HomeMy WebLinkAboutJF Engineering Amendment No. 19028-1 for Illuminaion Design (CP5-ST-3A-16-03)AMENDMENT NUMBER 19028-1 to
PROFESSIONAL SERVICES AGREEMENT
16030 - CHAPEL HILL EXTENSION LID
PROJECT: CP5-ST-3A-16-03
AGREEMENT NO. 19028
WHEREAS, the City and JF Engineering, PLLC entered into a Professional Services
Agreement on 9/21/2018 to provide engineering services with respect to the 16030 Chapel Hill
Extension LID project.,
NOW, THEREFORE, this agreement is amended to allow JF Engineering, PLLC to
provide additional engineering services as described on Exhibit A.
1. Scone of Work:
Additional scope associated with Franklin PUD requirements and illumination design
changes.
2. Fee•
The compensation for the work is based on a Time and Materials Basis not to exceed
the amount of $&966.0 for a total authorization amount of $217,588.00.
3. Time of performance:
The services shall be complete for the project on or before 12/31/2020.
DATED THIS 8TH DAY OF FEBRUARY, 2019.
CITY OF PASCO: JF ENGINEERING, PLLC:
Dave ity Manager Jolt i Fetterolf P.E., Owner
Amendment No. 19028-1 to Professional Services Agreement
JF Engineering, PLLC
16030 Chapcl Bill Exw-inion LID l'rujc#A
�agY'\
Exhibit A
ENGINEERING
�Ld PLLC
From: John Fetterolf
To: Steve Worley
cc: Mary Heather Ames
MEMORANDUM
Date: January 24, 2019
RE: Chapel Hill LID: Additional services request #1, FPUD Power system
As the design development of the lighting system has progressed, the Franklin PUD has
indicated that they will only accept a lighting system that utilizes #6 or #8 wire. This design
limitation, together with FPUD requirements, now requires a complete FPUD electrical system
will need to be extended from Goldstream and Road 68, towards Road 76. The FPUD is
requiring the full system be extended to a point at which the lighting system can meet the
FPUD's typical design standards.
After coordinating with our subconsultant and reviewing our own time anticipated to
complete the additional work necessary to complete this task, we are proposing a fee increase
of $8.966.00.
If you agree with our proposal, please sign below and return a copy to me. The amount
indicated above, will be amended to the original signed contract dated September 21, 2018.
All other terms of the original signed contract will remain in force.
-JF
Steve Worley, P.E.
Public Works Director
City of Pasco
CH Add srvcs-FPUD Elec.docx
Date
5220 S. Auburn PI. ■ Kennewick, WA • 509.551.8174 ■ John@JFEngineering.pro