HomeMy WebLinkAboutCapital Improvement Plan 2020-2025PASCO
WASHINGTON
2020-2025 ADOPTED
CAPITAL IMPROVEMENT PLAN
2020 – 2025 Capital Improvement Plan
Approved September 16, 2019
Resolution No. 3914
2020 – 2025 Capital Improvement Plan – Page ii
Pasco City Council
Matt Watkins, Mayor
Craig Maloney, Mayor Pro Tem
Blanche Barajas, District 1
Ruben Alvarado, District 2
Saul Martinez, District 3
Pete Serrano, District 4
David Milne, District 5
Executive Leadership
Dave Zabell, City Manager
Bob Gear, Fire Chief
Larry Dickerson, Interim Police Chief
Steve Worley, Public Works Director
Richa Sigdel, Finance Director
Zach Ratkai, Administrative & Community Services Director
Rick White, Community & Economic Development Director
Special Thanks to:
Angela Pashon, Policy Analyst
Charlene Sandland, Staff Accountant
Dan Ford, City Engineer
Darcy Buckley, Lead Accountant
DeShawn Robins, GIS Administrator
Griselda Garcia, Lead Accountant
Maria Serra, Senior Civil Engineer
Precilla Andaya, Administrative Assistant
City of Pasco
2020 – 2025 Capital Improvement Plan
Table of Contents
READER’S GUIDE ............................................................................................................................................................... v
CIP MESSAGE .................................................................................................................................................................... ix
SUMMARY ....................................................................................................................................................................... xv
Introduction ......................................................................................................................................................................... xv
Project Consideration Factors ............................................................................................................................................ xv
Capital Cost of Adopted Projects by Project Category ..................................................................................................xvi
Capital Cost of Adopted Projects by Revenue Source (Non-Utility) .......................................................................... xviii
Capital Cost of Adopted Projects by Revenue Source (Utility) ..................................................................................... xx
Funding ............................................................................................................................................................................... xxiii
PROJECT SHEETS ………………..…………………………………………………………………………………………… 1
Fire……………………………………………………………………………………………………………………. 1
General………………………………………………………………………………………………………………. 9
Park and Recreation………………………………………………………………………………………………. 15
Transportation.…...………………………………………………………………………………………………. 33
Utilities………..…...………………………………………………………………………………………………. 65
Irrigation...………………………………………………………………………………………………. 65
Process Water Reuse Facility..…………………………………………………………………………. 71
Sewer…....………………………………………………………………………………………………. 75
Stormwater..……………………………………………………………………………………………. 91
Water…...……………………………………………………………………………………………….97
GLOSSARY…………………………………………………………………………………………………………………117
COMPLETED PROJECTS
2020 – 2025 Capital Improvement Plan – Page iv
This page left intentionally blank
READER’S GUIDE
The CIP book is divided into three main sections:
CIP Message – Message from the City Manager regarding the adopted Capital Improvement Plan
(CIP).
Summary – Summary and analysis of projects presented in the adopted CIP.
Project Sheets – Details on each project, organized by groups and funding status.
The CIP is organized into nine major programs:
General – Includes general government facility construction and renovation, acquisition
of land for future use, and technology system acquisition and replacement.
Fire – Includes all Fire Department related projects. This is a temporary category created
due to a larger than usual number of capital projects in this category.
Parks – Includes renovation, replacement and construction of park and recreational
facilities and acquisition of parks and open space lands.
Transportation – Includes maintenance, construction and improvements to streets,
intersections, and pedestrian safety.
Utilities:
Irrigation – Includes maintenance, improvements, and construction of the City’s
irrigation conveyance systems.
Process Water Reuse Facility – Includes maintenance, improvements, and
construction of the City’s treatment and conveyance system for industrial
wastewater.
Sewer - Includes maintenance, improvements, and construction of the City’s sewer
treatment and conveyance systems.
Stormwater - Includes improvements to the City’s storm drain systems.
Water – Includes maintenance, construction and improvements to the City’s water
treatment and conveyance systems.
There are various parts to the project sheet:
Project Details – Adopted projects are evaluated by Staff on various criteria. Capital
projects recommended for inclusion in the CIP were rated based on criterias and are
2020 – 2025 Capital Improvement Plan – Page vi
represented in this section. Fields such as Assessment, Principal Need, and Justification show
the priority and impact of each project to the City.
Status – Indicates if the project is new or ongoing.
Project Number – This project number is used for internal tracking purposes.
Department – The Department responsible for the project.
Group – This indicates the type of project, regardless of department. For example,
transportation, water, sewer etc.
Assessment:
Urgent – The project is needed to combat an identified issue posing a threat to City
assets or core services.
Necessary – The project is needed to maintain core services at their current level or
combat an issue that may present a future or growing threat.
Desirable – The project would improve the current quality of services or quality of
life.
Principle Need:
Council Goal – The project will achieve goals set by the City Council.
Asset Protection – The project is designed to maintain and/or protect City property.
Reduce Future Costs – The project is designed to eliminate projected future costs
incurred by the City.
Service Protection – The project is designed to maintain core services.
Quality Improvement – The project is designed to enhance the quality of life for
residents.
Funding Status – This indicates the availability of funding for the project. If the project is
fully funded, all funding sources listed in the Revenue Sources section are secured and
available for drawdown. If the funding status is listed as partially or not funded, it simply
means that there are no current funding resources available, but that City will be seeking
funding opportunities to advance the project. A project listed in the CIP provides potential
funders with greater assurance that their potential investment received adequate review
and planning.
Justification – This provides the
justification on how this project
furthers priorities and goals adopted
by the Council – a further effort to
align the City Council’s goals to
existing plans, policies, and budget.
Summary Project Description – The description of project will give the reader an
understanding of the scope and impact of the project. This section is not be read as a full
scope description, but rather a summarized version that gives the reader high level
information.
Project Cost – The project costs are the best estimates available as of the preparation of
this plan and, as a result, can change as market conditions and project scope evolve. This
section is further broken down into the different components of the cost, such as, design,
land acquisition, construction, etc.
Funding Sources – The funding sources are the best estimates of sources currently available
or possible in the future.
2020 – 2025 Capital Improvement Plan – Page viii
This page left intentionally blank
CIP MESSAGE
Honorable Mayor and City Council, Pasco residents, business owners/operators, and interested
parties:
On behalf of staff, I am pleased to present to you the adopted City of Pasco Capital Improvement
Program 2020-2025 (CIP). The adopted CIP presents the plan for how major public facility
improvements will be financed, coordinated and timed over the next six years.
As policy makers and professionals, Council and staff have a responsibility to plan. Projects in this
document propose to strategically invest in the future of our community’s infrastructure in a
manner that promotes adopted City Council’s goals and lays the foundation for the development
and sustainability of the City for the next 20 years. The City, through the CIP, provides for fiscal
sustainability and economic vitality of our community through thoughtful, well-prioritized and
leveraged investment – using long-term planning to shape near-term decisions.
A capital project is defined as the construction, acquisition or renovation of buildings,
infrastructure, land, and major equipment with a value greater than $50,000. The project cost is
the best estimate available as of the date of the CIP plan preparation and can change as market
conditions and project scope evolve.
While the biennial budget and a capital improvement plan are intertwined, the six-year CIP is
subject to considerable change and should not be considered as an allocation or appropriation of
funding. This document provides project overviews, priority assessment, principle need,
justification, expense summaries, and projected revenue sources.
The adopted CIP represents nearly
$250 million in public infrastructure
investment, an increase of 22% over
the prior year. Most of the increase
is attributable to the progress made
in completion of facility and
comprehensive system plans, and
completion of project design across
many City’s departments. The
increases are across the board, with
the only
2020 – 2025 Capital Improvement Plan – Page x
reduction being in transportation category reflecting the eminent completion of two major
transportation projects, Chapel Hill Boulevard and Oregon Avenue. Construction of the
Lewis Street Overpass, Peanuts Park/Farmer Market, along with planned and needed
improvements at the Water Treatment Plant, Process Water Reuse Facility, and
Wastewater Treatment Plant, are the major drivers of the increase in the CIP.
BACKGROUND AND SUMMARY
There are many sources that fund CIP Projects including: grants, loans, utility charges,
bonded indebtedness, and taxes. These funding sources contribute to the acquisition of
land or buildings, design, construction, and management of projects.
The major categories of projects include:
o General: Public safety and city buildings.
o Parks & Recreation: New parks, trails, dock, and sporting facilities.
o Transportation: Road widening and development, replacements and traffic signal
improvements.
o Utilities: Sewer, stormwater, water, and wastewater expansions and improvements.
The six-year CIP includes projects that replace or maintain existing assets, provide capacity
needed to meet growth projections and required level of service, as well as projects that
enhance capacity or services to the public. Many of these projects are identified in the adopted
City Council Goals, Facility Plans, Master Plans, or other Strategic Plans.
FUNDING STRATEGY
The 2020-2025 CIP document is organized by the major categories mentioned above, and
further categorized to funded, partially funded, and unfunded sections. The term “unfunded”
or “not funded” does not mean that the project will never be funded or that they are not
important, it simply means that there are no current funding resources available. However,
because these projects are important, the City will be seeking funding opportunities to advance
these projects. A project listed in the CIP provides potential funders with greater assurance
that their investment received thoughtful review and planning.
Projects within Utilities like Water, Sewer or PWRF, include a significant number of unfunded
projects that will ultimately be funded by revenue bonds. The City is always looking for grants
and low interest loans to reduce the impact of such projects to ratepayers.
While the recommendations within the CIP take into consideration current rates and
assumptions about the need for future adjustments, because the document is a planning level
tool subject to multiple dynamics, many not entirely within the City’s control, a complete rate
sensitivity analysis is not included as part of the CIP. This work is more typically accomplished
in concert with the biennial budget.
UPDATE PROCESS
The adopted CIP is an update of the previously adopted 2019-2024 CIP. In updating the CIP, the
following factors were taken into account:
•Completed projects are removed from the update.
•Progress on those projects that received (budgeted) funding is reflected.
•Projects slated to receive funding in the next budget are modified.
•Projects identified through Council Goals or action are added.
•Projects identified through the comprehensive system planning process as needed for
system integrity or level of service needs within the six-year horizon are added.
•Project need, along with resources, financial and human, are evaluated and projects
prioritized.
•Projects are reviewed to coordinate for economy of scale, synergy and impact where
possible.
A project sheet is developed for each project, designed to provide the reader with a significant
amount of information at a glance, including if the project is “new” or “ongoing”. The adopted
2020-2025 CIP incorporates several “new” projects, particularly in the utility portions, as the
result of completed long-range planning efforts. These projects have evolved from “plug”
numbers and generic descriptions of anticipated improvements in earlier CIPs to specific well-
defined projects and planning level cost estimates. A more detailed description of the project
sheet is provided in the READER’S GUIDE of this document.
A note on projects identified within the comprehensive planning documents: while the CIP is
consistent with the recently adopted comprehensive system and facility plans, not every project
in a system plan will or should be reflected in the CIP. This is for a few reasons:
1.The CIP is a six-year plan, a comprehensive system looks at a twenty-year or longer
horizon. Many of the projects identified in a system plan will ultimately be included in
future CIPs. However, depending on many variables, it may take years for a project
identified in the system plan to be included into the CIP, or the project may be
accomplished differently than a City implemented capital project.
2.In the realm of utilities, the oversizing (water, sewer, and irrigation) portion of the CIP is
intended to address many of the large main projects identified in a system plan in
undeveloped areas that will eventually be built as the result of market-driven development.
While a specific pipeline may not be included in the CIP, the oversizing provision in the
CIP and biennial budget assures proper line sizing as systems expand.
3.Other opportunities for solving an issue might arise as problems are studied. Replacement
of an aging facility may be identified in a system plan, then later analysis provides a way
of bypassing the facility all together. Projects within the CIP are vetted to a much higher
degree, in terms of implementation, than in a system plan.
2020 – 2025 Capital Improvement Plan – Page xii
The process of evaluating each project, its relationship to other CIP projects, and issues in
the field, along with a comprehensive funding assessment for the project and the CIP
itself takes several months of staff time and expertise, as well as consultation with
engineering, planning and financial consultants.
COMPLETED PROJECTS
The reader will note several projects missing or significant changes in status in the current
document from the 2019-2024 CIP. The CIP is used as a tool to meet long-range Council
goals and address systems needs for expansion or to address deficiencies. The list below
includes projects completed, partially completed, or significant progress prior to 2020:
o Purchase of Land for Station 85
o Design for Station 83 and 84
o Design of Lewis Street Overpass
o Oregon Avenue Phase I Improvements
o Chapel Hill Boulevard
o Columbia Raw Water Intake – APWA-WA Project of the Year Award
o Butterfield Water Treatment Plant PLC and Controls Update
o Schuman Lane Waterline
o Chapel Hill Boulevard Irrigation Main – Road 84 to Road 68
o Chapel Hill Boulevard Water Main Upsize – Road 84 to Road 68
o Sycamore, Hugo & Waldemar Grind & Overlay
o Wastewater Treatment Plant PLC and Controls Update
o Harris Road Sewer Trunk Line
o Foster Wells Force Main
o 20th Avenue Overlay – Court Street to I-182
o Design of Irrigation Pump Station (IPS) at PWRF
o GESA Stadium – Lights and Seats
The business of implementing capital projects comes with multiple variables and dynamics
that can speed or impede progress. Considerable progress was made on numerous projects
between the time the draft CIP was prepared and the final CIP adopted by the City Council,
and far more progress still will occur prior to the 2021-2026 update. The better the quality
of planning and decision making on infrastructure investment, the more successful the
community will be overall on multiple levels.
CONCLUSION
As adopted, the 2020-2025 CIP supports City Council goals, is consistent with the City’s
long-range planning efforts, promotes our local economy, provides a roadmap, and
enables the City to meet requirements to qualify for participation of most grant and loan
programs. This plan is focused on advancing City Council Goals in addressing the current and
future needs of our growing community.
Much of the work contemplated in the CIP will not be seen by the users of the various
infrastructure systems: water, sewer, transportation, etc. However, the CIP and its
implementation facilitates the lives of our residents and the vitality of our businesses by helping
to create an environment where they have more time to focus on what is important to them.
The preparation of this document represents an extensive and thoughtful effort on the part of
dozens of dedicated City employees from every department in the organization. On behalf of the
City staff involved, it was our pleasure to assist the City Council in preparing this comprehensive
public infrastructure plan and to implement the projects therein to the benefit of the residents and
businesses that make up Pasco.
Sincerely,
Dave Zabell
City Manager
2020 – 2025 Capital Improvement Plan – Page xiv
This page left intentionally blank
SUMMARY
Introduction
The 2020-2025 Capital Improvement Plan (CIP) is a multi-year plan of capital projects with
estimated costs and proposed methods of financing. The Plan is reviewed on an annual basis and
updated to reflect the availability of resources, progress on execution of projects, changes in
policy, changes in cost or financial resources, and refinement of the projects.
Capital facilities are necessary to support the basic services that the City provides to support the
community as it currently exists, and as it is expected to develop over the next twenty years. The
state Growth Management Act (GMA) establishes many of the requirements for the Capital
Improvement Plan elements. RCW 36.70A.020 states that Capital Improvement Plans are to
“ensure that those public facilities and services necessary to support development shall be
adequate to serve the development at the time the development is available for occupancy and
use without decreasing current service levels below locally established minimum standards.”
The City’s Capital Improvement Plan consists of a list of capital projects, together with cost
estimates and proposed sources of funding for approved projects. However, Council
appropriates funding through the biennial Capital Projects Budget process. The City’s Biennial
Budget process requires Council’s approval to spend amounts listed in this CIP, add new projects,
or to increase the total approved cost of an existing project. Capital projects of a like nature,
which occur each year and are listed together in the CIP, may be included as separate projects in
the Capital Projects Budget, based on such factors as work location and construction start dates.
Capital Project Budgets may include related project work, which may not meet the accounting
definition of “capital,” but are directly related to the project. The Capital Projects Budget are
included as a section in the City’s “Biennial Operations & Capital Improvement Budget”
document. Any changes represented in the CIP for 2019 and 2020 have either already been
presented to the Council during the course of the year, or will be included in the Biennium
adjustment process.
Repair and maintenance work, and equipment purchases, though often significant in dollar
amount, will be included as part of the biennial Operating Budget.
The CIP and the Operating Budget are intertwined and changes to one document may result in
changes to the other. This is particularly true as projections for revenue, such as sales tax, REET
and one-time monies are identified throughout both processes. Neither document has yet been
finalized. There are some CIP projects in these lists that are also being considered as part of the
operating budget service package list, and there may be service package proposals that are more
appropriate to be considered as capital projects. The preliminary CIP reflects the best information
we have as of August, but some of the CIP lists may change over the coming months in response
to Council direction, budget decisions, or new information. Any changes will be clearly
highlighted when the Final CIP is brought to the Council for approval in December.
Project Consideration Factors
Many factors are considered when planning for capital projects. As mentioned before, the GMA
requires cities to have capital facilities in place and readily available when new development
occurs or a service area population grows. The Office of Financial Management estimates the
2020 – 2025 Capital Improvement Plan – Page xvi
addition of 51,000 new Pasco residents by the year 2038. Existing aging infrastructure that has
reached or is nearing the end of useful life need upgrades or replacement. In addition, the City
has seen rapid and steady population growth and expansion over the past quarter century. These
three factors are the major drivers of what is adopted in this plan.
The City Council’s adopted goals provide the strategic vision for the City. Staff places high
importance on projects proposed which align with Council’s goals. Factors, such as asset
protection, reducing future costs, service protection, and quality improvement are strongly
considered and noted on project sheets. Urgency of the need is also considered in appropriately
scheduling projects.
An additional factor to consider is that some granting agencies require local governments to have
an adopted Capital Improvement Plan in order to be eligible for grants and loans. Such projects,
if aligned with GMA requirements, Council Goals, or Master Plans will be included in this plan to
satisfy said requirement.
Capital Cost of Adopted Projects by Project Category
The chart (Exhibit 1) which follows shows the relative size of CIP over the past four years. The
adopted 2020-2025 CIP totals $249,612 thousand. Total cost of projects included in the CIP
amounts to 279,837 thousand, as they include past and current year planned expenditures. The
steady increase in the CIP plan is attributed to maintenance and enhancement needs of the
Wastewater Treatment Facility, Process Water Reuse Facility, Water Treatment Facility, as well as
the construction of the Lewis Street Overpass, Fire Stations, Community Center, and Peanuts Park.
Exhibit 1
Exhibit 2 below represents the projects by group over the past four years, whereas Exhibit 3
represents the capital costs by group for the adopted 2020-2025 CIP.
Group 2020-2025 2019-2024 2018-2023 2017-2022
Fire 25,947 19,405 9,575 9,735
General 11,695 12,727 7,843 10,669
Irrigation 1,980 1,963 1,351 3,285
Parks & Recreation 27,948 21,885 14,263 18,349
Process Water Reuse Facility 36,053 19,950 8,590 11,321
Sewer 56,766 38,177 34,645 39,477
Stormwater 1,029 1,889 1,409 1,799
Transportation 48,283 62,151 69,282 70,653
Water 39,911 26,500 28,737 28,695
Total 249,612 204,647 175,696 193,983
Exhibit 2
2020 – 2025 Capital Improvement Plan – Page xviii
Exhibit 3
Capital Cost of Adopted Projects by Revenue Source (Non-Utility)
Parks, Transportation, and General Capital Facilities projects are funded with internal fund
reserves sourced from general tax revenues, grants, cost sharing with neighboring municipalities,
local improvement districts (LIDs), impact fees, and the real estate excise tax (REET).
Capital project cost for non-utility projects for the City’s 2020-2025 capital improvement
planning period is $113,873 thousand. Exhibits 4 and 5 illustrate the capital costs by major revenue
sources and category. Significant projects adopted in this plan period are the relocation of Fire
Stations 83 and 84, the Lewis Street Overpass, Community Center, Animal Shelter, and Peanuts
Park.
Funding Category Funding Source Amount
Current and Future Debt 31,145
Future LTGO Bond 2,600
LTGO Bond 16,745
Section 108 Loan 3,800
Unsecured Revenue Bond 8,000
Grants 34,308
CDBG Grant 1,286
Connecting WA Grant 12,825
Federal STP Grant 3,403
RCO Grant 1,406
State Grant 10,576
TIB Grant 4,750
Capital Budget 62
Internal Fund Reserve 25,170
Arterial Fund 4,603
Capital Improvement Fund 5,822
General Fund 2,206
I-182 Corridor Traffic Impact Fund 1,248
Overlay Fund 7,331
Park Development Fund 3,109
Utility Rate 851
Unsecured Funding 15,842
Local Partnerships 7,408
City of Kennewick Contribution 1,600
City of Richland Contribution 1,600
Developer Contribution 3,300
Port of Pasco 425
Local Improvement District 483
Total Non-Utility Fund Source 113,873
Exhibit 4
2020 – 2025 Capital Improvement Plan – Page xx
Exhibit 5
As Council is aware, funding options for partially funded or completely unfunded projects such
as the Lewis Street Overpass are being explored. As is practice, Staff will keep exploring new
funding options for unsecured projects. For example, while in the 2019-2024 CIP Relocation of
Fire Stations 83 and 84 and Peanuts Park Restoration were adopted with significant unsecured
funding, this adopted CIP has identified specific and fully secured funding sources for these three
projects.
Capital Cost of Adopted Projects by Revenue Source (Utility)
Drinking water, wastewater, irrigation, stormwater, and PWRF services make up the City’s Utility
Fund. The fund is operated like a business and must be self-supporting. Utility projects are
historically funded through the combination of rates, expansion fees, grants, loans, and revenue
bonds.
In the past, State programs such as Public Works Trust Fund (PWTF) Loans were readily available
to assist cities with low interest loans. In recent times, the program has not been a reliable source
of funding for local projects, though the legislature is restoring funds to some programs.
Capital cost adopted for projects for the City’s 2020-2025 capital improvement planning period
is $135,739 thousand. Exhibits 6 and 7 illustrate the capital costs by major revenue categories
for the period 2020-2025.
The Wastewater Treatment Plant (WWTP) completed its facility planning process to meet
National Pollution Discharge Elimination Permit System (NPDES) requirements and address
future capacity and water quality needs. The Facility Plan has identified projects that are expected
to be a significant investment for the City (Phase 1 - $25.8M, Phase 2 - $15.4M).
The Process Water Reuse Facility (PWRF) was a unique public-private partnership for a City
when it was built more than twenty years ago. Such collaboration is becoming more common
as companies and cities look for ways to treat their industrial wastewater most efficiently.
As this concept is expanding, the demand for our facility is expanding as well. Furthermore, age,
size, and technology are driving upgrades needed to meet the significant current and future
demands. In 2017, Council authorized the City to hire PACE Engineers to conduct a
comprehensive facilities and engineering plan with a vision of renewing the facility, providing
for expansion of current system users, and attracting other agricultural processors to the area.
This effort is now complete, and it has provided staff with projects needed to maintain, upgrade,
and expand the facility. Capital cost for PWRF utility projects for the City’s 2020-2025 capital
improvement planning period are estimated to be in the order of $22,644 thousand. City staff
are currently in negotiations with various processors to find a path forward for funding these
improvements. All funding for PWRF projects has to be acquired through grant or participating
processors, unless projects contribute to further economic development of the City.
Exhibits 6 and 7 illustrate the capital costs by major funding categories for utility services. A large
part of unsecured funding is attributed to the expansion of capacity and refurbishment of aging
facilities. Public Works staff have been diligently working with State and Federal agencies to
receive grants or low interest loans to reduce the impact of these large investments to the rate
payers. Cities fund such large infrastructure projects through a combination of low interest loans,
grants, and revenue bonds. The funds are represented as unsecured until Council authorizes such
actions, and the bonds or loans are secured. The City is also looking to local partnership through
a Local Improvement District bond where the project provide specific benefit to the adjacent
properties. Action on formation of a LID requires Council approval, as well than more than 60%
votes from the benefitting property owners.
2020 – 2025 Capital Improvement Plan – Page xxii
Funding Category Funding Source Amount
Current and Future Debt 108,394
2017 Revenue Bond 3,571
Unsecured Local Grant/Loan 20,000
State Public Works Board Loan 10,688
Unsecured Revenue Bond 74,135
Grants 3,000
Federal EDA Grant 3,000
Local Partnerships 3,798
Local Improvement District (LID) 3,798
Internal Fund Reserve 20,547
Utility Expansion Fees 2,000
Utility Rate 18,547
Total Utility Fund Source 135,739
Exhibit 6
Exhibit 7
Funding
The CIP process is intended to identify the funding sources available for projects prioritized in
the next six years, with an additional fourteen years of strategic vision and planning. A large
amount of unsecured funding is expected and changes to cost estimates or revenue sources is
normal. The CIP, as its name suggest is a guiding document to help cities plan for critical
infrastructure maintenance and enhancement, as well as effectively and safely accommodate
growth.
The amounts shown are planned funding sources, and costs generally precede detailed design
work. The schedule of each project may also change as assumptions like scope, the local and
national economy, or even the weather change.
The CIP utilizes four main categories of funding sources – Internal fund reserves, grants, debt and
local partnerships. The revenue sources that comprise these categories are described below.
Internal fund reserves – This revenue source includes fund balance available for capital project
within each fund. This category includes estimates of annual ongoing revenue that will be received
from anticipated sources. These include excise and property tax revenues, impact fees, utility rates,
utility expansion fees charged to new customers and charges for existing and new customers.
These are largely distinguished by the fact that they are derived from the current year’s economic,
development, or usage activity. The City preserves fund balances as necessary and possible to
2020 – 2025 Capital Improvement Plan – Page xxiv
account for large investments on the horizon or for emergency purposes.
Notable assumptions for major current revenue sources are highlighted below.
Real Estate Excise Tax
(REET) consists of two
0.25% excise taxes
levied by the City
against real estate sales
(referred to as REET 1
and REET 2, for a total
of 0.5%). As real
estate sales increase/
decrease, collection of
the REET revenue
increases /decreases
with it. Due to a strong
housing market and
rising home prices,
REET revenue has been
rising through the
years. REET funds can be used for capital projects for a variety of local government needs. The
City has been diligently managing this fund, increasing the fund balance from $3,700 thousand
in 2014 to $8,850 thousand by end of 2018. While the revenue has been historically high, it is
important to remember that this revenue source is highly reliant on the real estate market. In
any given year, if the annual REET revenues are in excess of planned REET spending, the excess
funds are reserved to support future capital projects.
I-182 Corridor Traffic Impact consists of traffic
impact fees imposed to development within the
I-182 Corridor Subarea lying west of 20th Avenue
bounded on the north by City boundaries and
on the south and west by the Columbia River.
Similar to REET revenue, this fund has seen
significant increase due to high development
activity in this area. As with REET, this fund is
highly reliant on a strong local and national
housing market but also availability of land to
build in the geographic area.
Property Tax revenue consists of taxes levied on assessed valuation of property within the city
limit. Beginning in 1986, local governments have been allowed to levy less than the maximum
increase in property taxes allowed under law without losing the ability to levy higher taxes later,
if necessary. This provision encouraged districts to levy only what they needed rather than the
maximum allowable with the confidence that,
when additional revenues were needed, they
would be available, subject to a vote of the
legislative body. The banked capacity concept
allowed municipalities to be more fiscally
conservative and strategic without being
penalized. The City has taken advantage of the
flexibility allowed by law and has opted to bank
the capacity over the years as part of a long-term
strategy. In 2018, Council voted to use the
banked capacity to fund the relocation of Fire
Stations 83 and 84, as well as use any remainder
funds for high priority capital projects such as the
Community Center.
Motor Vehicle Fuel Tax consist of taxes on gas
sales. This is a tax collected by Washington State
and distributed to cities on a per capita basis.
Though this distribution basis has not historically
changed, the Legislature is looking into different
methods to tax fuel efficient and electric vehicles
in the future. This is expected to increase the total
tax revenue collected by the State to fund critical
State and local transportation infrastructure. This
tax is spread between Arterial and Street funds
within the City to use for maintenance and
construction of City streets.
Utility Rates and Expansion Fees – The utilities capital program funds equipment and infrastructure
requirements of the City’s water, sewer, irrigation, storm water, and process water reuse utilities.
Funding for the program comes from rates, fees and charges assessed on current and new utility
customers. The fees and rates are determined based on rate studies performed for each utility.
Debt represents a commitment to repay borrowed funds over an extended period of time.
While the City has a relatively large legal debt capacity, the main constraint is the ability to
repay the debt.
2020 – 2025 Capital Improvement Plan – Page xxvi
Exhibit 8
Bonds
The City Council may authorize the City Manager to sell bonds to raise revenue for capital
improvements. Those bonds are sold on the open market in exchange for cash payments,
essentially functioning as a loan for the City. In selling and managing bonds, the City seeks the
advice of both a bond counsel and an outside financial advisor. Interest rates on bond payments
are based on market conditions and the City’s bond rating, as determined by private rating
agencies. The City’s current bond rating is AA-, last evaluated in 2017 by S&P Global.
Debt Capacity - The total indebtedness for general purposes with or without a vote cannot exceed 2.5% of the
value of the taxable property within the City limits. 1.5% is the maximum limit for general purpose debt without
a vote (councilmanic).
Utility Revenue Bonds do not have such criteria, as utility funds are treated as a business unit and debt can be
issued if the rates can sustain debt service. The bond interest rates are driven by the market, but influenced by the
total financial health, of not just the fund, but of the City’s residents and its future needs.
Council has made some prudent financial decisions which are reflected in the history of City’s debt capacity.
General-purpose bonded indebtedness capacity for the City is $120,022 thousand. The current general-purpose
bond for the City is $8,865 thousand or 7% of the maximum allowable debt. It is also important to note that the
cities historically go through cycles of debt incurrence with aging facilities and growth.
The pattern and speed of Pasco’s growth will result in debt needing to be issued in a cyclical but not continuous
pattern. The last time the City issued a large amount of debt was in the 1990’s to build the PWRF, Library, and
Fire Stations. Exhibit 8 below demonstrates the variances in which the City has leveraged debt to fund large capital
projects over the last quarter century.
Unlimited Tax General Obligation Bonds (UTGO)
One of the most common methods of financing capital improvements for local governments is
through the issuance of municipal bonds known as “Unlimited Tax General Obligation Bonds” or
“UTGO Bonds.” The voters within the local government must approve UTGO Bonds. UTGO
Bonds are secured by and payable out of annual property taxes, in excess of regular property
taxes, unlimited as to rate or amount. In other words, a local government is obligated to levy
excess property taxes at whatever rate is necessary to repay the UTGO Bonds. Further, UTGO
Bonds constitute a general obligation of the local government, and, as such, the full faith, credit
and resources of the local government are pledged for their repayment.
The approval process requires Local government voters approve the bond ballot proposition at
a properly conducted election. UTGO Bonds must be approved by 60% of the qualified voters
within the local government. In addition, the total number of voters casting ballots at the election
cannot be less than 40% of the number of votes cast in the last state general election. Further, a
local government may only place a bond ballot proposition before its voters twice in any calendar
year.
The City currently doesn’t have any UTGO bonds outstanding. The last UTGO bonds issued by
the City were in 1999 to fund a library and a fire station.
Limited Tax General Obligation Bonds (LTGO)
Limited Tax General Obligation Bonds are also called “councilmanic” bonds or non-voted debt.
These bonds may be issued by a vote of the legislative body and require a majority support.
Because the voters have not been asked to approve a tax increase to pay for the principal and
interest, existing general fund revenues must be pledged to pay the debt service on a LTGO Bond.
The City issued $8,795 thousand of LTGO bonds in 2015 to build the Pasco Police and
Community Services Building.
Revenue Bond
Another debt financing option is Revenue Bonds to finance projects for any City enterprise which
is self-supporting like utilities. Payment comes from user fees; so the debt is not backed by the full
faith and credit of the City. Investors consider these somewhat less secure than general obligation
bonds as well.
Local Partnerships
The City also relies on partnership with other local agencies like Port or Pasco, Pasco School
District, City of Kennewick, City of Richland, individuals donations etc. to fund projects.
Additionally, the City has also used Local Improvement District – a method by which a group
of property owners can share in the cost of infrastructure improvements to fund project that
provide specific benefit to such property owners.
Grants
A significant portion of the funding for larger City capital projects comes from grants and loans
made by federal and state agencies. Almost all federal funds are 'passed through' a state agency
filter. Some of the major agencies involved in funding grants and loans are Transportation
Improvement Board (TIB), Washington State Recreation and Conservation Office (RCO), Water
Resources Program, Department of Ecology, etc. Parks and Transportation projects are the
largest benefactors of such grants and loans at the City of Pasco.
2020 – 2025 Capital Improvement Plan – Page xxviii
This page left intentionally blank
Pg#Project Group/Project Name
Total Project
Expenses
Project to Date
12/31/2018
Scheduled Year
2019 2020 2021 2022 2023 2024 2025
Total Request
2020-2025
Fire 28,149 97 2,105 16,745 8,014 128 530 507 23 25,947
2 Fire Station 83 Replacement 5,969 49 1,480 4,440 - - - - - 4,440
3 Fire Station 84 Replacement 12,676 46 325 12,305 - - - - - 12,305
6 Fire Station 85 Addition 8,302 2 300 - 8,000 - - - - 8,000
4 Fire Station 86 Property Purchase 500 - - - - - 500 - - 500
5 Fire Station 87 Property Purchase 500 - - - - - - 500 - 500
7 Training Center Car Prop 23 - - - - - - - 23 23
8 Training Center Improvements 179 - - - 14 128 30 7 - 179
General 13,173 187 1,291 7,715 3,865 115 - - - 11,695
10 Animal Shelter 5,017 187 30 4,800 - - - - - 4,800
11 Animal Shelter - Little League Parking Lot 615 - 15 600 - - - - - 600
13 Community Center 4,900 - 150 1,000 3,750 - - - - 4,750
12 Gesa Stadium 2,000 - 1,000 1,000 - - - - - 1,000
14 Wayfinding and Signage 641 - 96 315 115 115 - - - 545
Parks and Recreation 30,482 1,372 1,162 9,983 5,150 6,410 1,285 620 4,500 27,948
16 A Street Sporting Complex - Phase 1 606 35 132 439 - - - - - 439
17 Chapel Hill Park 713 13 - 700 - - - - - 700
24 Community Park Northwest 6,100 - - 1,400 - - - 200 4,500 6,100
30 Dog Park 450 - - - 450 - - - - 450
25 Franklin County Irrigation District (FCID) Trail Phases 1 and 2 870 - - - 55 360 35 420 - 870
31 Highland Park Parking and Field Expansion 825 - - - 75 750 - - - 825
18 Kurtzman Shelter 60 - - 60 - - - - - 60
32 Marina Dock Replacement - Dock B 1,650 - - - - 1,650 - - - 1,650
19 Pasco Sporting Complex 251 11 140 100 - - - - - 100
20 Peanuts Park Restoration 7,178 361 542 6,275 - - - - - 6,275
26 Road 48 Park 3,476 926 - - 50 1,250 1,250 - - 2,550
27 Road 54 Erwen Property 420 - - - 20 400 - - - 420
21 Road 84 Park 750 - - 350 400 - - - - 750
29 Sacajawea Levee Lowering 4,757 26 35 196 2,500 2,000 - - - 4,696
28 Sacajawea Trail Burlington Northern Santa Fe (BNSF) Crossing 1,650 - - 50 1,600 - - - - 1,650
22 Schlagel Park/Boat Basin Improvements 626 - 313 313 - - - - - 313
23 Sylvester Park Sporting Courts 100 - - 100 - - - - - 100
Transportation 59,326 6,789 4,254 16,165 12,419 3,492 4,565 5,952 5,690 48,283
34 Annual Pavement Preservation Program 5,499 - - 850 876 902 929 957 985 5,499
35 Argent Road - Phase 1 (Saraceno/Varney to 20th Avenue)2,015 200 1,815 - - - - - - -
36 Argent Road - Phase 2 (Road 36 Intersection Improvements)850 - - 128 722 - - - - 850
37 Argent Road - Phase 3 (Road 36 to Saraceno/Varney)300 - - - - - - - 300 300
49 Burns Road Pedestrian/Bicycle Pathway - Road 100 to Road 90 119 - - 11 108 - - - - 119
47 Burns Road Pedestrian/Bicycle Pathway - Road 84 to Road 68 102 - - 11 - - 91 - - 102
48 Burns Road Pedestrian/Bicycle Pathway - Road 90 to Road 84 71 - - 8 - 63 - - - 71
38 Citywide Traffic Controller Upgrades - Phase 2 3,556 - 300 3,256 - - - - - 3,256
Pg#Project Group/Project Name
Total Project
Expenses
Project to Date
12/31/2018
Scheduled Year
2019 2020 2021 2022 2023 2024 2025
Total Request
2020-2025
50 Court Street and Road 68 Intersection Improvements 860 - - - - 75 50 735 - 860
51 Crescent Road Surface Improvement 400 - - - - - - 45 355 400
52 Franklin County Irrigation District (FCID) Canal Bicycle/Pedestrian Pathway Study 870 - - - 90 360 420 - - 870
39 Industrial Way - Foster Wells to Kartchner Preservation 532 - - - 60 472 - - - 532
63 James Street Improvements - Oregon Avenue to East End 483 - - - 48 435 - - - 483
40 Lewis Street Corridor Improvements - 2nd Avenue to 5th Avenue 1,625 - 25 550 550 500 - - - 1,600
41 Lewis Street Overpass 28,639 6,589 2,023 10,540 9,487 - - - - 20,027
54 Pedestrian/Bicycle Access Road 100 Interchange 2,320 - - - - 120 2,200 - - 2,320
53 Pedestrian/Bicycle Access Road 68 Interchange 1,100 - - - - - 100 1,000 - 1,100
55 Pedestrian/Bicycle Access Sylvester Street Overpass 78 - - - 78 - - - - 78
57 Road 100 Widening - Court Street to Chapel Hill Boulevard 4,125 - - - - - 375 1,500 2,250 4,125
56 Road 44 and Argent Road Intersection Analysis 65 - - - - - - 65 - 65
42 Road 68 Widening - Interstate 182 to Chapel Hill Boulevard 308 - 58 250 - - - - - 250
43 Road 76 Overpass 300 - - - - - - - 300 300
58 Sandifur Parkway Extension - Phase 1 (West of Road 100)1,650 - - - - - 150 1,500 - 1,650
59 Sandifur Parkway Extension - Phase 2 (West of Road 100)1,650 - - - - - - 150 1,500 1,650
44 Sandifur Parkway Widening - Road 52 to Road 60 425 - - 25 400 - - - - 425
45 Signage and Striping Improvements at Road 68 and Burden Boulevard 260 - - 260 - - - - - 260
60 Traffic Analysis for Interstate Interstate 182 at Road 68 Interchange 300 - - - - 300 - - - 300
61 Traffic Analysis for Interstate Interstate 182 at State Route 395 Interchange 265 - - - - 265 - - - 265
62 Traffic Analysis for State Route 12 Interchange 250 - - - - - 250 - - 250
46 Wrigley Drive Extension 309 - 33 276 - - - - - 276
Irrigation 2,089 - 109 320 520 520 520 50 50 1,980
66 Annual Irrigation System Improvements - Development 350 - 50 50 50 50 50 50 50 300
67 Chapel Hill Boulevard to Interstate 182 - Irrigation Main 100 - - 100 - - - - - 100
68 Columbia River Intake Capacity Upgrades 229 - 59 170 - - - - - 170
70 Well Capacity Upgrades 1,410 - - - 470 470 470 - - 1,410
Process Water Reuse Facility 46,836 1,411 9,372 16,912 19,141 - - - - 36,053
72 Columbia East Lift Station and Force Main 15,129 1,199 5,621 8,309 - - - - - 8,309
73 Process Water Reuse Facility (PWRF) Irrigation Pump Station (IPS) Improvements 8,751 212 3,439 5,100 - - - - - 5,100
74 Process Water Reuse Facility (PWRF) Primary Treatment Improvement 22,956 - 312 3,503 19,141 - - - - 22,644
Sewer 58,518 469 1,283 20,734 10,142 7,923 4,770 6,473 6,724 56,766
76 9th and Washington Lift Station 680 53 131 496 - - - - - 496
77 Annual Sewer System Improvements - Development 1,600 200 200 200 200 200 200 200 200 1,200
80 Maitland Lift Station - Purchase and Install 4th Pump 106 18 46 42 - - - - - 42
81 Northwest Area Lift Station 3,500 - - 3,500 - - - - - 3,500
84 Northwest Area Trunkline - Sandifur Parkway Extension to Desiree Street 4,598 - - 4,598 - - - - - 4,598
78 Pearl Street Lift Station 1,149 141 335 673 - - - - - 673
85 Public Works Operation Center -- - - - - - - - -
79 Road 36 Lift Station Upgrades 693 57 135 501 - - - - - 501
86 Road 52 and Pearl Street Lift Station - Riverview 2,420 - 336 684 1,400 - - - - 2,084
87 Road 84 and Roberts Drive Lift Station - Riverview 2,500 - - - - 500 2,000 - - 2,500
88 Southeast Industrial Trunkline -- - - - - - - - -
89 Trunkline Deficiency - Court Street -- - - - - - - - -
83 Waste Water Treatment Plant (WWTP) Improvements - Phase 1 25,905 - 100 10,040 8,542 7,223 - - - 25,805
90 Waste Water Treatment Plant (WWTP) Improvements - Phase 2 15,367 - - - - - 2,570 6,273 6,524 15,367
Pg#Project Group/Project Name
Total Project
Expenses
Project to Date
12/31/2018
Scheduled Year
2019 2020 2021 2022 2023 2024 2025
Total Request
2020-2025
Stormwater 1,079 - 50 200 50 629 50 50 50 1,029
92 1st Avenue Pipe Rehab 249 - - - - 249 - - - 249
93 Annual Stormwater Improvements - Development 350 - 50 50 50 50 50 50 50 300
94 North Industrial Way Infiltration Retrofit Project 150 - - 150 - - - - - 150
96 Sylvester Pipe Relining 330 - - - - 330 - - - 330
Water 40,186 - 275 4,960 8,890 7,850 8,006 3,505 6,700 39,911
98 Annual Water System Improvements - Development 1,400 - 200 200 200 200 200 200 200 1,200
110 Automated Meter Reading 5,750 - - 750 1,000 1,000 1,000 1,000 1,000 5,750
99 Butterfield Water Treatment Plant (WTP) - Chlorine Safety 350 - 75 275 - - - - - 275
100 Emergency Power Improvements 2,200 - - 550 550 550 550 - - 2,200
111 Reservoir Storage Tank - Zone 2 7,500 - - - - - - 2,000 5,500 7,500
109 Reservoir Storage Tank - Zone 3 11,700 - - 150 2,850 4,200 4,500 - - 11,700
101 Transmission Main - West Pasco Water Treatment Plant (WPWTP) to Zone 3 3,000 - - 500 2,500 - - - - 3,000
112 Water Main Extension - Alton Street (Wehe Avenue to the alley west of Owen Street) 327 - - - - 327 - - - 327
113 Water Main Extension - Riverhaven Street (Road 36 to Road 40) 305 - - - - - - 305 - 305
102 Water Main Extension - Road 103 (Maple Drive to Willow Way) 113 - - - - 113 - - - 113
103 Water Main Replacement - Alley East of Wehe Avenue 140 - - 140 - - - - - 140
104 Water Main Replacement - Maple Drive, AC Main (Road 100 to Road 103) 250 - - 250 - - - - - 250
114 Water Main Replacement - Richardson Road (Road 92 to Road 96) 460 - - - - 460 - - - 460
115 Water Main Replacement - Road 60 (Court Street to West Pearl) 930 - - - - - 930 - - 930
116 Water Main Replacement - Road 76 (Wernett Road to Court Street)826 - - - - - 826 - - 826
105 Water Main Replacement - South 18th Avenue (Court Street to WA Street)79 - - - 79 - - - - 79
106 Water Main Replacement - Star Lane (Road 100 to Road 97)236 - - - 236 - - - - 236
108 West Pasco Water Treatment Plant (WPWTP) Improvements 4,620 - - 2,145 1,475 1,000 - - - 4,620
Grand Total 279,837 10,325 19,901 93,734 68,191 27,067 19,726 17,157 23,737 249,612
Pg#Project Group/Project Name
Total Project
Revenue
Project to Date
12/31/2018
Scheduled Year
2019 2020 2021 2022 2023 2024 2025
Total Request
2020-2025
INTERNAL FUND RESERVES 51,969 3,353 2,899 15,345 13,190 6,055 4,423 3,167 3,537 45,717
Arterial Street Fund 5,974 729 642 460 1,043 24 622 975 1,480 4,603
35 Argent Road - Phase 1 (Saraceno/Varney to 20th Avenue) 415 200 215 - - - - - - -
37 Argent Road - Phase 3 (Road 36 to Saraceno/Varney) 300 - - - - - - - 300 300
38 Citywide Traffic Controller Upgrades - Phase 2 415 - 40 375 - - - - - 375
50 Court Street and Road 68 Intersection Improvements 100 - - - - 9 5 86 - 100
51 Crescent Road Surface Improvement 100 - - - - - - 11 89 100
41 Lewis Street Overpass 1,756 529 327 - 900 - - - - 900
54 Pedestrian/Bicycle Access Road 100 Interchange 300 - - - - 15 285 - - 300
55 Pedestrian/Bicycle Access Sylvester Street Overpass 25 - - - 25 - - - - 25
57 Road 100 Widening - Court Street to Chapel Hill Boulevard 2,000 - - - - - 182 727 1,091 2,000
42 Road 68 Widening - Interstate 182 to Chapel Hill Boulevard 92 - 58 34 - - - - - 34
58 Sandifur Parkway Extension - Phase 1 (West of Road 100) 150 - - - - - 150 - - 150
59 Sandifur Parkway Extension - Phase 2 (West of Road 100) 150 - - - - - - 150 - 150
44 Sandifur Parkway Widening - Road 52 to Road 60 125 - - 7 118 - - - - 125
45 Signage and Striping Improvements at Road 68 and Burden Boulevard 35 - - 35 - - - - - 35
46 Wrigley Drive Extension 11 - 2 9 - - - - - 9
Capital Improvement Fund (REET)8,744 1,441 1,481 3,006 1,901 720 195 - - 5,822
10 Animal Shelter 73 63 10 - - - - - - -
49 Burns Road Pedestrian/Bicycle Pathway - Road 100 to Road 90 30 - - 3 27 - - - - 30
47 Burns Road Pedestrian/Bicycle Pathway - Road 84 to Road 68 26 - - 3 - - 23 - - 26
48 Burns Road Pedestrian/Bicycle Pathway - Road 90 to Road 84 16 - - 2 - 14 - - - 16
13 Community Center 1,150 - 150 1,000 - - - - - 1,000
2 Fire Station 83 Replacement 274 49 225 - - - - - - -
3 Fire Station 84 Replacement 371 46 325 - - - - - - -
6 Fire Station 85 Addition 302 2 300 - - - - - - -
52 Franklin County Irrigation District (FCID) Canal Bicycle/Pedestrian Pathway Study 286 - - - 30 118 138 - - 286
25 Franklin County Irrigation District (FCID) Trail Phases 1 and 2 90 - - - 55 - 35 - - 90
18 Kurtzman Shelter 60 - - 60 - - - - - 60
40 Lewis Street Corridor Improvements - 2nd Avenue to 5th Avenue 464 - 25 154 154 131 - - - 439
41 Lewis Street Overpass 1,566 1,244 293 15 14 - - - - 29
19 Pasco Sporting Complex 11 11 - - - - - - - -
20 Peanuts Park Restoration 1,207 - - 1,207 - - - - - 1,207
21 Road 84 Park 750 - - 350 400 - - - - 750
29 Sacajawea Levee Lowering 1,134 26 35 45 571 457 - - - 1,073
28 Sacajawea Trail Burlington Northern Santa Fe (BNSF) Crossing 700 - - 50 650 - - - - 700
22 Schlagel Park/Boat Basin Improvements 235 - 118 117 - - - - - 117
Pg#Project Group/Project Name
Total Project
Revenue
Project to Date
12/31/2018
Scheduled Year
2019 2020 2021 2022 2023 2024 2025
Total Request
2020-2025
General Fund 2,206 - - 1,206 - - 500 500 - 2,206
4 Fire Station 86 Property Purchase 500 - - - - - 500 - - 500
5 Fire Station 87 Property Purchase 500 - - - - - - 500 - 500
20 Peanuts Park Restoration 1,206 - - 1,206 - - - - - 1,206
I-182 Corridor Impact Fund 1,260 12 1 158 - 125 156 236 573 1,248
38 Citywide Traffic Controller Upgrades - Phase 2 158 - - 158 - - - - - 158
50 Court Street and Road 68 Intersection Improvements 25 - - - - 2 2 21 - 25
41 Lewis Street Overpass 13 12 1 - - - - - - -
54 Pedestrian/Bicycle Access Road 100 Interchange 50 - - - - 3 47 - - 50
53 Pedestrian/Bicycle Access Road 68 Interchange 25 - - - - - 2 23 - 25
57 Road 100 Widening - Court Street to Chapel Hill Boulevard 500 - - - - - 45 182 273 500
56 Road 44 and Argent Road Intersection Analysis 10 - - - - - - 10 - 10
43 Road 76 Overpass 300 - - - - - - - 300 300
60 Traffic Analysis for Interstate Interstate 182 at Road 68 Interchange 60 - - - - 60 - - - 60
61 Traffic Analysis for Interstate Interstate 182 at State Route 395 Interchange 60 - - - - 60 - - - 60
62 Traffic Analysis for State Route 12 Interchange 60 - - - - - 60 - - 60
Park Development Fund 4,270 971 190 3,089 20 - - - - 3,109
16 A Street Sporting Complex - Phase 1 256 32 35 189 - - - - - 189
11 Animal Shelter - Little League Parking Lot 615 - 15 600 - - - - - 600
17 Chapel Hill Park 713 13 - 700 - - - - - 700
24 Community Park Northwest 1,400 - - 1,400 - - - - - 1,400
19 Pasco Sporting Complex 240 - 140 100 - - - - - 100
26 Road 48 Park 926 926 - - - - - - - -
27 Road 54 Erwen Property 20 - - - 20 - - - - 20
23 Sylvester Park Sporting Courts 100 - - 100 - - - - - 100
Street Overlay Fund 7,331 - - 1,868 1,218 1,374 929 957 985 7,331
34 Annual Pavement Preservation Program 5,499 - - 850 876 902 929 957 985 5,499
39 Industrial Way - Foster Wells to Kartchner Preservation 532 - - - 60 472 - - - 532
41 Lewis Street Overpass 1,000 - - 1,000 - - - - - 1,000
44 Sandifur Parkway Widening - Road 52 to Road 60 300 - - 18 282 - - - - 300
Utility Expansion Fees 2,000 - - 500 500 500 500 - - 2,000
81 Northwest Area Lift Station 500 - - 500 - - - - - 500
109 Reservoir Storage Tank - Zone 3 1,500 - - - 500 500 500 - - 1,500
Pg#Project Group/Project Name
Total Project
Revenue
Project to Date
12/31/2018
Scheduled Year
2019 2020 2021 2022 2023 2024 2025
Total Request
2020-2025
Utility Rate 20,184 200 586 5,058 8,508 3,312 1,520 500 500 19,398
92 1st Avenue Pipe Rehab 249 - - - - 249 - - - 249
66 Annual Irrigation System Improvements - Development 350 - 50 50 50 50 50 50 50 300
77 Annual Sewer System Improvements - Development 1,600 200 200 200 200 200 200 200 200 1,200
93 Annual Stormwater Improvements - Development 350 - 50 50 50 50 50 50 50 300
98 Annual Water System Improvements - Development 1,400 - 200 200 200 200 200 200 200 1,200
67 Chapel Hill Boulevard to Interstate 182 - Irrigation Main 100 - - 100 - - - - - 100
68 Columbia River Intake Capacity Upgrades 229 - 59 170 - - - - - 170
100 Emergency Power Improvements 2,200 - - 550 550 550 550 - - 2,200
94 North Industrial Way Infiltration Retrofit Project 150 - - 150 - - - - - 150
40 Lewis Street Corridor Improvements - 2nd Avenue to 5th Avenue 300 - - 100 100 100 - - - 300
41 Lewis Street Overpass 550 - 27 275 248 - - - - 523
109 Reservoir Storage Tank - Zone 3 2,500 - - 150 2,350 - - - - 2,500
96 Sylvester Pipe Relining 330 - - - - 330 - - - 330
101 Transmission Main - West Pasco Water Treatment Plant (WPWTP) to Zone 3 3,000 - - 500 2,500 - - - - 3,000
102 Water Main Extension - Road 103 (Maple Drive to Willow Way) 113 - - - - 113 - - - 113
104 Water Main Replacement - Maple Drive, AC Main (Road 100 to Road 103) 250 - - 250 - - - - - 250
103 Water Main Replacement - Alley East of Wehe Avenue 140 - - 140 - - - - - 140
105 Water Main Replacement - South 18th Avenue (Court Street to WA Street) 79 - - - 79 - - - - 79
106 Water Main Replacement - Star Lane (Road 100 to Road 97) 236 - - - 236 - - - - 236
70 Well Capacity Upgrades 1,410 - - - 470 470 470 - - 1,410
108 West Pasco Water Treatment Plant (WPWTP) Improvements 4,620 - - 2,145 1,475 1,000 - - - 4,620
46 Wrigley Drive Extension 28 - - 28 - - - - - 28
CURRENT AND FUTURE DEBT 149,614 481 9,594 54,318 38,083 13,210 11,326 9,578 13,024 139,539
2017 Revenue Bond 4,662 269 822 3,571 - - - - - 3,571
76 9th and Washington Lift Station 680 53 131 496 - - - - - 496
99 Butterfield Water Treatment Plant (WTP) - Chlorine Safety 350 - 75 275 - - - - - 275
80 Maitland Lift Station - Purchase and Install 4th Pump 106 18 46 42 - - - - - 42
78 Pearl Street Lift Station 1,149 141 335 673 - - - - - 673
79 Road 36 Lift Station Upgrades 693 57 135 501 - - - - - 501
83 Waste Water Treatment Plant (WWTP) Improvements - Phase 1 1,684 - 100 1,584 - - - - - 1,584
HAEFIC Loan 500 212 288 - - - - - - -
73 Process Water Reuse Facility (PWRF) Irrigation Pump Station (IPS) Improvements 500 212 288 - - - - - - -
Section 108 Loan 3,800 - - 3,800 - - - - - 3,800
20 Peanuts Park Restoration 3,800 - - 3,800 - - - - - 3,800
State PWB Loan 11,000 - 312 688 10,000 - - - - 10,688
74 Process Water Reuse Facility (PWRF) Primary Treatment Improvement 11,000 - 312 688 10,000 - - - - 10,688
Pg#Project Group/Project Name
Total Project
Revenue
Project to Date
12/31/2018
Scheduled Year
2019 2020 2021 2022 2023 2024 2025
Total Request
2020-2025
Unsecured Local Grant/Loan 20,000 - - 5,000 3,000 2,000 2,570 3,000 4,430 20,000
83 Waste Water Treatment Plant (WWTP) Improvements - Phase 1 10,000 - - 5,000 3,000 2,000 - - - 10,000
90 Waste Water Treatment Plant (WWTP) Improvements - Phase 2 10,000 - - - - - 2,570 3,000 4,430 10,000
Unsecured Revenue Bond 88,802 - 6,667 21,914 25,083 11,210 8,756 6,578 8,594 82,135
110 Automated Meter Reading 5,750 - - 750 1,000 1,000 1,000 1,000 1,000 5,750
72 Columbia East Lift Station and Force Main 8,489 - 3,180 5,309 - - - - - 5,309
6 Fire Station 85 Addition 8,000 - - - 8,000 - - - - 8,000
81 Northwest Area Lift Station 3,000 - - 3,000 - - - - - 3,000
84 Northwest Area Trunkline - Sandifur Parkway Extension to Desiree Street 800 - - 800 - - - - - 800
73 Process Water Reuse Facility (PWRF) Irrigation Pump Station (IPS) Improvements 8,251 - 3,151 5,100 - - - - - 5,100
74 Process Water Reuse Facility (PWRF) Primary Treatment Improvement 11,956 - - 2,815 9,141 - - - - 11,956
111 Reservoir Storage Tank - Zone 2 7,500 - - - - - - 2,000 5,500 7,500
109 Reservoir Storage Tank - Zone 3 7,700 - - - - 3,700 4,000 - - 7,700
86 Road 52 and Pearl Street Lift Station - Riverview 2,420 - 336 684 1,400 - - - - 2,084
87 Road 84 and Roberts Drive Lift Station - Riverview 2,500 - - - - 500 2,000 - - 2,500
83 Waste Water Treatment Plant (WWTP) Improvements - Phase 1 14,221 - - 3,456 5,542 5,223 - - - 14,221
90 Waste Water Treatment Plant (WWTP) Improvements - Phase 2 5,367 - - - - - - 3,273 2,094 5,367
112 Water Main Extension - Alton Street (Wehe Avenue to the alley west of Owen Street) 327 - - - - 327 - - - 327
113 Water Main Extension - Riverhaven Street (Road 36 to Road 40) 305 - - - - - - 305 - 305
114 Water Main Replacement - Richardson Road (Road 92 to Road 96) 460 - - - - 460 - - - 460
115 Water Main Replacement - Road 60 (Court Street to West Pearl) 930 - - - - - 930 - - 930
116 Water Main Replacement - Road 76 (Wernett Road to Court Street) 826 - - - - - 826 - - 826
Future Bond 20,850 - 1,505 19,345 - - - - - 19,345
12 Gesa Stadium 2,000 - 1,000 1,000 - - - - - 1,000
10 Animal Shelter 1,600 - - 1,600 - - - - - 1,600
2 Fire Station 83 Replacement 4,945 - 505 4,440 - - - - - 4,440
3 Fire Station 84 Replacement 12,305 - - 12,305 - - - - - 12,305
LOCAL PARTNERSHIP 12,150 124 820 7,062 409 435 - 1,534 1,766 11,206
City of Kennewick Contribution 1,672 62 10 1,600 - - - - - 1,600
10 Animal Shelter 1,672 62 10 1,600 - - - - - 1,600
City of Richland Contribution 1,672 62 10 1,600 - - - - - 1,600
10 Animal Shelter 1,672 62 10 1,600 - - - - - 1,600
Developer Contribution 3,300 - - - - - - 1,534 1,766 3,300
51 Crescent Road Surface Improvement 300 - - - - - - 34 266 300
58 Sandifur Parkway Extension - Phase 1 (West of Road 100) 1,500 - - - - - - 1,500 - 1,500
59 Sandifur Parkway Extension - Phase 2 (West of Road 100) 1,500 - - - - - - - 1,500 1,500
LID 4,281 - - 3,798 48 435 - - - 4,281
63 James Street Improvements - Oregon Avenue to East End 483 - - - 48 435 - - - 483
84 Northwest Area Trunkline - Sandifur Parkway Extension to Desiree Street 3,798 - - 3,798 - - - - - 3,798
Pg#Project Group/Project Name
Total Project
Revenue
Project to Date
12/31/2018
Scheduled Year
2019 2020 2021 2022 2023 2024 2025
Total Request
2020-2025
Port of Pasco 1,225 - 800 64 361 - - - - 425
35 Argent Road - Phase 1 (Saraceno/Varney to 20th Avenue) 800 - 800 - - - - - - -
36 Argent Road - Phase 2 (Road 36 Intersection Improvements) 425 - - 64 361 - - - - -
GRANTS 49,409 6,364 5,737 16,694 11,305 3,474 2,697 2,251 886 37,308
CBC Grant 1,225 - 800 64 361 - - - - 425
35 Argent Road - Phase 1 (Saraceno/Varney to 20th Avenue) 800 - 800 - - - - - - -
36 Argent Road - Phase 2 (Road 36 Intersection Improvements) 425 - - 64 361 - - - - 425
CDBG Grant 1,672 361 450 296 296 269 - - - 861
40 Lewis Street Corridor Improvements - 2nd Avenue to 5th Avenue 861 - - 296 296 269 - - - 861
20 Peanuts Park Restoration 811 361 450 - - - - - - -
Connecting WA Grant 15,000 1,050 1,125 4,500 8,325 - - - - 12,825
41 Lewis Street Overpass 15,000 1,050 1,125 4,500 8,325 - - - - 12,825
Federal EDA Grant 3,065 65 - 3,000 - - - - - 3,000
72 Columbia East Lift Station and Force Main 3,065 65 - 3,000 - - - - - 3,000
Federal STP Grant 7,441 3,754 284 3,403 - - - - - 3,403
38 Citywide Traffic Controller Upgrades - Phase 2 2,983 - 260 2,723 - - - - - 2,723
41 Lewis Street Overpass 3,754 3,754 - - - - - - - -
42 Road 68 Widening - Interstate 182 to Chapel Hill Boulevard 216 - - 216 - - - - - 216
45 Signage and Striping Improvements at Road 68 and Burden Boulevard 225 - - 225 - - - - - 225
46 Wrigley Drive Extension 263 - 24 239 - - - - - 239
Franklin Co .09 Grant 1,000 1,000 - - - - - - - -
72 Columbia East Lift Station and Force Main 1,000 1,000 - - - - - - - -
Grant Government Capital Budget 154 - 92 62 - - - - - 62
20 Peanuts Park Restoration 154 - 92 62 - - - - - 62
RCO Grant 741 - 295 446 - - - - - 446
16 A Street Sporting Complex - Phase 1 350 - 100 250 - - - - - 250
22 Schlagel Park/Boat Basin Improvements 391 - 195 196 - - - - - 196
TIB Grant 5,000 - 250 4,750 - - - - - 4,750
41 Lewis Street Overpass 5,000 - 250 4,750 - - - - - 4,750
Unsecured RCO Grant 960 - - - 200 760 - - - 960
25 Franklin County Irrigation District (FCID) Trail Phases 1 and 2 360 - - - - 360 - - - 360
27 Road 54 Erwen Property 400 - - - - 400 - - - 400
28 Sacajawea Trail Burlington Northern Santa Fe (BNSF) Crossing 200 - - - 200 - - - - 200
Pg#Project Group/Project Name
Total Project
Revenue
Project to Date
12/31/2018
Scheduled Year
2019 2020 2021 2022 2023 2024 2025
Total Request
2020-2025
Unsecured State Grant 10,355 - - 151 2,042 2,396 2,629 2,251 886 10,355
50 Court Street and Road 68 Intersection Improvements 735 - - - - 64 43 628 - 735
52 Franklin County Irrigation District (FCID) Canal Bicycle/Pedestrian Pathway Study 584 - - - 60 242 282 - - 584
54 Pedestrian/Bicycle Access Road 100 Interchange 1,970 - - - - 102 1,868 - - 1,970
53 Pedestrian/Bicycle Access Road 68 Interchange 1,075 - - - - - 98 977 - 1,075
55 Pedestrian/Bicycle Access Sylvester Street Overpass 53 - - - 53 - - - - 53
57 Road 100 Widening - Court Street to Chapel Hill Boulevard 1,625 - - - - - 148 591 886 1,625
56 Road 44 and Argent Road Intersection Analysis 55 - - - - - - 55 - 55
29 Sacajawea Levee Lowering 3,623 - - 151 1,929 1,543 - - - 3,623
60 Traffic Analysis for Interstate Interstate 182 at Road 68 Interchange 240 - - - - 240 - - - 240
61 Traffic Analysis for Interstate Interstate 182 at State Route 395 Interchange 205 - - - - 205 - - - 205
62 Traffic Analysis for State Route 12 Interchange 190 - - - - - 190 - - 190
Unsecured State Grant (SRTS) 220 - - 22 81 49 68 - - 220
49 Burns Road Pedestrian/Bicycle Pathway - Road 100 to Road 90 89 - - 8 81 - - - - 89
47 Burns Road Pedestrian/Bicycle Pathway - Road 84 to Road 68 76 - - 8 - - 68 - - 76
48 Burns Road Pedestrian/Bicycle Pathway - Road 90 to Road 84 55 - - 6 - 49 - - - 55
WA State Capital Budget 2,575 134 2,441 - - - - - - -
72 Columbia East Lift Station and Force Main 2,575 134 2,441 - - - - - - -
UNSECURED FUNDING 15,938 - 96 315 5,204 3,893 1,280 627 4,523 15,842
Unsecured Funding 15,938 - 96 315 5,204 3,893 1,280 627 4,523 15,842
13 Community Center 3,750 - - - 3,750 - - - - 3,750
24 Community Park Northwest 4,700 - - - - - - 200 4,500 4,700
30 Dog Park 450 - - - 450 - - - - 450
25 Franklin County Irrigation District (FCID) Trail Phases 1 and 2 420 - - - - - - 420 - 420
31 Highland Park Parking and Field Expansion 825 - - - 75 750 - - - 825
32 Marina Dock Replacement - Dock B 1,650 - - - - 1,650 - - - 1,650
26 Road 48 Park 2,550 - - - 50 1,250 1,250 - - 2,550
28 Sacajawea Trail Burlington Northern Santa Fe (BNSF) Crossing 750 - - - 750 - - - - 750
7 Training Center Car Prop 23 - - - - - - - 23 23
8 Training Center Improvements 179 - - - 14 128 30 7 - 179
14 Wayfinding and Signage 641 - 96 315 115 115 - - - 545
OTHER 750 - 750 - - - - - - -
Sale of Assets 750 - 750 - - - - - - -
2 Fire Station 83 Replacement 750 - 750 - - - - - - -
Grand Total 279,830 10,322 19,896 93,734 68,191 27,067 19,726 17,157 23,737 249,611
2020 - 2025 Capital Improvement Plan - 1 of 117
2020-2025 Capital Improvement Plan
Fire Station 83 Replacement
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 274 49 225 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 5,695 - 1,255 4,440 - - - - - 4,440
Other - - - - - - - - - -
Total Expenditures 5,969 49 1,480 4,440 - - - - - 4,440
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement Fund REET 1 274 49 225 - - - - - - -
LTGO Bond 4,945 - 505 4,440 - - - - - 4,440
Sale of Assets 750 - 750 - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 5,969 49 1,480 4,440 - - - - - 4,440
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Fire Station 83 Replacement
PICTURE
Project Number - 18001
Ongoing
Fire
Fire
Necessary
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Fully Funded
Justification
Summary Project Description
This project includes the relocation and construction of Fire Station 83. The current station location does not allow response times to meet current target times with the
new growth experienced within the City's urban growth boundary (UGB). The relocation of the station to the proposed location will maintain the current service demand
inside the Pasco UGB to within 6-minutes or less travel time of a staffed station.
The Fire Department Master Plan identified the requirement to
relocate the station to match current staffing requirements
(apparatus and personnel)
This meets the Council Goal of:
Community Safety
Consultant rendering of a proposed fire station
2020 - 2025 Capital Improvement Plan - 2 of 117
2020-2025 Capital Improvement Plan
Fire Station 84 Replacement
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 371 46 325 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 12,305 - - 12,305 - - - - - 12,305
Other - - - - - - - - - -
Total Expenditures 12,676 46 325 12,305 - - - - - 12,305
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement Fund REET 1 371 46 325 - - - - - - -
LTGO Bond 12,305 - - 12,305 - - - - - 12,305
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 12,676 46 325 12,305 - - - - - 12,305
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Fire Station 84 Replacement
Project Number - 18002
Ongoing
Fire
Fire
Necessary
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Fully Funded
Justification
Summary Project Description
This project includes the relocation and construction of Fire Station 84, which was acquired as part of an asset transfer due to annexation of land. The current station does
not provide for good crew quarters and apparatus access. The current station was not designed with an attached crew quarter, training room, or the ability to house modern
fire apparatus. The replacement will also address additional training and community rooms, as well as additional administrative office space to facilitate growth along with
the community.
The Fire Department Master Plan identified the requirement to
relocate the station to match current staffing requirements
(apparatus and personnel)
This meets the Council Goal of:
Community Safety
Consultant rendering of a proposed fire station
2020 - 2025 Capital Improvement Plan - 3 of 117
2020-2025 Capital Improvement Plan
Fire Station 86 Property Purchase
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way 500 - - - - - 500 - - 500
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures 500 - - - - - 500 - - 500
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
General Fund 500 - - - - - 500 - - 500
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 500 - - - - - 500 - - 500
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Fire Station 86 Property Purchase
Project Number - 20044
New
Fire
Fire
Desirable
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Fully Funded
Justification
Summary Project Description
As the community continues to grow, it will become more difficult and expensive to secure property for fire stations. As soon as suitable locations can be identified, Council
should attempt to purchase property for future fire stations.
Meeting Council's 6-minute Fire travel time goal
Maintain WSRB Protection Class 3
This meets the Council Goal of:
Community Safety
Google map of the future growth area
2020 - 2025 Capital Improvement Plan - 4 of 117
2020-2025 Capital Improvement Plan
Fire Station 87 Property Purchase
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way 500 - - - - - - 500 - 500
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures 500 - - - - - - 500 - 500
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
General Fund 500 - - - - - - 500 - 500
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 500 - - - - - - 500 - 500
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Fire Station 87 Property Purchase
Project Number - 20045
New
Fire
Fire
Desirable
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Fully Funded
Justification
Summary Project Description
As the community continues to grow, it will become more difficult and expensive to secure property for fire stations. As soon as suitable locations can be identified, Council
should attempt to purchase property for future fire stations.
Meeting Council's 6-minute Fire travel time goal
Maintain WSRB Protection Class 3
This meets the Council Goal of:
Community Safety
Google map of the future growth area
2020 - 2025 Capital Improvement Plan - 5 of 117
2020-2025 Capital Improvement Plan
Fire Station 85 Addition
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 2 2 - - - - - - - -
Land & Right-of-Way 300 - 300 - - - - - - -
Construction 8,000 - - - 8,000 - - - - 8,000
Other - - - - - - - - - -
Total Expenditures 8,302 2 300 - 8,000 - - - - 8,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement REET 2 302 2 300 - - - - - -
Unsecured Revenue Bond 8,000 - - - 8,000 - - - - 8,000
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 8,302 2 300 - 8,000 - - - - 8,000
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses 6,400 - - - 1,000 900 900 1,600 2,000 6,400
Net Impact 6,400 - - - 1,000 900 900 1,600 2,000 6,400
*amounts shown in thousands
Fire Station 85 Addition
PICTURE
Project Number - 19003
New
Fire
Fire
Necessary
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Partially Funded
Justification
Summary Project Description
This project will construct a Fire station on Road 100 on property purchased in 2019. This station will primarily serve the area south of Interstate 182 and west of Road 76. It
will be second on call in the areas of Stations 83 and 84 when those stations are on other calls. As the City expands, adding additional stations on the west and north sides of
the City will be critical to maintaining travel times and the Washington Surveying and Rating Bureau (WSRB) rating.
Meeting Council's 6-minute Fire travel time goal
Maintain the Washington Surveying and Rating Bureau (WSRB)
Protection Class 3
This meets the Council Goal of:
Community Safety
Consultant rendering of a proposed fire station
2020 - 2025 Capital Improvement Plan - 6 of 117
2020-2025 Capital Improvement Plan
Training Center Car Prop
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Flammable Car Prop 23 - - - - - - - 23 23
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Expenditures 23 - - - - - - - 23 23
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Funding 23 - - - - - - - 23 23
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 23 - - - - - - - 23 23
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Not Funded
Justification
Summary Project Description
In 2017, a Strategic Plan for the Pasco Fire Department was initiated to develop a training center for the Fire Department and its consortium members. These features would
bring valuable assets to the training ground. This car prop would prepare personnel to extinguish car fires.
Training Center Car Prop
PICTURE
Project Number - 20005
New
Fire
Fire
Necessary
Maintain WSRB Protection Class 3 by helping meet training
requirements
Meet demands of a growing City with high level of qualified
firefighters tasked with a variety of emergency situations
Firefighter Safety and Health
Rendering for proposed prop
2020 - 2025 Capital Improvement Plan - 7 of 117
2020-2025 Capital Improvement Plan
Training Center Improvements
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Gear Washer/Dryer 14 - - - 14 - - - - 14
2 Box Fire System 128 - - - - 128 - - - 128
Rescue Systems 1 Props 30 - - - - - 30 - - 30
Asphalt 50'x50'7 - - - - - - 7 - 7
Total Expenditures 179 - - - 14 128 30 7 - 179
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Funding 179 - - - 14 128 30 7 - 179
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 179 - - - 14 128 30 7 - 179
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Not Funded
Justification
Summary Project Description
In 2017, a strategic plan for the Pasco Fire Department was initiated to develop a training center for the Pasco Fire Department and its consortium members. These features
would bring valuable assets to the training ground. The gear washer and dryer would support the Healthy In, Healthy Out program and benefit overall health and safety of
the work force, especially with presumptive illness legislation. The machines would decrease overall exposure to products of combustion as a result of training. Station 81
would also utilize the cleaning systems. The 2 Box Fire System would assist with fire behavior labs, support fire academies, assist with instructor development, and has a
possibility of generating revenue from outside agencies. Rescue Systems 1 capabilities will better prepare personnel to the many hazards that the Pasco Fire Department
may encounter in a urban and rural environment.
Training Center Improvements
Project Number - 20004
New
Fire
Fire
Necessary
Maintain WSRB Protection Class 3 by helping meet training
requirements
Meet demands of a growing City with high level of qualified
firefighters tasked with a variety of emergency situations
Firefighter Safety and Health
Raise the basic skill level of the entire workforce
Rescue Systems 1 capabilities would promote joint training with
Public Works and support activities Photos of the proposed props
2020 - 2025 Capital Improvement Plan - 8 of 117
General
2020 - 2025 Capital Improvement Plan - 9 of 117
2020-2025 Capital Improvement Plan
Animal Shelter
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 217 187 30 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 4,800 - - 4,800 - - - - - 4,800
Other - - - - - - - - - -
Total Expenditures 5,017 187 30 4,800 - - - - - 4,800
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement REET 2 73 63 10 - - - - - - -
City of Kennewick Contribution 1,672 62 10 1,600 - - - - - 1,600
City of Richland Contribution 1,672 62 10 1,600 - - - - - 1,600
Future LTGO Bond 1,600 - - 1,600 - - - - - 1,600
- - - - - - - - - -
Total Funding 5,017 187 30 4,800 - - - - - 4,800
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Growth
Fully Funded
Justification
Summary Project Description
This project will replace the current Animal Control Facility which has reached the end of its lifespan. The new facility will meet new standards for animal care and provide a
modern facility for Pasco, Richland, and Kennewick. This is a group project with funding coming from all three cities.
This meets the Council Goal of:
Quality of Life
2018 Facility Plan
Specific goal of completing a new Animal Shelter
Consultant rendering of the proposed project
Animal Shelter
PICTURE
Project Number - 18004
Ongoing
ACS
General
Necessary
2020 - 2025 Capital Improvement Plan - 10 of 117
2020-2025 Capital Improvement Plan
Animal Shelter - Little League Parking Lot
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
2018 Facility Plan
Specific goal of completing a new Animal Shelter
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 15 - 15 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 600 - - 600 - - - - - 600
Other - - - - - - - - - -
Total Expenditures 615 - 15 600 - - - - - 600
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Park Development Zone 1 615 - 15 600 - - - - - 600
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 615 - 15 600 - - - - - 600
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses 54 - - - 10 10 11 11 12 54
Net Impact 54 - - - 10 10 11 11 12 54
*amounts shown in thousands
Project Number - 20001
New
ACS
General
Necessary
Consultant rendering of the proposed project area
Quality Improvement
OPERATING IMPACT ANNUAL OPERATING IMPACT
PROJECT SCOPE ANNUAL ALLOCATION
The chosen location for the new animal shelter is on the shared parking lot for the Pasco Little League facility. Through discussion with the Pasco Little League, it was
determined that a shared parking lot will accommodate both the little league and animal shelter demands. Staff also contends that parking and sidewalk improvements will
enhance the aesthetic view corridor along A Street as well as ensure that a public project meets the development standard that the City requires of the private sector. This
will be funded by the Pasco Park Development Fund.
Animal Shelter - Little League Parking Lot
PICTUREFully Funded
Justification
This meets the Council Goal of:
Summary Project Description
2020 - 2025 Capital Improvement Plan - 11 of 117
2020-2025 Capital Improvement Plan
Gesa Stadium
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 2,000 - 1,000 1,000 - - - - - 1,000
Other - - - - - - - - - -
Total Expenditures 2,000 - 1,000 1,000 - - - - - 1,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Future Bond 2,000 - 1,000 1,000 - - - - - 1,000
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 2,000 - 1,000 1,000 - - - - - 1,000
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project is in the second year of a two-year project to update and improve Gesa Stadium. In 2020, we will improve and expand the visiting team's clubhouse, adding
new batting cages and re-designing the right-field fence line. These improvements not only modernize the stadium, but also conform the facility to minor league baseball
standards.
Photo at Gesa Stadium
Gesa Stadium
PICTURE
Project Number - 19001
Ongoing
ACS
General
Necessary
2020 - 2025 Capital Improvement Plan - 12 of 117
2020-2025 Capital Improvement Plan
Community Center
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 150 - 150 - - - - - - -
Land & Right-of-Way 750 - - 750 - - - - - 750
Construction 4,000 - - 250 3,750 - - - - 4,000
Other - - - - - - - - - -
Total Expenditures 4,900 - 150 1,000 3,750 - - - - 4,750
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement REET 2 1,150 - 150 1,000 - - - - - 1,000
Unsecured Funding 3,750 - - - 3,750 - - - - 3,750
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 4,900 - 150 1,000 3,750 - - - - 4,750
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue 442 - - - 80 84 88 93 97 442
Expenses 2,293 - - - 415 436 458 480 504 2,293
Net Impact 2,735 - - - 495 520 546 573 601 2,735
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
This is a replacement facility for the former senior center which was sold to the Pasco School District in 2016. This facility needs to be planned, designed, and located in a
way that ensures the biggest return on investment to the City, as well as the biggest impact on the recreational lives of the public.
Conceptual rendering and not reflective a future design for Pasco
Community Center
PICTURE
Project Number - 18005
Ongoing
ACS
General
Necessary
2020 - 2025 Capital Improvement Plan - 13 of 117
2020-2025 Capital Improvement Plan
Wayfinding and Signage
Status
Department
Group
Assessment
Principal Need
Funding Status
Community Transportation Network
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 96 - 96 - - - - - - -
Land & Right-of-Way 45 - - 15 15 15 - - - 45
Construction 500 - - 300 100 100 - - - 500
Other - - - - - - - - - -
Total Expenditures 641 - 96 315 115 115 - - - 545
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Funding 641 - 96 315 115 115 - - - 545
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 641 - 96 315 115 115 - - - 545
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Other
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
This is a regional project in the Tri-Cities through which coordinated wayfinding signage gets placed in pre-determined locations. Signage will range from regional signage to
localized signage to downtown signage. The current intention is to establish regional signage first, then work on coordinating wayfinding in the downtown area in
conjunction with the Lewis Street Overpass and the Peanuts Park renovation.
Consultant rendering of the proposed project area
Wayfinding and Signage
PICTURE
Project Number - 18008
Ongoing
ACS
General
Desirable
2020 - 2025 Capital Improvement Plan - 14 of 117
2020 - 2025 Capital Improvement Plan - 15 of 117
2020-2025 Capital Improvement Plan
A Street Sporting Complex - Phase 1
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Economic Vitality
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 103 3 100 - - - - - - -
Land & Right-of-Way 104 32 32 40 - - - - - 40
Construction 399 - - 399 - - - - - 399
Other - - - - - - - - - -
Total Expenditures 606 35 132 439 - - - - - 439
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
RCO Grant 350 - 100 250 - - - - - 250
Park Development Zone 1 256 32 35 189 - - - - - 189
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 606 32 135 439 - - - - - 439
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
Phase 1 of this project will be three fields and a parking lot, as funded with the $350,000 in Recreation and Conservation Office (RCO) grant funds obtained in 2019. Phase 2
will be to add additional multi-use sports fields.
Conceptual rendering of the proposed project
A Street Sporting Complex - Phase 1
PICTURE
Project Number - 18028
Ongoing
ACS
Parks & Recreation
Desirable
2020 - 2025 Capital Improvement Plan - 16 of 117
2020-2025 Capital Improvement Plan
Chapel Hill Park
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Economic Vitality
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 1 1 - - - - - - - -
Land & Right-of-Way 12 12 - - - - - - - -
Construction 700 - - 700 - - - - - 700
Other - - - - - - - - - -
Total Expenditures 713 13 - 700 - - - - - 700
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Park Development Zone 3 713 13 - 700 - - - - - 700
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 713 13 - 700 - - - - - 700
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses 80 - - - 15 15 16 17 17 80
Net Impact 80 - - - 15 15 16 17 17 80
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
5-Acre community park that is highly desired by this area of the City. Design completed in 2018 and cost estimates for 5-acre park submitted at over $700,000.
Consultant rendering of the proposed project area
Chapel Hill Park
PICTURE
Project Number - 18011
Ongoing
ACS
Parks & Recreation
Necessary
2020 - 2025 Capital Improvement Plan - 17 of 117
2020-2025 Capital Improvement Plan
Kurtzman Shelter
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 60 - - 60 - - - - - 60
Other - - - - - - - - - -
Total Expenditures 60 - - 60 - - - - - 60
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement Fund REET 1 60 - - 60 - - - - - 60
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 60 - - 60 - - - - - 60
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
Installation of a shelter adjacent to the existing splash pad. There is currently no shade or shelter in the park.
Photo of a similar regionally-based project
Kurtzman Shelter
PICTURE
Project Number - 19020
New
ACS
Parks & Recreation
Desirable
2020 - 2025 Capital Improvement Plan - 18 of 117
2020-2025 Capital Improvement Plan
Pasco Sporting Complex
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 11 11 - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 240 - 140 100 - - - - - 100
Other - - - - - - - - - -
Total Expenditures 251 11 140 100 - - - - - 100
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Park Development Zone 2 240 - 140 100 - - - - - 100
Capital Improvement Fund REET 1 11 11 - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 251 11 140 100 - - - - - 100
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
Remove the volleyball courts and install batting cages at the Pasco Sporting Complex. The batting cages can be rented to serve as a revenue stream for the complex. The
project also includes the installation of shelters, an off-leash dog area; upgrades to better serve customers.
Photos of the Pasco Sporting Complex
Pasco Sporting Complex
PICTURE
Project Number - 18022
Ongoing
ACS
Parks & Recreation
Necessary
2020 - 2025 Capital Improvement Plan - 19 of 117
2020-2025 Capital Improvement Plan
Peanuts Park Restoration
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Economic Vitality
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 678 361 317 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 6,500 - 225 6,275 - - - - - 6,275
Other - - - - - - - - - -
Total Expenditures 7,178 361 542 6,275 - - - - - 6,275
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
CDBG Grant 811 361 450 - - - - - - -
Section 108 Loan (secured)3,800 - - 3,800 - - - - - 3,800
Capital Improvement Fund REET 2 1,207 - - 1,207 - - - - - 1,207
Grant Government Capital Budget 154 - 92 62 - - - - - 62
General Fund 1,206 - - 1,206 - - - - - 1,206
Total Funding 7,178 361 542 6,275 - - - - - 6,275
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
Peanuts Park is located in downtown Pasco and is a focal point for the area. The restoration of this urban park is a key element to the revitalization and redevelopment of
downtown Pasco. The park as we know it today will be demolished and a new park plan will be put in place for the area. The final project will include the installation of
features such as shade structures, new trees, furniture, green space, restrooms, and a renovated farmers market pavilion. The acquisition of property for replacement
parking may also be included, as well as an area parking study.
Consultant rendering of the proposed project area
Peanuts Park Restoration
PICTURE
Project Number - 18023
Ongoing
ACS
Parks & Recreation
Necessary
2020 - 2025 Capital Improvement Plan - 20 of 117
2020-2025 Capital Improvement Plan
Road 84 Park
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Economic Vitality
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 50 - - 50 - - - - - 50
Land & Right-of-Way 300 - - 300 - - - - - 300
Construction 400 - - - 400 - - - - 400
Other - - - - - - - - - -
Total Expenditures 750 - - 350 400 - - - - 750
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement Fund REET 1 750 - - 350 400 - - - - 750
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 750 - - 350 400 - - - - 750
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This neighborhood 5-acre park is slated to be built in conjunction with a new school.
Consultant rendering of the proposed project area
Road 84 Park
PICTURE
Project Number - 19023
New
ACS
Parks & Recreation
Desirable
2020 - 2025 Capital Improvement Plan - 21 of 117
2020-2025 Capital Improvement Plan
Schlagel Park and Boat Basin Improvements
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Economic Vitality
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 10 - 5 5 - - - - - 5
Land & Right-of-Way - - - - - - - - - -
Construction 616 - 308 308 - - - - - 308
Other - - - - - - - - - -
Total Expenditures 626 - 313 313 - - - - - 313
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
RCO Grant 391 - 195 196 - - - - - 196
Capital Improvement Fund REET 1 235 - 118 117 - - - - - 117
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 626 - 313 313 - - - - - 313
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
In 2019, the City of Pasco obtained an RCO grant for $626,000 to repair and replaced the boat launch, upgrade the parking and lighting, and install a new restroom facility.
The boat launch on the north side of the Columbia River is the only boat launch in the immediate area. Coupled with the marina, it is heavily used. Not only is Schlagel Park
vital to the boating recreation needs of the region, but it is also a gateway to the City of Pasco and its look needs to be improved.
Photos of the Schlagel Park and Boat Basin
Schlagel Park and Boat Basin Improvements
PICTURE
Project Number - 18027
Ongoing
ACS
Parks & Recreation
Necessary
2020 - 2025 Capital Improvement Plan - 22 of 117
2020-2025 Capital Improvement Plan
Sylvester Park Sporting Courts
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Economic Vitality
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 100 - - 100 - - - - - 100
Other - - - - - - - - - -
Total Expenditures 100 - - 100 - - - - - 100
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Park Development Zone 1 100 - - 100 - - - - - 100
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 100 - - 100 - - - - - 100
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
Replace and upgrade deteriorated tennis courts with basketball and/or futsal courts.
Consultant rendering of the proposed project area
Sylvester Park Sporting Courts
PICTURE
Project Number - 18029
Ongoing
ACS
Parks & Recreation
Necessary
2020 - 2025 Capital Improvement Plan - 23 of 117
2020-2025 Capital Improvement Plan
Community Park Northwest
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Economic Vitality
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 200 - - - - - - 200 - 200
Land & Right-of-Way 1,400 - - 1,400 - - - - - 1,400
Construction 4,500 - - - - - - - 4,500 4,500
Other - - - - - - - - - -
Total Expenditures 6,100 - - 1,400 - - - 200 4,500 6,100
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Park Development Zone 2 1,400 - - 1,400 - - - - - 1,400
Unsecured Funding 4,700 - - - - - - 200 4,500 4,700
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 6,100 - - 1,400 - - - 200 4,500 6,100
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
Purchase and construct a community park in the northwest area of Pasco or Broadmoor area. This park will be 20-40 acres and include parking, a playground, restrooms,
walking trails, shelters, and start active and passive recreation.
Photo of a similar regionally-based project
Community Park Northwest
PICTURE
Project Number - 18012
New
ACS
Parks & Recreation
Desirable
2020 - 2025 Capital Improvement Plan - 24 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Community Transportation Network
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 55 - - - 55 - - - - 55
Land & Right-of-Way - - - - - - - - - -
Construction 815 - - - - 360 35 420 - 815
Other - - - - - - - - - -
Total Expenditures 870 - - - 55 360 35 420 - 870
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement Fund REET 2 90 - - - 55 - 35 - - 90
Unsecured RCO Grant 360 - - - - 360 - - - 360
Unsecured Funding 420 - - - - - - 420 - 420
- - - - - - - - - -
- - - - - - - - - -
Total Funding 870 - - - 55 360 35 420 - 870
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Franklin County Irrigation District (FCID) Trail Phases 1 and 2
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
Construction of a trail on top of the covered FCID canal. Phase 1 from Road 100 to Road 111. Phase 2 from Road 100 to Road 84.
Franklin County Irrigation District (FCID) Trail Phases 1 and 2
PICTURE
Desirable
Aerial photo of the proposed project area
Project Number - 18015
Ongoing
ACS
Parks & Recreation
2020 - 2025 Capital Improvement Plan - 25 of 117
2020-2025 Capital Improvement Plan
Road 48 Park
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Economic Vitality
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 54 4 - - 50 - - - - 50
Land & Right-of-Way 922 922 - - - - - - - -
Construction 2,500 - - - - 1,250 1,250 - - 2,500
Other - - - - - - - - - -
Total Expenditures 3,476 926 - - 50 1,250 1,250 - - 2,550
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Park Development Zone 3 926 926 - - - - - - - -
Unsecured Funding 2,550 - - - 50 1,250 1,250 - - 2,550
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 3,476 926 - - 50 1,250 1,250 - - 2,550
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
Recently acquired property in Central Pasco. Serving as a focus for a central community park-sized development. Early ideas include a splash pad, sports courts, restrooms,
parking lots, ropes course, etc.
Aerial photo of the proposed project area
Road 48 Park
PICTURE
Project Number - 18019
New
ACS
Parks & Recreation
Desirable
2020 - 2025 Capital Improvement Plan - 26 of 117
2020-2025 Capital Improvement Plan
Road 54 Erwen Property
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Economic Vitality
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 20 - - - 20 - - - - 20
Land & Right-of-Way - - - - - - - - - -
Construction 400 - - - - 400 - - - 400
Other - - - - - - - - - -
Total Expenditures 420 - - - 20 400 - - - 420
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Park Development Zone 3 20 - - - 20 - - - - 20
Unsecured RCO Grant 400 - - - - 400 - - - 400
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 420 - - - 20 400 - - - 420
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project is to improve the parking and picnic areas at Road 54 and Sylvester Street. Park upgrades will be exercise and recreation focused and offer a hub and connection
for the Heritage Trail.
Photos of Road 54 Erwin Property
Road 54 Erwen Property
PICTURE
Project Number - 18024
Ongoing
ACS
Parks & Recreation
Necessary
2020 - 2025 Capital Improvement Plan - 27 of 117
2020-2025 Capital Improvement Plan
Sacajawea Trail BNSF Crossing
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Community Transportation Network
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 50 - - 50 - - - - - 50
Land & Right-of-Way - - - - - - - - - -
Construction 1,600 - - - 1,600 - - - - 1,600
Other - - - - - - - - - -
Total Expenditures 1,650 - - 50 1,600 - - - - 1,650
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement Fund REET 2 700 - - 50 650 - - - - 700
Unsecured RCO Grant 200 - - - 200 - - - - 200
Unsecured Funding 750 - - - 750 - - - - 750
- - - - - - - - - -
- - - - - - - - - -
Total Funding 1,650 - - 50 1,600 - - - - 1,650
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
Construct a tunnel connecting the existing trail with Schlagel Park, revising the route taking trail users off State Route 397.
Consultant rendering of the proposed project area
Sacajawea Trail BNSF Crossing
PICTURE
Project Number - 18025
Ongoing
ACS
Parks & Recreation
Desirable
2020 - 2025 Capital Improvement Plan - 28 of 117
2020-2025 Capital Improvement Plan
Sacajawea Levee Lowering
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Community Transportation Network
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 257 26 35 196 - - - - - 196
Land & Right-of-Way - - - - - - - - - -
Construction 4,500 - - - 2,500 2,000 - - - 4,500
Other - - - - - - - - - -
Total Expenditures 4,757 26 35 196 2,500 2,000 - - - 4,696
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement Fund REET 1 1,134 26 35 45 571 457 - - - 1,073
Unsecured State Grant 3,623 - - 151 1,929 1,543 - - - 3,623
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 4,757 26 35 196 2,500 2,000 - - - 4,696
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
The project will lower the existing levee height and widen the trail to improve user safety. The given section is the final portion of the Sacajawea Trail at the original height.
The completion of this project will connect the trail from Road 72 to Road 52.
Rendering and aerial photo of the proposed project area
Sacajawea Levee Lowering
Project Number - 18026
Ongoing
ACS
Parks & Recreation
Necessary
2020 - 2025 Capital Improvement Plan - 29 of 117
2020-2025 Capital Improvement Plan
Dog Park
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 50 - - - 50 - - - - 50
Land & Right-of-Way - - - - - - - - - -
Construction 400 - - - 400 - - - - 400
Other - - - - - - - - - -
Total Expenditures 450 - - - 450 - - - - 450
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Funding 450 - - - 450 - - - - 450
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 450 - - - 450 - - - - 450
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Dog Park
PICTURE
Project Number - 18013
New
ACS
Facilities
Desirable
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
Dog parks are sorely needed in both Pasco and the Tri-Cities region. The tentative plan would be to utilize land near the current and proposed animal shelter in the vicinity of
the Pasco Little League park area along both the river and the trailhead at Riverview Park.
Photo of a similar regionally-based project
2020 - 2025 Capital Improvement Plan - 30 of 117
2020-2025 Capital Improvement Plan
Highland Park Parking and Field Expansion
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 75 - - - 75 - - - - 75
Land & Right-of-Way - - - - - - - - - -
Construction 750 - - - - 750 - - - 750
Other - - - - - - - - - -
Total Expenditures 825 - - - 75 750 - - - 825
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Funding 825 - - - 75 750 - - - 825
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 825 - - - 75 750 - - - 825
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Highland Park Parking and Field Expansion
PICTURE
Project Number - 20046
New
ACS
Facilities
Desirable
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
This has been a long-discussed project involving Highland Park, which serves Pasco youth football. This project would include expansion of the parking lot and park area onto
the City-owned property to the west. In addition, adjacent streetscape improvements and landscaping would be worked into the design.
Consultant rendering of the proposed project
2020 - 2025 Capital Improvement Plan - 31 of 117
2020-2025 Capital Improvement Plan
Marina Dock Replacement - Dock B
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Economic Vitality
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 1,650 - - - - 1,650 - - - 1,650
Other - - - - - - - - - -
Total Expenditures 1,650 - - - - 1,650 - - - 1,650
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Funding 1,650 - - - - 1,650 - - - 1,650
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 1,650 - - - - 1,650 - - - 1,650
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
Replace dock damaged in the winter of 2019.
Photos at the Marina Dock
Marina Dock Replacement - Dock B
PICTURE
Project Number - 20002
Ongoing
ACS
Parks & Recreation
Urgent
2020 - 2025 Capital Improvement Plan - 32 of 117
Transportation
2020 - 2025 Capital Improvement Plan - 33 of 117
2020-2025 Capital Improvement Plan
Annual Pavement Preservation Program
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 5,499 - - 850 876 902 929 957 985 5,499
Other - - - - - - - - - -
Total Expenditures 5,499 - - 850 876 902 929 957 985 5,499
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Street Overlay Fund 5,499 - - 850 876 902 929 957 985 5,499
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 5,499 - - 850 876 902 929 957 985 5,499
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Asset Protection
Fully Funded
Justification
The City has implemented a Pavement Preservation Program to assess and maintain quality streets within the City that are free of potholes and provide good ride quality.
This program preserves and extends the life of the streets with low-cost methods that help avoid reconstruction of those streets. The program includes crack seal, overlay
and microsurfacing of City streets. Prioritization is determined by considering both the Pavement Preservation Program itself and the pavement rating system. This will also
encompass 50% of the Alley Hard Surface project funding.
Photo of an annual pavement preservation project
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Summary Project Description
Project Number - 20006
Ongoing
Public Works
Transportation
Annual Pavement Preservation Program
PICTURE
Necessary
2020 - 2025 Capital Improvement Plan - 34 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 415 200 215 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 1,600 - 1,600 - - - - - - -
Other - - - - - - - - - -
Total Expenditures 2,015 200 1,815 - - - - - - -
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
CBC Grant 800 - 800 - - - - - - -
Port of Pasco 800 - 800 - - - - - - -
Arterial Street Fund 415 200 215 - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 2,015 200 1,815 - - - - - - -
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Argent Road - Phase 1 (Saraceno/Varney to 20th Avenue)
This project was originally considered in its entirety from Road 36 to 20th Avenue. It also includes two important stakeholders in Columbia Basin Community College (CBC)
and the Port of Pasco (Port). Due to the immediate improvements necessary as part of the development of the Port’s property, namely the new Marriot hotel, it became
necessary to break the project into two phases; Phase 1 includes improvements from Varney Lane/Saraceno Way to 20th Avenue while Phase 2 extends from Road 36 to
Varney Lane/Saraceno Way.
Improvements include street widening with a new roadway surface along with curb/gutter and sidewalk. Utilities, including stormwater, will also be built as part of the
improvements.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Argent Road - Phase 1 (Saraceno/Varney to 20th Avenue)
PICTURE
Desirable
Promote a highly-functional multi-modal transportation network
Aerial photo of the proposed project area
Project Number - 12001
Ongoing
Public Works
Transportation
Public Safety
Fully Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 35 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 128 - - 128 - - - - - 128
Land & Right-of-Way - - - - - - - - - -
Construction 722 - - - 722 - - - - 722
Other - - - - - - - - - -
Total Expenditures 850 - - 128 722 - - - - 850
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
CBC Grant 425 - - 64 361 - - - - 425
Port of Pasco 425 - - 64 361 - - - - 425
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 850 - - 128 722 - - - - 850
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Promote a highly-functional multi-modal transportation network
This project will construct intersection improvements to improve the current level of service. The intersection improvements will be either a signalized intersection or a
roundabout.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Aerial photo of the proposed project area
Argent Road - Phase 2 (Road 36 Intersection Improvements)
Summary Project Description
Argent Road - Phase 2 (Road 36 Intersection Improvements)
PICTURE
Project Number - 20011
New
Public Works
Transportation
Desirable
Growth
Fully Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 36 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 300 - - - - - - - 300 300
Land & Right-of-Way - - - - - - - - - -
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures 300 - - - - - - - 300 300
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 300 - - - - - - - 300 300
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 300 - - - - - - - 300 300
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Argent Road - Phase 3 (Road 36 to Saraceno/Varney)
This project will construct widening, access, and frontage improvements, as well as intersection control improvements at Road 36. These improvements focus on the needs
of the adjacent stakeholders which include the Port of Pasco (Port) and Columbia Basin Community College (CBC).
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Argent Road - Phase 3 (Road 36 to Saraceno/Varney)
PICTURE
Desirable
Promote a highly-functional multi-modal transportation network
Aerial photo of the proposed project area
Project Number - 20010
New
Public Works
Transportation
Growth
Fully Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 37 of 117
2020-2025 Capital Improvement Plan
Citywide Traffic Signal Controller Upgrades - Phase 2
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way 300 - 300 - - - - - - -
Construction 3,256 - - 3,256 - - - - - 3,256
Other - - - - - - - - - -
Total Expenditures 3,556 - 300 3,256 - - - - - 3,256
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 415 - 40 375 - - - - - 375
I-182 Corridor Impact Fund 158 - - 158 - - - - - 158
Federal STP Grant 2,983 - 260 2,723 - - - - - 2,723
- - - - - - - - - -
- - - - - - - - - -
Total Funding 3,556 - 300 3,256 - - - - - 3,256
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Fully Funded
Justification
Replace all obsolete signal equipment with updated signal controllers, signal equipment, signal interconnect equipment, optimized corridor timing plans, vehicle detection
system and emergency vehicle priority system. Pedestrian access will be upgraded to meet the current Americans with Disabilities Act (ADA) right-of-way accessibility design
guidelines for the signalized intersections.
Phase 1 of this project, which focused on intersections that did not require the acquisition of rights-of-way for sidewalk ramp ADA upgrades, was completed in 2018. This
project is Phase 2 of the same project, which includes those intersections that require the acquisition of rights-of-way for sidewalk ramp ADA upgrades.
Consultant map of the proposed project area
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Summary Project Description
Project Number - 18031
New
Public Works
Transportation
Citywide Traffic Signal Controller Upgrades - Phase 2
PICTURE
Desirable
2020 - 2025 Capital Improvement Plan - 38 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 60 - - - 60 - - - - 60
Land & Right-of-Way - - - - - - - - - -
Construction 472 - - - - 472 - - - 472
Other - - - - - - - - - -
Total Expenditures 532 - - - 60 472 - - - 532
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Street Overlay Fund 532 - - - 60 472 - - - 532
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 532 - - - 60 472 - - - 532
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Industrial Way - Foster Wells to Kartchner Preservation
This project will resurface Industrial Way between Foster Wells Road and the railroad tracks next to Reser's Fine Foods.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Industrial Way - Foster Wells to Kartchner Preservation
PICTURE
Desirable
Promote a highly-functional multi-modal transportation network
Aerial photo of the proposed project area
Project Number - 20025
New
Public Works
Transportation
Asset Protection
Fully Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 39 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 70 - 25 15 15 15 - - - 45
Land & Right-of-Way - - - - - - - - - -
Construction 1,555 - - 535 535 485 - - - 1,555
Other - - - - - - - - - -
Total Expenditures 1,625 - 25 550 550 500 - - - 1,600
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
CDBG Grant 861 - - 296 296 269 - - - 861
Capital Improvement Fund REET 1 464 - 25 154 154 131 - - - 439
Stormwater Utility 300 - - 100 100 100 - - - 300
- - - - - - - - - -
- - - - - - - - - -
Total Funding 1,625 - 25 550 550 500 - - - 1,600
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Lewis Street Corridor Improvements - 2nd Avenue to 5th
Avenue
The project is intended to tie the improvements made with the overpass project into those made under the Peanuts Park Improvement Project. Taking into account the
anticipated increase in pedestrian and bicycle traffic, as well as the positive impact to businesses within this corridor, this project is intended to enhance the accessibility to
businesses and improve the safety and efficiency of the transportation corridor.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Summary Project Description
Lewis Street Corridor Improvements - 2nd Avenue to 5th Avenue
PICTURE
Desirable
Aerial photo of the proposed project area
Quality Improvement
Fully Funded
Justification
Project Number - 20007
New
Public Works
Transportation
2020 - 2025 Capital Improvement Plan - 40 of 117
2020-2025 Capital Improvement Plan
Lewis Street Overpass
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 3,498 2,564 934 - - - - - - -
Land & Right-of-Way 4,059 4,025 34 - - - - - - -
Construction 21,081 - 1,054 10,540 9,487 - - - - 20,027
Other - - - - - - - - - -
Total Expenditures 28,639 6,589 2,023 10,540 9,487 - - - - 20,027
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 1,756 529 327 - 900 - - - - 900
Street Overlay Fund 1,000 - - 1,000 - - - - - 1,000
I-182 Corridor Impact Fund 13 12 1 - - - - - - -
Capital Improvement Fund REET 2 1,566 1,244 293 15 14 - - - - 29
Water Utility 250 - 12 125 113 - - - - 238
Stormwater Utility 300 - 15 150 135 - - - - 285
Connecting WA Grant 15,000 1,050 1,125 4,500 8,325 - - - - 12,825
TIB Grant 5,000 - 250 4,750 - - - - - 4,750
Federal STP Grant 3,754 3,754 - - - - - - - -
Total Funding 28,639 6,589 2,023 10,540 9,487 - - - - 20,027
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Fully Funded
Justification
This project will construct a new overpass between 2nd Avenue and Oregon Avenue on Lewis Street to replace the existing underpass, built in 1937, which is deteriorating.
The right-of-way acquisition was completed in 2013 and all necessary demolition of existing structures on the west side of the proposed overpass was completed in 2014.
The design for this project was completed in 2019 and construction will be bid in late 2019. Construction will likely start in early 2020.
Consultant rendering of the proposed project area
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Completion of the Lewis Street Overpass design concept process,
securing gap funding for construction and achievement of "shovel-
ready" status
Summary Project Description
Project Number - 13007
Ongoing
Public Works
Transportation
Lewis Street Overpass
PICTURE
Necessary
2020 - 2025 Capital Improvement Plan - 41 of 117
2020-2025 Capital Improvement Plan
Road 68 Widening - Interstate 182 to Chapel Hill Blvd
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 58 - 58 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 250 - - 250 - - - - - 250
Other - - - - - - - - - -
Total Expenditures 308 - 58 250 - - - - - 250
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 92 - 58 34 - - - - - 34
Federal STP Grant 216 - - 216 - - - - - 216
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 308 - 58 250 - - - - - 250
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Summary Project Description
This project will construct a widening of Road 68 from the Interstate 182 interchange south to Chapel Hill Boulevard.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Aerial photo of the proposed project area
Road 68 Widening - Interstate 182 to Chapel Hill Blvd
PICTURE
Project Number - 20009
New
Public Works
Transportation
Desirable
Growth
Fully Funded
Justification
This meets the Council Goal of:
Promote a highly-functional multi-modal transportation network
2020 - 2025 Capital Improvement Plan - 42 of 117
2020-2025 Capital Improvement Plan
Road 76 Overpass
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 300 - - - - - - - 300 300
Land & Right-of-Way - - - - - - - - - -
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures 300 - - - - - - - 300 300
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
I-182 Corridor Impact Fund 300 - - - - - - - 300 300
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 300 - - - - - - - 300 300
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - -
*amounts shown in thousands
Summary Project Description
An overpass was suggested as part of the Department of Natural Resources (DNR) property improvements. That area is defined as south of Interstate 182, east of Road 84
and west of Road 68. This overpass would help to take the pressure off of the interchange at Road 68 by providing another access route to the popular businesses along
Road 68.
The initial money allocated is to analyze the effectiveness of the overpass and provide a feasibility plan for its construction.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Aerial photo of the proposed project area
Road 76 Overpass
PICTURE
Project Number - 19037
New
Public Works
Transportation
Desirable
Public Safety
Fully Funded
Justification
This meets the Council Goal of:
Promote a highly-functional multi-modal transportation network
2020 - 2025 Capital Improvement Plan - 43 of 117
2020-2025 Capital Improvement Plan
Sandifur Parkway Widening - Road 52 to Road 60
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 25 - - 25 - - - - - 25
Land & Right-of-Way - - - - - - - - - -
Construction 400 - - - 400 - - - - 400
Other - - - - - - - - - -
Total Expenditures 425 - - 25 400 - - - - 425
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Street Overlay Fund 300 - - 18 282 - - - - 300
Arterial Street Fund 125 - - 7 118 - - - - 125
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 425 - - 25 400 - - - - 425
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Summary Project Description
This project will complete Sandifur Parkway from Road 52 to Road 60 where there is currently a half street. Finishing the roadway will improve safety and provide the same
street width for the continuation of Sandifur Parkway. The estimate of 425k includes curb/gutter, sidewalk. Right-of-way may be required.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Aerial/site photo of the proposed project area
Sandifur Parkway Widening - Road 52 to Road 60
PICTURE
Project Number - 17001
New
Public Works
Transportation
Desirable
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Promote a highly-functional multi-modal transportation network
2020 - 2025 Capital Improvement Plan - 44 of 117
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 25 - - 25 - - - - - 25
Land & Right-of-Way - - - - - - - - - -
Construction 235 - - 235 - - - - - 235
Other - - - - - - - - - -
Total Expenditures 260 - - 260 - - - - - 260
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 35 - - 35 - - - - - 35
Federal STP Grant 225 - - 225 - - - - - 225
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 260 - - 260 - - - - - 260
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
OPERATING IMPACT ANNUAL OPERATING IMPACT
Promote a highly-functional multi-modal transportation network
Continued emphasis on improvements in Road 68/I-182/Burden
Boulevard corridor
Summary Project Description
Often identified as Pasco’s most congested corridor, this project, in conjunction with the Wrigley Drive Extension Project, is intended to reduce traffic congestion, increase
efficiency, and improve safety. This project will include signing, striping, and channelization considerations on Burden Boulevard and Road 68 to reduce the stacking of
vehicles in the westbound lanes at the intersection.
PROJECT SCOPE ANNUAL ALLOCATION
2020-2025 Capital Improvement Plan
Signage and Striping Improvements at Road 68 and
Burden Boulevard
Aerial photo of the proposed project area
Signage and Striping Improvements at Road 68 and Burden
Boulevard
PICTURE
Project Number - 20008
New
Public Works
Transportation
Desirable
Public Safety
Fully Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 45 of 117
2020-2025 Capital Improvement Plan
Wrigley Drive Extension
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 53 - 33 20 - - - - - 20
Land & Right-of-Way - - - - - - - - - -
Construction 256 - - 256 - - - - - 256
Other - - - - - - - - - -
Total Expenditures 309 - 33 276 - - - - - 276
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Water Utility 11 - 2 9 - - - - - 9
Irrigation Utility 11 - 2 9 - - - - - 9
Sewer Utility 13 - 3 10 - - - - - 10
Federal STP Grant 263 - 24 239 - - - - - 239
Arterial Street Fund 11 - 2 9 - - - - - 9
Total Funding 309 - 33 276 - - - - - 276
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Wrigley Drive Extension
PICTURE
Desirable
This project, identified by Washington State Department of Transportation (WSDOT) as an important co-effort with the Road 68 and Burden Road
Intersection/Channelization Improvements Project, in addressing congestion, efficiency, and safety concerns associated with the Road 68 Corridor. This connection will
provide another alternative to residents for accessing Road 68 at a signalized intersection. Although no frontage improvements are being considered as part of this effort,
this project will provide a core-road, that when adjacent properties develop, those additional improvements will be added. This improvement will provide an important
connection to Road 68 for area residents and will relieve some of the demand placed upon the intersection of Road 68 and Burden Boulevard. Improvements include a new
roadway surface without curb/gutter and sidewalk. Utilities, including potable water, irrigation water, and sanitary sewer, are also being extended.
PROJECT SCOPE ANNUAL ALLOCATION
Project Number - 15009
Ongoing
Public Works
Transportation
Public Safety
Fully Funded
Justification
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Continued emphasis on improvements in Road 68/I-182/Burden
Boulevard corridor
Aerial photo of the proposed project area
2020 - 2025 Capital Improvement Plan - 46 of 117
2020-2025 Capital Improvement Plan
Burns Road Pedestrian/Bicycle Pathway -
Road 84 to Road 68
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 11 - - 11 - - - - - 11
Land & Right-of-Way - - - - - - - - - -
Construction 91 - - - - - 91 - - 91
Other - - - - - - - - - -
Total Expenditures 102 - - 11 - - 91 - - 102
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement Fund REET 2 26 - - 3 - - 23 - - 26
Unsecured State Grant (SRTS)76 - - 8 - - 68 - - 76
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 102 - - 11 - - 91 - - 102
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Burns Road Pedestrian/Bicycle Pathway - Road 84 to Road 68
PICTURE
Desirable
This project will construct a 12 foot wide multi-use pathway on the south side of Burns Road.
PROJECT SCOPE ANNUAL ALLOCATION
Aerial photo of the proposed project area
Project Number - 20033
New
Public Works
Transportation
Quality Improvement
Partially Funded
Justification
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Undertaking a comprehensive and inclusive transportation planning
and analysis process to include facilitation of traffic flow in major
corridors, support integration of pedestrian, bicycle and other non-
vehicular means of transportation
2020 - 2025 Capital Improvement Plan - 47 of 117
2020-2025 Capital Improvement Plan
Burns Road Pedestrian/Bicycle Pathway -
Road 90 to Road 84
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 8 - - 8 - - - - - 8
Land & Right-of-Way - - - - - - - - - -
Construction 63 - - - - 63 - - - 63
Other - - - - - - - - - -
Total Expenditures 71 - - 8 - 63 - - - 71
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement Fund REET 2 16 - - 2 - 14 - - - 16
Unsecured State Grant (SRTS)55 - - 6 - 49 - - - 55
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 71 - - 8 - 63 - - - 71
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Burns Road Pedestrian/Bicycle Pathway - Road 90 to Road 84
PICTURE
Desirable
This project will construct a 12 foot wide multi-use pathway on the south side of Burns Road.
PROJECT SCOPE ANNUAL ALLOCATION
Aerial photo of the proposed project area
Project Number - 20013
New
Public Works
Transportation
Quality Improvement
Partially Funded
Justification
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Undertaking a comprehensive and inclusive transportation planning
and analysis process to include facilitation of traffic flow in major
corridors, support integration of pedestrian, bicycle and other non-
vehicular means of transportation
2020 - 2025 Capital Improvement Plan - 48 of 117
2020-2025 Capital Improvement Plan
Burns Road Pedestrian/Bicycle Pathway -
Road 100 to Road 90
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 11 - - 11 - - - - - 11
Land & Right-of-Way - - - - - - - - - -
Construction 108 - - - 108 - - - - 108
Other - - - - - - - - - -
Total Expenditures 119 - - 11 108 - - - - 119
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement Fund REET 2 30 - - 3 27 - - - - 30
Unsecured State Grant (SRTS)89 - - 8 81 - - - - 89
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 119 - - 11 108 - - - - 119
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Burns Road Pedestrian/Bicycle Pathway - Road 100 to Road 90
PICTURE
Desirable
This project will construct a 12 foot wide multi-use pathway on the south side of Burns Road.
PROJECT SCOPE ANNUAL ALLOCATION
Aerial photo of the proposed project area
Project Number - 20012
New
Public Works
Transportation
Quality Improvement
Partially Funded
Justification
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Undertaking a comprehensive and inclusive transportation planning
and analysis process to include facilitation of traffic flow in major
corridors, support integration of pedestrian, bicycle and other non-
vehicular means of transportation
2020 - 2025 Capital Improvement Plan - 49 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 75 - - - - 75 - - - 75
Land & Right-of-Way 50 - - - - - 50 - - 50
Construction 735 - - - - - - 735 - 735
Other - - - - - - - - - -
Total Expenditures 860 - - - - 75 50 735 - 860
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 100 - - - - 9 5 86 - 100
I-182 Corridor Impact Fund 25 - - - - 2 2 21 - 25
Unsecured State Grant 735 - - - - 64 43 628 - 735
- - - - - - - - - -
- - - - - - - - - -
Total Funding 860 - - - - 75 50 735 - 860
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Intersection improvements at the intersection of Road 68 and Court Street to improve efficiency and safety.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Court Street and Road 68 Intersection Improvements
Summary Project Description
Court Street and Road 68 Intersection Improvements
PICTURE
Desirable
Aerial photo of the proposed project area
Project Number - 19043
New
Public Works
Transportation
Public Safety
Partially Funded
Justification
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Continued emphasis on improvements in Road 68/I-182/Burden
Boulevard corridor
2020 - 2025 Capital Improvement Plan - 50 of 117
2020-2025 Capital Improvement Plan
Crescent Road Surface Improvement
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 45 - - - - - - 45 - 45
Land & Right-of-Way - - - - - - - - - -
Construction 355 - - - - - - - 355 355
Other - - - - - - - - - -
Total Expenditures 400 - - - - - - 45 355 400
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 100 - - - - - - 11 89 100
Developer Contribution 300 - - - - - - 34 266 300
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 400 - - - - - - 45 355 400
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Aerial photo of the proposed project area
Summary Project Description
This project is intended to design and construct an asphalt road from Road 108 to Chapel Hill Boulevard. The existing roadway does not make connection to Chapel Hill
Boulevard in its present extents. Although no frontage improvements are being considered as part of this effort, this project will provide a core-road. When adjacent
properties develop, those additional improvements will be added. This improvement will provide an important connection to Road 100 for area residents and will relieve
some of the demand placed upon the southern end of Road 100.
PROJECT SCOPE ANNUAL ALLOCATION
Promote a highly-functional multi-modal transportation network
OPERATING IMPACT ANNUAL OPERATING IMPACT
Crescent Road Surface Improvement
PICTURE
Project Number - 17012
New
Public Works
Transportation
Desirable
Public Safety
Partially Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 51 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 90 - - - 90 - - - - 90
Land & Right-of-Way - - - - - - - - - -
Construction 780 - - - - 360 420 - - 780
Other - - - - - - - - - -
Total Expenditures 870 - - - 90 360 420 - - 870
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Capital Improvement Fund REET 2 286 - - - 30 118 138 - - 286
Unsecured State Grant 584 - - - 60 242 282 - - 584
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 870 - - - 90 360 420 - - 870
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Frankin County Irrigation District (FCID) Canal
Bicycle/Pedestrian Pathway Study
This project, originally identified in the 2019-2024 Capital Improvement Plan as FCID Trail – Phase 2, will be further evaluated with new information as to ownership of the
property. As a part of that evaluation, the City will endeavor to coordinate with multiple stakeholders to create a plan to secure and build a 12 foot wide pedestrian/bicycle
asphalt pathway further extending and connecting those pathways through and around the City of Pasco.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Franklin County Irrigation District Canal Bicycle/Pedestrian Pathway
Study
Desirable
Aerial photo of the proposed project area
Project Number - 20021
New
Public Works
Transportation
Public Safety
Partially Funded
Justification
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Undertaking a comprehensive and inclusive transportation planning
and analysis process to include facilitation of traffic flow in major
corridors, support integration of pedestrian, bicycle and other non-
vehicular means of transportation
2020 - 2025 Capital Improvement Plan - 52 of 117
2020-2025 Capital Improvement Plan
Pedestrian/Bicycle Access - Road 68 Interchange
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 100 - - - - - 100 - - 100
Land & Right-of-Way - - - - - - - - - -
Construction 1,000 - - - - - - 1,000 - 1,000
Other - - - - - - - - - -
Total Expenditures 1,100 - - - - - 100 1,000 - 1,100
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
I-182 Corridor Impact Fund 25 - - - - - 2 23 - 25
Unsecured State Grant 1,075 - - - - - 98 977 - 1,075
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 1,100 - - - - - 100 1,000 - 1,100
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Pedestrian/Bicycle Access - Road 68 Interchange
PICTURE
Desirable
This project will widen the existing Road 68 overpass to accommodate a pedestrian walkway.
PROJECT SCOPE ANNUAL ALLOCATION
Aerial photo of the proposed project area
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Undertaking a comprehensive and inclusive transportation planning
and analysis process to include facilitation of traffic flow in major
corridors, support integration of pedestrian, bicycle and other non-
vehicular means of transportation
Public Safety
Partially Funded
Justification
Project Number - 20015
New
Public Works
Transportation
2020 - 2025 Capital Improvement Plan - 53 of 117
2020-2025 Capital Improvement Plan
Pedestrian/Bicycle Access - Road 100 Interchange
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 120 - - - - 120 - - - 120
Land & Right-of-Way - - - - - - - - - -
Construction 2,200 - - - - - 2,200 - - 2,200
Other - - - - - - - - - -
Total Expenditures 2,320 - - - - 120 2,200 - - 2,320
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 300 - - - - 15 285 - - 300
I-182 Corridor Impact Fund 50 - - - - 3 47 - - 50
Unsecured State Grant 1,970 - - - - 102 1,868 - - 1,970
- - - - - - - - - -
- - - - - - - - - -
Total Funding 2,320 - - - - 120 2,200 - - 2,320
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Pedestrian/Bicycle Access - Road 100 Interchange
PICTURE
Desirable
This project will improve the existing Road 100 overpass to accommodate a pedestrian walkway.
PROJECT SCOPE ANNUAL ALLOCATION
Aerial photo of the proposed project area
Project Number - 20014
New
Public Works
Transportation
Public Safety
Partially Funded
Justification
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Undertaking a comprehensive and inclusive transportation planning
and analysis process to include facilitation of traffic flow in major
corridors, support integration of pedestrian, bicycle and other non-
vehicular means of transportation
2020 - 2025 Capital Improvement Plan - 54 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 78 - - - 78 - - - - 78
Land & Right-of-Way - - - - - - - - - -
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures 78 - - - 78 - - - - 78
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 25 - - - 25 - - - - 25
Unsecured State Grant 53 - - - 53 - - - - 53
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 78 - - - 78 - - - - 78
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
This project will provide the design phase of a pedestrian walkway at the Sylvester Street overpass at US 395 to allow for safe pedestrian crossing.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Pedestrian/Bicycle Access - Sylvester Street Overpass
Summary Project Description
Pedestrian/Bicycle Access - Sylvester Street Overpass
PICTURE
Desirable
Example photo from Court St Over 395 & aerial photo of the proposed project area
Project Number - 20016
New
Public Works
Transportation
Public Safety
Partially Funded
Justification
This meets the Council Goal of:
Quality of Life
Promote a highly-functional multi-modal transportation network
Undertaking a comprehensive and inclusive transportation planning
and analysis process to include facilitation of traffic flow in major
corridors, support integration of pedestrian, bicycle and other non-
vehicular means of transportation
2020 - 2025 Capital Improvement Plan - 55 of 117
2020-2025 Capital Improvement Plan
Road 44 and Argent Road Intersection Analysis
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 65 - - - - - - 65 - 65
Land & Right-of-Way - - - - - - - - - -
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures 65 - - - - - - 65 - 65
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
I-182 Corridor Impact Fund 10 - - - - - - 10 - 10
Unsecured State Grant 55 - - - - - - 55 - 55
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 65 - - - - - - 65 - 65
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Road 44 and Argent Road Intersection Analysis
PICTURE
Project Number - 20018
New
Public Works
Transportation
Desirable
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
Connecting a heavily populated residential area of the City with an arterial street, Argent Road, this intersection continues to receive a large volume of traffic with concerns
of the level of service falling below allowable limits.
The City will undertake an evaluation with Franklin County to determine the best course of action, if any, to ensure that the intersection continues to perform at an
acceptable level. Coordination with Franklin County is necessary as the intersection is currently within the County.
Promote a highly-functional multi-modal, transportation network
Aerial photo of the proposed project area
2020 - 2025 Capital Improvement Plan - 56 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 375 - - - - - 375 - - 375
Land & Right-of-Way 500 - - - - - - 500 - 500
Construction 3,250 - - - - - - 1,000 2,250 3,250
Other - - - - - - - - - -
Total Expenditures 4,125 - - - - - 375 1,500 2,250 4,125
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 2,000 - - - - - 182 727 1,091 2,000
I-182 Corridor Impact Fund 500 - - - - - 45 182 273 500
Unsecured State Grant 1,625 - - - - - 148 591 886 1,625
- - - - - - - - - -
- - - - - - - - - -
Total Funding 4,125 - - - - - 375 1,500 2,250 4,125
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Road 100 Widening - Court Street to Chapel Hill Boulevard
This project is intended to improve both deficiencies in right-of-way and road surface width in areas that used to be within the County. Road 100 is a major arterial providing
citizen's direct access to the interchange at Interstate 182. The extents of this project are Court Street on the south and Chapel Hill Boulevard on the north.
Improvements include street widening with a new roadway surface, along with curb/gutter and sidewalk. Utilities, including stormwater, will also be built as part of the
improvements.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Road 100 Widening - Court Street to Chapel Hill Boulevard
PICTURE
Desirable
Promote a highly-functional multi-modal transportation network
Aerial photo of the proposed project area
Project Number - 19035
New
Public Works
Transportation
Growth
Partially Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 57 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 1,650 - - - - - 150 1,500 - 1,650
Land & Right-of-Way - - - - - - - - - -
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures 1,650 - - - - - 150 1,500 - 1,650
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 150 - - - - - 150 - - 150
Developer Contribution 1,500 - - - - - - 1,500 - 1,500
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 1,650 - - - - - 150 1,500 - 1,650
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Sandifur Parkway Extension - Phase 1 (West of Road 100)
This project extends Sandifur Parkway from Road 100 to the east approximately 2,800 feet to a future north-south road (name TBD). This north-south roadway encompasses
the trunk sewer main.
This project would include a new asphalt roadway surface, curb/gutter, and sidewalks consistent with Sandifur Parkway, as it exists on the west side of Road 100. This
project would also modify the current connection of Harris Road into Road 100, as well as its potential alignment change to address a future northwest loop ramp for the
interchange improvement as originally identified in the 2017 Feasibility Traffic Study for Interchanges. Although this alignment and connection change would be made,
development is anticipated to finish the necessary frontage improvements.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Sandifur Parkway Extension - Phase 1 (West of Road 100)
PICTURE
Desirable
Promote a highly-functional multi-modal transportation network
Aerial photo of the proposed project area
Project Number - 20022
New
Public Works
Transportation
Public Safety
Partially Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 58 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 1,650 - - - - - - 150 1,500 1,650
Other - - - - - - - - - -
Total Expenditures 1,650 - - - - - - 150 1,500 1,650
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Arterial Street Fund 150 - - - - - - 150 - 150
Developer Contribution 1,500 - - - - - - - 1,500 1,500
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 1,650 - - - - - - 150 1,500 1,650
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Sandifur Parkway Extension - Phase 2 (West of Road 100)
This project continues the extension of Sandifur Parkway with a connection to the Pahlisch Homes development. This project would include a new asphalt roadway surface,
curb/gutter, and sidewalks consistent with Sandifur Parkway Phase 1.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
Sandifur Parkway Extension - Phase 2 (West of Road 100)
PICTURE
Desirable
Promote a highly-functional multi-modal transportation network
Aerial photo of the proposed project area
Project Number - 20023
New
Public Works
Transportation
Public Safety
Partially Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 59 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 300 - - - - 300 - - - 300
Land & Right-of-Way - - - - - - - - - -
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures 300 - - - - 300 - - - 300
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
I-182 Corridor Impact Fund 60 - - - - 60 - - - 60
Unsecured State Grant 240 - - - - 240 - - - 240
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 300 - - - - 300 - - - 300
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Public Safety
Partially Funded
Justification
This meets the Council Goal of:
Project Number - 20017
New
Public Works
Transportation
Traffic Analysis for Interstate 182 at Road 68
Interchange
As a continuing effort associated with the Road 68 corridor and the Interstate 182 interchange, a traffic analysis is proposed that will further study the connectivity of this
critical interchange to determine if improvements can be made to improve efficiency, provide better connectivity for motorists, and reduce congestion.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Promote a highly-functional multi-modal transportation network
Summary Project Description
Traffic Analysis for Interstate 182 at Road 68 Interchange
PICTURE
Desirable
Aerial photo of the proposed project area
2020 - 2025 Capital Improvement Plan - 60 of 117
2020-2025 Capital Improvement Plan
Traffic Analysis for Interstate 182 at
State Route 395 Interchange
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 265 - - - - 265 - - - 265
Land & Right-of-Way - - - - - - - - - -
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures 265 - - - - 265 - - - 265
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
I-182 Corridor Impact Fund 60 - - - - 60 - - - 60
Unsecured State Grant 205 - - - - 205 - - - 205
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 265 - - - - 265 - - - 265
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Aerial photo of the proposed project area
Summary Project Description
As a continuing effort associated with the Interstate 182 interchange feasibility study done recently by the City of Pasco, this effort will further study the connectivity of this
critical interchange to determine if improvements can be made to improve efficiency and provide better connectivity for motorists, taking the pressure off other areas of the
City transportation network.
PROJECT SCOPE ANNUAL ALLOCATION
Promote a highly-functional multi-modal transportation network
OPERATING IMPACT ANNUAL OPERATING IMPACT
Traffic Analysis for Interstate 182 at State Route 395 Interchange
PICTURE
Project Number - 20019
New
Public Works
Transportation
Desirable
Public Safety
Partially Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 61 of 117
2020-2025 Capital Improvement Plan
Traffic Analysis for State Route 12 Interchange
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 250 - - - - - 250 - - 250
Land & Right-of-Way - - - - - - - - - -
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures 250 - - - - - 250 - - 250
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
I-182 Corridor Impact Fund 60 - - - - - 60 - - 60
Unsecured State Grant 190 - - - - - 190 - - 190
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 250 - - - - - 250 - - 250
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Aerial photo of the proposed project area
Summary Project Description
Identified as a possible interchange improvement by WSDOT this location serves a large potential industrial area that the City of Pasco has already invested money in. This
analysis, in conjunction with WSDOT and Federal Highways, would provide the information to better prepare a strategic plan in addressing transportation connectivity with
State Route (SR) 12 in this area.
PROJECT SCOPE ANNUAL ALLOCATION
Promote a highly-functional multi-modal transportation network
OPERATING IMPACT ANNUAL OPERATING IMPACT
Traffic Analysis for State Route 12 Interchange
PICTURE
Project Number - 20020
New
Public Works
Transportation
Desirable
Public Safety
Partially Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 62 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 48 - - - 48 - - - - 48
Land & Right-of-Way - - - - - - - - - -
Construction 435 - - - - 435 - - - 435
Other - - - - - - - - - -
Total Expenditures 483 - - - 48 435 - - - 483
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
LID 483 - - - 48 435 - - - 483
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 483 - - - 48 435 - - - 483
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
James Street Improvements - Oregon Avenue to East End
This project is intended to provide a safe and consistent roadway to many of Pasco’s heavy machinery and agricultural/industrial oriented businesses. James Street has
evolved over time as different businesses located along its sides into what is now an inconsistent mixture of intermingled access points, utility risers, and poorly lit travel
ways.
This project will redefine the heavily used roadway by providing a new heavy-duty roadway section, curb/gutter and pedestrian considerations along with right-of-way
improvements. These improvements will enhance accessibility and safety for the traveling public and the businesses within this corridor, now and in the future.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Summary Project Description
James Street Improvements - Oregon Avenue to East End
PICTURE
Desirable
Promote a highly-functional multi-modal transportation network
Aerial photo of the proposed project area
Project Number - 20024
New
Public Works
Transportation
Public Safety
Not Funded
Justification
This meets the Council Goal of:
2020 - 2025 Capital Improvement Plan - 63 of 117
This page intentionally left blank.
2020 - 2025 Capital Improvement Plan - 64 of 117
Irrigation
2020 - 2025 Capital Improvement Plan - 65 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 350 - 50 50 50 50 50 50 50 300
Other - - - - - - - - - -
Total Expenditures 350 - 50 50 50 50 50 50 50 300
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 350 - 50 50 50 50 50 50 50 300
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 350 - 50 50 50 50 50 50 50 300
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Photo of an annual irrigation system improvements project
Annual Irrigation System Improvements - Development
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This is an annual program to address the irrigation system needs and enable the City to extend/improve irrigation lines when an opportunity presents itself with a private
development or other City project. The program anticipates future annexations and the need to extend irrigation services. The implementation of this program improves
irrigation service to the community.
This is an ongoing effort to improve efficiency and effectiveness in
the use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public
facilities
Annual Irrigation System Improvements - Development
PICTURE
Desirable
Project Number - 20032
New
Public Works
Irrigation
2020 - 2025 Capital Improvement Plan - 66 of 117
2020-2025 Capital Improvement Plan
Chapel Hill Boulevard to Interstate 182 -
Irrigation Main
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 20 - - 20 - - - - - 20
Land & Right-of-Way - - - - - - - - - -
Construction 80 - - 80 - - - - - 80
Other - - - - - - - - - -
Total Expenditures 100 - - 100 - - - - - 100
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 100 - - 100 - - - - - 100
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 100 - - 100 - - - - - 100
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will replace an existing 10 inch irrigation main currently under Interstate 182 east of Road 84 with a 12 inch irrigation main. The existing 10 inch main
under the freeway is connected to a 12 inch main on the north side of Interstate 182 and a 16 inch main on the south side. This creates a pinch point in the
irrigation system. Replacing the existing 10 inch main with a larger size pipe will increase the operating pressures within the system to meet the City's established
requirements.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Aerial photo of the proposed project area
Chapel Hill Boulevard to Interstate 182 - Irrigation Main
PICTURE
Project Number - 18054
New
Public Works
Irrigation
Necessary
2020 - 2025 Capital Improvement Plan - 67 of 117
2020-2025 Capital Improvement Plan
Columbia River Intake Capacity Upgrades
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 59 - 59 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 170 - - 170 - - - - - 170
Other - - - - - - - - - -
Total Expenditures 229 - 59 170 - - - - - 170
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 229 - 59 170 - - - - - 170
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 229 - 59 170 - - - - - 170
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
Prior to the Columbia Water Intake Project being completed, 75% of the water pumped out of the Columbia River from the existing intake structure went to the West
Pasco Water Treatment Plant (WPWTP) and 25% went to the irrigation system. With the completion of the new Columbia Water Intake Project, the previous existing
intake structure can now be dedicated 100% to the irrigation system. However, the condition of the older intake structure needs to be evaluated and the capacity of
the intake structure needs to be increased to accommodate the growth in irrigation needs. This project will evaluate, design and construct needed improvements.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Photo of the proposed project area
Columbia River Intake Capacity Upgrades
PICTURE
Project Number - 20034
New
Public Works
Irrigation
Necessary
2020 - 2025 Capital Improvement Plan - 68 of 117
2020-2025 Capital Improvement Plan
Irrigation Projects Allocated From Transportation
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 2 - 2 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 9 - - 9 - - - - - 9
Other - - - - - - - - - -
Total Expenditures 11 - 2 9 - - - - - 9
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 11 - 2 9 - - - - - 9
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 11 - 2 9 - - - - - 9
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Summary Project Description
This page is intended as a place holder for any or all transportation projects that also require irrigation utility funds.
Wrigley Drive Extension $2,000 in 2019, $9,000 in 2020
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Irrigation Projects Allocated From Transportation
Ongoing
Public Works
Irrigation
Necessary
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Community Transportation Network
Promote a highly-functional multi-modal transportation network
Aerial photo of the proposed project area
2020 - 2025 Capital Improvement Plan - 69 of 117
2020-2025 Capital Improvement Plan
Well Capacity Upgrades
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 50 - - - 50 - - - - 50
Land & Right-of-Way - - - - - - - - - -
Construction 1,360 - - - 420 470 470 - - 1,360
Other - - - - - - - - - -
Total Expenditures 1,410 - - - 470 470 470 - - 1,410
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 1,410 - - - 470 470 470 - - 1,410
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 1,410 - - - 470 470 470 - - 1,410
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will refurbish or re-drill existing wells that have sand or cavitation problems, including Island Estates Well, Village Well, and Northwest Commons well.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
This is a rendering of the proposed project
Well Capacity Upgrades
PICTURE
Project Number - 20035
New
Public Works
Irrigation
Necessary
2020 - 2025 Capital Improvement Plan - 70 of 117
Process Water Reuse Facility
2020 - 2025 Capital Improvement Plan - 71 of 117
2020-2025 Capital Improvement Plan
Columbia East Lift Station and Force Main
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 694 622 72 - - - - - - -
Land & Right-of-Way 597 311 286 - - - - - - -
Construction 13,838 266 5,263 8,309 - - - - - 8,309
Other - - - - - - - - - -
Total Expenditures 15,129 1,199 5,621 8,309 - - - - - 8,309
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 8,489 - 3,180 5,309 - - - - - 5,309
Federal EDA Grant 3,065 65 - 3,000 - - - - - 3,000
WA State Capital Budget 2,575 134 2,441 - - - - - - -
Franklin Co .09 Grant 1,000 1,000 - - - - - - - -
- - - - - - - - - -
Total Funding 15,129 1,199 5,621 8,309 - - - - - 8,309
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Columbia East Lift Station and Force Main
PICTURE
Project Number - 17003
Ongoing
Public Works
PWRF
Necessary
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Consultant photo of the proposed project area
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Service Protection
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
The Columbia East Lift Station portion of this project has been designed, is under construction and will be completed in 2019.
The remainder of this project is for the design and construction of two force mains that will serve multiple food processors in the Commercial Avenue Kahlotus Highway area
and direct food process water (industrial waste) to the City's Process Water Resource Facility (PWRF). Three food processors will have use of this force main: Simplot,
Grimmway and Freeze Pack. This project will allow for the diversion of 1.5 MGD of industrial waste away from the municipal wastewater treatment plant to the PWRF.
2020 - 2025 Capital Improvement Plan - 72 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 249 212 37 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 8,502 - 3,402 5,100 - - - - - 5,100
Other - - - - - - - - - -
Total Expenditures 8,751 212 3,439 5,100 - - - - - 5,100
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 8,251 - 3,151 5,100 - - - - - 5,100
HAEIFIC Loan 500 212 288 - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 8,751 212 3,439 5,100 - - - - - 5,100
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Project Number - 18070
Ongoing
Public Works
PWRF
Consultant photo of the proposed project area
Process Water Reuse Facility (PWRF) Irrigation Pump
Station (IPS) Improvements
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Service Protection
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
The Process Water Reuse Facility (PWRF) includes an Industrial Pump Station (IPS). The IPS are in serious need of replacement due to piping that is deteriorating to the point
of failure. If the current pump station were to have a major failure, there would be no way to pump the process water out of the facility to the crop fields. Complete shut
down of all food processor partners would be needed until repairs could be made.
This project was fully designed in 2019. Construction is anticipated to begin in 2019 and be completed in 2020.
Process Water Reuse Facility (PWRF) Irrigation Pump Station (IPS)
Improvements
PICTURE
Necessary
2020 - 2025 Capital Improvement Plan - 73 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 1,502 - 312 1,190 - - - - - 1,190
Land & Right-of-Way - - - - - - - - - -
Construction 21,454 - - 2,313 19,141 - - - - 21,454
Other - - - - - - - - - -
Total Expenditures 22,956 - 312 3,503 19,141 - - - - 22,644
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
State PWB Loan 11,000 - 312 688 10,000 - - - - 10,688
Unsecured Revenue Bond 11,956 - - 2,815 9,141 - - - - 11,956
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 22,956 - 312 3,503 19,141 - - - - 22,644
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Process Water Reuse Facility (PWRF) Primary Treatment
Improvement
OPERATING IMPACT ANNUAL OPERATING IMPACT
This meets the Council Goal of:
Summary Project Description
This project will construct improvements to the Process Water Reuse Facility (PWRF) to allow for additional capacity and improved treatment of the food processors'
industrial waste being pumped to the facility. This project will also address the odor issues that currently plague the facility.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Google photo of the proposed project area
PICTURE
PROJECT SCOPE ANNUAL ALLOCATION
Process Water Reuse Facility (PWRF) Primary Treatment
Improvement
Project Number - 19055
New
Public Works
PWRF
Necessary
Service Protection
Partially Funded
Justification
2020 - 2025 Capital Improvement Plan - 74 of 117
Sewer
2020 - 2025 Capital Improvement Plan - 75 of 117
2020-2025 Capital Improvement Plan
9th and Washington Lift Station
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 60 53 7 - - - - - - -
Land & Right of Way - - - - - - - - - -
Construction 620 - 124 496 - - - - - 496
Other - - - - - - - - - -
Total Expenditures 680 53 131 496 - - - - - 496
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
2017 Revenue Bond 680 53 131 496 - - - - - 496
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 680 53 131 496 - - - - - 496
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Service Protection
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
The project will address the following issues: deficient isolation and check valves, wetwell access hatches corrosion and deterioration, drywell access safety improvements,
perimeter security, defective flow meter, transfer switch obsolescence, harmonic conditioner obsolescence, wetwell electrical connection access safety and drywell motor
termination box access safety.
This lift station was originally built in 1964 and rehabilitated in 1999. It is responsible for conveying sanitary sewer flows from the western portions of the City to the Waste
Water Treatment Plant (WWTP).
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Aerial photo of the proposed project area
9th and Washington Lift Station
Project Number - 16007
Ongoing
Public Works
Sewer
Necessary
2020 - 2025 Capital Improvement Plan - 76 of 117
2020-2025 Capital Improvement Plan
Annual Sewer System Improvements - Development
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right of Way - - - - - - - - - -
Construction 1,600 200 200 200 200 200 200 200 200 1,200
Other - - - - - - - - - -
Total Expenditures 1,600 200 200 200 200 200 200 200 200 1,200
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 1,600 200 200 200 200 200 200 200 200 1,200
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 1,600 200 200 200 200 200 200 200 200 1,200
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This is an annual program to address sewer system needs and enable the City to extend/improve sanitary sewer lines when an opportunity presents itself with a private
development or other City project. The program anticipates future annexations and the need to extend sewers. Implementation of this program improves sanitary sewer
service to the community to help address public health issues.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Annual Sewer System Improvements - Development
PICTURE
Project Number - 20036
New
Public Works
Sewer
Desirable
Photos from an annual sewer system development project
2020 - 2025 Capital Improvement Plan - 77 of 117
2020-2025 Capital Improvement Plan
Pearl Street Lift Station
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 247 141 106 - - - - - - -
Land & Right of Way 5 - 5 - - - - - - -
Construction 897 - 224 673 - - - - - 673
Other - - - - - - - - - -
Total Expenditures 1,149 141 335 673 - - - - - 673
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
2017 Revenue Bond 1,149 141 335 673 - - - - - 673
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 1,149 141 335 673 - - - - - 673
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will completely rebuild the existing sanitary sewer lift station in a nearby location.
Originally built in the 1950's, this station has very poor reliability and functionality. It has a track record of failing and backing up into a nearby residence. The access to the
control center for this lift station is in the middle of a sidewalk on a busy street posing significant safety issues. This lift station is a priority.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Aerial photo of the proposed project area
Pearl Street Lift Station
PICTURE
Project Number - 15002
Ongoing
Public Works
Sewer
Necessary
2020 - 2025 Capital Improvement Plan - 78 of 117
2020-2025 Capital Improvement Plan
Road 36 Lift Station Upgrades
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 165 57 108 - - - - - - -
Land & Right of Way - - - - - - - - - -
Construction 528 - 27 501 - - - - - 501
Other - - - - - - - - - -
Total Expenditures 693 57 135 501 - - - - - 501
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
2017 Revenue Bond 693 57 135 501 - - - - - 501
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 693 57 135 501 - - - - - 501
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Asset Protection
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will provide upgrades to the sanitary sewer lift station at Road 36.
In addition to the sewer flows tributary to this lift station, this pump station has two additional lift stations pumping into it. The detention time and pump run cycles indicate
the current configuration is at capacity. Downstream surging is occurring indicating small pipe sizing issues. This pump station has overflowed onto airport property in the
past.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Aerial photo of the proposed project area
Road 36 Lift Station Upgrades
Project Number - 16006
Ongoing
Public Works
Sewer
Necessary
2020 - 2025 Capital Improvement Plan - 79 of 117
2020-2025 Capital Improvement Plan
Maitland Lift Station - Purchase and Install 4th Pump
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 21 18 3 - - - - - - -
Land & Right of Way - - - - - - - - - -
Construction 85 - 43 42 - - - - - 42
Other - - - - - - - - - -
Total Expenditures 106 18 46 42 - - - - - 42
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
2017 Revenue Bond 106 18 46 42 - - - - - 42
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 106 18 46 42 - - - - - 42
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project includes the installation of a 4th pump and a Variable Frequency Drive (VFD) to accommodate low flows. This improvement will decrease the slugging of the
headwork's and minimize the ragging of the impellers due to lower flows. Currently, the station pumps are oversized for the existing flows which cause the pumps to cycle
frequently and run at a minimum speed which creates ragging.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Photo of the Maitland Lift Station
Maitland Lift Station - Purchase and Install 4th Pump
PICTURE
Project Number -15003
Ongoing
Public Works
Sewer
Necessary
2020 - 2025 Capital Improvement Plan - 80 of 117
2020-2025 Capital Improvement Plan
Northwest Area Lift Station
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 350 - - 350 - - - - - 350
Land & Right of Way - - - - - - - - - -
Construction 3,150 - - 3,150 - - - - - 3,150
Other - - - - - - - - - -
Total Expenditures 3,500 - - 3,500 - - - - - 3,500
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 3,000 - - 3,000 - - - - - 3,000
Utility Expansion Fees 500 - - 500 - - - - - 500
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 3,500 - - 3,500 - - - - - 3,500
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Growth
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will partner with a private developer to construct a regional sanitary sewer lift station to serve the Northwest area of the City. The Developer will construct the
lift station to serve their development while the increase in the capacity of the lift station will be this project. A portion of the Northwest area can gravity flow to the new
Harris Road sewer trunk main. The remaining area, due to topography, will need to flow to this regional lift station and be pumped to an extension of the Harris Road Sewer
Transmission Main project. The estimates shown for this project are for the City's portion of the lift station project only.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Aerial photo of the proposed project area
Northwest Area Lift Station
PICTURE
Project Number - 19050
New
Public Works
Sewer
Necessary
2020 - 2025 Capital Improvement Plan - 81 of 117
2020-2025 Capital Improvement Plan
Sewer Projects Allocated From Transportation
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 3 - 3 - - - - - - -
Land & Right of Way - - - - - - - - - -
Construction 10 - - 10 - - - - - 10
Other - - - - - - - - - -
Total Expenditures 13 - 3 10 - - - - - 10
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 13 - 3 10 - - - - - 10
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 13 - 3 10 - - - - - 10
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Project Scope ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This page is intended as a place holder for any or all transportation projects that also require sewer utility funds.
Wrigley Drive Extension $3,000 in 2019, $10,000 in 2020
Promote a highly-functional multi-modal transportation network
Aerial photo of the proposed project area
Sewer Projects Allocated From Transportation
Ongoing
Public Works
Sewer
Desirable
2020 - 2025 Capital Improvement Plan - 82 of 117
2020-2025 Capital Improvement Plan
Waste Water Treatment Plant
(WWTP) Improvements - Phase 1
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 3,462 - 100 3,362 - - - - - 3,362
Land & Right of Way - - - - - - - - - -
Construction 22,443 - - 6,678 8,542 7,223 - - - 22,443
Other - - - - - - - - - -
Total Expenditures 25,905 - 100 10,040 8,542 7,223 - - - 25,805
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Local Grant/Loan 10,000 - - 5,000 3,000 2,000 - - - 10,000
Unsecured Revenue Bond 14,221 - - 3,456 5,542 5,223 - - - 14,221
2017 Revenue Bond 1,684 - 100 1,584 - - - - - 1,584
- - - - - - - - - -
- - - - - - - - - -
Total Funding 25,905 - 100 10,040 8,542 7,223 - - - 25,805
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Asset Protection
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
In 2019, the City completed the Waste Water Treatment Plant (WWTP) Facility Plan. This plan is required by the Washington Department of Ecology when a facility
approaches its design capacity. This plan identifies the future needs and expansion requirements to accommodate future growth for the next 20+ years. This project is the
first phase of the WWTP improvements as recommended by the WWTP Facility Plan. The following projects from the Facility Plan are included in this phase of the project:
1A Outfall Study; 1B Secondary Treatment Project 1; 1C Outfall Project 1; 1D Mechanical Dewatering; 1E Mechanical Thickening
NOTE: Costs for this project shown below have been escalated for inflation and are slightly different from the numbers shown in the Facility Plan.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Consultant rendering of the proposed project area
PICTURE
Waste Water Treatment Plant (WWTP) Improvements - Phase 1
Project Number - 19072
New
Public Works
Sewer
Necessary
2020 - 2025 Capital Improvement Plan - 83 of 117
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 400 - - 400 - - - - - 400
Land & Right of Way - - - - - - - - - -
Construction 4,198 - - 4,198 - - - - - 4,198
Other - - - - - - - - - -
Total Expenditures 4,598 - - 4,598 - - - - - 4,598
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
LID 3,798 - - 3,798 - - - - - 3,798
Unsecured Revenue Bond 800 - - 800 - - - - - 800
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 4,598 - - 4,598 - - - - - 4,598
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
2020-2025 Capital Improvement Plan
Northwest Area Trunkline - Sandifur Parkway Extension
to Desiree Street
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will extend the Northwest Area sewer trunkline from Sandifur Parkway Extension to Desiree Street. This project will provide sewer service to the Northwest area
as it continues to develop.
The sewer trunk line from Harris Road to Sandifur Parkway Extension is currently proposed to be constructed by Developers.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Northwest Area Trunkline - Sandifur Parkway Extension to Desiree
Street
PICTURE
Necessary
Aerial photo of the proposed project area
Project Number - 20040
New
Public Works
Sewer
2020 - 2025 Capital Improvement Plan - 84 of 117
2020-2025 Capital Improvement Plan
Public Works Operation Center
PICTURE
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right of Way - - - - - - - - - -
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures - - - - - - - - - -
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding - - - - - - - - - -
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Summary Project Description
Project Scope ANNUAL ALLOCATION
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources, the delivery of municipal
services, programs, and long-term maintenance and viability of public
facilities The information for this project is currently being developed as part of the Comprehensive Sewer Plan
Update project. There is a need for an Equipment Maintenance Facility. Once the plan is complete we
will be able to present detailed information.
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Works Operations Center
Project Number - 20037
New
Public Works
Sewer
Necessary
Growth
Not Funded
Justification
This meets the Council Goal of:
Consultant rendering of the proposed project area
2020 - 2025 Capital Improvement Plan - 85 of 117
2020-2025 Capital Improvement Plan
Road 52 and Pearl Street Lift Station - Riverview
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 300 - - 300 - - - - - 300
Land & Right of Way - - - - - - - - - -
Construction 2,120 - 336 384 1,400 - - - - 1,784
Other - - - - - - - - - -
Total Expenditures 2,420 - 336 684 1,400 - - - - 2,084
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 2,420 - 336 684 1,400 - - - - 2,084
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 2,420 - 336 684 1,400 - - - - 2,084
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
To sustain development within the east Riverview area at an appropriate density, the construction of a sanitary sewer lift station is needed. The construction of this east
lift station will make properties within this sub-basin area (as described in the 2014 Sewer Comprehensive plan) able to be served by City sanitary sewer.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Consultant map rendering of the proposed project area
Road 52 and Pearl Street Lift Station - Riverview
PICTURE
Project Number - 19053
Ongoing
Public Works
Sewer
Desirable
2020 - 2025 Capital Improvement Plan - 86 of 117
2020-2025 Capital Improvement Plan
Road 84 and Roberts Drive Lift Station - Riverview
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 500 - - - - 500 - - - 500
Land & Right of Way - - - - - - - - - -
Construction 2,000 - - - - - 2,000 - - 2,000
Other - - - - - - - - - -
Total Expenditures 2,500 - - - - 500 2,000 - - 2,500
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 2,500 - - - - 500 2,000 - - 2,500
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 2,500 - - - - 500 2,000 - - 2,500
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
To sustain development within the west Riverview area at an appropriate density, the construction of a sanitary sewer lift station is needed. The construction of this west lift
station will make properties within this sub-basin area (as described in the 2014 Sewer Comprehensive plan) able to be served by City sanitary sewer.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Consultant map rendering of the proposed project area
Road 84 and Roberts Drive Lift Station - Riverview
PICTURE
Project Number - 19052
New
Public Works
Sewer
Desirable
2020 - 2025 Capital Improvement Plan - 87 of 117
2020-2025 Capital Improvement Plan
Southeast Industrial Trunkline
PICTURE
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right of Way - - - - - - - - - -
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures - - - - - - - - - -
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding - - - - - - - - - -
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Growth
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities The information for this project is currently being developed by RH2 as part of the Comprehensive
Sewer Plan Update project. This is a placeholder and this project will be added to the CIP next year
when we have more detailed information to present.
Necessary
Consultant map rendering of the proposed project area
Southeast Industrial Trunkline
Project Number - 20042
New
Public Works
Sewer
2020 - 2025 Capital Improvement Plan - 88 of 117
2020-2025 Capital Improvement Plan
Trunkline Deficiency - Court Street
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right of Way - - - - - - - - - -
Construction - - - - - - - - - -
Other - - - - - - - - - -
Total Expenditures - - - - - - - - - -
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding - - - - - - - - - -
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Growth
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
The information for this project is currently being developed by RH2 as part of the Comprehensive
Sewer Plan Update project. This is a placeholder and this project will be added to the CIP next year
when we have more detailed information to present.
Necessary
Consultant map rendering of the proposed project area
Trunkline Deficiency - Court Street
Project Number - 20041
New
Public Works
Sewer
2020 - 2025 Capital Improvement Plan - 89 of 117
2020-2025 Capital Improvement Plan
Waste Water Treatment Plant (WWTP)
Improvements - Phase 2
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 2,570 - - - - - 2,570 - - 2,570
Land & Right of Way - - - - - - - - - -
Construction 12,797 - - - - - - 6,273 6,524 12,797
Other - - - - - - - - - -
Total Expenditures 15,367 - - - - - 2,570 6,273 6,524 15,367
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Local Grant/Loan 10,000 - - - - - 2,570 3,000 4,430 10,000
Unsecured Revenue Bond 5,367 - - - - - - 3,273 2,094 5,367
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 15,367 - - - - - 2,570 6,273 6,524 15,367
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Asset Protection
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
In 2019, the City completed the Waste Water Treatment Plant (WWTP) Facility Plan. This plan is required by the Washington Department of Ecology when a facility
approaches its design capacity. This plan identifies the future needs and expansion requirements to accommodate future growth for the next 20+ years. This project is the
second phase of the WWTP improvements as recommended by the WWTP Facility Plan. The following projects from the Facility Plan are included in this phase of the
project:
2A Secondary Treatment Project 2; 2B Outfall Project 2; 2C UV Expansion Project
NOTE: This phase extends to 2026.
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
Consultant rendering of the proposed project area
PICTURE
Waste Water Treatment Plant (WWTP) Improvements - Phase 2
Project Number - 19075
New
Public Works
Sewer
Necessary
2020 - 2025 Capital Improvement Plan - 90 of 117
Stormwater
2020 - 2025 Capital Improvement Plan - 91 of 117
2020-2025 Capital Improvement Plan
1st Avenue Pipe Rehab
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 249 - - - - 249 - - - 249
Other - - - - - - - - - -
Total Expenditures 249 - - - - 249 - - - 249
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 249 - - - - 249 - - - 249
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 249 - - - - 249 - - - 249
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will reline 348 linear foot of 30 inch concrete pipe under 1st Avenue between West Lewis Street and West Columbia Street, repair joint offsets with couplings
between West Sylvester Street and West Bonneville Street, repair 3 slightly offset joints located north of West Bonneville Street and reline 842 linear feet of 18 inch pipe
tributary to Volunteer Park.
Aerial photo of the proposed project area
1st Avenue Pipe Rehab
PICTURE
Project Number - 18065
New
Public Works
Stormwater
Desirable
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
THIS PROJECT MAY BE PARTIALLY ADDRESSED BY LEWIS STREET OVERPASS PROJECT. FURTHER
RESEARCH IS NEEDED
2020 - 2025 Capital Improvement Plan - 92 of 117
2020-2025 Capital Improvement Plan
Annual Stormwater Improvements - Development
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 350 - 50 50 50 50 50 50 50 300
Other - - - - - - - - - -
Total Expenditures 350 - 50 50 50 50 50 50 50 300
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 350 - 50 50 50 50 50 50 50 300
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 350 - 50 50 50 50 50 50 50 300
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This is an annual program to address stormwater system needs and enable the City to extend or improve storm sewer lines when an opportunity presents itself with a
private development or other City project. The program anticipates future annexations and the need to extend storm sewers. Implementation of this program improves
stormwater service to the community and addresses public health issues.
Photo of an annual stormwater improvements project
Annual Stormwater Improvements - Development
Project Number - 20043
New
Public Works
Stormwater
Desirable
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
2020 - 2025 Capital Improvement Plan - 93 of 117
2020-2025 Capital Improvement Plan
North Industrial Way Infiltration Retrofit Project
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 150 - - 150 - - - - - 150
Other - - - - - - - - - -
Total Expenditures 150 - - 150 - - - - - 150
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 150 - - 150 - - - - - 150
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 150 - - 150 - - - - - 150
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Asset Protection
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project consists of installing two 2-stage drywells, comprised of 72 inch modified drywells with modified Type 1 catch basins for pretreatment, along North Industrial
Way to reduce flows to the existing infiltration facility. Drywell overflows will surface flow to the existing infiltration facility. Additional analysis is recommended to identify
any existing onsite stormwater management within the tributary area (i.e. infiltration facilities at upstream properties) and update the infiltration facility tributary area to
reflect the findings.
The existing infiltration pipe and facility handles an estimated contributing area of 37-acres. It currently does not have enough capacity during peak precipitation events,
resulting in flooding that covers up to half of the North Industrial Way and downstream driveways.
Google photo of the proposed project area
North Industrial Way Infiltration Retrofit Project
PICTURE
Project Number - 18064
New
Public Works
Stormwater
Desirable
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
2020 - 2025 Capital Improvement Plan - 94 of 117
2020-2025 Capital Improvement Plan
Stormwater Projects Allocated From Transportation
Status
Department
Group
Assessment
Principal Need
Funding Status
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 600 - 15 250 235 100 - - - 585
Other - - - - - - - - - -
Total Expenditures 600 - 15 250 235 100 - - - 585
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 600 - 15 250 235 100 - - - 585
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 600 - 15 250 235 100 - - - 585
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Summary Project Description
This page is intended as a place holder for any or all transportation projects that also require stormwater utility funds.
Lewis Street Overpass $15,000 in 2019, $150,000 in 2020 and $135,000 in 2021
Lewis Street Corridor Improvements $100,000 in 2020, $100,000 in 2021 and $100,000 in 2022
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Stormwater Projects Allocated From Transportation
Ongoing
Public Works
Stormwater
Necessary
Public Safety
Fully Funded
Justification
This meets the Council Goal of:
Quality of Life
Community Transportation Network
Rendering and aerial photo of the proposed project area
2020 - 2025 Capital Improvement Plan - 95 of 117
2020-2025 Capital Improvement Plan
Sylvester Pipe Relining
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 330 - - - - 330 - - - 330
Other - - - - - - - - - -
Total Expenditures 330 - - - - 330 - - - 330
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 330 - - - - 330 - - - 330
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 330 - - - - 330 - - - 330
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PICTURE
PROJECT SCOPE ANNUAL ALLOCATION
Sylvester Pipe Relining
Project Number - 18067
New
Public Works
Stormwater
Desirable
Quality Improvement
Fully Funded
Justification
Aerial photo of the proposed project area
OPERATING IMPACT ANNUAL OPERATING IMPACT
This meets the Council Goal of:
Summary Project Description
This project includes the following relining:
• 8th Avenue from West Margaret to West Park of 15" = 302.5 LF • West Sylvester from 8th to 6th of 15” = 673 LF
• West Park from 8th to 5th of 15” = 958 LF • West Sylvester from 6th to 5th of 21” = 497 LF
• West Park from 5th to 4th of 18” = 520 LF • 6th Avenue from Sylvester to Yakima of 15” = 140 LF
• 5th Avenue from West Park to West Henry of 15” = 656 LF
• 10th Avenue from West Irving to West Sylvester of 10” (Relined) = 364 LF, (Replaced) = 20 LF
• West Sylvester from 10th to 8th of 12” = 738 LF
This is part of an ongoing effort to improve efficiency and
effectiveness in the use of public resources in the delivery of
municipal services, programs, and long-term maintenance and
viability of public facilities
2020 - 2025 Capital Improvement Plan - 96 of 117
Water
2020 - 2025 Capital Improvement Plan - 97 of 117
2020-2025 Capital Improvement Plan
Annual Water System Improvements - Development
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 1,400 - 200 200 200 200 200 200 200 1,200
Other - - - - - - - - - -
Total Expenditures 1,400 - 200 200 200 200 200 200 200 1,200
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 1,400 - 200 200 200 200 200 200 200 1,200
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - -
Total Funding 1,400 - 200 200 200 200 200 200 200 1,200
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Annual Water System Improvements - Development
Project Number - 20026
Ongoing
Public Works
Water
Necessary
Service Protection
Fully Funded
Justification
This meets the Council Goal of:
This is an ongoing efforts to improve efficiency and effectiveness in
the use of public resources in the delivery of municipal services,
programs and long-term maintenance and viability of public facilities
As private developments occurs, it is sometimes necessary to
financially assist with the increase in water system sizes to
accommodate further development beyond the Developer's current
project
Photos of an annual water system Improvements project
Summary Project Description
This project will provide necessary funds to improve the City's water system to accommodate future development. For example, a developer may be required to install an 8
inch water line to and through their development. The City's Water Comprehensive Plan identifies that a 24 inch water line is needed in this area to provide water system
improvements and efficiencies for all customers. This project allows for reimbursement to developers for the upsize improvements beyond those needed for private
development.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
2020 - 2025 Capital Improvement Plan - 98 of 117
2020-2025 Capital Improvement Plan
Butterfield Water Treatment Plant (WTP) -
Chlorine Safety
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 75 - 75 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 275 - - 275 - - - - - 275
Other - - - - - - - - - -
Total Expenditures 350 - 75 275 - - - - - 275
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
2017 Revenue Bonds 350 - 75 275 - - - - - 275
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 350 - 75 275 - - - - - 275
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses 50 - - - 10 10 10 10 10 50
Net Impact 50 - - - 10 10 10 10 10 50
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
The Butterfield Water Treatment Plant uses chlorine gas for disinfection during the water treatment process. This project will construct an emergency air scrubber system
that will protect staff and citizens should there ever be a leak in the chlorine system. The system will include detectors, vacuum, and duct systems and a scrubber that will
absorb the chlorine so it does not get released into the air.
Google photo of the Butterfield Water Treatment Plant project area
Butterfield Water Treatment Plant (WTP) - Chlorine Safety
PICTURE
Project Number - 17004
Ongoing
Public Works
Water
Necessary
This is an ongoing efforts to improve efficiency and effectiveness in
the use of public resources in the delivery of municipal services,
programs and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 99 of 117
2020-2025 Capital Improvement Plan
Emergency Power Improvements
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 200 - - 50 50 50 50 - - 200
Land & Right-of-Way - - - - - - - - - -
Construction 2,000 - - 500 500 500 500 - - 2,000
Other - - - - - - - - - -
Total Expenditures 2,200 - - 550 550 550 550 - - 2,200
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 2,200 - - 550 550 550 550 - - 2,200
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 2,200 - - 550 550 550 550 - - 2,200
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
OPERATING IMPACT ANNUAL OPERATING IMPACT
This meets the Council Goal of:
Summary Project Description
There is currently major back-up power deficiencies in the water system. The existing systems that lack back-up power include: the Butterfield Intake, Road 36 Booster
Station, Riverview Booster Station, and Eastside Booster Station. Eastside Booster Station currently has generator hook-ups and a manual transfer switch for the towable
generator at the Foster Wells Lift Station. All other stations mentioned above require both the generator hook-ups and automatic transfer switches, as well as a generator, to
ensure continued full operation in the event of a power loss.
Google photo of the proposed project
PICTURE
PROJECT SCOPE ANNUAL ALLOCATION
Emergency Power Improvements
Project Number - 20031
New
Public Works
Water
Necessary
Quality Improvement
Fully Funded
Justification
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 100 of 117
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 300 - - 300 - - - - - 300
Land & Right-of-Way 200 - - 200 - - - - - 200
Construction 2,500 - - - 2,500 - - - - 2,500
Other - - - - - - - - - -
Total Expenditures 3,000 - - 500 2,500 - - - - 3,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 3,000 - - 500 2,500 - - - - 3,000
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 3,000 - - 500 2,500 - - - - 3,000
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
2020-2025 Capital Improvement Plan
Transmission Main - West Pasco Water Treatment
Plant (WPWTP) to Zone 3
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Growth
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
With the completion of the new Columbia Water Intake project, which pumps water from the Columbia River to the WPWTP, a new transmission main from the WPWTP can
now be installed to Pressure Zone 3. This will provide the necessary flows and pressures to accommodate the growing northwest area of the City. This main will cross under
Interstate 182. The amounts shown represents the City's participation for this project. Since this project was anticipated, an additional steel casing was installed under
Interstate 182 for this water line as part of the Harris Road Sewer Project (which also went under Interstate 182). It was determined more efficient to have both the sewer
casing and the casing for this future water main to be installed at the same time, thus saving the City money.
This project will be done in conjunction with the WPWTP Improvement project as this will be the discharge pipe for the new filter banks.
Transmission Main - WPWTP to Zone 3
PICTURE
Necessary
Aerial photo of the proposed project area
This is an ongoing efforts to improve efficiency and effectiveness in
the use of public resources in the delivery of municipal services,
programs and long-term maintenance and viability of public facilities
Project Number - 20028
New
Public Works
Water
2020 - 2025 Capital Improvement Plan - 101 of 117
2020-2025 Capital Improvement Plan
Water Main Extension - Road 103
(Maple Drive to Willow Way)
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 13 - - - - 13 - - - 13
Land & Right-of-Way - - - - - - - - - -
Construction 100 - - - - 100 - - - 100
Other - - - - - - - - - -
Total Expenditures 113 - - - - 113 - - - 113
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 113 - - - - 113 - - - 113
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 113 - - - - 113 - - - 113
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will construct approximately 825 linear feet of 8 inch ductile iron water main along Road 103 connecting the water mains on Maple Drive and Willow Way.
This connection will loop the water system and improve the flow characteristics of the system and eliminate dead-ends in the area. Looping the system with properly sized
water mains provides increased flows and pressures that help with fire protection. This project will also improve water quality to customers in this area by reducing the need
to flush the system due to the existing dead-end lines.
Aerial photo of the proposed project area
Water Main Extension - Road 103 (Maple Drive to Willow Way)
PICTURE
Project Number - 20029
New
Public Works
Water
Desirable
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 102 of 117
2020-2025 Capital Improvement Plan
Water Main Replacement - Alley East of Wehe Avenue
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 140 - - 140 - - - - - 140
Other - - - - - - - - - -
Total Expenditures 140 - - 140 - - - - - 140
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 140 - - 140 - - - - - 140
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 140 - - 140 - - - - - 140
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will construct approximately 470 linear feet of 8 inch ductile iron water main (to replace an existing 2 inch main) in the alley directly east of Wehe Avenue, south
of East Alton Street and north of East Helena Street. One fire hydrant will be installed at the intersection of the alley and East Alton Street.
This connection will install a properly sized water main for the existing and new homes in the area and provide an opportunity to install a fire hydrant. When the water main is
installed later on East Alton Street this line will be connected to form a looped system in the area and eliminate the existing dead-end pipes. Making this connection will also
provide better flows in the distribution system and improves water quality for the customers in the area.
PICTURE
Desirable
Aerial photo of the proposed project area
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
Project Number - 19073
New
Public Works
Water
Water Main Replacement - Alley East of Wehe Avenue
2020 - 2025 Capital Improvement Plan - 103 of 117
2020-2025 Capital Improvement Plan
Water Main Replacement - Maple Drive, AC Main
(Road 100 to Road 103)
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 30 - - 30 - - - - - 30
Land & Right-of-Way - - - - - - - - - -
Construction 220 - - 220 - - - - - 220
Other - - - - - - - - - -
Total Expenditures 250 - - 250 - - - - - 250
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 250 - - 250 - - - - - 250
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 250 - - 250 - - - - - 250
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will replace approximately 1,200 linear feet of existing 6 inch asbestos concrete water line with 8 inch ductile iron pipe. The project would also install 1 or 2 new
fire hydrants. At this time, the pipe is in decent condition and is not in a deteriorated state.
Aerial photo of the proposed project area
Water Main Replacement - Maple Drive, AC Main (Road 100 to Road
103)
PICTURE
Project Number - 20030
New
Public Works
Water
Desirable
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 104 of 117
2020-2025 Capital Improvement Plan
Water Main Replacement - South 18th Avenue
(Court Street to WA Street)
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design - - - - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 79 - - - 79 - - - - 79
Other - - - - - - - - - -
Total Expenditures 79 - - - 79 - - - - 79
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 79 - - - 79 - - - - 79
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 79 - - - 79 - - - - 79
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will replace an undersized 2 inch water service with 8 inch ductile iron water main and install a new hydrant for better fire protection.
Aerial photo of the proposed project area
Water Main Replacement - South 18th Avenue (Court Street to WA
Street)
PICTURE
Project Number - 19074
New
Public Works
Water
Desirable
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 105 of 117
2020-2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 10 - - - 10 - - - - 10
Land & Right-of-Way - - - - - - - - - -
Construction 226 - - - 226 - - - - 226
Other - - - - - - - - - -
Total Expenditures 236 - - - 236 - - - - 236
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 236 - - - 236 - - - - 236
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 236 - - - 236 - - - - 236
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Water Main Replacement - Star Lane (Road 100 to Road 97)
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will replace an existing 2 inch water line with an 8 inch main and install a fire hydrant to serve this area. This will increase reliability and fire flow.
This project will improve the flow characteristics of the system in the area. Replacing the existing system with properly sized water mains provides increased flows and
pressures that help with fire protection.
Water Main Replacement - Star Lane (Road 100 to Road 97)
PICTURE
Desirable
Aerial photo of the proposed project area
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
Project Number - 19046
New
Public Works
Water
2020 - 2025 Capital Improvement Plan - 106 of 117
2020-2025 Capital Improvement Plan
Water Projects Allocated From Transportation
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 14 - 14 - - - - - - -
Land & Right-of-Way - - - - - - - - - -
Construction 247 - - 134 113 - - - - 247
Other - - - - - - - - - -
Total Expenditures 261 - 14 134 113 - - - - 247
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 261 - 14 134 113 - - - - 247
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 261 - 14 134 113 - - - - 247
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Water Projects Allocated From Transportation
Ongoing
Public Works
Water
Necessary
Quality Improvement
Fully Funded
Justification
This meets the Council Goal of:
Community Transportation Network
Promote a highly-functional multi-modal transportation network
Rendering and aerial photo of the proposed project area
Summary Project Description
This page is intended as a place holder for any or all transportation projects that also require water utility funds.
Lewis Street Overpass $12,000 in 2019, $125,000 in 2020 and $113,000 in 2021
Wrigley Drive Extension $2,000 in 2019, $9,000 in 2020
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
2020 - 2025 Capital Improvement Plan - 107 of 117
2020-2025 Capital Improvement Plan
West Pasco Water Treatment Plant
(WPWTP) Improvements
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 645 - - 645 - - - - - 645
Land & Right-of-Way - - - - - - - - - -
Construction 3,975 - - 1,500 1,475 1,000 - - - 3,975
Other - - - - - - - - - -
Total Expenditures 4,620 - - 2,145 1,475 1,000 - - - 4,620
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Utility Rate 4,620 - - 2,145 1,475 1,000 - - - 4,620
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 4,620 - - 2,145 1,475 1,000 - - - 4,620
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Growth
Fully Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will provide the necessary improvements to increase treatment capacity at the WPWTP. This project includes adding a new bank of micro-filters (along with all
other related improvements) to increase water treatment capacity from the current 6 million gallons per day (MGD) to 12 MGD. Includes (2) banks of micro filters, high service
pumping, automatic strainers, backwash facility improvements (river discharge?), intake pumping, plant/intake backup power.
NOTE: The cost of this project has been scaled for inflation. Therefore, the numbers shown below will be slightly different from the numbers shown in the Facility Plan.
West Pasco Water Treatment Plant (WPWTP) Improvements
PICTURE
Project Number - 16008
New
Public Works
Water
Necessary
This is an ongoing efforts to improve efficiency and effectiveness in
the use of public resources in the delivery of municipal services,
programs and long-term maintenance and viability of public facilities
Photo of the current proposed project area
2020 - 2025 Capital Improvement Plan - 108 of 117
2020-2025 Capital Improvement Plan
Reservoir Storage Tank - Zone 3
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 650 - - 150 500 - - - - 650
Land & Right-of-Way 500 - - - 500 - - - - 500
Construction 10,550 - - - 1,850 4,200 4,500 - - 10,550
Other - - - - - - - - - -
Total Expenditures 11,700 - - 150 2,850 4,200 4,500 - - 11,700
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 7,700 - - - - 3,700 4,000 - - 7,700
Utility Rate 2,500 - - 150 2,350 - - - - 2,500
Utility Expansion Fees 1,500 - - - 500 500 500 - - 1,500
- - - - - - - - - -
- - - - - - - - - -
Total Funding 11,700 - - 150 2,850 4,200 4,500 - - 11,700
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses 30 - - - - - 10 10 10 30
Net Impact 30 - - - - - 10 10 10 30
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Growth
Partially Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will design and construct a new 5.75 million gallon water storage tank in the Water Zone 3 to accommodate growth in the northwest area of the City.
Consultant map of the proposed project area
Reservoir Storage Tank - Zone 3
PICTURE
Project Number - 18041
New
Public Works
Water
Necessary
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 109 of 117
2020-2025 Capital Improvement Plan
Automated Meter Reading
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 150 - - 150 - - - - - 150
Land & Right-of-Way - - - - - - - - - -
Construction 5,600 - - 600 1,000 1,000 1,000 1,000 1,000 5,600
Other - - - - - - - - - -
Total Expenditures 5,750 - - 750 1,000 1,000 1,000 1,000 1,000 5,750
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 5,750 - - 750 1,000 1,000 1,000 1,000 1,000 5,750
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 5,750 - - 750 1,000 1,000 1,000 1,000 1,000 5,750
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Reduce Future Cost
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will begin the process of installing automatic water meter readers. As the City continues to grow and the number of water accounts increases, it is important to
begin installing automatic reading meters. This will save money in the future, as each new meter will be able to be read automatically either by 1) simply driving by the house
or business with a data collector that receives the meter signal Automated Meter Reading (AMR) or 2) the water meter signal will be received remotely at City offices
Advanced Metering Infrastructure (AMI). The goal is to add drive-by AMR system to new accounts as they come online and move to an AMI system as the necessary telemetry
infrastructure can be developed. This project will reduce the cost of future meter reading. It will also increase reliability and accuracy in meters read, as well as provide early
detection of leaks so they can be addressed immediately.
Google photo of the proposed project
Automated Meter Reading
PICTURE
Project Number - 18050
New
Public Works
Water
Desirable
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 110 of 117
2020-2025 Capital Improvement Plan
Reservoir Storage Tank - Zone 2
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 500 - - - - - - 500 - 500
Land & Right-of-Way 500 - - - - - - 500 - 500
Construction 6,500 - - - - - - 1,000 5,500 6,500
Other - - - - - - - - - -
Total Expenditures 7,500 - - - - - - 2,000 5,500 7,500
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 7,500 - - - - - - 2,000 5,500 7,500
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 7,500 - - - - - - 2,000 5,500 7,500
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
Reservoir Storage Tank - Zone 2
PICTURE
Project Number - 20027
New
Public Works
Water
Necessary
Growth
Not Funded
Justification
This meets the Council Goal of:
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
Consultant map of the proposed project area
Summary Project Description
This project will design and construct a new 3.5 million gallon water storage tank in the Water Zone 2 (industrial area) to accommodate growth in the northeast area of the
City.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
2020 - 2025 Capital Improvement Plan - 111 of 117
2020-2025 Capital Improvement Plan
Water Main Extension - Alton Street
(Wehe Avenue to the alley west of Owen Street)
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 27 - - - - 27 - - - 27
Land & Right-of-Way - - - - - - - - - -
Construction 300 - - - - 300 - - - 300
Other - - - - - - - - - -
Total Expenditures 327 - - - - 327 - - - 327
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 327 - - - - 327 - - - 327
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 327 - - - - 327 - - - 327
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will construct approximately 1,000 linear feet of 8 inch ductile iron water main along Alton Street from Wehe Avenue to the alley west of Owen Avenue. One fire
hydrant would be installed at the intersection of Wehe Avenue and Alton Street. The existing fire hydrant on Alton Street between Owen Street and Beech Street would be
relocated to this new line.
This connection will loop the water system and eliminate dead-end pipes in the area. Looping the system with properly sized water mains provides increased flows and
pressures that help with fire protection. The existing undersized main (approximately 470 linear feet) in the alley located directly west of Owen Street will also be replaced by
8 inch ductile iron water main between Alton Street and Helena Street.
Aerial photo of the proposed project area
Water Main Extension - Alton Street (Wehe Avenue to the alley
west of Owen Street)
PICTURE
Project Number - 18046
New
Public Works
Water
Necessary
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 112 of 117
2020-2025 Capital Improvement Plan
Water Main Extension - Riverhaven Street
(Road 36 to Road 40)
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 20 - - - - - - 20 - 20
Land & Right-of-Way - - - - - - - - - -
Construction 285 - - - - - - 285 - 285
Other - - - - - - - - - -
Total Expenditures 305 - - - - - - 305 - 305
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 305 - - - - - - 305 - 305
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 305 - - - - - - 305 - 305
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will construct approximately 1,400 linear feet of 8 inch ductile iron water main along Riverhaven Street from Road 36 to Road 40. The dead-end water mains at
the southern end of these streets would be connected to the new water main.
This connection will loop the water system and improve the flow characteristics of the system and eliminate dead-ends in the area. Looping the system with properly sized
water mains provides increased flows and pressures that help with fire protection. This project will also improve water quality to customers in this area by reducing the need
to flush the system due to the existing dead-end lines.
Aerial photo of the proposed project area
Water Main Extension - Riverhaven Street (Road 36 to Road 40)
PICTURE
Project Number - 18048
New
Public Works
Water
Desirable
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 113 of 117
2020-2025 Capital Improvement Plan
Water Main Replacement - Richardson Road
(Road 92 to Road 96)
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 50 - - - - 50 - - - 50
Land & Right-of-Way - - - - - - - - - -
Construction 410 - - - - 410 - - - 410
Other - - - - - - - - - -
Total Expenditures 460 - - - - 460 - - - 460
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 460 - - - - 460 - - - 460
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 460 - - - - 460 - - - 460
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
The water main in Richardson Road between Road 92 and Road 96 is currently not connected and they are undersized thin wall PVC pipe.
This project was identified in the 2009 water master plan but was not completed. The project would improve the flow characteristics of the area (approximately 1,800 feet of
8 inch water main, eliminating 3 dead-end lines) and could possibly even extend over to Road 88 (approximately 1,350 feet of 8 inch water main, eliminating another dead-
end line). Eliminating the dead-end lines requires less annual flushing maintenance and improves water quality for those residents. An 8 inch main would also allow for the
installation of fire hydrants (there is currently only 1 fire hydrant on a 6 inch line to cover about 4-6 blocks of houses).
Aerial photo of the proposed project area
Water Main Replacement - Richardson Road (Road 92 to Road 96)
PICTURE
Project Number - 18043
New
Public Works
Water
Necessary
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 114 of 117
2020-2025 Capital Improvement Plan
Water Main Replacement - Road 60
(Court Street to West Pearl)
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 30 - - - - - 30 - - 30
Land & Right-of-Way - - - - - - - - - -
Construction 900 - - - - - 900 - - 900
Other - - - - - - - - - -
Total Expenditures 930 - - - - - 930 - - 930
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 930 - - - - - 930 - - 930
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 930 - - - - - 930 - - 930
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will replace approximately 3,000 linear feet of existing 6 inch thin wall PVC water line with approximately 1,400 linear feet of 12 inch ductile iron pipe along Road
60 and approximately 1,600 linear feet of 6 inch ductile iron pipe along West Pearl Street, West Agate Street and 62nd Place. This project will also install three new fire
hydrants.
Not completing this project puts the City at a higher risk of having a property damage claim from a future leak. When there is a water main break the ground tends to wash
out and settle in the area of the leak, which can put more strain on the pipe remaining in the ground and lead to more leaks. The undersized pipe also does not provide
optimum water flow to the hydrants in this area.
Aerial photo of the proposed project area
Water Main Replacement - Road 60 (Court Street to West Pearl)
PICTURE
Project Number - 18044
New
Public Works
Water
Desirable
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 115 of 117
2020-2025 Capital Improvement Plan
Water Main Replacement - Road 76
(Wernett Road to Court Street)
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Design 26 - - - - - 26 - - 26
Land & Right-of-Way - - - - - - - - - -
Construction 800 - - - - - 800 - - 800
Other - - - - - - - - - -
Total Expenditures 826 - - - - - 826 - - 826
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Unsecured Revenue Bond 826 - - - - - 826 - - 826
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Total Funding 826 - - - - - 826 - - 826
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 - 2025
Revenue - - - - - - - - - -
Expenses - - - - - - - - - -
Net Impact - - - - - - - - - -
*amounts shown in thousands
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Quality Improvement
Not Funded
Justification
This meets the Council Goal of:
Summary Project Description
This project will replace approximately 1,700 linear feet of existing 4 inch and 6 inch thin wall irrigation class PVC water line and replace it with 12 inch ductile iron pipe. The
project would also install 4 new fire hydrants. Road 76 is intended to be one of the larger water mains that supply some of the residential areas that are now beginning to see
substantial development. The project would also help loop the 12 inch main that extends down from Argent Road to the main in Court Street. Water mains made of thin wall
PVC pipe cannot be worked on in the same manner as ductile iron pipe and thicker C900 class PVC pipe due to the fragile nature of the pipe. Not completing this project could
hinder the ability of any new properties from being able to connect to the City water, and stops the fire department from having an uninterrupted supply of water for
firefighting purposes on this street. This line is currently a pinch point in the water distribution system due to the smaller size.
Aerial photo of the proposed project area
Water Main Replacement - Road 76 (Wernett Road to Court Street)
PICTURE
Project Number - 18045
New
Public Works
Water
Desirable
This is an ongoing effort to improve efficiency and effectiveness in the
use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities
2020 - 2025 Capital Improvement Plan - 116 of 117
ADA Americans with Disabilities Act
AMI Advanced Metering Infrastructure
AMR Automated Meter Reading
BNSF Burlington Northern Santa Fe
CBC Columbia Basin Community College
CDBG Community Development Block Grant
CIP Capital Improvement Plan
EDA Economic Development Administration
DNR Department of Natural Resources
FCID Franklin County Irrigation District
I-182 Interstate 182
IPS Irrigation Pump Station
LID Low Impact Development
LTGO Limited Tax General Obligation
MGD Million gallons per day
PVC Polyvinyl chloride
PORT Port of Pasco
PWRF Process Water Resource Facility
RCO Recreation and Conservation Office
REET Real Estate Excise Taxes
SR State Route
SRTS Safe Routes to School
STP Surface Transportation Program
TBD To Be Determined
TIB Transportation Improvement Brand
UGB Urban Growth Boundary
VFD Variable Frequency Drive
WPWTP West Pasco Water Treatment Plant
WSDOT Washington State Department of Transportation
WSRB Washington Surveying and Rating Bureau
WTP Water Treatment Plant
WWTP Wastewater Treatment Plant
Table of Acronyms