HomeMy WebLinkAboutClearwater Construction & Management - Columbia East FM Change Order No. 3 CP9-SR-2A-17-01CITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 3 Project No: CP9-SR-2A-17-01 Project Title: 17003 Columbia East Pump Station Contractor: Clearwater Construction & Management Description of Change: CO Request #1 -Conduit & Pad for future odor option Detalt as Appropriate: Wet well ventilation system wl ll include power and concrete pad for future odor unit. -------------------·-- Contract Bid Amount: SALES TAX@ 8.6%: Total : $ 2 ,458,335.00 $ 211,416.81 $ 2,669,761.81 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal $ 23,956.90 Subtotal $ 5 ,196.18 Sales ta:<@ 8.6 % $ 2 060.29 Sales tax @ 8 .6% $ 446.87 Total $ 26,017.19 Total $ 5,643.05 - Total Change Orders To Date $ 31,860.24 New Contract Amount $ 2,701,412.05 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES --·--1 NO 1 Contract Time Prior to this Change Order .............................. .. 180 Modification to Contract time by this Change Order ................... . 0 revised Total Contract Time .................................................. .. 180 It is mutually agreed by both pa rti es that this Change Order fully describes the change{s) that Is (are) being made and that the compensation for this Change Order is full and complete and Is the only compensation due or owing for this Change Order. Further, It is mutually agreed that this document wi ll supplement the present Contract Documents and that the provisions of the previously exe cuted Contra ct Documents shall apply to this Change Order. APPROVED: ~t(M✓• 1/(/1 1 ECTMANAGER Dal.e APPROVED: ,.. 4'ti.L!Ltt [1'/r.Cw CONST.MANAGER ( Clearwater Construction & Management, LLC Project: 17003 East Columbia Pump Station Chanae Order Reauest #: 01 Revision 1 Date: 4/10/2019 Description of Change: Wet well ventilation system will include power and concrete pad for futu re odor unit. (excludes any odor unit) Reason For Change: Air exchanqe and air pressure in wet well. Change Directed By: PACE Enginering Delay's Caused By Change TBD Labor to place new concrete pad under odor unit, trenching for Labor: electrical, layout and piping $ 1,065.60 $ - TOTAL LABOR $ 1,065.60 1 O" PVC piping per detail 11 on PM-7 (revised to candy cane design), (no insulation included) removed flanges per Material: discussion 4/5 $ 1,300.00 Concrete Pad (Concrete, forming mat, base) $ 350.00 $ - TOTAL MATERIAL $ 1,650.00 Equipment: $ - $ - TOTAL EQUIPMENT $ - Subcontracts: Power city Electric $ 1,589.33 $ - $ - Other Costs: TOTAL SUBCONTRACTS $ 1,589.33 Total Costs: $ 4,304.93 Labor O&P 29% $ 309.02 Material O&P 21% $ 346.50 Equipment O&P 21% $ - Subcontractor O&P 10% $ 158.93 Total Markup $ 814.46 Total With Markup $ 5,119.39 Tax at 7.90% To be added to In voice Insurance and Bond at 1.50% $ 76.79 $ 76.79 Total Amount This Change Order Request: $ 5,196.18 Additional Workinq Days Required: TBD Notes: Revised per discussion at meeting 4/5/19 Siqned : Clearwater Construction Date: Signed: Owners Representative Date: