Concrete Curb & Gutter 62 LF $ 50.00 $ 3 ,100.00
Concrete Pedestrian Curb 62 LF $ 35.00 $ 2,170.00
Concrete Valley Gutter 23 .5 LF $ 65.00 $ 1,527 .50
Subtotal $ -$ 12,040 .50
12% M .U. $ -$ 1,444.86
Subcontractor Total With Markup $ 13,485.36
Memo Pa5co
Public Works Department
Engineering Division
To:
From:
Date:
Re:
Dan Ford, P .E., City Engineer
Kent Mccue, Construction Manager ~
October 3, 2019
Change Orders for 20th Avenue Overlay 2 -lD::J!.2..
The change order is necessary to remove additional curb/gutter and sidewalk that was not
taken into consideration to fit the new ADA appurtenances into the existing corners during
the design phase.
• Page 1