HomeMy WebLinkAbout3914 ResolutionRESOLUTION NO. 39
A RESOLUTION approving the Capital Improvement Plan for
Calendar Years 2020-2025.
WHEREAS, staff has prepared the Capital Improvement Plan which defines the capital
projects proposed to be undertaken by the City over the ensuing six years; and
WHEREAS, on September 9, 2019, the Capital Improvement Plan was presented to the
City Council for review and prioritization; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO,
WASHINGTON:
That the Pasco City Council hereby approves the Capital Improvement Plan for calendar
years 2020-2025 as the City's list of capital projects proposed to be undertaken by the City over
the coming six years, with the understanding that implementation of any project listed in the
Capital Improvement Plan is subject to budget appropriation.
PASSED by the City Council of the City of Pasco this 16th day of September, 2019.
Matt Watkins
Mayor
ATTEST:
K-4-kvv/
Debra Bw4ti—
City Clerk
APPROVED AS TO FORM:
2020 2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 2025
Design 415 200 215
Land Right of Way
Construction 1,600 1,600
Other
Total Expenditures 2,015 200 1,815
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 2025
CBC Grant 800 800
Port of Pasco 800 800
Arterial Street Fund 415 200 215
Total Funding 2,015 200 1,815
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 2025
Revenue
Expenses
Net Impact
amounts shown in thousands
Summary Project Description
This project was originally considered in its entirety from Road 36 to 20th Avenue.It also includes two important stakeholders in Columbia Basin Community
College CBC)and the Port of Pasco Port).Due to the immediate improvements necessary as part of the development of the Port’s property,namely the
new Marriot hotel,it became necessary to break the project into phases.Phase 1 includes improvements from Varney Lane/Saraceno Way to 20th Avenue,
Phase 2 makes improvements to the intersection of Road 36 and Argent,while Phase 3 connects the previous two projects.
Improvements include street widening with a new roadway surface along with curb/gutter and sidewalk.Utilities,including stormwater,will also be built as
part of the improvements.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Public Safety
Fully Funded
Justification
This meets the Council Goal of:
Promote a highly functional multi modal
transportation network
This is an actual area photo of the proposed project
Argent Road Phase 1 Saraceno/Varney to 20th
Ave.)
Argent Road Improvements 20th Avenue to Saraceno
Way
PICTURE
Desirable
Project Number 12001
Ongoing
Public Works
Transportation
Page 20 of 119
2020 2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 2025
Design 128 128 128
Land Right of Way
Construction 722 722 722
Other
Total Expenditures 850 128 722 850
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 2025
CBC Grant 425 128 722 850
Port of Pasco 425
Total Funding 850 128 722 850
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 2025
Revenue
Expenses
Net Impact
amounts shown in thousands
Summary Project Description
This project will construct intersection improvements to improve the current level of service.The intersection improvements will be either a signalized
intersection or a roundabout.
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Growth
Fully Funded
Justification
This meets the Council Goal of:
Promote a highly functional multi modal
transportation network
This is an actual area photo of the proposed project
Argent Road Phase 2 Rd 36 Intersection
Improvements)
Argent Road and Road 36 Intersection Improvements
PICTURE
Desirable
Project Number 20011
New
Public Works
Transportation
Page 21 of 119
2020 2025 Capital Improvement Plan
Status
Department
Group
Assessment
Principal Need
Funding Status
Quality of Life
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 2025
Design 300 300 300
Land Right of Way
Construction
Other
Total Expenditures 300 300 300
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 2025
Arterial Street Fund 300 300 300
Total Funding 300 300 300
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2018 2019 2020 2021 2022 2023 2024 2025 2020 2025
Revenue
Expenses
Net Impact
amounts shown in thousands
Summary Project Description
This project will construct widening,access,and frontage improvements to that portion of Argent Road.This project connects the previous two
improvement projects.These improvements focus on the needs of the adjacent stakeholders,which include the Port of Pasco Port),and Columbia Basin
Community College CBC).
PROJECT SCOPE ANNUAL ALLOCATION
OPERATING IMPACT ANNUAL OPERATING IMPACT
Growth
Fully Funded
Justification
This meets the Council Goal of:
Promote a highly functional multi modal
transportation network
This is an actual area photo of the proposed project
Argent Road Phase 3 Rd.36 to Saraceno/Varney)
Argent Road Improvements Saraceno Way to Road
36
PICTURE
Desirable
Project Number 20010
New
Public Works
Transportation
Page 22 of 119
2020-2025 ProposedCapital Improvement
Capital Improvement Program TrendPage
2020-2025 CIP by
Design for Lewis Street -
20th Ave Overlay – Court
Harris Road Sewer Trunk
FundingCurrent and Future Debt –
Revenue SourcesPage 30 of
All internal funds are
1.Council Goals2.Master
PROJECT HIGHLIGHTSFIREPage 33 of
SummaryPg# Project Group/Project
Continuing ProjectsRelocation of Station
New ProjectsoStation 86 and
Design Completed•Fully Funded –
Unsecured Funding•Estimated Cost -$
PROJECT HIGHLIGHTSGeneralPage 39 of
SummaryPg# Project Group/Project
Continuing ProjectsAnimal Shelter (Pg.
New ProjectsoAnimal Shelter – Little
Animal Shelter•Design - Complete•
Community Center (Pg. 13)•
GESA Stadium (Pg. 12)•
PROJECT HIGHLIGHTSParks and RecreationPage
SummaryProject Group/Project NameTotal
Continuing Projects“A” Street
New ProjectsMarina Dock Replacement –
A” Street Sporting Complex (
Community Park Northwest (Pg.
Peanuts Park Restoration (Pg.
Road 48 Park (Pg.
Sacajawea Levee Lowering (Pg.
PROJECT HIGHLIGHTSTransportationPage 55 of
Project Group/Project NameTotal
Continuing ProjectsLewis Street Overpass (
New ProjectsSandifur Extension (Pg.
Annual Pavement Preservation Program (
Bike/Pedestrian Access•Burns
Citywide Traffic Controller Upgrades –
Lewis Street Corridor Improvements
Lewis Street Overpass (Pg.
Road 100 Widening - Court
Sandifur Parkway Extension - Phase
PROJECT HIGHLIGHTSUtilities – Process Water
SummaryProject Group/Project NameTotal
Continuing Projects Columbia East
New ProjectsNo new projectsPage
Irrigation Pump Station (IPS)
Primary Treatment Plant Improvement (
PROJECT HIGHLIGHTSUtilities – Sewer Page
SummaryProject Group/Project NameTotal
Continuing Projects WWTP Improvements -
New ProjectsoNW Area Trunkline -
Northwest Area Lift Station (
NW Area Trunkline –Sandifur (
WWTP Improvements - Phase 1 (
PROJECT HIGHLIGHTSUtilities – Stormwater Page
SummaryProject Group/Project NameTotal
PROJECT HIGHLIGHTSUtilities - Irrigation Page
Project Group/Project NameTotal
New ProjectsoColumbia River Intake
Columbia River Intake Capacity
Well Capacity Upgrades (Pg.
PROJECT HIGHLIGHTSUtilities - Water Page
SummaryProject Group/Project NameTotal
Continuing Projects Reservoir Storage
New ProjectsoEmergency Power Improvements (
Emergency Power Improvements (Pg.
Reservoir Storage Tank Zone
Transmission Main West Pasco
West Pasco Water Treatment
Upcoming PlansoWater Treatment Facility