HomeMy WebLinkAboutCapital Improvement Plan 2019-2024 I fis ;mz14oAF
i�
Nqap7A,
Capital Improvement
Plan
2019-2024
Table of Contents
I. INTRODUCTION................................................................................................................................................................ii
Capital Cost of Proposed Projects by Project Category...............................................................................iii
Capital Cost of Proposed Projects by Revenue Source (Utility Excluding PWRF)..................................v
Capital Cost of Proposed Projects by Revenue Source (PWRF)................................................................vii
Capital Cost of Proposed Projects by Revenue Source (Non-Utility)........................................................ix
II. Project Consideration Factors.............................................................................................................................................xii
III. Financing and Debt............................................................................................................................................................ xiv
IV. Project Summary by Category............................................................................................................................................. xx
V. Project Summary by Revenue Source............................................................................................................................... xxiv
VI. Table of Acronyms...........................................................................................................................................................xxxii
1 1 PAGE
INTRODUCTION
The 2019-2024 Capital Improvement Plan (CIP) is a multi-year plan of capital projects with estimated costs, and proposed
methods of financing. The Plan is reviewed on an annual basis and updated to reflect the availability of resources,progress on
execution of projects, changes in policy, changes in cost or financial resources, and refinement of projects.
Capital facilities are necessary to support the basic services that the Cities provide to support the community as it currently exists, and
as it is expected to develop over the next twenty years. The state Growth Management Act (GMA) establishes many of the requirements
for the Capital Improvement Plan element. RCW 36.70A.020 states that Capital Improvement Plans are to "ensure that those public
facilities and services necessary to support development shall be adequate to serve the development at the time the development is
available for occupancy and use without decreasing current service levels below locally established minimum standards".
The City's Capital Improvement Plan consists of a list of capital projects, together with cost estimates and proposed sources of
funding for approved projects. However, Council appropriates funding through the biennial Capital Projects Budget process.
The City's Biennial Budget process requires Council's approval to spend amounts listed in this CIP, add new projects, or to
increase the total approved cost of an existing project. Capital project works of a like nature which occur each year and listed
together in the CIP may be included as separate projects in the Capital Projects Budget based on such factors as work location
and construction start dates. Capital Project Budgets may include related project work which may not meet the accounting
definition of"capital"but are directly related to the project. The Capital Projects Budget will be included as a section in the
City's "Biennial Operations & Capital Improvement Budget"document, when such document is created.
Repair and maintenance work, and equipment purchases, though often significant in dollar amount, will be included as part of
the biennial Operating Budget.
It is important to note that a multi-year Capital Improvement Plan does not represent a final commitment from the City Council.
The approval of the Plan does not authorize spending on projects within the Plan. Budget appropriations for Capital Projects are
made through the biennial Operating and Capital budget process as mentioned above.
111 PAGE
Capital Cost of Proposed Projects by Project Category
The total cost for all projects within the City's 2019-2024 capital Project Category Total
improvement planning period is $204,796,544. Exhibits 1.1 and
1.2 illustrate the capital costs and split by project Category. This FaclUties 12,725,544
is an increase of 17%from the City's approved 2018-2023 Fire & Anibutalice 19,405,000
Capital Improvement Plan of$175,695,788. This increase can be
885,000
attributed to proposed extensive improvement and expansion of 1}
Process Water Resource Facility (PWRF), and P - F 19,950,000
relocation/replacement of Fire Stations 83 and 84. Sewer 35,177,000
Transportation 52,151,000
Water 25,5 00.000
Ini ation 2,113,000
Stom ater 1,889.000
Total 204,7961544
Exhibit 1.1
III PAGE
2019-2024 Capital Improvement Plan by Project Category
($204,796,544)
Irrigation Stormwater
I°/0 1%
Facilities
Water 6'
Ambulance
FF Parks& rr
Transportation
I ' ,
Sewer
ori
MMAO
Exhibit 1.2
IV PAGE
Capital Cost of Proposed Projects by Revenue Source (Utility Excluding PWRF)
Drinking water, wastewater, irrigation, stormwater, and PWRF evenue Source 2019-2020 2019-2024
services make up the City's Utility Fund. The fund is operated Current Revernme Bond 3,093,000 3,093,000
like a business and must be self-supporting. Utility projects are Grant 0 1250.000
historically funded through combination of rates, expansion fees,
grants, loans, and revenue bonds.
� � Fundic 14,479,000 5551,000
Utflity Rate 4,03 ,000 8.385,000
In the past state programs like Public Works Trust Fund Total 2116081000 691679?000
Loans (PWTF) were readily available to assist cities with
low interest loans. The program has not been a reliable Exhibit 2.1
source of funding for local projects in recent times, though
the legislature is restoring funds to some programs. 2019-2020 Capital Improvement Plan by Revenue Source
(Utility excluding PWRF-$21,608,000)
This section excludes the capital project costs for PWRF to
account for the uniqueness of the facility,potential for and
impact of additional users, as well as the significant [lilk Rate �Me Bond
capital facilities effort anticipated that benefits from
19:Po t4leO
Council's stand-alone review.
Capital cost proposed for projects for the City's 2019-2024
capital improvement planning period is $68,679,000. Exhibits
2.1, 2.2, and 2.3 illustrate the capital costs by major revenue
categories for the period 2019-2024, as well as the biennium Insecu ed FU1Aa-
budget period of 2019-2020. 67®Po
The Wastewater Treatment Plant (WWTP) is nearing completion _
of a facility planning process to meet National Pollution
Discharge Elimination Permit System (NPDES) requirements MOM
and address future capacity and water quality needs. The
ongoing facility plan will identify projects that are expected to be Exhibit 2.2
a significant investment for the City ($18.7M). Cities fund such
V PAGE
large infrastructure projects through a combination of Public 2019-2424 Capital Improvement Plan by Revenue Source
Works Trust Fund loans, grants, and revenue bonds. The funds (Utility Excluding PWRF-$68,679,000)
are represented as unsecured until Council authorizes such
actions, and the bonds or loans are secured. camut Rerenue Raid
S%. GTaat
2%h
UHL&Rate
12%
Un seru rent Fu ndl n.,
Exhibit 2.3
VI PAGE
Capital Cost of Proposed Projects by Revenue Source (PWRF)
The Process Water Resource Facility (PWRF) is a unique Revenue Source 2019-2020 2019-2024
facility for a City, and for its time when it was built more than Grants 1,661,000 1,661,000
twenty years ago. This concept is becoming more common as Unsecured Funding 17,489,000 17.489.000
companies and Cities lookfor ways to treat their industrial Loan 500,000 500,000
wastewater most efficiently. The collaboration that has existed Uaty Rate 300,000 300,000
in Pasco for the last two and a half decades is being replicated
Total 19,950,000 19,950,000
around the country.
As this concept is expanding, the demand for our facility is Exhibit 3.1
expanding as well. Furthermore, age, size, and technology are 2019-2020 Capital Improvement Plan by Revenue Source
driving upgrades needed to meet the significant current and (Utility excluding PWRF-$19,950,000)
future demands. In 2017, Council authorized the City to hire vftu
Pace Engineers to conduct a comprehensive facilities and j
engineering plan with a vision of renewing the facility,providing
for expansion of current system users, and attracting other
agricultural processors to the area.
Capital cost for PWRF utility projects for the City's 2019-2024
capital improvement planning period are estimated to be in the
order of$19,950,000. Exhibits 3.1, 3.2 and 3.3 illustrate the
capital costs by major revenue categories. A large part of
unsecured funding is attributed to the expansion of capacity and
refurbishment of an aging facility. City staff are currently in
negotiations with various processors to find a path forward for
funding these improvements. All funding for PWRF projects has
to be acquired through grant or participating processors, unless Exhibit 3.2
projects contribute to further economic development of the City.
VII PAGE
2019-2024 Capital Improvement Plan by Revenue Source
(iltil ity excluding PWRF-$19,950,000)
UrINh-Efate
t�
Exhibit 3.3
VIII PAGE
Capital Cost of Proposed Projects by Revenue Source (Non-Utility)
Parks, Transportation, and General Capital Facilities projects Revenue Source 2019-2020 2019-2024
are funded with general revenue, grants, cost sharing with Unsecured Funding 29,330,000 55,743,000
neighboring municipalities, local improvement districts (LIDS), Cram 17,395,000 17395,000
impact fees, and the real estate excise tax (BEET). Internal Funds 15,617,044 23,711,044
Capital project cost for non- utility projects for the City's 2019- Proposed LID 7,921,000 7,921,000
2024 capital improvement planning period is $116,184,544. Municiipalbes Partnership 2,900,000 2,900,000
Exhibits 4.11 4.2, and 4.3 illustrate the capital costs by major Loan 2,000,000 2,000,000
revenue categories and the funding split. Significant projects Other 3,908,500 6,497,500
proposed in this plan for the biennial budget period of 2019- Total 79,071,544 116,167,544
2020 are relocation of Fire Stations 83 and 84, Lewis Street
Overpass, and Peanuts Park. Exhibit 4.1
As Council is aware,funding options for partially or fully
unfunded projects like Fire Station relocations, Peanuts Park, as
well as the Lewis Street Overpass are being explored. Large part
of unsecured funding for Peanuts Park is expected to be covered
through Section 108 loan, whereas funding for Lewis Street
Overpass will be a continual process for the Council and staff.
IX I PAGE
2019-2020 Capital Improvement Plan by Revenue Source (Non-Utility)
($79,071,544)
Loan
2%
Municipalities Partnership
4%
Proposed LID
10°/a Unsecured Funding
37%
Internal Funds
200/c
Grant
22%
i.—,
Exhibit 4.2
X PAGE
2019-2024 Capital Improvement Plan by Revenue Source (Non-Utility)
($116,167,544)
Loan
Municipalities Partnership 2%
2%
1
Proposed LID
7%
Unsecured Funding
48%
Internal Funds
20%
Grant
15%
Exhibit 4.3
XI PAGE
Project Consideration Factors
Many factors are considered when planning for capital projects. As mentioned before, GMA requires cities to have capital facilities in place
and readily available when new development occurs or a service area population grows. Office of Financial Management estimates an
addition of 50,000 new residents by the year 2038 for the City. Existing aging infrastructure that have reached or are nearing end of thier
useful life also need upgrades or replacement. These two factors are the major drivers of what is proposed in this plan.
The City Council's adopted provide the strategic vision for the City. Staff places high importance on projects proposed which align with
Council's goals. Other factors might not align with GMA requirements, Council goals, or Master Plans but are important for operations. Such
factors, like asset protection, reducing future costs, service protection, or quality improvement are considered and stated on project sheets.
Urgency of the need is also considered to appropriately schedule projects.
An additional factor to consider is that some granting agencies require local governments to have an adopted of Capital Improvement Plan in
order to be eligible for grants and loans. Such projects, if aligned with GMA requirements, Council Goals, or Master Plans will be included in
this plan to satisfy said requirement.
XII I PAGE
Principle Need
Council Goal-Project is designed to achieve goals set by the City Council.
Asset Protection -Project is designed to maintain and/or protect city property.
Reduce Future Costs - The project is designed to reduce or eliminate projected future costs incurred by the City.
Service Protection - The project is designed to maintain core services.
Quality Improvement- The project is designed to enhance the quality of life for residents.
Asset Assessment
Urgent- The project is needed to combat an identified issue posing a threat to City assets or core services.
Necessary- The project is needed to maintain core services at their current levels or combat an issue that may present a future
or growing threat.
Desirable- The project would improve the current quality of services or quality of life.
XIII PAGE
Financing and Debt
Water Rates Expansion Fees - Utility
Wastewater Rates Investment Interest
Irrigation Rates Real Estate Excise Taxes (REST)
Stormwater Rates Utility Taxes
Motor Vehicle Fuel Taxes
Grant
Surface Transportation Program State Recreation Conservation Office (RCO)
Transportation Improvement Board(TIB) Safe Routes to School (SRS)
Economic Development Administration (EDA) Community Development Block Grant (CDBG)
Connecting Washington .09 Franklin County Grant(Sales Tax Funding for Public
Transportation Alternatives Program (TAP) Facilities in Rural Counties)
Utility Revenue Bonds Safe Drinking Water Loans
Unlimited Tax General Obligation Bonds (UTGO) Limited Tax General Obligation Bond(LTGO)
Other
Impact Fees Public/Private Partnerships
Local Improvement Districts Donations
Multi-Jurisdictional Partnerships
XIV PAGE
The total indebtedness for general purposes with or without a vote cannot exceed 2.5%of the value of the taxable property within
the City limits. 1.5%is the maximum limit for general purpose debt without a vote(councilmanic).
Utility revenue bonds do not have such criteria, as utility funds are treated as a business unit and debt can be issued if the rates
can sustain debt service. The bond interest rates are driven by the total financial health of not just the fund but of the City's
residents, and its future needs.
Council has made some prudent financial decisions which are reflected in the history of City's debt capacity. General-purpose
bonded indebtedness capacity for the City is$120,022,000. The current general-purpose bond for the City is$9,660,000, or 8%of
the maximum allowable debt. It is also important to note that the cities historically go through cycles of debt incurrence with aging
facilities and growth.
The pattern and speed of Pasco's growth will result in debt needing to be issued in cyclical but not continuous pattern. The last
time the City issued a large amount of debt was in the 1990's to build PWRF, Library, and Fire Stations. Exhibit S below
demonstrates the variances in which the City has leveraged debt to fund large capital projects over the last quarter century.
XV I PAGE
Debt as a Percentage of Debt Limit
90%
80%
70%
60°/a
500/0
40%
30%
20%
100/0
0%
7 kr, tO n 00 a� O N M � v] I'D n 00 0� O N M +17 n
a� a+ a, a+ a� o 0 0 0 0 0 0 0 0 0
o 0 o v o 0 o c o 0 o v o 0 o c o 0
N N N N ri N N N N N N N N N N N N N
Exhibit S
XVI PAGE
Below are major funding sources available to the City to fund CIP projects:
Bonds
The City Council may authorize the City Manager to sell bonds to raise revenue for capital improvements. Those bonds are sold on the open
market in exchange for cash payments, essentially functioning as a loan for the City. In selling and managing bonds, the City seeks the advice
of both a bond counsel and an outside financial advisor. Interest rates on bond payments are based on market conditions and the City's bond
rating, as determined by private rating agencies. The City's current bond rating is AA-, last evaluated in 2017 by S&P Global.
Unlimited Tax General Obligation Bonds (UTGO)
One of the most common methods of financing capital improvements for local governments is through the issuance of municipal bonds
known as "Unlimited Tax General Obligation Bonds" or"UTGO Bonds." The voters within the local government must approve UTGO
Bonds. UTGO Bonds are secured by and payable out of annual property taxes, in excess of regular property taxes,unlimited as to rate or
amount. In other words, a local government is obligated to levy excess property taxes at whatever rate is necessary to repay the UTGO Bonds.
Further, UTGO Bonds constitute a general obligation of the local government, and, as such, the full faith, credit and resources of the local
government are pledged for their repayment.
The approval process requires Local government voters approve the bond ballot proposition at a properly conducted election. UTGO Bonds
must be approved by 60% of the qualified voters within the local government. In addition, the total number of voters casting ballots at the
election cannot be less than 40% of the number of votes cast in the last state general election. Further, a local government may only place a
bond ballot proposition before its voters twice in any calendar year.
Voted indebtedness for cities may not exceed 2.5% of Assessed Value (AV) for general municipal purposes (any outstanding non-voted, or
councilmanic debt is counted against this 2.5%), 2.5% for certain utility purposes, and 2.5% for certain parks, open space and economic
development purposes. The total amount of voted and non-voted debt may not exceed 7.5%. The City has significant bonding capacity, with
XVII I PAGE
voted indebtedness being 0.2588% in 2017. The City currently doesn't have any UTGO bonds outstanding. The last UTGO bonds issued by
the City were in 1999 to fund a library and a fire station.
Limited Tax General Obligation Bonds (LTGO)
Limited Tax General Obligation Bonds are also called"councilmanic"bonds or non-voted debt. These bonds may be issued by a vote of the
legislative body and require a majority support. Because the voters have not been asked to approve a tax increase to pay for the principal and
interest, existing general fund revenues must be pledged to pay the debt service on a LTGO Bond. The City issued $8,795,000 of LTGO
bonds in 2015 to build the Pasco Police and Community Services Building.
Revenue Bond
Another debt financing option is Revenue Bonds to finance projects for any City enterprise which is self-supporting like utilities. Payment
comes from user fees; so the debt is not backed by the full faith and credit of the City. Investors consider these somewhat less secure than
general obligation bonds as well.
Grants and Loons
Some of the funding for larger City capital projects comes from grants and loans made by federal and state agencies. Almost all federal funds
are 'passed through' a state agency filter. Some of the major agencies involved in funding grants and loans are Transportation Improvement
Board (TIB), Washington State Recreation and Conservation Office (RCO), Water Resources Program, Department of Ecology, etc. Parks
and Transportation projects are the largest benefactors of such grants and loans at City of Pasco.
On-Going Revenue
Revenue created by services like water, sewer, taxes etc. These revenues are used to fund Capital projects in their respective areas. City
follows the applicable regulation around special revenue funds, enterprise funds and general funds.
XVIII I PAGE
Loco/ Improvement District (LID)
A Local Improvement District (LID) is a method by which a group of property owners can share in the cost of infrastructure improvements.
LID's can be used to help finance improvements including:
a) Street Overlays, Repair, and Construction
b) Street Lighting
c) Utility Expansion(Water, Sewer, Storm Drain, Irrigation)
d) Overhead Power Conversion to Underground
e) Street Beautification and Revitalization Projects
f) Park Construction and Improvements
XIX I PAGE
Project Summary by Category
Current
Total Project Year Plan Plan Plan Plan Plan Plan Total
Page Project to Date Anticipated Year Year Year Year Year Year Request
# Project Name Cost 12/31/17 Cost 2019 2020 2021 2022 2023 2024 2019-2024
GENERAL 33,085,651 44,000 910,107 28,131,544 3,550,000 200,000 250,000 - - 32,131,544
FACILITIES 13,558,544 44,000 788,000 9,151,544 3,375,000 200,000 - 12,726,544
10-11 Animal Control Shelter 4,991,000 44,000 603,000 4,344,000 - - 4,344,000
12-13 Downtown Police Substation&Services Facility 100,000 50,000 50,000 50,000
14-15 City Hall Remodel Phase I1 1,767,544 100,000 1,667,544 1,667,544
16-17 Wayfnding&Signage 650,000 35,000 190,000 225,000 200,000 615,000
18-19 ConurunityCenter 4,050,000 - 900,000 3,150,000 - 4,050,000
20-21 Gesa Stadium 2,000,000 - 2,000,000 - 2,000,000
FIRE/AMBULANCE 19,527,107 122,107 18,980,000 175,000 250,000 19,405,000
2-3 Fire Station 83 Replacement 5,966,952 47,107 5,919,845 - - 5,919,845
4-5 Fire Station 84 Replacement 12,705,155 75,000 12,630,155 - - 12,630,155
6-7 Fire Station 81 Remodel 605,000 - 180,000 175,000 250,000 605,000
8-9 Fire Station 85 Land Purchase 250,000 250,000 - - 250,000
XX PAGE
Current
Total Project Year Plan Plan Plan Plan Plan Plan Total
Lge Project to Date Anticipated Year Year Year Year Year Year Request
Project Name ALLW Cost 12/31/17 Cost 2019 2020 2021 2022 2023 2024 2019-2024
PARK&RECREATION 23,491,000 137,000 1,469,000 7,465,000 3,605,000 5,500,000 2,560,000 1,435,000 1,320,000 21,885,000
24-25 Peanuts Park Restoration 6,007,000 104,000 678,000 5,225,000 - - - - - 5,225,000
26-27 Schlagel Park Improvements 736,000 16,000 - 110,000 610,000 720,000
28-29 Chapel Hill Park 440,000 - 20,000 420,000 - 420,000
30-31 Highland Park Restroom/Concession/Storage Building 210,000 10,000 200,000 200,000
32-33 Dog Park 200,000 - 200,000 - 200,000
34-35 Road 84 Park 800,000 400,000 400,000 - 800,000
36-37 Road 54 Park Improvement Erwen Property 320,000 - 20,000 300,000 320,000
38-39 Rd 48 Park Development 1,250,000 - 1,250,000 - - - 1,250,000
4041 Community Park-Northwest 2,500,000 - - - 200,000 1,400,000 900,000 2,500,000
4243 A Street Sporting Complex 1,072,000 32,000 140,000 900,000 - - - - 1,040,000
4445 Sylvester Park Tennis Court Upgrades 80,000 - - - 80,000 80,000
4647 Marina Dock Replacement 1,800,000 500,000 - 1,300,000 1,300,000
4849 Pasco Sporting Complex Update Phase I1 250,000 150,000 100,000 - 100,000
50-51 Memorial Pool Upgrades 500,000 - 500,000 500,000
52-53 Kurt anan Shelter 60,000 - 60,000 - 60,000
54-55 Parks&Facilities Sign Replacement 50,000 - - 20,000 15,000 15,000 50,000
56-57 Sacajawea Heritage Trail-Levee Lowering 4,696,000 17,000 79,000 100,000 - 2,500,000 2,000,000 4,600,000
58-59 Sacajawea Heritage Trail-BNSF Tunnel Passage 1,650,000 - - 50,000 1,600,000 - - 1,650,000
60-61 FCID Trail Phase 1 415,000 - - 55,000 360,000 415,000
62-63 FCID Trail Phase 11 455,000 - - - - - - 35,000 420,000 455,000
TRANSPORTATION 72,511,000 6,517,000 3,843,000 16,682,000 19,638,000 15,881,000 1,550,000 2,270,000 6,1303000 62,1519000
66-67 Chapel Hill Blvd Extension-LID 150 11,714,000 19,000 1,454,000 10,241,000 - - - - - 10,241,000
68-69 Argent Road(20th Ave to Rd 44) 7,195,000 272,000 794,000 1,634,000 317,000 4,178,000 6,129,000
70-71 Lewis Street Overpass 34,142,000 6,089,000 1,053,000 1,000,000 15,447,000 10,553,000 27,000,000
72-73 James Street hriprovements 1,617,000 3,000 45,000 480,000 1,089,000 - 1,569,000
74-75 Road 68 Interchange Improvements 796,000 134,000 114,000 548,000 - 548,000
76-77 Crescent Road(Rd 108 to Chapel Hill Blvd) 200,000 - - - 200,000 200,000
78-79 Sandifer Parkway Widening(Rd 52 to 60) 250,000 250,000 250,000
80-81 Road 100 Widening 1,220,000 - 1,220,000 1,220,000
82-83 Wrigley Drive Extension 354,000 354,000 - 354,000
84-85 Sacajawea Park Road Overlay 385,000 385,000 385,000
86-87 20th Avenue Court Street to Interstate 182 Overlay 440,000 440,000 440,000
88-89 Sycamore,Hugo&Waldemar Grind&Overlay 195,000 - - 195,000 - - 195,000
90-91 Annual Sidewalk&Complete Street Project 800,000 100,000 200,000 200,000 100,000 100,000 100,000 800,000
92-93 Pavement Preservation Program 3,360,000 - 555,000 555,000 750,000 750,000 750,000 3,360,000
94-95 Sandifur Sidewalk Replacement 80,000 - 80,000 - - - - 80,000
96-97 City Wide Traffic Signal Improvement Phase II 3,383,000 383,000 1,500,000 1,500,000 - - 3,000,000
98-99 Court Street&Road 68 Intersection hnprovements 850,000 - - - 150,000 700,000 850,000
100-101 Oregon Ave(SR397)Corridor Improvement Phase II 2,730,000 - - 200,000 2,530,000 2,730,000
102-103 Road 76 Overpass 50,000 50,000 - - 50,000
104-105 Pedestrian Walkway on Road 68 Overpass 1,250,000 - 1,250,000 1,250,000
106-107 Pedestrian Walkway on Sylvester Street Overpass 1,500,000 1,500,000 1,500,000
Current
Total Project Year Plan Plan Plan Plan Plan Plan Total
Project to Date Anticipated Year Year Year Year Year Year Request
Project Name Cost 12/31/17 Cost 2019 2020 2021 2022 2023 2024 2019-2024
MUMS 94,000,000 495,000 4,876,000 30,770,000 10,788,000 9,379,000 13,421,000 12,701,000 11,570,000 88,629,000
IRRIGATION 2,188,000 - 75,000 1,000,000 453,000 165,000 165,000 165,000 165,000 2,113,000
144-145 Annual Irrigation System Improvements-Development 525,000 25,000 200,000 200,000 25,000 25,000 25,000 25,000 500,000
146-147 Annual Irrigation Upsize-Development 350,000 50,000 50,000 50,000 50,000 50,000 50,000 50,000 300,000
148-149 System Improvement&Rehab Projects 540,000 - 90,000 90,000 90,000 90,000 90,000 90,000 540,000
150-151 Chapel Hffi Boulevard(Road 84 to Road 68) 220,000 220,000 - - - - - 220,000
152-153 Chapel Hill Boulevard to Interstate 182-Irrigation Main 100,000 100,000 100,000
154-155 Chapel Hill Boulevard Pressure Reducing Valve(PRV) 90,000 90,000 90,000
156-157 Irrigation Main Extension-Wrigley Drive 213,000 100,000 1133000 213,000
158-159 System Evaluation Project 150,000 150,000 - 150,000
PROCESS WATER REUSE FACILITY 22,820,000 147,000 2,723,000 17,111,000 2,839,000 19,950,000
204-205 Cohrtnbia East Force Maui&Lift Station 10,509,000 122,000 2,517,000 6,943,000 927,000 7,870,000
206-207 PWRF Solids Handling Improvements 325,000 25,000 - 300,000 - 300,000
208-209 PWRF Irrigation Pump Station(IPS)Improvements 4,454,000 - 183,000 4,271,000 4,271,000
210-211 Foster Wells Automatic Transfer Switch Replacement 173,000 23,000 150,000 - 150,000
212-213 PWRF Prinary Treatment hnprovement 7,359,000 - - 5,447,000 1,912,000 - - - - 7,359,000
SEWER 40,303,000 348,000 1,778,000 10,173,000 5,850,000 5,424,000 5,420,000 6,110,000 5,200,000 38,177,000
162-163 Annual Sewer System Improvements-Development 717,000 17,000 100,000 100,000 100,000 100,000 100,000 100,000 100,000 600,000
164-165 Annual Sewer Upsize-Development 700,000 - 100,000 100,000 100,000 100,000 100,000 100,000 100,000 600,000
166-167 WWTP Facility Capital Improvement Projects 18,696,000 160,000 - - - 3,536,000 5,000,000 5,000,000 5,000,000 18,536,000
168-169 Wastewater Treatment Plant(PLC)s and Controls Upgrade 855,000 - 855,000 - - - - - 855,000
170-171 River Outfall Phase I 6,464,000 - 1,464,000 5,000,000 6,464,000
172-173 Harris Road Sewer Transmission Main 3,829,000 114,000 1,215,000 2,500,000 - 2,500,000
174-175 9th&Washington Lift Station 793,000 27,000 35,000 731,000 - 731,000
176-177 Pearl Street Lift Station 1,173,000 17,000 266,000 510,000 380,000 890,000
178-179 Road 36 Liff Station Upgrades 338,000 12,000 45,000 281,000 - 281,000
180-181 Maitland Lift Station-Purchase/Install 4th Pump 150,000 1,000 17,000 132,000 132,000
182-183 Broadmoor Area Lift Station 3,500,000 - - 3,500,000 - 3,500,000
184-185 Road 52&Pearl Street Lift Station 1,370,000 - 270,000 1,100,000 - - 1,370,000
186-187 Road 84&Roberts Drive Lift Station 1,130,000 - - 220,000 910,000 1,130,000
188-189 Road 44 Corrosion&Odor Control 588,000 588,000 - - 588,000
XXII PAGE
Current
Total Project Year Plan Plan Plan Plan Plan Plan Total
Project to Date Anticipated Year Year Year Year Year Year Request
Project Name MA Cost 12/31/17 Cost 2019 2020 2021 2022 1 2023 2024 2019-2024
UTILITIES 94,000,000 495,000 4,876,000 30,770,000 10,788,000 9,379,000 13,421,000 12,701,000 11,570,000 88,629,000
STORMWATER 1,889,000 - - 200,000 200,000 310,000 779,000 200,000 200,000 1,889,000
192-193 Annual Stomrvater Improvements-Development 600,000 100,000 100,000 100,000 100,000 100,000 100,000 600,000
194-195 Capital Stomtwater Participation Program 600,000 100,000 100,000 100,000 100,000 100,000 100,000 600,000
196-197 North Industrial Way Infiltration Retrofit Project 110,000 - - 110,000 - - - 110,000
198-199 1 st Avenue Pipe Rehab 249,000 - 249,000 249,000
200-201 Sylvester Pipe Relining 330,000 - - - 330,000 - - 330,000
WATER 26,800,000 300,000 2,286,000 1,446,000 3,480,000 7,057,000 6,226,000 6,005,000 26,500,000
110-111 Annual Water System Improvements-Development 700,000 100,000 100,000 100,000 100,000 100,000 100,000 100,000 600,000
112-113 Annual Water Upsize-Development 700,000 100,000 100,000 100,000 100,000 100,000 100,000 100,000 600,000
114-115 Chapel Hill Boulevard Water Main Upsize 920,000 - 920,000 - - - - - 920,000
116-117 Aquifer Storage&Recovery(ASR)System 1,950,000 100,000 - - 350,000 1,500,000 1,850,000
118-119 West Pasco(WTP)Plant Improvements 3,476,000 - 800,000 856,000 1,100,000 720,000 3,476,000
120-121 Butterfield(WTP)-Chlorine Safety 325,000 75,000 250,000 - - 325,000
122-123 Automated Meter Reading 3,750,000 - - 750,000 1,000,000 1,000,000 1,000,000 3,750,000
124-125 Reservoir Storage Tank(s) 11,700,000 150,000 2,850,000 4,200,000 4,500,000 11,700,000
126-127 Water Main Extension-Afton Street(Wehe Ave to the alley west of0wen St) 327,000 - 327,000 - - 327,000
128-129 Water Main Extension-Riverhaven Street(Rd 36 to Rd 40) 305,000 - 305,000 305,000
130-131 Water Main Replacement-Star Lane(Rd 100 to Rd 97) 218,000 218,000 - 218,000
132-133 Water Main Replacement-South 18th Ave(Court St to WA Ave) 73,000 73,000 - 73,000
134-135 Water Main Replacement-Alley East of Wehe Ave 140,000 - 140,000 - 140,000
136-137 Water Main Replacement-Road 60(Court St to W Pearl) 930,000 - 930,000 - 930,000
138-139 Water Main Replacement-Richardson Road(Rd 92 to Rd 96) 460,000 - 460,000 - 460,000
140-141 Water Main Replacement-Road 76(Wemett Rd to Court St) 826,000 - - - - 826,000 - 826,000
223,087,651 7,193,000 11,098,107 83,048,544 37,581,000 30,960,000 17,781,000 16,406,000 19,020,000 204,796,544
XXIII I PAGE
Project Summary by Revenue Source
Current
MrMlProject to Year Total
Total Fund Date Anticipated Plan Year Plan Year Plan Year Plan Year Plan Year Plan Year Request
Page# Project Name Contribution 12/31/17 Cost 2019 2020 2021 2022 2023 2024 2019-2024
INTERNAL CITY FUNDS 27,269,651 379,000 1,819,107 11,533,544 5,319,000 3,839,000 1,100,000 2,235,000 1,045,000 25,071,544
Ambulance Utility Rate 302,500 - - 90,000 87,500 - 125,000 - - 302,500
6-7 Fire Station 81 Remodel 302,500 - - 90,000 87,500 - 125,000 - 302,500
Arterial 4,684,000 42,000 501,000 931,000 1,446,000 19714,000 - 50,000 4,141,000
96-97 City Wide Traffic Signal Improvement Phase II 435,000 - 123,000 183,000 129,000 - - 312,000
68-69 Argent Road Widening(20th Ave to Rd 44) 3,126,000 - 364,000 731,000 317,000 1,714,000 2,762,000
74-75 Road 68 Interchange Improvements 73,000 42,000 14,000 17,000 - - 17,000
70-71 Lewis Street Overpass 1,000,000 - - - 1,000,000 - 1,000,000
100-101 Oregon Ave(SR397)Corridor Improvement Phase II 50,000 - - - - - 50,000 50,000
Capital Improvement REET 1 3,9009651 16,000 372,107 2,612,544 185,000 15,000 700,000 3,512,544
32-33 Dog Park 165,000 - - 165,000 - - - 165,000
26-27 Schlagel Park Improvements 236,000 16,000 - 110,000 110,000 220,000
14-15 City Hall Remodel PhaseII 1,767,544 - 100,000 1,667,544 - - 1,667,544
4041 Comirnmity Park-Northwest 700,000 - - - 700,000 700,000
52-53 Kurlanan Shelter 60,000 - 60,000 - - 60,000
54-55 Parks&Facilities Sign Replacement 50,000 - 20,000 15,000 15,000 50,000
2-3 Fire Station 83 Replacement 272,107 47,107 225,000 - - 225,000
4-5 Fire Station 84 Replacement 400,000 75,000 325,000 325,000
4849 Pasco Sporting Complex Phase II 250,000 - 150,000 100,000 - - - 100,000
Capital Improvement REET 2 7,390,500 184,000 732,000 4,477,000 737,500 905,000 125,000 35,000 195,000 6,474,500
10-11 Animal Control Shelter 2,091,000 44,000 603,000 1,444,000 - - - - - 1,444,000
66-67 Chapel Hill Blvd Extension-LID 150 1,281,000 19,000 - 1,262,000 1,262,000
18-19 Community Center 900,000 - 900,000 900,000
30-31 Highland Park Restroon✓Concession/Storage Building 110,000 - 110,000 110,000
24-25 Peanuts Park Restoration 125,000 104,000 21,000 - 21,000
58-59 Sacajawea Heritage Trail-BNSF Tunnel Passage 700,000 - 50,000 650,000 700,000
6-7 Fire Station 81 Remodel 302,500 90,000 87,500 125,000 302,500
8-9 Fire Station 85 Land Purchase 250,000 - 250,000 - - 250,000
56-57 Sacajawea Heritage Trail-Levee Lowering 1,046,000 17,000 79,000 100,000 850,000 950,000
12-13 Downtown Police Substation&Services Facility 100,000 - 50,000 50,000 - 50,000
60-61 FCID Trail Phase 1 55,000 - - 55,000 55,000
62-63 FCID Trail Phase 2 230,000 - - 35,000 195,000 230,000
50-51 Memorial Pool Upgrades 200,000 200,000 - - 200,000
XXIV P A G E
Current
Project to Year Total
Total Fund Date Anticipated Plan Year Plan Year Plan Year Plan Year Plan Year Plan Year Request
Page# Project Name JW Contribution 12/31/17 Cost 2019 2020 2021 2022 2023 2024 2019-2024
INTERNAL CITY FUNDS 27,269,651 379,000 1,819,107 11,533,544 5,319,000 3,839,000 1,100,000 2,235,000 1,045,000 25,071,544
Economic Development 100,000 61,000 39,000 - - - - - - -
16-17 Wayfinding and Signage 35,000 - 35,000
204-205 Columbia East Force Main&Lift Station 65,000 61,000 4,000 - -
Guarantee Fund 1,058,000 - - 1,058,000 1,058,000
66-67 Chapel Hill Blvd E)dension-LID 150 1,058,000 - - 1,058,000 1,058,000
Park Development 2,287,000 - 52,000 960,000 420,000 255,000 600,000 2,235,000
28-29 Chapel Hill Park 440,000 - 20,000 420,000 - - - 420,000
36-37 Road 54 Park Improvement Erwen Property 195,000 - - - 20,000 175,000 195,000
4445 Sylvester Park Tennis Court Upgrades 80,000 - - - 80,000 80,000
4243 A Street Sporting Complex 172,000 32,000 140,000 - - 140,000
4041 Community Park-Northwest 600,000 - - - 600,000 600,000
34-35 Road 84 Park 800,000 400,000 400,000 - - 800,000
Street 880,000 100,000 280,000 200,000 100,000 1009000 100,000 880,000
90-91 Annual Sidewalk&Complete Street Project 800,000 100,000 200,000 200,000 100,000 100,000 100,000 800,000
94-95 Sandifir Sidewalk Replacement 80,000 - 80,000 - - - - 80,000
Street Overlay 6,358,000 3,000 45,000 1,3059000 2,005,000 750,000 750,000 7509000 750,000 6,310,000
76-77 Crescent Road(Rd 108 to Chapel Hill Blvd) 200,000 - - - 200,000 - - - - 200,000
70-71 Lewis Street Overpass 1,000,000 1,000,000 - - - - 1,000,000
92-93 Pavement Preservation Program 3,360,000 555,000 555,000 750,000 750,000 750,000 3,360,000
72-73 James Street Improvements 528,000 3,000 45,000 480,000 - - - - - 480,000
78-79 Sandi&Parkway Widening(Rd 52 to Rd 60) 250,000 - - - 250,000 250,000
84-85 Sacajawea Park Road Overlay 385,000 385,000 - 385,000
86-87 20th Avenue Court Street to Interstate 182 Overlay 440,000 440,000 - 440,000
88-89 Sycamore,Hugo&Waldemar Grund&Overlay 195,000 - - 195,000 195,000
Traffic Impact Fee 309,000 739000 78,000 - 1589000 - 1589000
96-97 City Wide Traffic Signal Improvement Phase II 158,000 - - - 158,000 158,000
68-69 Argent Road Widening(20th Ave to Rd 44) 151,000 73,000 78,000 - - -
XXV I PAGE
Current
Project to Year Total
Total Fund Date Anticipated Plan Year Plan Year Plan Year Plan Year Plan Year Plan Year Request
Page# Project Nam Contribution 12/31/17 Cost 2019 2020 2021 2022 2023 2024 2019-2024
GRANT 30,331,000 6,441,000 3,584,000 4,701,000 14,355,000 250,000 1,000,000 - - 20,306,000
0.09 Franklin County Grant 500,000 - 75,000 375,000 50,000 - - 425,000
204-205 Collunbia East Force Main&Lift Station 500,000 75,000 375,000 50,000 425,000
CDBG Grant 811,000 678,000 133,000 - 133,000
24-25 Peanuts Park Restoration 811,000 678,000 133,000 - 133,000
Connecting WA Grant 15,000,000 1,053,000 1,0009000 12,947,000 - - 13,9479000
70-71 Lewis Street Overpass 15,000,000 1,053,000 1,000,000 12,947,000 - - 13,947,000
Department of Commerce Grant 2,575,000 1,3399000 1,091,000 145,000 - - 1,236,000
204-205 Columbia East Force Main&Lift Station 2,575,000 1,339,000 1,091,000 145,000 - - 1,236,000
Department of Ecology Grant 1,325,000 75,000 - - 250,000 19000,000 1,250,000
116-117 Aquifer Storage&Recovery(ASR)System 1,325,000 75,000 250,000 1,000,000 1,250,000
Economic Development Administration Grant 65,000 61,000 49000 - - -
204-205 Columbia East Force Main&Lift Station 65,000 61,000 4,000 -
STP Grant 999089000 6,380,000 360,000 1,9559000 1,213,000 - - 39168,000
96-97 City Wide Traffic Signal Improvement Phase 11 2,643,000 - 260,000 1,170,000 1,213,000 2,383,000
70-71 Lewis Street Overpass 6,089,000 6,089,000 - - - -
68-69 Argent Road Widening(20th Ave to Rd 44) 199,000 199,000 - - -
74-75 Road 68 Interchange Improvements 673,000 92,000 100,000 481,000 481,000
82-83 Wrigley Drive Extension 304,000 - - 304,000 304,000
TAP Grant 1479000 147,000 - - 147,000
96-97 City Wide Traffic Signal Improvement Phase H 147,000 147,000 147,000
XXVI I P A G E
Current
Project to Year Total
Total Fund Date Anticipated Plan Year Plan Year Plan Year Plan Year Plan Year Plan Year Request
Page# Contribution 12/31/17 Cost 2019 2020 2021 2022 2023 2024 2019-2024
LOAN 2,683,000 - 183,000 2,500,000 - - - - - 2,500,000
HAEFIC Loan 683,000 183,000 500,000 500,000
208-209 PWRF Irrigation Pump Station(IPS)Improvements 683,000 183,000 500,000 500,000
InterfundLoan 2,000,000 - 2,000,000 - - 29000,000
20-21 Gesa Stadium 2,000,000 - 2,000,000 2,000,000
INSURANCE 500,000 500,000 - - -
4647 Marina Dock Replacement 500,000 500,000 -
MUNICIPALITIES PARTNERSHIP 2,900,000 - 2,900,000 - - 2,900,000
10-11 Animal Control Shelter 2,900,000 2,900,000 - 2,900,000
PRIVATE DONATIONS 170,000 170,000 - 170,000
32-33 Dog Park 35,000 35,000 35,000
30-31 Highland Park Restroom/Concession/Storage Binding 35,000 35,000 35,000
50-51 Memorial Pool Upgrades 100,000 100,000 100,000
PRIVATE PARTNERSHIPS 3,619,000 352,000 903,000 - 29364,000
68-69 Argent Road Widening(20th Ave to Rd 44) 3,619,000 352,000 903,000 - 2,364,000 3,267,000
PROPOSED LID 9,375,000 1,454,000 7,921,000 - - - 7,921,000
66-67 Chapel Hill Blvd Extension-LID 150 9,375,000 1,454,000 7,921,000 - - 7,921,000
REGIONAL MUNICIPALITIES DONATIONS 100,000 - 100,000 - - - 100,000
50-51 Memorial Pool Upgrades 100,000 100,000 - - 100,000
SALES OF ASSETS 7509000 750,000 - - 750,000
2-3 Fire Station 83 Replacement 750,000 750,000 - - 750,000
SCHOOL DONATIONS 100,000 100,000 - -
50-51 Memorial Pool Upgrades 100,000 100,000 - - 100,000
XXVII P A G E
Current
Project to Year Total
Total Fund Date Anticipated Plan Year Plan Year Plan Year Plan Year Plan Year Plan Year Request
Page# Project Name Contribution 12/31/17 Cost 2019 2020 2021 2022 2023 2024 2019-2024
UNSECURED 130,471,000 160,000 1,128,000 45,407,000 15,891,000 23,432,000 13,837,000 13,406,000 17,210,000 129,183,000
Unsecured 44,656,000 - 1,118,000 13,432,000 8,165,000 14,341,000 19700,000 2,370,000 3,5309000 43,538,000
18-19 CornrrnniityCenter 3,150,000 - - 3,150,000 - - - - 3,150,000
70-71 Lewis Street Overpass 10,553,000 - 10,553,000 10,553,000
46-47 Marina Dock Replacement 1,300,000 - 1,300,000 1,300,000
24-25 Peanuts Park Restoration 1,290,000 1,290,000 - 1,290,000
176-177 Pearl Street Lift Station 357,000 - 357,000 357,000
72-73 James Street Improvements 1,039,000 - 1,039,000 - 1,039,000
16-17 Wayfnding and Signage 615,000 190,000 225,000 200,000 615,000
188-189 Road 44 Corrosion&Odor Control 588,000 - - 588,000 588,000
38-39 Road 48 Park Development 750,000 - 750,000 750,000
58-59 Sacajawea Heritage Trail-BNSF Tunnel Passage 750,000 - 750,000 - 750,000
204-205 Columbia East Force Main&Lift Station 7,304,000 1,095,000 5,477,000 732,000 6,209,000
212-213 PWRFPrimary Treatment Improvement 7,359,000 - 5,447,000 1,912,000 - 7,359,000
98-99 Court Street&Road 68 Intersection Improvements 850,000 - - 150,000 700,000 - - 850,000
100-101 Oregon Ave(SR397)Corridor Improvement Phase II 2,680,000 - - 150,000 2,530,000 2,680,000
80-81 Road 100 Widening 1,220,000 - 1,220,000 - 1,220,000
102-103 Road 76 Overpass 50,000 50,000 - - 50,000
122-123 Automated Meter Reading 3,750,000 - 750,000 1,000,000 1,000,000 1,000,000 3,750,000
172-173 Harris Road Sewer Transmission Main 878,000 - 878,000 - - - - 878,000
210-211 Foster Weds Automatic Transfer Switch Replacement 173,000 23,000 150,000 150,000
Unsecured Future Bond 17,250,000 - 17,250,000 - 17,2509000
2-3 Fire Station 83 Replacement 4,944,845 - 4,944,845 4,944,845
4-5 Fire Station 84 Replacement 12,305,155 - 12,305,155 12,305,155
Unsecured Grant 2,815,000 10,000 55,000 - 2,750,000 2,8059000
30-31 Highland Park Restroom/Concession/Storage Budding 65,000 10,000 55,000 - 55,000
104-105 Pedestrian Walkway on Road 68 Overpass 1,250,000 - - 1,250,000 1,250,000
106-107 Pedestrian Walkway on Sylvester Street Overpass 1,500,000 1,500,000 1,500,000
XXVIII I PAGE
Current
Project to Year Total
Total Fund Date Anticipated Plan Year Plan Year Plan Year Plan Year Plan Year Plan Year Request
Page# Project Name Contribution 12/31/17 Cost 2019 2020 2021 2022 2023 2024 2019-2024
UNSECURED m 130,471,000 1609000 1,128,000 45,407,000 15,891,000 23,432,000 139837,000 13,406,000 17,210,000 129,183,000
Unsecured RCO Grant 7,660,000 - - - 19600,000 29275,000 2,560,000 100,000 1,125,000 79660,000
36-37 Road 54 Park Improvement Erwen Property 125,000 - 125,000 - - - 125,000
56-57 Sacajawea Heritage Trail-Levee Lowering 3,650,000 - 1,650,000 2,000,000 3,650,000
26-27 Schlagel Park hnprovenents 500,000 500,000 - - 500,000
42-43 A Street Sporting Complex 900,000 900,000 - 900,000
4041 Connnmity Park-Northwest 1,200,000 - 200,000 100,000 900,000 1,200,000
60-61 FCID Trail Phase I 360,000 360,000 - - 360,000
62-63 FCID Trail Phase H 225,000 - 225,000 225,000
38-39 Road 48 Park Development 500,000 - 500,000 - 500,000
58-59 Sacajawea Heritage Trail-BNSF Tunnel Passage 200,000 200,000 - - - 200,000
Unsecured Revenue Bond 54,309,000 160,000 - 10,889,000 6,126,000 6,816,000 9,577,000 10,936,000 9,8059000 54,1499000
124-125 Reservoir Storage Tank(s) 11,700,000 - - - 150,000 2,850,000 4,200,000 4,500,000 11,700,000
166-167 WWTP Facility Capital Improvement Projects 18,696,000 160,000 - 3,536,000 5,000,000 5,000,000 5,000,000 18,536,000
168-169 Wastewater Treatment Plant(PLC)s and Controls Upgrade 855,000 - 855,000 - - - - 855,000
136-137 Water Main Replacement-Road 60 930,000 - 930,000 930,000
208-209 PWRF Irrigation Pump Station(IPS)Improvements 3,771,000 3,771,000 - 3,771,000
170-171 River Outfall Phase 1 6,464,000 1,464,000 5,000,000 6,464,000
130-131 Water Main Replacement-Star Lane(Rd 100 to Rd 97) 218,000 218,000 - - 218,000
126-127 Water Main Extension-Alton Street 327,000 - 327,000 327,000
138-139 Water Main Replacement-Richardson Road(Rd 92 to Rd 96) 460,000 460,000 460,000
140-141 Water Main Replacement-Road 76(Wernett Rd to Court St) 826,000 - 826,000 - 826,000
128-129 Water Main Extension-Riverhaven Street(Rd 36 to Rd 40) 305,000 - - 305,000 305,000
178-179 Road 36 Lift Station Upgrades 281,000 281,000 - 281,000
184-185 Road 52&Pearl Street Lift Station 1,370,000 - 270,000 1,100,000 - 1,370,000
118-119 West Pasco(W1P)Plant huprovements 3,4769000 800,000 856,000 1,100,000 720,000 3,476,000
182-183 Broadmoor Area Sewer Lift Station 3,500,000 3,500,000 - - - - 3,500,000
186-187 Road 84&Roberts Drive Lift Station 1,130,000 - 220,000 910,000 1,130,000
Unsecured Section 108 Loan 3,781,000 - - 39781,000 - - 3,7819000
24-25 Peanuts Park Restoration 3,781,000 3,781,000
XXIX P A G E
Current
Project to Year Total
Total Fund Date Anticipated Plan Year Plan Year Plan Year Plan Year Plan Year Plan Year Request
Page# Project Name JIIL Contribution 12/31/17 Cost 2019 2020 2021 2022 2023 2024 2019-2024
CURRENT REVENUE BOND 4,860,000 189,000 1,578,000 3,070,000 23,000 - - - - 3,093,000
Utility 2013 Revenue Bond 25,000 25,000 - - -
206-207 PWRF Solids Handling Improvements 25,000 25,000 - - -
Utility 2015 Revenue Bond 946,000 105,000 35,000 806,000 - - 806,000
174-175 9th&Washington Lift Station 766,000 - 35,000 731,000 731,000
120-121 Butterfield(WTP)-Chlorine Safety 75,000 - - 75,000 75,000
176-177 Pearl Street Lift Station 8,000 8,000 - -
172-173 Harris Road Sewer Transmission Main 84,000 84,000
178-179 Road 36 Lift Station Upgrades 12,000 12,000
180-181 Maitland Lift Station-Purchase/Install 4th Pump 1,000 1,000 - - -
Utility 2017 Revenue Bond 3,889,000 59,000 1,543,000 2,264,000 239000 - - 2,2879000
174-175 9th&Washington Lift Station 27,000 27,000 - - - -
176-177 Pearl Street Lift Station 808,000 9,000 266,000 510,000 23,000 533,000
172-173 Harris Road Sewer Transmission Main 2,860,000 23,000 1,215,000 1,622,000 - 1,622,000
178-179 Road 36 Liff Station Upgrades 45,000 - 45,000 - -
180-181 Maitland Lin Station-Purchase/Instaff 4th Pump 149,000 17,000 132,000 132,000
XXX PAGE
Current
Project to Year Total
Total Fund Date Anticipated Plan Year Plan Year Plan Year Plan Year Plan Year Plan Year Request
Page# Project NameMK� Contribution 12/31/17 Cost 2019 2020 2021 2022 2023 2024 2019-2024
UTILITY RATE 9,959,000 24,000 500,000 2,993,000 1,993,000 1,075,000 1,844,000 765,000 765,000 9,435,000
Utility Rate 9,959,000 24,000 500,000 29993,000 1,993,000 1,075,000 1,844,000 765,000 765,000 9,4359000
198-199 1 st Avenue Pipe Rehab 249,000 - - - - - 249,000 - - 249,000
120-121 Butterfield(WTP)-Chlorine Safety 250,000 - 250,000 - 250,000
150-151 Chapel Hill Boulevard(Rd 84 to Rd 68) 220,000 - 220,000 - - - 220,000
144-145 Annual Irrigation System Improvements-Development 525,000 25,000 200,000 200,000 25,000 25,000 25,000 25,000 500,000
146-147 Annual Irrigation Upsize-Development 350,000 50,000 50,000 50,000 50,000 50,000 50,000 50,000 300,000
152-153 Chapel Hill Boulevard to Interstate 182-Irrigation Main 100,000 - 100,000 - - - - - 100,000
156-157 Irrigation Main Extension-Wrigley Drive 213,000 100,000 113,000 213,000
206-207 PWRF Solids Handling Improvements 300,000 300,000 - 300,000
162-163 Annual Sewer System hnprovements-Development 717,000 17,000 100,000 100,000 100,000 100,000 100,000 100,000 100,000 600,000
164-165 Annual Sewer Upsize-Development 700,000 - 100,000 100,000 100,000 100,000 100,000 100,000 100,000 600,000
196-197 North Industrial Way Infiltration Retrofit Project 110,000 - - - 110,000 - - - 110,000
200-201 Sylvester Pipe Relining 330,000 - - - - 330,000 - - 330,000
110-111 Annual Water System Improvements-Development 700,000 100,000 100,000 100,000 100,000 100,000 100,000 100,000 600,000
112-113 Annual Water Upsize-Development 700,000 100,000 100,000 100,000 100,000 100,000 100,000 100,000 600,000
114-115 Chapel Hill Boulevard Water Main Upsize 920,000 - - 920,000 - - - - - 920,000
172-173 Harris Road Sewer Transmission Main 7,000 7,000 - - - - -
116-117 Aquifer Storage&Recovery(ASR)System 625,000 - 25,000 - - 100,000 500,000 - - 600,000
192-193 Annual Stomnvater Improvements-Development 600,000 - 100,000 100,000 100,000 100,000 100,000 100,000 600,000
194-195 Capital Stommater Participation Program 600,000 100,000 100,000 100,000 100,000 100,000 100,000 600,000
158-159 System Evaluation Project 150,000 150,000 - - - - - 150,000
154-155 Chapel Hill Boulevard Pressure Reducing Valve(PRV) 90,000 90,000 - - - - - 90,000
148-149 System Improvement&Rehab Projects 540,000 90,000 90,000 90,000 90,000 90,000 90,000 540,000
68-69 Argent Road Widening(20th Ave to Rd 44) 100,000 - - 100,000 - - - 100,000
74-75 Road 68 Interchange Improvements 50,000 50,000 - - 50,000
70-71 Lewis Street Overpass 500,000 - 500,000 500,000
82-83 Wrigley Drive Extension 50,000 50,000 - 50,000
72-73 James Street Improvements 50,000 - 50,000 50,000
134-135 Water Main Replacement-Alley East of Wehe Ave 140,000 - 140,000 140,000
132-133 Water Main Replavement-South 18th Ave(Court St to WA Ave) 73,000 73,000 - 73,000
223,087,651 7,193,000 11,098,107 83,048,544 37,581,000 30,9609000 17,781,000 16,406,000 199020,000 204,796,544
XXXI I P A G E
Table of Acronyms
ADA -Americans with Disabilities Act PPD-Pasco Police Department
ACS-Administrative Community Services PWRF-Process Water Resource Facility
AFG-Assistance to Firefighters Grant RCO-Recreation and Conservation Office
ASR -Aquifer Storage &Recovery REET-Real Estate Excise Taxes
ATS-Automatic Transfer Switch ROW-Right of Way
BNSF-Burlington Northern Santa Fe SRS-Safe Routes to School
CBC- Columbia Basin Community College STP-Surface Transportation Program
EPA -Environmental Protection Agency TAP- Transportation Alternative Program
FCID-Franklin County Irrigation District TIB - Transportation Improvement Brand
FY-Fiscal Year TREC- Tri-Cities Rivershore Enhancement Council
LLC -Limited Liability Company UGA -Urban Growth Area
MG-Million Gallon UGB- Urban Growth Boundary
MGD-Million gallons per day VFD- Variable Frequency Drive
NW-North West WPWTP- West Pasco Water Treatment Plant
PVC-Polyvinyl chloride WSDOT- Washington State Department of Transportation
PFD-Pasco Fire Department WSRB - Washington Surveying and Rating Bureau
PR -Pressure Reducing Valve WWTP- Wastewater Treatment Plant
PLC-Programmable Logic Controllers
XXXII P A G E
This Page Intentionally Left Blank
XXXIII I PAGE
I Capital Improvement Plan 2019-2024
PASC�
1 /
~rr
L' y
1-
f�t �
f�
Fire Station 83 Replacernent Summary Project Description
Project Number-18001 Relocation and construction of Fire Station 83.The current station location does not allow response times to meet current target times with
the new growth within the c.Ry urban growth boundary.Relocation of the station to proposed location will maintain the current service
Status New demand inside the Pasco UGB within s m inutes or less travel time of a staffed stat lon.
Department Fire
Group General
Assessment Necessary
Principal Need Council Goal
Council Goals Community Safety
r _ ■
Fire Department Master Plan identified the requirement to relocate station to better serve the community Inside the urban growth boundary,
Fire Department Master Plan identifies additional stations to add capacity for Broadmoor area development in order to meet the Council
goal of maintaining the target of 6 minute travel time.
This meets the Council Coal of;
COMMUNITYSAFFTY- Working to ach ievelm aintain target fire response time through operat lonaI improvements and long-range planning
of facilities and staffing.
PROJECT SCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/1017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 272.107 - 47.107 225.000 - 225,000
Land&Right of Way - - - - -
Construction 5,694,845 - 5,694,845 - 5,694.845
Other - - -
Total Experdtures 5.966.952 47,107 5,919,845 5.919.8
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/3112017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Capital Improvement R E E T 1 272.107 - 47.107 225.000 225,000
Unsecured Future Bond 4,944,845 - 4,944,845 - 4,944,845
Sale of Assets 750.000 - 750,000 - - 750,000
Total Funcling 5,956,952 47,107 5,919,845
jML e
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue
Ex uses - -
3 Capital Improvement Plan 2019-2024
c"QTY o�~ Fire Station
; 4 Replacement
PASO
MAM
- -
r
Fire Station 84 Replacernent Summary Project
-roject Nurnber-18002 Relocation and construction of Fire Station 84 which was acquired as part of an asset transfer due to annexation of land. The current station
does not provide for good crew quarters and apparatus access.The current station was not designed with attached crew quo rbers,training
Status New room or the ability to house modern fire apparatus.The replacement will also address additional training and corn munity rooms as well as
Department Fire additional administrative office space to facilitate growth along with the community.
Group General
Assessment Necessary
Principal Need Council Goal
Council Goals Community Safety
Fire Department Master Plan identified the requirement to replace the station to match current staffing requirements(apparatus and personnel}.
This meets the Council Gaal of,
C 0 MMUNITY SA FETY-Working to achievelmaintain target fire response tin a through operational im provernants and long-range planning of
facilities and staffing.
PROJECTSCOPE ■ ■
ol
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 400,000 - 75,000 325.000 - - - - - 325,000
Land&Right of Way - - - - - - - - -
Construction 12,305,155 - 12,305.155 - - - 12.305.155
Ether - - - - -
Total .- 75,000 12,630,155
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 21123 2024 2019-2024
Capital improvement REST 1 400,000 - 75,000 325.000 - - - - - 325,000
Unsecured Future Bond 12,305,155 - - 12.305.155 - - - - - 12,305,155
Total .;ng 12,705,155 75,DOO 1Z630,155i
,155
OPERATIVG MPACT ANNUAL ■
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Revenue - - - -,Expenses - - - -
5 Capital Improvement Plan 2019-2024
Fire Station 81 Remodel
e r
6 Capital Improvement Plan 2019-2024
NumberFire Station 81 Remodel Summary Project Descriptkn
Project 9++ Remodel of Station 81 to accommodate larger crew size.The current station living areas are growing increasingly crowded. The remodel
would include removing two non-bearing walls and upgrades to networking capabilities for Locution installation and accompanying finish
Status Necessary work.Additionally.a water drop is to be installed in Bay 3 to allow for refill of the Type 6 Engine,
Department Fire
Group General FY2020-Additional Turnout Storage and increase restroom capacity
Assessment Necessary
Principal Need Quality Improvement FY2022-Additional Bay area @$250/sq. ft.
Council Goals
This meets the Council Goal of-
COMM UNITY SAFE
f:COMMUNI-TYSAFETY-Working to achievelmaintain target fire response times through operation improvements and long-range planning
of facilities and staffing.
COMMUNITYSAFFTY-Focus on a long-term goal of improving the Washington State Ratings Bureau community rating to Class 4.
PROJECTSCOPE /
Total Project to Scheduled Plan Plan pian Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018_ 2019 2020 2M 2022 2023 2024 2019.2024
Design 40.000 - 15.000 15.000 - 10.000 - - 40,000
Land& Right of Way - - -
Construction 495,000 - - 150,000 145,000 200 000 495,000
Other 70.000 - 15.000 15.000 40 000 - 70,000
Totai Expenditures 605,000 180,000 175,000 251DAM 605,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12131/2017 2018 2019 20 2021 2022 2023 2024 2019-2024
C ital Inn governent RE ET 2 605,000 - 180,000 175,000 - 250.000 605,000
■ ia ,
nPFRATINGMPACT ANNUAL OPERATING
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
ht act 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Revenue - - -
Ex uses - - - -T74
7 Capital Improvement Plan 2019-2024
Fire Station 85 Land Purchase
M�Rwpiv
e r
8 Capital Improvement Plan 2019-2024
Fire Station 85 Land Purchase Summary Project Description
Project Number-19003 Purc hase adequate land for Fire Station 85 to meet Council Goals and provide continuous level of service provision to UGA.
Status New
Departm ent Fire
Group General
Assessment Necessary
Principal Need CouncI Goal
Council Goals Commurity Safe;}
Fire Department Master Plan identifies additional stations to add capacity for Broadmoor area development in order to meet the Council
goal of m aintaining the target of 5 minute travel time.
This m eets the Cou nc il Goal of
COMMUNITYSAFETY-Working to achieve/maintain target fire response times through operation improvements and long-range planning
of fac ilities and staffing.
PROJECT1 ' _ ANNUAL ALLOCATION
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expendifures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2078 2019 2020 2021 2022 2023 2024 2019.2024
Design - - - - -
Land&Right of Way _ - 250,400 - - 250.000
Construction - - - -
Other - - - -
Total •- I III 250,000 250,DOO
Total Projectto Plan Plan Plan Plan Plan Plan Plan Total
Fending Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112097 2018 2099 2020 2021 2022 2023 2024 2019.2024
Qgpdal Improvement REET 2 250,044 - - 254,440 - - 250.000
Total Funding 250,000
iOPERAIINGAWPACTI
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
in act 92/39/2097 2018 2099 2020 2021 2022 2023 2024 2099.2024
Revenue -
Ex nses -
9 Capital Improvement Plan 2019-2024
CITY OF
PASO
'■ r
Th-Cifies
AnimalControl •
A
Animal1312 S i
■
th Avenue
Pasco. Washington 99301
AW .,
Animal Control r I r
Project Number-18004 This construction project wil replace the existing Animal Control facility-The current facityhas outlived its expected life span farthe
building-The new facility will meet the new requirements for animal control facilities-This is a joint project with the Cityof Pasco,
Status Ongoing Kennewick and Richland-
Department ACS
Group Parks
Assessment Necessary
Principal Need Council Goal
Council Goals 0ualty of Life
This meets the Council Goal of.
QUALITY OF LAFE-Commencement of construction of new animal control facility.
PROJECTO•
Total Project to ScheduAed Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 647,000 44,000 603,000 - - -
Land&Right of Way - - - - - - -
Construction 1,444,000 - - 1.444.000 - - - 1,444,000
Other 2,900,000 - - 2-900.000 - - 2,900,000
rrr rrr 603,0004.344.000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Elate Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2012 2019 2020 2021 2022 2023 2024 2019-2024
Capital tnprovementREEf 2 2,091,000 44-000 603.000 1,444,000 1,444,000
Municipalities Partnership 2,900,000 - - 2,900,000 2,900,000
Total Funding III 44,000 603,000 4,344,000 4,344,000
OPERA TiVG IMPA C ANNUAL OPERA
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating tnpact Operating Year Year Year Year Year Year Year Year Request
Impact 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue
-
Expenses - -
11 Capital Improvement Plan 2019-2024
-� Downtown Police Substation & Services
Facility
W Court St W cou n St
z
z
�'IMer�eSt Pasco
W Octave$t >
W Henry St z a
Pasco Police Department
{
W Nixon St
N W Sylvester St p
ti I q
0
G
e 'fs 7 W Shoshone St
Map data 02017 Google
12 Capital Improvement Plan 2019-2024
Downtoym Police Substation
Project 18007 Remodel of office space In Downtown ac Toss from Peanuts Park.
Status Ongoing Secure new,more effective centralized Iocation for PPD in downtown Pasco,that will give police visibility and presence in the center of
Department Police downbotirm and especially Peanuts Park. This is being proposed in coordination with the capital it provements for Peanuts Park and Farmers
Group General IrltarkeL
Assessment Necessary
Principal Need Service Protection
Council Goals Community Safety
Justification
This meets the Council Goal of
COMMUN ITYSAFFTY-Enhancing proactive comm unity policing efforts.
CDMMUNITYSAFFTY-Continued efforts to improve police/community relations.
PROJECTSCOPEr
Tota! Project to Scheduled Plan Plan Plan Pin Plan Plan Total
FxpenMM Project Date Year Year Year Year YOW Year Year Request
Expenses t?/3112017 2018 2019 2020 _ 2021 2022 2023 2024 2019.2024
Design -
Land&Riqht of Way - -
Construction 100.100 - 50.000 50.000 50.000
❑ther -
. . .- . 11111 111 I III
031
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2019 2019 2020 2021 2422 2023 2024 2019-2024
CaV I Im governent REST 2 100 000 50.000 50.000 - 50.000
. r: r 1 1 1 1 1
I'
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/39/2017 2018 2019 2020 2021 2022 2023 2024 2099.2024
Revenue - - - - - -
Ex enses - - -
13 Capital Improvement Plan 2019-2024
City Hall Remodel Phase 11
PASO
y
14
w
f� S
r ` •
Capital Improvement1 • 1
Remodel Phase 111 ! r r
Project City Hall was renovated originally for City use in 1995.Mror renovations have been undertaken in 2003 and 2008.The m ove of the Police
Department
Into new facilities in early 2017 cleared the way for renovators to accommodate some reconfiguration of spaces to better serve
Status New the public a5 well as to house growth of staff expected over the next several years.An initial remodel phase was underway in 2017 to house
Department ACS Information Services.relocate the Prosecutor's Office and Human Resources.Additional phases are contemplated to update windows,
Croup Parks relocate perm fitting services to the 1st floor to better serve the public and provide additional space for Finance and Engineering.
Assessment Necessary
Principal Need Council Goal
Council Goals Quality of Life
1
Improve safety,functionality,and extend functional use of the fac iIity while ac cam m odating m oderate growth needs as a low cost alternative
to building a new fac iIity.
This meets the Council Goal of
QUA1ffYOFtEE-Ongoing efforts to improve effectiveness in the use of public resources in the delivery of municipal services,programs
and long-term maintenance and viability of public Mies-
PROJECTSCOPE
R
Total Project to Scheduled Plan P1art Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/39/2017 2018 2099 2020 2021 2022 2023 2074 2099.2024
Design 100.000 - 100.000 - -
Land&Ri ht of Way - - - - -
Construction 1,667,544 - - 1.667.544 - - 1.557,544
Other -ETotal xpenditures
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 9213912017 2018 2099 2020 20.21 2022 2023 2024 2019.2024
Ca "tal Improvement-REET 1 1.767.544 - 100.0001 1.667.544 - 1.667.544
Total Funding 1,767,5Uii iii 11
OPERATNG MPACT ANNUAL OPERA
Total Plan Plan Plan Plant Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year VkNV Year Year Year Request
i» act 12/39/2097 2019 2019 2020 2021 2022 2023 2024 2099-2024
Revenue - - - - -
Ex eases - - - - - -
1 N
15 Capital Improvement Plan 2019-2024
Wayfinding & Signage
e r
� w
16 Capital Improvement Plan 2019-2024
Signage Summary Project Descdption
Project Number-18008 Project throughout the Tn-Cties in conjunction with TR EC to standardize directional signage to guide visitors and residents to City
amenities,including downtown,recreational activities,restaurants,parks etc-
Status Ongoing
Department ACS
Group Parks
Assessment Necessary
Pnrncipal Need Council Goal
Council Goals Comm unity Transpo0ation Network
Pasco's component of regional wayfinding efforts to improve navigation for residents and visitors.
This meets the Council Goal of
COMMUNITY TRANSPORTATION NETWORK=Undertaking a comprehensive and inclusive transportation planning and analysis
process to include facilitation of traffic flow in matorcorndors.support integration of pedestrian,bicycle and other non-vehrcularmeans of
transportation-
PROJECT
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 92)31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design - - - - -
Land&Right of Way - - - - - - -
Construction - - - - - - - - - -
Other 650-000 - 35.000 190.000 225-000 200.000 - - 615,000
Totalr rrr 35,000 190,000200,000 1315.0130
Total Project to Plan Platt Plan Plan Plan Plan Plan Total
Funding Sources Project bate Year Year Year Year Year Year Year Request
Revenue 1213112017 2078 2079 2020 2021 2022 2023 2024 2019-2024
Economic Development 35.000 35,000 - -
Unsecured Funding 615,000 - 190.000 225,000 200,000 615.000
Total Funding 650,000 III 225,000 200,000 616,000
ANNUAL OPERATING IMPACT
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating inpact Operating Year Year Year Year Year Year Year Year Request
hrpact 72131/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - -
Expenses - - - -
17 Capital Improvement Plan 2019-2024
Community Center
e r
Ile
ew
r
� ftii.
-not•- ' I
18 Capital Improvement Plan 2019-2024
Community Cente r Summary Project Descrip don
The sale of the 7th Avenue Senior Center funds are to be used toward the construction of a new Community Center.The Center is to have
social,active and passive recreational opportunities for the citizens of Pasco.
Status New
Department ACS
Group Parks
Assessment Desirable
Principal Need Council Goal
Council Goals 0ualily of Life
Provide a central venue to hast comm unity interaction,events,and programs,ultimately strengthening the Pasco comm unity identity-
This meets the Council Goal of
QUALITY OFLFE-Contnued efforts to des ignatelacquire adequate site for new comm unity center and comm unity park-
Aff PROJECTSCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 150,000 150,000 150.000
Land&Right of Way 750,000 750,000 - 750,000
Construction 3,150,000 - - 3-150.000 - 3,150,000
Other - - - - -
Total Expenditures 1 all Irl
Total P►o,fect to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Unsecured Funds 3,150,000 - 3,150,000 - - - 3,150,000
Capital Improvement REET 2 900,000 900,000 - - - - - 900,000
Total Funding 4,050,000 ++ 000 3,150,000 - 4,050.000
OPERA
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Inpact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2079-2024
Revenue - - - - - - - -
Expenses 1,200,000 1;00 000 300,000 300,000 300,000 1,200,000
30%rrr-- -ff; 300GDO 300,000 1,200,000
19 Capital Improvement Plan 2019-2024
-� Gesa Stadium
W�
_�- - - (UL 01.171 h^'F
?p
Y.
20 Capital Improvement Plan 2019-2024
Gesa Stadium Project Description
Stadium Upgrades and Irnpromnents:
Replace: Lower box seats
Status New 1 mprovements:Concession Stands, Baseball Field Seating Areas
Department Facilities New Visiting Gubhouse addition, Batting Cage
Group General Upgrade:Lights to LED,Sound System Press Box
Assessment Necessary Gesa Stadum was constructed in 1995 in order to attract a professional basebaI team to Pasco and the TrimCities,The stadium was been continuously utilized
Principal Need Asset Protection as such since its opening In 1995.The staclum is currently leased to Northwest Baseball Ventures I, ILLC.as owner of the Tri-City Dust Devils.
Council Goals Quality of Life The stadium is now over twenty years did and is in need of upgrades,both for maintenance and renewal as well as to continue to meet professional baseball
standards.
This meets the Co unci Goal of.
QUALITY OF LIFE-Ongoing efforts to improve efficiency and effectiveness in the use of public resources in the delivery of municipal services,
programs and long-term maintenance and viabiity of public facilities.
PROJECTSCOPE ! !
Total Project to Scheduled Platt Plan Plan Plan Plan Plant Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 200,000 - 200.000 - - - 200,000
Land&Right of Way - - - - - - -
Construction 1,800,000 - 1,800.000 - - - - 1,800.000
Other - - - - - -Total -
0i0 ire I
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Interfund Loan 2,000,000 - - 2,000,000 - - - - 2,000,000
Total Funding 2,000,000 IIF III FI &1 a,
OPERA OPERATING
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating ftnpacr Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - - - - -
Ex enses - - - - -
21 Capital Improvement Plan 2019-2024
This Page Intentionally Left Blank
22 Capital Improvement Plan 2019-2024
Parks and
0
Recreation
23 Capital Improvement Plan 2019-2024
PASC�
='_�'_ --__� - �� -- _ -__sem-_- _- -_ -•}K�
24 Capital Improvement Plan 2019-2024
Peanuts Park Restoration Description
Project Number-18023 Peanuts Park is centrally located in downtown Pasco and is a focal point of the area. The restoration of this urban park is a key element to the
revitalization and redevelopment of downtown Pasco.The park as we know it today will be demolished and a new park plan will be put in place
Status Ongoing for the area.The final project will include the installation of features such as shade structures,new trees,furniture,green space,restrooms and a
Department Public Works renovated farmers market pavilion-Acquisition of property for replacernent parking may also be included,as well as an area parking study-
Group Parks
Assessment Necessary
Principal Need Council Goal
Council Goals Economic vitality
This meets the Council Goal of:
ECONOMIC VITALITY-Implementation of downtown infrastructure improvements including;Peanuts Park,Farmers Market,and
streetscapelgateway upgrades.
PROJECTO•
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
FXpenditures Project Date Year Year Year Year Year Year Year Request
EApenses 92/37/2097 2018 2019 2020 2029 2022 2023 2024 2099-2024
Design 782,000 104.000 678.000
Land&Right of Way - - - -
Construction 5.225,000 5.225.000 5.225,000
Other - -
:Total Expenditures 6,007,000 104.000 678,000 5,225,000 5,225.000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12137/2017 2018 2099 2020 2021 2022 2023 2024 2099-2024
CDt3G Grant 811,000 678,000 133,000 133,000
Unsecured Section 108 Loan 3,781,000 3,781,000 3,781,000
Capital Improvement REET 2 125,000 104,000 21,000 21,000
Unsecured Funding 1.290,000 1,290,000 1,290,000
Total Funding 6,007,000 104,000 678,000 5,225,iri 5,225,000
OPERATING
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Op crating Year Year Year Year Year Year Year Year Request
Impact 12/39/2097 2098 2019 2020 2021 2022 2023 2024 2019.2024
Revenue _
Expenses - - - -
25 Capital Improvement Plan 2019-2024
F
PASco -
� f
' i i- AJ � w ' •'4 3
k �
r r
i'
* • }syr
Schlagel Park Improvements Summary Project Description
Project N umber-18027 Replace the boat launch,upgrade parking and Ighting,install new restroom facility-The boat launch has faced on the east side which
leaves only one available lane,also in poor condition itself-This is the only launch within m les and is heavily used by the boating public and
Status Ongoing is an integral part of the marina operation.
Department ACS
Group Parks The restroom in the park has also failed and should be moved from its present location[Far north property border]to a location closer to
Assessment Necessary the boat launch,(Far south ptopertyborder)-
Principal Need Council Gaal
Council Goals Economic Vitality 70%of costs will be covered by RCO grant funds-
This meets the Council Goal of:
QUALITY OF LIFE-0 ngoing efforts to inprove effectiveness in the use of public resources in the delivery of m unic.0al services,
programs and Io ng-term maintenance and viabItyof public facilities-
ECONOMiC VITALITY-Identification of alternatives for City/Port of Pasco and other regional partners for coordination on waterfront plan
I plem e ntation and simiarprojects
-
•� 411
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2099 2020 2021 2022 2023 2024 2019-2024
Design 126,000 16 000 - 110.000 110,000
Land&Right of Way - -
Construction 610,000 - - 610.000 - - 610,000
Other - - -
Total Exper 16,000 110,000 610,000 r rrr
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 92!3712017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Captal ImprovementREET 1 236.000 16-000 110.000 110-000 220.000
Unsecured RCO Grant 500,000 - - - 500.000 - - 500.000
ToW Funding 736,000 , 16,000 110,000 610,000 720,000
s
Total 712/y3l/201
Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Request
hrpact 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - - - - - -
Expenses - -
27 Capital Improvement Plan 2019-2024
-� Chapel Hill Park
e r
- :^.�[.,Tie' :�',•''` ti'r,•_ -
I
rte• r_•
28 Capital Improvement Plan 2019-2024
Chapel Hill Park Summary Project Description
Project Number-1B011 5 Acre community park to include trees, green space,playground picnic area and other features comparable to other neighborhood parks throughout the city.
Status Ongoing
Department ACS
Group Parks
Assessment Necessary
Principal Need Council Goal
Council Goals Quality of Life
This meets the Council Goal of:
QUALITY OF LIFE-Continued efforts to d as ig natela cqu i re adequate site for new community center and community park.
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Bate Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 20,000 - 20,000 - - - -
Land 8 Right of Way - - - - -
Construction 420,000 - 420,000 - - - 420,600
Other - - - - -
Total Expenditures fiii 20,000 420,ODO 420,0001
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Protect Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Park Development 440,000 20.000 420.000 - - 420.000
Total i iii 71717
OPERATAVG AIPACT
Total 712/3 /2017
Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Request
impact 2018 2019 2620 2021 2022 2023 2024 2019-2024
Revenue - -
Ex nses 94,621 15,000 15,300 15,606 15,918 16,236 16,561 94,621
iii 15,300 15,606 15,918 16,236 16,561 94 62M
29 Capital Improvement Plan 2019-2024
CITY P� 'Highland
Park
I , e 1 1 1 ' 1
PASO
Storage i 1
•�.� 'til ,-- . '�,,. . ��
Ast
- _ - �- rH1GHLAND PARK
30 Capital Improvement2019-2024
Highland Park RestroonrilConcessionlStorage Summary Project • r
Building
Projectrer- 18017 Construct a restroomlconcessions/storage building at 4ghland Park position centrally between the three feetbaII fields. Electricity,water
and plumbing are already in place. Project would allow the elimination of con ex storage containers currently in the park. Project will
Status Ongoing enhance customer experience through permanent restrooms and concessions,constructed in compliance with AOA requirements.
Department ACS
Group Parks
Assessm ent Necessary
Principal Need Council Goal
Council Goals Quality of Life
This meets the Council Goal of.
QUAL.ITYOF LIFE-Ongoing efforts to irn prove effectiveness in the use of public resources in the delivery of municipal services,
programs and long-term maintenance and viability of public facilities.
PROJECTSCOPE ANNUAL ALLOCATION
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Toral
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 10.000 - 10.000 -
Land 8 Right of Way 200.000 - 200.000 - 200,000
Construction - - -
Other -Total -
•• 210.000 k 11F .II 111 11111
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2418 2419 2020 2021 2422 2023 2024 2019.2024
Capital Improvement REST 2 110.000 - 110.000 110,000
Unsecured Grant 65.000 10.000 55.000 - 55,000
Private Donations 35.000 - - 35.000 - - - - 35,000
Total . r 21 0,0D0 a LIr rr rrr ,i irr
OPERA TJVG IMPA CT ANNUAL OPERATJVG IMPACT
Total Plan Flan Plan Plan Plan Plan Plan Plan Total
Operating inpact Operating Year Year Year Year Year Year Year Year Request
Impact 1213112017 2018 2019 2020 2021 2022 2023 2024 2099.2024
Revenue - - - -
Ex nses - - - -
31 Capital Improvement Plan 2019-2024
Park
PASO -
���� 1 � �+ • �'` ,,� �� * l��� , :rte, �rN ,
''*�`�*, #Tr; C��e5��nimalCo�irol Shelter � �'-i •�
c. �r� ■� , r r �t
• '�;r°' �nR;�; _ ,� ��� �� �'" � 5aca�awea Herttage:T��a�l rking Lat . 7 �" i� �•
,y�,•�.,� � � ,�;. � M�� rivef7��w QarkTra�l•AcceSs � �.
r 1< ee 41 i � •�
• '-£� :�:F `� �' ,�....: •.>. �. _,,, j..arg�e€}ogArea 77ff +.
32
_- '�.a,.• .:�X62.{.:,. .� ��� - I
Y .. ..—w::" ",-"•i����'e:,r.•.• _j-j�Jr-7 a".' - 'r',ve..si
Capital1 1
■aa Park Summary ProjectDescription
ProjectI Build a dog park for the community.This location would allow for Animal Control to utilize the park with potential adoptive animals as they
are located close by.This location is also located at a trail head to the Sacajawea Heritage Trail walking path.allowing for trail users to
Status Ongoing conveniently access the dog park. The facility would be fenced.irrigated and m aintalned by City staff.
Department ACS
Group Parks
Assessment Necessary
Principal Need Council Goal
Council Goals Quality of Life
J M;
This meets the Ccuncil Gcal of:
QUALITYOFLIFF-Ongoing efforts to improve effectiveness in the use of public resources in the delivery of municipal services,
programs and long-term maintenance and viability of public facilities.
PROJECT . •
Total Project to Scheduled Plan Plan Pian Plan Plan Plan Total
Expenditures Project Date Year Year Year Sar Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Desiqn - - -
Land&Right of Way - - - - -
Constructon 200.000 - 200.000 - - - 200,000
Other - - - - - - - -
Total .- . 10,00 MEFI I III I I I LI
Total Project to Plan Plan Plan Pian Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Private Donations 35,000 - 35.400 - - - - 3 5.000
Capital Innrovern erd REST 1 165 000 - - 165.400 - - - - - 165.000
Total Funding I r III 11 III 1 1 1 1 1
Total Plan Plan Plan? Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Requesf
Impact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 20'19.2024
Revenue - - -
Ex 9enses 18.524 1 DDD 3 060 3121 3184 3.247 33121 18 924
.. III 1.1 3,121 3r184 3.247 3.3 12 1 Ou 924
33 Capital Improvement Plan 2019-2024
- Road 84 Park
e r
,.o!rt viwYflus RainF'.':'' _ - ��f�sr
----i i�f — - tim T
,-I
AJ
L.
�
®EB m
' • I'�i ���SEE SYfEET C1.f71 F'j � :: F i�41 4 k I �S SHEET C1 O2 i �I
I •� - P I _ _ _ }: L—_ � I ,. ISI
5 ACRE BOUNDARY +
BOUNDARY _
1
C1.00
34 Capital Improvement Plan 2019-2024
Road 84 Park Summary Project Description
Project N umber-19023 Purchase and develop neighborhood park.
Status New
Department ACS
Group Parks
Assessment Necessary
Pr ncipal Need Council Gaal
Council Goals Quality of Life
This meets the Council Goal of-
QUA LITY
f-QUALITY OF LAFE -Continued efforts to des ignatelacquire adequate site tornew communRycenter and communitypark.
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses !213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 100,000 - 100,000 100,000
Land&Right of Way 300,000 - 300,000 - - 300,000
Construction 400,000 - - 400,000 - 400,000
Other - - - - -
Total Expenditures
:�r
Tote/ Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Soumes Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Park Development 800,000 - 400,000 400,000 800,000
Total Funding 800,000 IIk lk 400,000 800,000
OPERATRVGiMPACT ANNUAL /
Total Plan Plan Pibn Plan Plan Plan Plan Plan Total
Operating impact Operating Year Year Year Year Year Year Year Year Request
kapact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue -
Expenses 76 200 - 15,000 15,000 15,300 15,300 1500 76,200
iii 15,000 15300 15,300 15,600 76,200
35 Capital Improvement Plan 2019-2024
Road 54 Park Improvement Erwen
Property
1
36 Capital Improvement Plan 2019-2024
Road 64 Park Improve me ntErvan Properly Description
Improve parking and picnic area at Road 54 and West Sylvester Street. Park upgrades will be exerc ise-focused and the park will serve as
a hub connecting Sacajawea Heritage Trail routes to the east and west.
Status 0 ngo rng
Department ACS
Group Pa rks
Assessment Necessary
Principal Need Council Goal
Council Goals 0uaity of Life
This m eats the Council Goal of-
QUALfTY OF LIFE -Ongoing efforts to improve efficiency and effectiveness in the use of public resources in the delivery of municipal
services, programs and long-term maintenance and viability of public facilities.
PROJECTSCOPE ANNUAL ALLOCATION
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2422 2023 2024 2019-2024
Design 20.000 20.000 - 20.000
Land&Right of Way - - -
Construction 300000 300,000 3 00,000
Other - -
Total Expenditures1 111 1 111 11 111 1 111
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Park Development 195.000 20,000 175,000 195,000
Unsecured RCO Grant 125,000 - 125,000 125,000
Total Funding err 20,000 300,000 320,000
IL OPERA
Total Plan Play? Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
inpact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue -
Expenses - - -
37 Capital Improvement Plan 2019-2024
Road 48 Park Development
e r
. _ _ -=.saw ,.,�� - _ •
L W PEARL"
12
9
ig
S 12
HfT _: 14
� 15 .
■
I FGEND s 11 d •"
7 PA 0.KING LOT 1100 SPACES,6 AOA] �, SOCCER FIELD IFULL]
2 PARKING LOT(365PACES,9 AOA] 1 SOCCER FI ELO I 4 x
y. S
3 RESTROOM BUILDING 13 SOCCER FIELD(6D.Y 00)
Oq SPLASH PAD 1q GASKET.-LL COURT II 11
OTOT PLAYGROUND 15 MULTI USE SPORT COURTS 0X1
{(1 PLAYGROUND 16 PARK SIGNAGE
7 LARGE SHELTER 17 PROPOSED FIRE STATION LOCATION 13
♦; MEDIUM SHELTERf
ul
18 ROPES CHALLENGE COURSE
OS SMALL SHELTER 79 PO•WIDEACCESS ROAD ;
16 OPEN PLAY AREA 41
_ --- �r♦ a _ _ - - yy� 1
N EW PARK D EVELOPM EN T A R EA --WALKING TAIL ,� ..]�itlC�Y� L}.;rI.I'. �• r��€. ��__p��"_ � fty- �
R
•
ROAD 48 PARK CONCEPT
38 Capital Improvement Plan 2019-2024
Road Development . Description
Project Number Development of recently acquired communtypark.in Central Pasco. Development will include splash pad,sport courts,restrooms,
parking lot,irrigation system,ropes course,trails and open green areas.
Status 0 ngo ing
Department ACS
Group Pa rtes
Ass essm ent Necessary
Principal Need Council Goal
Council Goals Q ua€ty of Life
This meets the Council Goal of:
QUALITY OF LIFE -Continued efforts to designate/acquire adequate site for new com m unity center and com munity park.
QUALITY OF LIFE -Continued efforts to provide additional soccer and sports fields.
-�
Total Project to Scheduled Plan Plan Plan Plan Plan PlanTotal
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2098 2019 2020 2021 2022 2023 2024 2099-2024
Design - - - -
Land&Right of Way - -
Construction 1.250.000 - - 1.250.000 - - 1250.000
Other -
Total ExpendftlfeS 000 0 t rpt
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Unsecured Funding 750,000 750.000 750.000
Unsecured RCO Grant 500.000 - 500.000 500,000
Total Funding 0,0
-A OPERATINGIMPACT
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Mpact 12/31/2017 2018 2019 2020 2021 2022 2423 2024 2019-2024
Revenue -
Expenses - -
39 Capital Improvement Plan 2019-2024
-� Community Park - Northwest
COW>� � 11
lox
13 t r
40ODA
�
ow
40 Capital Improvement Plan 2019-2024
Conrvinity Park-Northwest dw� Summary Project Description
Project 1 Purc hase and Construct a community park located in future BroadmoorlNorthwest are of Pasco.Park will be 20-40 acres and include
parking,playground,restroom facilities,waking trails, rentable shelters andlor buildings and a variety of active and passive green space.
Status Ongoing
Department ACS
Group Parks
Assessment Necessary
Principal Need Council Goal
Council Goals Quality of Lft
This meets the Council Goal of:
QUALITYOFLIFE-Continued efforts to designatelacquire adequate site for new community center and community park.
-. . r r r
Total Project to Scheduled Plan Plan Plan Plan Plan Plat) Total
Expenditures Project Date Year Year Year Year Year Year Yea!' Request
Expenses 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 200.000 - - - 2 - 200.000
Land&Right of Way 1.400,000 - 1.400.000 - 1,400,000
Construction 900.000 - - 900.000 900.000
Other - - - J
Totai Expenditures2.500.000 20D.00D 1,400,000 9M000 2,500,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 9213112097 2098 2019 2020 2021 2022 2023 2024 2019.2024
Park Development 600.000 - - - 600,000 - 600,000
Unsecured RCO Grant 1,200,000 - - - 200,000 100.000 900.000 1.200.000
Capitat Improvement t REET 1 700.000 - - - - - 700.000 700.000
Total . . Z5001000 200,000 1,400,000 900,00 Z500,000
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating inpact Operating Year Year Year Year Year Year Year Year Request
Impact 12/39/7097 2018 2019 2020 2021 2022 2023 2024 2019.2024
Revenue - -
Ex uses 66.245 - - - - 56,245 66.245
41 Capital Improvement Plan 2019-2024
A Street Sporting Complex
�,"Kif-
k
-- _qqww
Opp,
LEGEND
ACCESS DRIVE
PHASE I PARKING LOTWITH LIGHTS
4109 SPACES,d ADA)
PAD AND SHELTER FOR MULTIPLE
PORTABLE RESTROOMS
EAST'A'ST _ {;y SOCCER FIELD NG(FULL SIZE)
PHASEIIPARK• ��!-�-�- �Y�-�� •t�.����- � �,� Sv�}�, mow- lv� �f �v (1O9SPACES.dI ADAOT WITH LIGHTS
PHASE 11 PARKING LOT WITH LIGHTS
1166 SPAC E5,8 All
�7 PARKING LOT RAMP TO UPPER
PARKING LOT
^B SLO PE TO UPPE R F IELDS
[g'AERMANENT RESTROOM!
tJ CONCESSIONS BUILDI NG/SHELTER
4 4 4 8 4 4 L 70 STORAGE BUILDING
I� 77 2 PADS WITH POWER AND WATER
FOR FOOD TRUCKS
12
PHASE I PHASE II i 12 ADA WALK
I .1 12 I 13 PLAYGROUND
1 74 LIGHTED SOCCER FIELD[FULL SIZEy
75 SPECTATOR BLEACHERS
® s I
l..,I111111111111...r1111111111[]�.. g - �. 6
$ ""y` ,3' Illllllllllllll 191171'
� ;illllll[111�,�,.11111111111�^
r I
I
PHASE II PHASE III
s I
I
4 4 4 14 'IS 1A `
� I
I
C± I
I
t 7A' STREET SPORTS COMPLEX CONCEPT
42 Capital Improvement Plan 2019-2024
Street Sporting Corrplex Summary ProjectDescription
- f: Development of City owned A Street property capable of providing&14 multi use sports fields to support growing sport field needs
c"ide.
Status Ongoing
Department ACS
Group Pa rks
Assessment Necessary
Principal Heed Council Goal
Council Goals Quality of Life
This meets the Council Goal of
QUAL1TYOFLEE-Continued efforts to provide additional soccer and sports fields.
PROJECTSCOPEr r�
Total 7ectScheduled Plan Plan Plan Plan Plan Plan Tota!
Expenditures Project Year Year Year Year Year Year Year Request
Ex nses 2018 2019 2020 2021 2022 2023 2024 2019.2424
Design iQQ,Q00 - 100.400 - - 100.000
Land&Right of Way 72,000 - 32.000 40.000 - - 4 0,000
Construction 900,000 - - - 900.000 - - 900,000
Other - - - - - - - -
Total Expenditures 1.072,00.0 32.000 140.000 900.000 1.040,000
Total Project to Plan Plan Plan Plan Plan Plan Plait Total
Funding Sources Project Date Year Year year Year Year Year Year Request
Revenue 1213112017 2016 2019 2020 2021 2022 2023 2024 2019.2024
Park Deveiopm ent 172.000 - 32,000 144.000 - - - 140.000
Unsecured RCO Grant 900,000 - - 900,000 - - 900.000
. .l Funding 1i iii rir i iii sir iii I I III
i
Total Plan Plan Plan Plan Plea Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12131/2017 2018 2019 2020 2029 2022 2023 2.024 2019.2024
Revenue - - - - - - -
Ex en ses 270,000 1 1 30.000 60.000 60,000 60.000 60 OOO 270 000
30,000 60,000 60.000 .r rrr 60,000 270.000
43 Capital Improvement Plan 2019-2024
PASO
Upgrades
i� t• i
lot
44 Capital
ti. �.. Y.
ESTER P�IRK �
■
Improvement
Upgrade s Summary ProjectDescription
Upgrade aging,unusable and underutilized tennis courts. Update fencing and convert two tennis courts to hybrid basketballffutsal courts.
Renovate the remaining tennis court.
Status 0 ngo ing
Department ACS
Group Parks
Assessment Necessary
Principal Need Council Goal
Council Goals Quality of Life
I i
This meets the Council Goal of-
QUALITY OF_LFE -Ongoing efforts to improve effectiveness in the use of public resources in the delivery of municipal services
programs and long-term maintenance and viabildy of public facilities
PROJECTSCOPE •
MM
TotalProject to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design -
Land&Right of Way -
Construction 80,000 80,000 BUM
Other - -
Total Expenditures 80,ODO
:r rrr :r rrr
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Park Development 80.000 i 80.0000 80.DGD
Total r 1 80,000 I1111
I I I 1 1 1 1
OPERATfiVG AIPACTI
Total Plan Plan Pian Plan Plan Plan Plan Plan Total
Operating bnp act Op a rating Year Year Yea r Year Year Year Year Year Request
inpact 12/31/2017 2098 2019 2020 2021 2022 2023 2024 2019-2024
Revenue -
Expenses -
45 Capital Improvement Plan 2019-2024
CITY pF
PASC�
r
r4 -
N r.
•.�
. 1
46 Capital Improvement •
Marina Dock ReplacementProjectDescription
Project Replace 2nd outdated dock which is no longer in compliance nor able to be repaired cost effectively.
Status Ongoing
Department ACS
Group Parks
Assessment Necessary
Principal Need Council Goal
Council Goals Economic Vitality
Y.
This meets the Council Goal of:
QUAL mroF fJEE-Ongoing efforts to improve effectiveness in the use of public resources in the deliveryof municipal services,
programs and long-term maintenance and viability of public facilities.
..OO' ll. i
Total Project to Scheduled PA3n Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 1213112017 2018 2019 2020 2021 2822 2023 2024 2019-2024
Design - - - - - - -
Land&Right of Way - - - - - -
Construction 1,800,000 - 000 000 - - 1,300,000 - - 1,300,000
Total -
:fr rrF
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Unsecured Fund 1,300,000 - - 1,300,000 - 1,300,000
insurance 500,000 - 500,000 - - - - -
:iiiiiill 1111
ii 1111 ii Pill
OPERA77NGMPACT ANNUAL OPERA
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
kn act 12/39/2017 2098 2019 2020 2021 2022 2023 20,24 2099.2024
Revenue - -
Ex enses - - -
I ML a III Py,14 M
47 Capital Improvement Plan 2019-2024
Pasco Sporting
Complex Update
PASC�
Phase 11
48 Capital Improvement Plan 2019-2024
.z
a-'
Pasco Sporting pd. DescriptionProject Number- =+ Remove volleyball courts and install batting cages at Pasco Sporting Complex.The batting cages can be rented to serve as a revenue
stream forthe complex-Project also includes installation of shelters,an off leash dog area,upgrades to better serve customers and make
Status Ongoing the complex the best in the Tri-Gies.Improvements planned in 2019 include the renovation and upgrade of the splash pad.
Department ACS
Group Pa rks
Assessment Necessary
Prncipal feed Council Goal
Council Goals Quality of Life
This meets the Council Gaal of-
-QUALIFY—OF LIFE -Ongoing efforts to improve efficiency and effectiveness in the use of public resources in the delivery of municipal
services,programs and long4erm maintenance and viabilily of public facilities.
•O
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design -
Land&Right of Way - - - - -
Construction 250.000 150,000 100,000 - 100,000
Other -
Total Expenditures I I II 1 111 11 Ilr ii ill
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Capital Improvement REET 1 250,000 - 150,000 100,000 100,000
Total Funding 250,000 + ++► 100,000 100,000
ANNUAL OPERA TIVG IMPACT
Total Plan Plan Flan Plan Plan Plan Plan Plan Total
Operating impact Operating Year Year Year Year Year Year Year Year Request
kapact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue 10.000 2,000 2.000 2.000 2.000 2,000 10,000
Expenses 9,000 1.500 1.500 1.500 1,500 1.500 1.500 9,000
II 3,500 3,500 3,500 3,500 3,5W 19,000
49 Capital Improvement Plan 2019-2024
Memorial Pool Upgrades
e r
! i
.......................................................................................•...............................
iF' .,
Bulkhead
Existing Starting Exlsting.5tarting
t Block Anchors BbckAichors
Practice area 01;7 lanes of 25 yds Practice area#2:7 lanes of 25 ydsLi
4
dk
f
� f
Diving Well ' D141716 I1f1.111: : }
Dome
6LEACHERS
r
'�•......................................................................................................................•
50 Capital Improvement Plan 2019-2024
Memorial Pool Upgrades Summary Project Description
Project Number-19021 Installation of a climate control"bubble"to enable year round use of Memorial Pool.This will allow Pasco to be the only Municipality in the
region with year round regulation-sized pool service.
Status New
Department ACS Additionally,a removable bulkhead will be purchased that will allow the pool to be divided into 2 sections while creating an additional space
Group Parks for sin ultaneous dive events,increasing team and toumain ent capacity_
Assessment Necessary
Principal Need Council Goal Schools and private organizations have partnered with the City in funding.
Council Goals Quality of Life
This meets the Council Goal of
QUALITYOF LFE-Coordination with the Pasco Public Facilities district and the Regional Public Facilities District to fully investigate
alternatives to provide the Pasco voters with a choice to decide on the development of a regional aquatic facility
UALRYOFLFE-Ongoing efforts to improve effectiveness in the use of public resources in the delivery of municipal services,
programs and long-term maintenance and viability of public facilities.
PROJECTSCOPE
Tata! Pro]ect to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12131/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design - - - - - - - -
Land 8 Right of Way - - - - -
Construction 500.000 500.000 - - - 500,000
Other - - - - - -
Total Expenditures 500.000 1 1 11
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213912017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Capital Improvement REET 2 200.000 - 200,000 - 200,000
School Donations 100.000 - - 100.000 - - 100.000
Private Donations 100,000 - - 100,000 - - 100,000
Regional Municipalities Donations 100,000 100,000 - - 100:000
Total Funding 600,000
OPERATING IMPACT ANNUAL 0PERATI1YG MPACT
Total Plan Plan Plan Plan plan Phn Plan Plan Total
Oparafftg lnped Operating Year Year Year Year Year Year Year Year Request
in act 12/31/2017 2018 2019 2020 2021 M2 2023 2024 2019-2024
Revenue -
Expenses - - - - -
51 Capital Improvement Plan 2019-2024
CITY OP
PASO
• r
f'
.} ;�#:-• �^#�. f � .}f �' Y SIL ,+
yr .
--1
Capital52 1 1
Kurtz ■ Description
NumberProject 19020 Installation of a shelter adjacent to the existing splash pad.Currently no seating area or shade for parer"uaroll ians or break area for
splash pad users.
Status New
Departrn ent ACS
Group Parks
Assessment Desirable
Principal Need Council Goal
Council Goals Quality of Life
This meets the Council Goal of.
QUAL ITYOF I FE-Ongoing efforts to improve effectiveness in the use of public resources in the dellmy of municipal services.
programs and long-terns maintenance and viability of public facilities.
PROJECT . -
Tota! Project to Scheduled Plan Plan Puri Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design - - - - -
Land&Right of Way - - - - - -
Construction 60.000 - - 60.000 - - %000
Other - - - - -
Total Expendftures 60.000
Tota! Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year' Year Year Year Year Request
Revenue 1213112017 2018 2019 21020 2021 2022 2023 2024 2019-_2024
CgOal Improvement R E E T 1 60,000 - - 60.000 - 60,000
Total .: . 60,M0 1 111 .I III
IANNUAL OPERA 71VG MPACr
70perating
Plan Plan-T Plan Plan Plan Plan Plan Plan Tota!
Operating Impact Year Year Year Year Year Year Year Year Request
12/31/2077 2018 2019 2020 2021 2022 2023 2024 2019.2024
Revenue -
Ex ses -
53 Capital Improvement Plan 2019-2024
- Parks & Facilities Sign Replacement
e r
LIBERTY
54 Capital Improvement Plan 2019-2024
Facilities - Description
Project will refresh City Logo and signage in front of all City Paries and Facilities.Will be replaced with cast concrete.
Status New
Department ACS
Group Pa rks
Assessment Desirable
Principal Need Council Goal
Council Goals 0 ualily of Life
IMUMME
This meets the Council Goal of-
QUA LITY
f-QUALITY OF LIFE -Ongoing efforts to Iprove effic ie nc y a nd effectiveness in the use of public resources in the delivery of municipal
services,programs and long-term maintenance and viabiiyof public facilities.
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
7Des
enditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
- - -
Land&Right of Way - -
Construction 50,OOo 2Q , ,i =G ;= 00 54,000
Other
Total Expenditures 50,000 20,000 15,ODO 15.000 50,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Capital Improvement REET 1 "0000 20,000 15,000 15,000 50.000
Total Funding 1 1 20,000 15,000 15,DOO 50,000
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
,inpact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue
Expenses -
55 Capital Improvement Plan 2019-2024
-� Sacajawea Heritage Trail - Levee
Lowering
a- �+►� •' , �- �; •�. _ �*` u Multipurpose Trail
* '" t*`> e*��ri 3 a Q Pedestrian Pathway
". Public pen Space ;= a Sidewalk
d
� ��� a 4 ,- r� View Point '
- RailroadBdffer
Q Significant Intersection
Pedestrian Oriented
a - Street Front
e' _
Q Q Qkr�
e10
j-, t44k, C �ptoo
Sacagawea Trail
1 Osprey
Trail Undercrossing Pointe
Columbia River New Sacagawea
Trail Link
56 Capital Improvement Plan 2019-2024
Sacajavi Heritage Trail-Levee Lovaring Summary Project Desictiption
Project will lower exstIng levee height and widen trail to rinprave user safety-The given section is the final podion of the Sac ajawea
Heritage Trail atop a levee at an unsafe height and width.The completion of this project will connect Sacajawea Heritage Trail from Road
Status Ongoing 72 to Road 52
DepartmentACS
Group Parks
Assessment Necessary
Principal Need Council Goal
Counci Goals Comm unty Transportation Network
This meets the Council Gaal of:
COMMUNITY TRANSPORTATION NETVVORi[-Undertaking a comprehensive and inclusive transportation planning and analysis
process to include facilitation oftraffic flow in major corridors,support integration of pedestrian,WWIe and other non-vehicular means of
transportation-
PROJECT SCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12131.12017 2019 2019 2020 2021 2022 2023 2024 2019-2024
Design 196.000 i 7,000 79,000 100,000 100,000
Land&Right of Way - - - - -
Construction 4.500.000 - - 2.500.000 2.000000 4,500,000
Other - - - - -
Total Ex • ttt ttt ttt tt ttt tt ttt tit ttt 1 is
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Pr*d Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Capital hprovemert REEF 2 1,046,000 17.000 79.000 100.000 850.000 - 950,000
Unsecured RCO Grant 3,6503000 - - 1.650.000 2.000.000 3,650,000
Total Funding III I ElfI I l i l I I III III III .r r pit
f
III
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
h?pact 7213712017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - -
Expenses - - - - -
57 Capital Improvement Plan 2019-2024
-� Saca awea Heritage Trail - BNSF Tunnel
Passage
i � 4
AF
MMO
R. M
r �
i L_
i
Y V
f "
1
A 't iVk,Aida
58 Capital Improvement Plan 2019-2024
Description
Project Number-18025 Construct a tunnel underpass connecting the existing Sac ajawea Heritage Trail with Schlagel Parti reverting path users off of SR 397 and
keeping them on the safe trail.Path will link existing osprey Point Trail system with the 5acajawea Trails extending along the riverfront
Status Ongoing through Chiawana Park
Department ACS
Group Parks
Assessment Desirable
Principal Heed Council Goal
Council Goals Community Transportation Network
This meets the Council Goal of:
COMMUNITY TRANSPORTAMN NETWORK-Undertaking a comprehensive and inclusive transportation planning and analysis
process to include facilitation of traffic flow in major corridors,support integration of pedestrian,bicycle and other non-vehicular meads of
transportation-
PROJECT SCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project dare Year Year Year Year Year Year Year Request
Expenses 1213912097 2098 2019 2020 2021 2022 2023 2024 2019-2024
Design 50.000 50.000 50,000
Land&Right of Way - -
Construction 1.600 000 1.600,000 9.600,000
Other -
Total Expenditures1,650,000 NMI di
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 92/31/2097 209E 2099 2020 2021 2022 2023 2024 2019-2024
Capital Improvement REST 2 700,000 50,000 650,000 700,000
Unsecured RCO Grant 200,000 - 200,000 200,000
Unsecured Fundincl 750,000 750,000 750,000
Total Funding 1,650,000
OPERA TJVG OWPACT ANNUAL 1
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating hrpact Operating Year Year Year Year Year Year Year Year Request
kn act 12/39/2017 2098 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - -
Ex R
erases
59 Capital Improvement Plan 2019-2024
-� FCID Trail Phase I
e r
IZZ
at
f
J }•fir "��� !r .
60 Capital Improvement Plan 2019-2024
Description
Construction of a trail and/or linear park from Road 100 to Road 111 above the FC❑covered irrigation ditch-This path would provide a
non-vehicular path linking the north and southem neighborhoods-
Status Ongoing
Department ACS
Group Parks
Assessment Desirable
Principal Need Council Goal
Council Goals Comm urutyTrans portation Network
This meets the Council Goal of
COMMUNITY TRANSPORTATION NETIMORI[-Undertaking a comprehensive and inclusive transportation planning and analysis
process to include facilitation of traffic flow in major corridors,support integration of pedestrian,bicycle and other non-vehicular means
of transportation.
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Tota!
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2422 2023 2024 2019-2024
Design 55,000 55-000 X0
Land IS Right of Way - - -
Construcbon 360,000 360-000
Other - -
Total Expenditum rrrrrr Ir rrr rrr
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project date Year Year Year Year Year Year Year Request
Revenue ??,31/1417 2018 2419 2424 2421 2022 2023 2024 2019-2024
Capital improvement REST 2 55,000 55.000 - 55.000
Unsecured RCO Grant 360,000 - 360.000 360,000
Total Funding iii � III
OPERATAfGMACT 11
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/1017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue -
Expenses 6 - 3,247 3312 6,559
2.47 3,312 6,559
61 Capital Improvement Plan 2019-2024
-� FCID Trail Phase II
� r
f I • /r
J � .
" i .] —
ab 4S 4
JAI
eb
^. * � A• rF lb• + � 1
62 Capital Improvement Plan 2019-2024
FICID Trail Phase 11 Summary Project Descniption
Project N umber-18016 Construction of a trail andlor Inear park from Road 100 to Road 84 above the FCID covered irrigation ditch.
Status Ongoing
Department ACS
Group Parks
Assessment Desirable
Principal Heed Council Goal
Council Goals Community Transportation Network
This meets the Council Goal of:
COMMUNITY TRANSPORTATJONNETWORK-Undertaking a comprehensive and inclusive transportation planning and analysis
process to include facilitation of traffic flow in major corridors,support integration of pedestrian,bicycle and other non-vehicular means of
transportation.
•. ANNUAL ALLOCATION
Total Project to Scheduled Plan Plan Plan Plan Plata Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 121/2017 2098 20.19 2020 2021 2022 2023 2024 2019-2024
Design 35,000 - - - - - - 35,000 - 35,000
Land&Right of Way - - -
Construction 420,000 - - - - - - - 420,000 420,000
Other -
1 011070 1!!
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 121/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Capital tinprovement REEF 2 230,000 - - - - - 35.000 195.000 230,000
Unsecured RCO Grant 225,000 - - 225,000 225.060
Total Funding 455,000
OPERATNGJWPACT ANNUAL I
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Fnpact Operating Yaar Year Year Year Year Year Year Year Request
in act 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - -
Expenses - - - - -
63 Capital Improvement Plan 2019-2024
This Page Intentionally Left Blank
64 Capital Improvement Plan 2019-2024
65 Capital Improvement Plan 2019-2024
Chapel Hill Boulevard Extension -
LID 150
-• - r� i
461
ChWd
■
}
�r.
1 J Y
1
F' J B
r ,
r '
+ GiFF
r � 4
1 _
66 Capital Improvement Plan 2019-2024
ChapelI Summety ProjectDescription
Project Number-16030 This project wit extend Chapel Hit Boulevard from Road 68 to Road 84,and will include the necessary signal improvements at the
intersection of Road 68 and Chapel Hit Boulevard.The extension will provide a circulation route that w it help ease congestion in the Road
Status Ongoing 68 corridor and in addition,will promote economic development for the large vacant parcels between Road 68 and Road 84.The City is
Department Public Works forming an LID with the applicable land owners to assist in the funding of the project.The City will participate in the cost sharing of a 5th
Group Transportation lane on Chapel Hill Boulevard between Road 68 and Road 76,and in the proposed roundabouts at the intersections of Road 76 and Road
Assessment Desirable 84.
Principal Need Qual9y Improvement
Council Goals CommunityTransportation Network
This meets the Council Goal of
RUALIrY OFLFE-This project w it enhance connectwity and ease of access to both Road 100 and Road 68 corridors South of 1-182.
C OMMUNITY TRA NSPOR TA TION NETMRK-This connection will provide an alternate circulation route to both ArgeN Road and
Sandifur Parkway,and serve as a primary arterial for Sc hod,residential,and commercial travel
COMMUNITYSAFE TY-This connection will enhance target fire and EMS response times to residences,schools,and businesses m the
Chapel Hill area-
PROJECTSCOPE ANNUAL ALLOCATION
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Epwml(1 m Project Late Year Year Y"r Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 1.473:000 19.000 1.454.000 - -
Land&Right of Way 30-ODO - - 30,000 30,000
Construction 7,884,ODO - 7.884,000 7,884,00)
Other 2.327.ODO - 2,327,000 2,327,00)
Total Expenditures 111 M0001,454,000 10,241,000 10,241 111
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project bate Year Year Year Year Year Year Year Request
Revenue 12131/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Proposed LID 9,375.000 - 1.454.000 7,921.000 7,921.000
Capital linprovement REET 2 1.281,ODO 19-000 - 1,262.000 - - - 1,262.000
Guarantee Fund 1.058,ODO - - 1,058,000 - - - - 1,058,OOD
TotalIII 19,000 1,454,000 10,241,000 10,241,000
OPERA AL- 1101111111. a
Total plan Plan Plan Plan Plan Plan Plan Plan
oparatltp bead Operating year Year Year Year Year Year Year Year
Impact 1213'112017 20'18 2019 2020 2021 2022 2023 2024 20197-2024
Revenue - -
Expenses - - - - - - -
IM Ifit—t-74
67 Capital Improvement Plan 2019-2024
OF
PASO -
Il��u�
of• -7
I I
i r
y/ ••L •� 14 �i
7.
J
•} *• -
FFM
AN
'C r .9 ..
- ii;•�tiL .rr5 7• I•� *:."i Yr+: ti-� ----. �*+- � ,• L•: .r
Arge nt Road(20 Ave to Rd 44) Summary Project Description
• This project consists of two phases of improvements:
Status 0 ngoing 'Phase 1–20th Avenue to Varney LanelSaraceno Way
Department Public Works 'Phase 11–Varney LanelSaraceno Way to Road 36
Group Transportation
Assessment Desirable The complete project takes into account future traffic capacity needs,that will result in widening,access,and frontage improvements as
Princ pa Need Reduce Future Casts we 11 as intersection control improvements at both 20th Puenue and Road 36.These im provements focus on the needs of the adjacent
Council Goals Community Transportatian Network stakeholders which include the Portof Pasco[Pasco Airport}and Columbia Basin Comm unity College{CBC}-
This meets the Council Goal of:
QUALITY OF LIFE-This project will enhance safety and access for cit¢ens traveling to the Airport,CBC,or using the 20th and Argent
connection as a route to access 1-182-
COMMUNITY TRANSPORTATION NETWORK-This project proactively supports transportation infrastructural needs for this rapidly
developing area,enhancing vehicular traffic flow and ensuring safe and effective pedestrian,bicycle,and other non-vehicular access-
1111:1 ll�l llilll�;l Jill
-� . 1111 4111111111111111 •
Total Project to Scheduled Plan Plan Plan Plan Plan Pion
Expendltrrros Project Dare Year Year Year Year Year Year Year
Expenses 12/3112017 2018 2079 2020 2021 2022 2023 2024
Design 860,000 272,000 242,000 346,000 - -
Land&Right of Way 869,000 - 552,000 - 317,000 - - -
Construction 506ro00 1,288,000 - 4,178,000 -
Other - -7 rrr rrr •• rrr iii -il) . 00 • rii
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12131/2017 2018 2019 2020 2021 2022 2423 2024 2019-2024
STP Grant 199,000 199,000 - - - -
Private Partnerships 3,619,000 - 352.000 903.000 - 2,364,000 - 3,2671000
Arterial 3,126,000 - 364,000 731,000 317,000 1,714,000 - - 2,762,000
Traffic Impact Fee 151,000 73,000 78,000 - - - - -
Stormwater 100,000 - - 100,000 - - 100,000
Total Funding 7,195,000 272,000 794,000 1,634,000
Total Plein Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12+3112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue
Expenses - - - - - -
69 Capital Improvement Plan 2019-2024
- Lewis Street Overpass
�e r�
� 5
� J
I � -
I
yr a
s
k
�T
i
I:;A .i r
70 Capital Improvement Plan 2019-2024
Lewis Street Overpass Summary Project Description
This project will construct a new overpass between 2nd Avenue and Oregon Avenue on Lewis Street to replace the ex sting
underpass,built in 1937,which is deteriorating.R ig ht-of-way acquisition was completed in 2013 and all necessary demolition of
Status Ongoing existing structures on the west side of the proposed overpass where completed in 2014-
Department Public Works
G roup Trans portation
Assessment Necessary
Principal Need Council Goal
Councl Goals Corn munity Transportation Network
This meets the Council Goal of
QUALITY OF LIFE-This project will support the viabtityof downtown Pasco,providing safe and easy access,bridging East and
Central Pasco together.
COMMUNITY TRANSPORTATiON NETWORK -This project is a crucial link in the City's street system,serving as the prmaryof
two cross streets,connecting the East side of Pasco w 9 h the downtown core,south of 1-182.
PROJECTSCOPE ANNUAL ALLOCATION
Total Project to Schedulod Plan Plan Plant Plan Plan Plan Total
Expenditures Project Aare Year Year Year Year Year Year Year Request
Expenses 12137/2077 2018 2019 2020 2021 2022 2023 2024 2419-2024
Design 4,052,0M 1,999,000 1,053,000 1,000,004 - - 1,000,000
Land&Right of Way 4,090,000 4,090,000
Construction 26,DDD,DDO - - 15,447,004 10,553,000 - 26:000:000
Other
Total Expenditures 34,142,000 6,089,000 1.053.000 1,000,ODD 111 1D,553,ODD 27,000,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project ❑ate Year Year Year Year Year Year Year Request
Revenue 12/.31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
STP Grant 6,089,000 6.089.000 - - - - -
Connecting WAGrant 15,000,000 - 1,053,000 1,000,000 12,947,000 - - 1339473000
Arterial 1,000,000 - - - 1,004,000 - 1,000,000
Street Overlay 1,000,000 - - - 1,000,064 - 1,000,000
Unsecured Funding 10,553,000 - - - 10,553,000 - - 10,553,000
Sto rm w ate r 250,000 - - - 250,000 - - 250,000
Water 250,000 - - - 254,000 - - 254,404
Total Funding 34,142,000 6,089,000 1,053,000 1,000,000 IFI 10,553,000 27,000,000
OPERA T#VG MPACT ANNUAL OPERA
Total Plan Plan Plan Plan Plan Plan Plan Plan Tatal
OperatHtg Mnpact Operating Year Year Year Year Year Year Year Year Request
Impact 92/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue -
Expenses - - - - - -
71 Capital Improvement Plan 2019-2024
CITY OP" James
e ee Improvements' ee
PASO
_t k
T�' �� rte• �� `
• -
a
�"�cing east on Js�mes street
James Street Improv ements Summary Project Description
Project Number-16010 This project will improve and widen James St-,a heavily used cross street of 0regon Avenue,in m ed iately so uth of the 1-182 and US-395
intersection-As a majority of businesses along the 0 regon Ave corridor cater to ag-centered business,providing safer access and travel
Status Ongoing for heavy machinery is critical.
Department Public Works
Group Transportation
Assessment Desirable
Principal Need Service Protection
Council Goals Comm unity Transportation Network
This meets the Council Goal of,
COMMUNITY TRANSPORTATION NETWORK-This project will ensure ease of access and improve safetyalong a heavily used
commercial street.
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12131/1017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 153,D00 300".. 45,00u 105,000 - 105:000
Land&Right of Way - - -
Construction 1,464,000 - 375,000 1,089,000 - 1,464,000
Other - - -
Total Expenditures 000iii iii :r iii i.• iii .38
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12131/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Stormwater 50,000 - 50,000 50,000
Street Overlay 528,000 3,000 45,000 480,000 - - 480,000
Unsecured Funding 1.039,000 - - 1.039,000 - - 1,039,000
Total Funding iii 3,000 46,000 480,000 1,089,0001,569,000
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/1017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - -
Expenses - - - -
73 Capital Improvement Plan 2019-2024
CITY OP
PASO -
rry^.L�r j1�5- r .�'ali�,lD=;ut•: - � � l+� � ,a ,,
w +"
CD .`-Y—.ai e -Ur3: Ca rider 1
no Dr i 'legs-ID p ? Ori
5�turna-Di '� ..i eP L-o�is�rille-
oral r. �- m o -ct° k dr
o files R i c ,
rs
a+ `° 0 Q
Dohel'S'-C]r .'�Dadg '-Ur o
si
G0.''dEf'©'ter F 'Iwayr3_• _.3� %� �•
�:.. b is I a C7'r" , ♦ f • q� I r ■ li1 I ..
o - ,�r.i
� ��` � . z ■ ~+ � � ',�+iii`y
ri f
Hrfle:UI'
,E
r '
Road 68 Interchange Improvements A 0-1
Project Number- 105 This project is intended reduce traffic congestion and travel In a while increas mg safety along the Rd.68 corridor. This project will be
com pleted incoordination and partnership w th WSDOT Prelim marydeterminations to reduce congestion in the area may include,but are
Status Ongoing not lim ded to
Department Public Works
Group Transportation -Connecting Wrigley Drive from Convention Dr to Rd 68.
Assessm ent Necessary -Signing and Striping an Burden Blvd and Road 68 to reduce stacking of vehic les in the westbound tumlanes of Burden Blvd at Rd.68.
Principal Need Council Goal Widening of Rd.68 between 1-182 and Chapel Hill Blvd
Council Goals Community Transportation Network
r
This meets the Council Gaal of
QUALITY OF LFE& COMMUNITY TRANSPORTATION NETWORK -Traffic revisions and improvements will increase the efficiency,
effectiveness, and safety of those traveling through this area.while providing greater connectivixyof the City's transportation network.
PROJECTSCOPE ANNUAL ALLOCATION
Total Project to scheduled Plan Plan Plan Plan Plan Plan Total
EM@nditrn Project pate Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 184.000 134.000 50.000
Land&Right of Way - - - - -
Construction 612,000 64,000 548,000 548,000
Other - - -
Total Expenditures iii 134,000i 548,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
STP Grant 673.000 92.000 1 D0,404 481.000 481,460
Storm water 50,000 - 50.000 50,004
Arterial 73.000 42.000 14.000 17.000 - 17,000
Total Funding iii iii 114AOO 648,000 U8,000
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating inpact Operating Year Year Year Year Yaar Year Year Year Request
knpact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue -
Expenses - -
75 Capital Improvement Plan 2019-2024
-� Crescent Road (Rd 108 to Chapel Hill
Blvd)
CHAPEL HIL. BL,
01
CD
w <
P
A
d
R
Llfl
76 Capital Improvement Plan 2019-2024
C re scent Road JRd 108 to Chapel Hill Blvd) Summary Project Description
Project N umber-17012 Improve Crescent Road from Road 108to Chapel Hill Boulevard to a paved roadway section,thereby enhancing roadway connectuity,
and improving the level of service for roadway users in the vicinity by reducing demand on Road 100-
Status Ongoing
Department Public Works
Group Transportation
Assessment Desirable
Principal Heed Service Protection
Council Goals Com county Transportation Network
This meets the Council Goal of
QUALff Y OF LAFE&COMMUNITY TRANSPORTATION NETWORK - This road connection will reduce overall traffic demand along
South Rd.100,while providing a secondary point of ingress/egress for emergency responders.
PROJECTa
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project nate Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 45.000 wr.roo 4171.000
Land&Right of Way -
Construction 155,000 r;r ii j 155,000
Other - _
Total Expendqures 200.000 rrrrr
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project pate Year Year Year Year Year Year Year Request
Revenue M112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Street Overlay 200,000 1-100 200.000
Total Funding 200,000
0PERATJVG IMPACT
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating hrpact Operating Year Year Year Year Year Year Year Year Request
inpact 12137/20'17 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue -
Expenses - - -
77 Capital Improvement Plan 2019-2024
CITY OP" Sandifur Parkway , , 52
to 60)
PASOWidening
78 Capital Improvement Plan 2019-2024
1y i
L
� � 1
r _ �
1 _
Sandifur - .1 Description
' 17001 This project will complete Sandifur Parkway by canstructing the narth half of the street from RDad 60 to Road 52.This will im prove safety
and provide the same street width for the continuation of Sandifur Parkway.
Status New
Department Public Works
Group Transportation
Assessment Necessary
Principal Need Quality improvements
Council Goals CommunityTransportation Network
This meets the Council Goal of:
QUALITYOFLFE&COIN1NUNlfYTRANSPORTATIONNETWORIC-This road completion will provide consistent connection across
San difur P arkw ay,a primary East-West Arterial supporting significant residential trafftc flow.
PROJECTSCOPEr r
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses .1213112017 2018 2099 2020 2021 2022 2023 2024 2019-2024
Design 50,000 50,400 50,000
Land&Right of Way - - - -
Construction 200,000 200,404 - 200,040
,Other - -
Total1. 1 000r, r! t rrr
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2099 2020 2021 2022 2023 2024 2019.2024
Street Overlay 250,000 250,000 250,000
Total Funding 250,000 250,000 250,000
OPERA TfiVG MPAC T ANNUAL r
Total Plan Plan Plan Pian Plan Plan Plan Plan Total
Operating impact Operating Year Year Year Year Year Year Year Year Request
impact 12131/2017 2018 2019 2020 2021 2022 2423 2024 2019-2024
Revenue - - -
Expenses - - - -
79 Capital Improvement Plan 2019-2024
CITY PF , t I t I I t a
co -
�����iiglll I Illlluu�
In
C p 4rt`7 5
pb 7.�^F�•,° yr a .r
�9f�'+ k'
Road 100 Wdening Summary ProjectDescription
Project N umber-19035 This project will mprove traffic conditions by inproving Road 100 from Court Street to Chapel Hill Boulevard- These inprove menis will
include widening and other inprovements such as curb,gutters,sidewalks,bike lanes and landscape strips-
Status New
Department Public Works
Group Transportation
Assessment Necessary
Principal Need Qualty Improvements
Council Goals Comm unity Transportation Network
This meets the Counc i Goal of
QUALITY CF LAFE&COMMUNITY TRANSPORTATION NETWORK -Improving vehicle,pedestrian and bicyclist safely as traffic
volumes inc re ase to and through the R iverview area.
PROJECT19
Total 712MjM/2017
ect to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 120,000 %n i)i)i) 120,000
Land&Right of Way - -
Construchon 1,100,000 ' 1.00 00111 1,100,000
Other - -
Total Expenditures r r r r r rI r,rI rI
Total Plnject to Plan Plan Plan Plan Plan Plan Pian Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Unsecured Funding 1,220,000 - - - 1220,000 1,220,000
Total Funding III r rrr r FrF
OPERATIVGNPACT ANNUAL OPERATING MPACT
Toter Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 1213112017 2078 2019 2020 2021 2422 2023 2024 2019-2024
Revenue - -
Expenses - - - - -
81 Capital Improvement Plan 2019-2024
CITY OF
PASO -
Potential fufure r� - : 4,
roundabout
f 'wrigle . Driv09,e
.r - ,�.a■
}y _ - •, fir- i •.
._a� lam.! f _ _ L 1 • ■ W , AWMMAMILMand +
pet
- # �•-! ,�
- Burden Blvd.
„y,.
rArAr. r F,AV • IL
{
Facing east on Clemente Lane
WrigleyDrive Extension Summary ProjectDescription
15009 This project includes the des On and construction of a"core"road,28 It in width without curb and gutter,for an app roxinate length of 500 it,
connecting Wngley Drive from Convention Drive to Clemente Lane,thus providing a through street to Road 68-Construction w I I also include
Status Ongoing the extension of water and sewer Ines underthe new road section.This project will ease west and southbound congestion at the 8urdenl68
Department Public Works intersection,and is associated with the Rd.68 Interchange Irnprovements project-This project also includes the relocation of an existing
Group Transportation center-pivot irrigation system.
Assessment Desirable
Principal Need Service Protection
Council Goals Comm unity Transportation Network
This meets the Council Gaal of
QUALITY OF LIFE&COMMUNITY TRANSPORTATION NEMORK -This project will increase travel effeciency in the area,and provide
interconnectivity of utilities.
PROJECT SCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 1
213912097 2018 20.19 2020 202.1 2022 2023 2024 2019-2024
Design 59,000 - - 59,000 - - - - - 59,000
Land&Right of Way - - - - - - - -
Construchon 295,000 295,000 295,000
Other - - - - -
rrr rrr rrr
Total Project to Flan Plan Flan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
STP Grant 304.000 304 000 304.033
Storm water 50.000 50.000 50,000
Total Funding iii
OPERATNGAIPACT
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating impact Operating Year Year Year Year Year Year Year Year Request
knpact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue
Expenses - -
83 Capital Improvement Plan 2019-2024
- Sacaj awes Park Road Overlay
� r
i
K
Aa`
84 Capital Improvement Plan 2019-2024
Sacajayna Park Road Overlay Description
' This project will overlay approximately5,000lnear feet of pavement from the intersection at the BNSF Railroad crossing to Highway 12.
Asphalt in this area has deteriorated andlorpieces missing and needs to be resurfaced- The shoulders of road have also broken away,
Status Ongoing causing a very narrow and unsafe traveling lanes-This road is a main thoroughfare for Port of Pasco related activities-
Department Public Warks
Group Transportation
Assessment Necessary
Principal Need Council Goal
Council Goals Comm unity Transportation Network
This meets the Council Goal of-
COMMUNITY TRANSPORTATION NETWORK -Ensuring safe and reliable infrastructure for Port of Pasco activities and maintaining a
critical connection to regional Highway 12-
PROJECTSCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 17/3112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 35.000 35.000 35,000
Land&Right of Way - - - -
Construction - - - - - - -
Other 350-000 350-000 350,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Protect Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 20.18 2019 2020 2021 2022 2023 2024 2019-2024
Street Overlay 385,000 - - 385,000 385,000
Total Funding 385,000 385,000 38ry,000
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating lrnpact Operating Year Year Year Year Year Year Year Year Request
hrpact 92/31/2017 2018 2019 2020 2021 2022 2023 2024 2099-2024
Revenue -
Expenses - -
85 Capital Improvement Plan 2019-2024
-� 20th Avenue Court Street to Interstate 182
e r
Overlay
t W. PEARL ST -; � � M VP PEARL ST
. Y.4��IIr�,s ��. I•wg� a I I 'q ' �I � / - �y -I :11
'� ,ter .-tip- I ". -�„ f • ,��` _ �'�+
'%Ys �� `� w+.• ..+��JII_�_ �'^�pp��LL 'l.`�� �' � x -i .h %l. i
111- ..
.. •ate , `'.- , -. r
�_. "`�--yam '"i -?�.p, *-gym., i�� ��rr•;x ! �. �
W. AGATE ST
F
oz tea.
VP. COURT ST W. COURT ST
I �
86 Capital Improvement Plan 2019-2024
20th Avenue Court Street to Interstate 182 Overlay Summary ProjectDescription
"roject N umber-19039 This project will grind,overlay,&stripe 20th Ave-from Court Street to Interstate 182,curb to curb-Asphalt is deteriorating and in need of
replacement-This area is rated as"Poor"in the Pavement Rating Assessment-
Status New
Department Public Works
Group Transportation
Assessment Urgent
Principal Need Public Safety
Council Goals Comm unity Trans portation Network
This meets the Council Goal of:
OUALIrYOF LFE 8 COMMUNgYTRANSPORTA-A2N NETWORK-This section of 20th Ave serves as one of four 1-182 cross street
entrance/exits into Pasco and this project ensures the pavement is improved to acceptable conditions.
PROJECTSCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 17/3112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 40,000 40.000 40,000
Land&Right of Way - - - -
Construction 400,000 - - 400.000 - - 400,004
Other - - - 1
rotal Expendftires 440.000 440,000 440,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Protect Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Street Overlay 440,000 440.000 440,000
Total Funding • I III I I I I I
OPERA
Total Plan Plan Plan Plan Plan Pian Plan Pian Total
Operating knp act operating Year Year Year Year Year Year Year Year Request
hrpact 92/31/2017 2018 2419 2020 2021 2022 2023 2024 2099-2024
Revenue -
Expenses - -
87 Capital Improvement Plan 2019-2024
-� Sycamore, Hugo & Waldemar Grind &
� r
Overlay
E. HIGHLANDS St
A.
a.
E. -PARKN-EW Blvd
t
.sur
- — - Vin•
.-. E. BROADWAY St_
6
O
r
88 Capital Improvement Plan 2019-2024
Project Description
Project Number-19040 This project will grind and overlay Sycamore-Hugo and Waldemar Avenues between Parkview Blvd and Highland Street(800 block) The
existing asphalt in these areas has deteriorated and/or is missing and needs to be replaced
Status New
Department Public Works
Group Transportation
Assessment Necessary
Principal Need Council Gaal
Council Goals Community Transportation Network
This meets the Council Goal of-
QUALITY OF LilFE d COMMUNITY TRA NSPOR TA TION NETWORK -Provides direct access to over 50 residences and serves the
surrounding neighborhood
PROJECTSCOPE ANNUAL ALLOCATION
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Des gi - -
Land&Right of Way - - - - -
Construction 195.000 - 195 060 195,000
tither - - -
Total Expenditures 000 rrr 111
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2015-2024
Street Overlay 195-000 195,000 195.000
Totaliii 195,000 195,000
OPERA TfiVG Al T J
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
hrpaci 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Revenue - - - - - - - -
Expenses -
89 Capital Improvement Plan 2019-2024
CITY OP" Annual
' , . ' , Complete
' . . . .
Proj ect
PASO
90 Capital Improvement Plan 2019-2024
ti
x.*s
Annual Sidewalk& Complete Streets Project • Description
Project Numbert This protect will remew the 2018 sidewalk inventory completed by staff,develop policies and mei hods to address needs and then construct or replace
missing or damaged sidewalks as recommended A significant amount ofthe sidewalk panels throughout the city are a public safety concern as identified
Status New by and wthin the Counal Goals
Department Public Works
Tree roots are a signAcant reason why many of our panels across the city ha%e Iiked/c racked andlor separated from their foundation causing this public
Group Transportation
safety concern
Assessment Urgent
Principal Need Council Goal These issues are also causing non compliance with ADA sidewalk standards.This protect supports Council Goal#3. There have been over 1,000 sidewalk
Council Goals Community Transportation Network related issues by operational staff.
This meets the Council Goal of.
QUALIT-YQELEE-Improves the use of public resources in the delivery of long-term maintenance of public facilities.
COMMUIIITYTRAIISPORTATIO11IIETWORI( -Supports pedestrian,bicycle and other non-vehicular means of transportation.
COlV MUHITYSAFETY-Reviews the inventory of City sidewalks and considers policies methods to address needs.
PROJECT SCOPEr
Total Project to Scheduled Pram Plan Plan Plan Plan Plan Total
Expenditures Pro)ecr Dare Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
D es ign
Land&Right of Way - - - - -
Construction 800,000 100,000 200.000 200.000 100.000 100.000 100.000 800.D00
Other - - - - - -
Total Expenditures 800,000 100,000 200,000 200,000 100,000 100.000 100,000 800,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 72!3112017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Street 800.000 100.000 200,000 200,000 100,000 100,000 100_000 800,000
Total Funding 800,000, 100,000 200,000 200.000 100,000 100,000 100.000 800.D00
OPERA77fiG IMPACT • •
Total Plan Plan Plan Plan Plan Plan Plan Plan rota!
Operating Impact Operating Year Year Year Year Year Year Year Year Request
In acr 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Revenue j -
Ex V
nses -
91 Capital Improvement Plan 2019-2024
Pavement Preservation Program
� r
r
- - - F d.
L
i �F •yf r ' 'i -��
� r
4
+11 L11 �• r ,
y• 5 s
92 Capital Improvement Plan 2019-2024
rvation P rog ram Summary Project Description
Project N umber-18030 The City has implemented a Pavement Preservation Program to assess and maintain qual ly streets within the City that are free of
potholes and provide good ride quality-This program preserves and extends the life of the streets with low cost methods which help avoid
Status Ongoing reconstruction of those streets-The program includes crack seal,overlay and m ic ros u rfac ing of City streets- Phor&ation its determined by
Department Public Works considering both the Pavement Preservation Program itself and the pavement rating system-This will also encompass 50%of the Alley
Group Transportation Hard Surface project funding.
Assessment !Necessary
Principal Heed Asset Protection
Council Goals Cam m unity Transportation Network
This meets the Council Gaal of-
QUALITY OF LIFE& COMMUNIT Y TRANSPORTA TION NETWORK - Preserving our infrastructure through proactive maintenance
while ensuring quality of life is held to a high standard.
PROJECT SCOPE ANNUALAUOCA77ON
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 1213111017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 125,000 - 25.000 25.000 25,000 25,000 25,000 125,000
Land&Right of Way - - - - - - -
Construction 3,235,000 = 1 530.000 530.000 725,000' 725,000 725,000 3,235,004
Other 1 - - - - - -
Total Expeiidrtures .iiii750.000 3.360.000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213111017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Street Overlay 3,360.000 - 555.000 555.000 750.000 750.000 750.000 3.360.400
Total Funding 3,360,000 555,000 555,000 750,000 750,0N 750,000 3,360,000
Total Plan Plan Plan Pie Plan Plan Plan Plan Total
Operating inp act Operating Year Year Year Year Year Year Year Year Request
inpact 92/31/2017 2018 2019 2020 2021 2022 2023 2024 2099-2024
Revenue -
Expenses -
93 Capital Improvement Plan 2019-2024
CITY U� Sandifur
Sidewalk
ea , e ' aee
PASO
•R:II 6,�� N. •• v I�r.IR � �� I� _- � _ � YIyy �'I �'G
I, " ffffff
_ � • _.. 77
'a`�.•}-�;' .�r�.,«��SW"�'..t fin "�J�'�'��,:f � p -:.�r7`�11GI".W-'N-?'f-�._y�
�`• - :YI, 11V. �:I d , � ����-rE r r� � �s r •i`e��J � 'I - 4'.
E � :-pE,_,W'It., 'I ,�,� �.-.--•-y ,;� I 1111 .
94 Capital Improvement Plan 2019-2024
� � �� �.� V-."I I_� .y„ �, any � I � ��r�`—Y•ir�•�Ir'4 fes':.
Sidewalk -place me nt Summary Project Description
Project N umber-19042 Sandifur Parkway-Sidewalk Repair/Replacement from Road 76 to Road 90 on the north&south sides-This will also include landscaping
modifications-Approximately 125 panels-
States New
Department public Works Sidewalk panels in this location are raised creating a public safety hazard. Many of these panels are lifted as high as 4 inches. There are
Group Transportation a significant amount of trees in this area and the roots of these trees have caused many of the problems-
Assessment Urgent
Prncoal Need Council Goal
Council Goals CommuntyTransportation Network
This meets the Council Goals of:
QUALITY OFLFE-Improves the use of public resources in the delivery of long-term maintenance of public facilities
-
COMMUNITYTRANSPORTATION NETWORK -Supports pedestrian,bicycle and other non-vehicular means oftransportatian-
COMMUNITYSAFETY-Reviews the inventory of City sidewalks and considers policieslmethods to address needs.
PROJECTSCOPE ANNUAL ALL OCA DON
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 5,000 - 5.000 - 5.000
Land&Right of Way - -
Construction 75,000 75,000 - 75.000
Other - - - -8Total Expendaures 0,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 92/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2074
Street 80,000 80.000 80,000
Total Funding 80,000 i iii r k r r
OPERATJVGIMPACT ANNUAL OPERA
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating 6npact Operating Year Year Year Year Year Year Year Year Request
IMpact 92131/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue
Expenses -
95 Capital Improvement Plan 2019-2024
- City Wide Traffic Signal Improvement
� r
Phase II
POWERUNE ROAD Y �1
m
q CL
9ANDIFUR PARNy9AY E\ l
-- g FMO+ ROAD
� x5
0 TRI-CME5 RTC ER T
m N
AIRPORT
a
H SHORO 8 r^
� 1h
aieRi Ca iioy � .C+
a
ARGEROAD ARDENT ROAD
, -----
r PD a x 2 \
uvI OR s
z /z
RICHARCAIDSCO4
wrRP1 TT ST I IRNETT ST
1
� w p S s.a
opq W PEAR ST
Ti G
T
Fcw fR ST ~_ L -
at — WA
� .� —.
sT
R - OE
� Y R 1 WE R ; ❑
�wa�, 1_
IT
�. _ T .
f• /f///} w METAL111E
96 Capital Improvement Plan 2019-2024
City ViAde Traffic Signal Improvement Phase 11 Summary Project Description
Project N umber-18031 Replace all of the City's obsolete signal equipment with updated signal controllers,signal interconnect equipment,opt inized corridor timing
plans,vehicle detection system and emergencyvehicle priority system.Pedestrian access will be upgraded to meet currentADA right of
Status Ongoing way accessibttydesign guidelines for the signalized intersections.
Department Public Works
Group Transportation
Assessment Necessary
Principal Need Service Protection
Council Goals Comm unity Trans portation Network
This meets the Council Goal of;
OUALUXOELFE&COMMUNITY TRANSPORTATION NETWORK -Council is supported by increasing traffic efficiency,pedestrian
and vehicular safety.
PROJECT
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Prlvect Date Year Year Year Year Year Year Year Request
Expenses 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 83,000 83,000
Land&Right of Way 300,000 - 300,000 - - - - -
Construction 3,000,000 - - 1,500,000 1,500,000 - - - - 3,000,000
Other - - - - - -
111 383,000 1,500,000 1,500,000 3,0W,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
TAP Grant 147,000 - 147,000 - 147,000
STP Grant 2,643,000 - 260,000 1,170,000 1,213,000 - - - - 2,383,000
Arterial 435,000 - 123,000 183,000 129,000 - - 312,000
Traffic Impact Fee 158,000 - - - 158,000 - 158,000
Total Funding 3,383,000 383,000 1,500,000 1,500,000 3,000,000
OPERATING IMPACT ANNUAL OPERATING IMPACT
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
knpact 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - -
Expenses - - - - - - -
97 Capital Improvement Plan 2019-2024
Court Street & Road 68 Intersection
Improvements
4 P
f
_ f
. r
•r.
_ �• ,• � ;��'+� - +��~t + -Fir•. '�7 ,��
• F� FF• � S -
y
t
98 Capital Improvement Plan 2019-2024
Court Street& Road 68 Into rsection Improvements Summary Project Description
Project N umber-19043 This project will provide design and construction of Intersection improvements at the intersection of Road 68 and Court Street to improve
efficiency and safety. The recommended inprovements are still being evaluated and determined.
Status New
Department Public Works
Group Transportation
Assessment Necessary
Principal Heed Quality Improvement
Council Goals Community Transportation Network
This meets the Council Goal of:
Q UA LITY OF LIFE-hproves the efficiency and effectiveness of this intersection-
COMMUNITY TRA NSP ORTATAM NETWORK -Contnued emphas is on in p rove in e nts in the Road 6811-182/13urden Blvd-corridor-
PROJECTSCO
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Bate Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 105,000 - 105,000 - 105,000
Land&Right of Way 45,000 - 45,000 - - 45,000
Construction 700,000 - - 700,000 - 700,040
Other - - - - - -
Total Expenditures 850,000 ii iii
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Unsecured Funding 850,000 - 150.000 700,000 850,000
Total4 1 1 t
IL
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
inp act 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - - - - - - -
Expenses -
99 Capital Improvement Plan 2019-2024
�ITY PF Oregon
e ' . ee (SR
397)
Corridor
PASO
%q� [u, PhaseImprovement
I
100Capital Improvement1 • 1
0 re goorrido r Improvr Description
Phase 11
Project N umber-19032 This project will upgrade the existing Oregon Avenue corridor between Ainsworth Avenue and A Street,widening pavement,installing
medianlcurbing in select locations,res trip ing to create left tum lanes at intersections and two-w ay le#4u m between intersecWns-
Status New Installations of sidewalks,curb and gutter,ADA ramps,illumination and stormwater infrastructure will also be included.
Department Public Works
Group Transportation
Assessment Desirable
Principal Need Quality Improvement
Council Goals CommuntyTrans portation Network
This meets the Council Goal of-
COMMUNITY TRANSPORTATION NETWORK -Completion of planned Phase 2 improvements on Oregon Avenue-
PROJECT
7atalProject to Scheduled Plan Plan Plan Flan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 72/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 50,DD0 - - - - 50.000 - 50,000
Land&Right of Way 150,000 - 150.000 - 150,000
Construction 2,530,000 21530,000 2,530,000
;Other - - - -
iotal Expendtufes2,730,000 200,0002,530,00-D 2,730,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2029 2022 2023 2024 2019-2024
Arterial 50,000 50,000 50,000
Unsecured Funding 2,680,000 - 150,000 2,530,000 2,880,000
Total Funding 2,730,000 200.000 2,530,000 2,730,000
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
inpad 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue
- -
Expenses - - - -
101 Capital Improvement Plan 2019-2024
PASO Road 76 Overpass
A.
Aa
102 Capital Improvement Plan 2019-2024
��� sir.' �:r. _. .VrF,r`.• i/ � �-- .,.ir _r _�.. ._«'•ri' ... -
�. - '}r �- i .tri -f'.-p ��`� �► is ' � '"""N + •� ..,. �
Road 76 Overpass Description
Project N umber-19037 Extending Road 76 between Chapel Hit Boulevard and Burden Boulevard will serve as a con nectar between two arterial roadways and
provide an altemative to the congested Road 68 corridor.A feasibility study in 2017 identified this project as a way to increase traffic
Status New efficiency on the Interstate 182 corridor as well-
Department Public Works
Group Transportation
Assessment Desirable
Principal Heed Quality Improvements
Council Goals Community Transportation Network
111M P7111:17F110r,
This meets the Council Goal of
QUALITY OF LIFE 6 COMMUNITY TRANSPORTATION NETWORK -This project will reduce wad times and traffic volumes across 1-
182 at Rd-68-
PROJECTSCO 11111111y /
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Bate Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 50.004 50,000
Land&Right of Way - - -
Construction - -
Other - - -
Total Expenditures 50,000 r tri 111
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Unsecured Funding 50,000 - 50.000 50,000
Total
IL
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
inp act 1213112017 20'18 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - - - - - - -
Expenses -
MEMO
103 Capital Improvement Plan 2019-2024
low
-� Pedestrian Walkway on Road 68 Overpass
� r
i -
104 Capital Improvement Plan 2019-2024
Pedestrian Walkvmy on Road 68 Overpass Summary Project Description
Project N umber-19033 This project wit provide a pedestrian walkway across the 1-182/Rd-68 overpass to allow for safe pedestrian crossing-
Status New
Department Public Works
Group Transportation
Assessment Desirable
Principal Heed Council Goal
Council Goals Community Transportation Network
RIM Plil":M110r,
This meets the Council Goal of
QUALITYOFLIFE 6 COMMUNITY TRANSPORTATION NETWORK -Emphasizes improvements on the Rd-68 Corridor-
/ �
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Bate Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 250,000 250,000 250,000
Land&Right of Way - - - -
Construction 1,000,000 - 1,000,000 1.000,000
Other - -
Total Expenditures rrrr r rrr
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Unsecured Grants 1.250,000 1,250,000 1.250.000
- 1,250,000 1,260,000
IL
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
inp act 1213112017 20'18 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - - - - - - -
Expenses -
105 Capital Improvement Plan 2019-2024
CITY OP" Pedestrian
e , e , / ' on
Sylvester
e e e
Overpass
PASO
ME
106 Capital Improvement Plan 2019-2024
Pedestrian V61kway on SyllvesterStreet Overpass Summary Project Description
Project N umber-19034 Provide a pedestrian walkway at the Sylvester Street overpass at U5 395 to allow for safe pedestrian crossing.
Status New
Department Public Works
Group Transportation
Assessment Desirable
Principal Need Council Goal
Council Goals Comm unity Transportation Network
This meets the Council Goal of:
QUALfrY OF LFE&COMMUNfrY TRANSPORTATION NETWORK -This project improves Comm unity safety for pedestrians and
enhances qualityof life for residents-
PROJECTSCOPE ANNUAL ALLOCATION
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 300,000 - 300,000 300,000
Land&Right of Way - - - - -
Construction 1,200,000 - - - - - 1,200,000 1,200,040
Other - - - -
FMI,
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Protect Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Unsecured Grants 1,500,000 - 1.500,000 1,500,000
Total Funding 1,500,000 1,500,000 1,500,000
OPERATMIMPACT A NNUA L OPERA
Total Plan Plan Plan Plan Plan Pian Plan Pian Total
Operating knp act Operating Year Year Year Year Year Year Year Year Request
hrpact 92/31/2017 2018 2019 2020 2021 2022 2023 2024 2099-2024
Revenue -
Expenses - -
107 Capital Improvement Plan 2019-2024
This Page Intentionally Left Blank
108 Capital Improvement Plan 2019-2024
109 Capital Improvement Plan 2019-2024
Annual Wa t e r System Improvemencs -
�
Development
`
. -
.� . �.
if . . -
�
Ok
-
®\��:�
, � � . . • . - 2� � ����%w��
- �dw . - \�«�� ' � 24L
i
. . . . �� .
I10 Capital I poemm!Mm 2019-2024
Annual Mter System Improve ments- Summary Project Description
Development
Project Number-18036 This is an annual program that addresses waters ystem needs and enables the City to extend water lines when an opportunitypresents
itself with a private development or other Cllyproject(s).The program anticipates future annexations and need to extend waterlines.
Status Ongoing Implementation of this program improves service to the community.
Department Public Works
Group Water
Assessment Necessary
Principal Need Reduce Future Cost
Council Goals Quality of Life
This meets the Council Goal of
CUALffYOFL1FE-this project supports the development and delivery of efficient municipal services.
Total 712/13)1/2
ject to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project ate Year Year Year Year Year Year Year Request
Expenses 017 2018 2019 2020 2021 2022 2023 2024 2019.2824
Design - -
Land&Right of Way - - - - - - - - -
Construction 700,000 - 100,000 100,000 100.000 100.000 100.000 100.000 100,000 800,000
Other - - - - - - - - -
Total Expenditures700.00011 ill 100,000 100,000 100,000 100,000 100,000 100,000 shill
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2421 2022 2023 2024 2019.2024
Utility Rate 700,000 - 100,000 100,000 100.000 100,000 100.000 100.000 100.000 600,000
Total Funding 700,000 1 1 III 100,000 100,000 100,000 100,000 100,000 100,000 600,000
OPERA TJVG IMPACT
TotalPlan Plan Plan Plan Plan Plan Plan Plan Total
Operating lnpact Operating Year Year Year Year Year Year Year Year Request
inp act 12/31/2017 2018 2019 2020 2021 2022 2023 2424 2019.2024
Revenue - - - - - - -
Expenses - - - - - -
Net Impact
111 Capital Improvement Plan 2019-2024
Annual Water Upsize - Development
�eMmqpwk
i
f
' w _ -- ,.rte •�+����
41
,_ - �, �,• ;�; F . _*'� moi. ;�
112 Capital Improvement Plan 2019-2024
Annual Water Upsize -Development Summary Project Descriptim
-roject Number-18037 This project consists of setting aside an annual allotment of funds to be used to pay for potential upsizing of water lines related to
developer installed lines.
Status Ongoing
Department Public Works
Group Water
Assessment !Necessary
Principal Need Reduce Future Cost
Council Goals Quality of Life
This meets the Council Goal of.
QUALITY OF I FE-This projects supports the de,aelopment and delivery of efficient municipal services resulting in a higher quality of life.
PROJECTSCOPEr a
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
_Expenses 1213111017 2418 2099 2420 2.021 2022 2023 2024 2019.2024
Design - - - - - - - -
Land&Rght of Way - - - - - -
Construction 700,000 - 100,000 100,000 100.000 100.000 100.000 100.000 100.000 600.000
Other - - - - - - - - -
Total Expenditures rl rrl 100,000 100.000 100.000100,000 100,000 100,000 100.000 600,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
UtW Rate 700,000 - 100,000 100,000 100,000 100,000 100,000 100,000 100,000 800,000
Total Funding II 111 100,000 100,000 100,000 100,000 100,000 100,000 100,000 .11111
OPERATING
Total Plan Plan Plan plan Plan Plan Plan Plan Total
Operating hrpact Operating Year Year Year Year Year Year Year Year Request
Impact 12131r70f7 2018 2019 2020 202'1 2022 2023 2024 2019.2024
Revenue -
Ex enses - - - - - -
113 Capital Improvement Plan 2019-2024
-� Chapel Hill Boulevard Water Main Upsize
� r
R4 ` 4
U3
Ckqddill Blvd. �
114 Capital Improvement Plan 2019-2024
Chapel BoulevardWater MainUpsize SummaryProject Description
Project18038 This project will accommodate future growth and capacity needs. The City will partner with developer(s)in upsiikrg 6,400 linear feet of
domestic water line from the required 8"standard specification to 16",along Chapel Hil Blvd between Rd.84 and Rd.68.
Status Ongoing
Department Public Works
Group Water
Assessment Desirable
Principal Need Reduce Future Cost
Council Goals Financial Sustainability
This meets the Council Goal of
Economic Vitality and Financial Sustainability -This project seeks to ensure City infrastructure is developed with future growth in
mind.
. •
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2097 2.098 _ 2019 2020 2021 2022 2023 2024 2099.2024
Design - - - - - - - -
Land 81 Right of Way - - - - -
Construction 920,000 - - 920,000 - 920,000
Other - - - -
Total Expenditures • x000 rrrr rrrr
Total Project to Plan Plan Plan Plan Plant Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 1213112017 2098 2019 2024 2029 2022 2023 2024 2099.2024
Qtil Rate 920,000 920,000 - - 020.000
Total Funding 920,000 i iii r.
OPERATING OPERA
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12131/2017 2018 2019 2020 2021 2022 2023 2024 2099.2024
Revenue - - -
Ex nses - - - - - - -
Net Impact
115 Capital Improvement Plan 2019-2024
CITY QF Aquifer
' e Storage
& Recovery (ASR)
PASC�
���� ���� System
x
_ `M1
- _ _� �� `�r .l f' _ � �yj���.,�.- #{v. i' •tip,
_ � ���� -. #� •tri...- `(} ti
� t -
116 Capital Improvement1 • 1
Aquifer Storage&Recovery(ASR)System Summary Project Description
• 19049 The ASR concept is to reduce the City of Pasco's diversion from the Columbia River by providing the opportunity to store water
underground in a naturally occurring storage aquafer or"reserioir'during peak months and withdraw that water during high demands
Status New times.The City applied for and received a grant for$75.000 from the Department of Ecology-Office of Columbia River for a feasibility
Department Public Works study of this concept.The City will invest an additional$25,000to successfully complete this effort in 2018. if the feasibility studyshows
Group Water that an ASR is something the City could and should explore further.additional funding is planned to develop this concept to construction of
Assessment Necessary an ASR system. Costs in 2021 and 2022 are estimates at this time. More information well be available upon completion of the feasibility
Principal Need Service Protection study.
Council Goals Quality of Life
Y
This meets the Council Goal of:
O[1A11rYOF IEE -This project seeks to provide a sustainable mechanism for water delivery promoting a high quality of life for citizens.
PROJECT / •
Total Project to ScIieduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 121312017 2098 2019 2020 2021 2022 2023 2024 2019.2024
Design 350.000 - 100.000 - - 250.000 - - - 250,000
Land& Right of Way 100,000 - - - 100,000 - - - 100,000
Construction 1.500.000 - - - 1,500,000 - - 1,500,000
Other - - - - - - - -
Total Expenditures r rrr 100,000 350,000 1,500,000 1,850,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Department of Ecology 1.325,000 - 75,000 - - 250,000 1,000.000 - - 1,250,000
Utility Rate 625.000 - 25.000 - - 100,000 500,000 - - 600,000
Total Funding 1,950.000 I t l i l l 350,000 1,500.000 1,850.000
OPERA TiVG MPACT A NNUAL OPERA
Total Plan Plan Plant Plan Plan Placa Plan Plan Total
Operating lnpact Operming Year Year Year Year Year Year Year Year Request
ha acr 1213912017 2018 2099 2020 2029 2022 2023 2024 2019-2024
Re:enue - - - -
Ex enses - - - - - - -
117 Capital Improvement Plan 2019-2024
- West Pasco (WTP) Plant Improvements
e r
� _-
4Y.FL T 5i.,�ti.�f� s�'.�'£✓[yg�� �.. �
�fix-
4zE4 \
5� '2�� :�� F� � �"��"'•''"^.;�i'.���'�� � Y � .._ FBF
-.r.��'�`Y .:��+�'�� �€� - .�. a ,fir `1-! •' r, rT
1
'SM
OIL
;° 11V• Court
as
a _
z_
118 Capital Improvement Plan 2019-2024
Mst Pasco P)Plant ImprovementsDescription
- 16DOO The West Pasco Water Treatment Plant(WPWTP)will require addrbonal treatment and pumping capacity to accommodate future growth
within the City.This project includes a high service pump station.additional fitter backwash capability and the addiltion of two banks of
Status 0 ng of ng m is ro f Iters.
Department Public Works
Group Water The overall project(identified in the Water Comp Pian as 5-001-PS)increases water output from 6 to 12 million gallons per day(MGD).
Assessm ent Necessary This work will 1nclulde the planned PALL micro-fiiter expansion project.Although the West Pasco W TP expansions will increase potable
Princ[pal Need Service Protection water output from 6 MGD to 12 MGD,this project will be designed and constructed to process the backwash flows for the ulth ate
Council Goals Quality of Life production capacity of 18 MGD.This is being dome due to the need of obtaining EPA approval to discharge the waste stream to the
Colurnbia River.
This meets the Council Goal of
QUA IJTYOFLIFE -Th Is projects supports the development and delivery of efficient municipal water service,ensuring safe and sufficlent
water resources are available to provide necessary qua€4 of Iife.
PROJECT SCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 1,230.000 - - 800.000 430.000 - - - - 1,230,OOO
Land&Right of Way - - - - - -
Construction 2.246.000 - - 426.000 1.100.000 720.000 - 2246,000
Other - - - - - - - -
Total .: 000 800.000 856,000 1,100,000 720,0003,476,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2.019 2.020 2021 2022 2023 2_0_24_ 2019.2024
Unsecured Revenue Bond 3.476,000 - - 800.000 856,000 1.100.000 720.000 - - 3,476,000
., . - 800,000 856,000
iii 72%000 ................... 3,476,000
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating inpact Operating Year Year Year Year Year Year Year Year Request
lm act 12/39/2097 2018 2099 2020 2029 2022 2023 2024 2019.2024
Revenue
Ex nses - - - - -
119 Capital Improvement Plan 2019-2024
- Butterfield (WTP) - Chlorine Safety
�e r�
. 4 I
11 �
4
4
w
M �
64
r
120 Capital Improvement Plan 2019-2024
Butterfield Project Description
Project17004 This project consists of the installation of emergency air cleaning equipment at the Butterfield Water Treatment Plant,The system is
designed to remove contaminants from the atmasphere in the event of an accidental chlorine release.This safety improvement will bring
Status Ongoing the facility into compliance with the provisions of the 2015 Intemational Fire Code.The proposed improvements bring the facility into
Department Public Works current fire code compliance.The existing ventilation and abatement system was installed in 1987 and is no longer adequate to meet
Group Water current standards.Without these improvements,a sheared valve or punctured cylinder could not be repaired before the contents of the
Assessment Necessary one-ton chlorine cylinder had been discharged.thereby endangering both employees and the public.This safety improvement provides
Principal Need Ser.ice Protection greater protection to the public and first responders should such an event occur.This equipment is used to contain the toxic atmosphere
Council Goals Quality of Life thereby eliminating the active risk to the public and emergency services personnel.
This meets the Council Goal of:
QUALITY OF LEE-This projects supports the development and delivery of efficient municipal water service,ensuring safe and sufficient
water resources are available to provide necessary quality of I ife-
PROJECTSCOPE ANNUAL ALLOCATION
Total Pmject to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/312017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 75,000 - - 75,000 - - - - - 75,000
Land&Right of Way - - - - - - - - - -
Construction 250,000 - - - 250.000 - - - - 250,000
Other - - - - - - -Total -
000 75,000 250.D00 325,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/39/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Utility 2015 Revenue Bond 75,000 - 75,000 - - - - - 75,000
LifilkyRate 250,000 - - - 250,000 - - - - 250,000
■r.l Fundinr 325,000 75,000 250.000 325AN
OPERA TING AfPA C T ANNUAL OPERATAfG IMPACT
Total Plan Plan Plan PAW Plan Plan Plan Plan Total
Operating inpact Operating Year Year Year year Year Year Year Year Request
Rn act 121312017 2018 2019 2020 2029 2022 2023 2024 20.19.2024
Revenue - - - - - - - - -
Ex r.
nses - - - - - - - - -
121 Capital Improvement Plan 2019-2024
-� Automated Meter Reading
� r
Onnrinnnno]
E..lI J U U U U
GRY ilavF4 OFF L�
HIDWIQ' 2100
;y7.:•H�.'77 iYSliDO . 51X':1 rtw �t
'l' :�15196{ilfi7l U.N...l7'f.. :44)w .
PAAFT.6F'-1 N•r 61
µ�JI�YL_,i Et
- A 1$s'iU 1747YfEflVl3i '
i
* p 6
122 Capital Improvement Plan 2019-2024
Automated Meter Reading Summary Project Description
-roject Number-18050 This project would replace approximately 19,000 mechanical water meters and/or meter registers with new electronic encoder meters and
registers,which would allow for automated meter reading which is faster,more accurate and provides more information regarding leaks and
Status Ongoing high consumption.
Department Public Works
Group Water
Assessment Desirable
Principal Need Quality Improvement
Council Goals Quality of Life
This meets the Council Goal of:
FIVANCG4L SUS.TANABL(TY-Continuation of cost of ser*e+recovery targets in evaluating City services.
QUAL11YOFLEE - Ongoing efforts to im prove efficiency and effectiveness in tie use of public resources in the delivery of municipal
services. programs. and long-term maintenance and viability of public facilities.
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design - -
Land&Right of Way - - - - - - -
Construction 3,750.000 - - - 750.000 1,000.000 1.0x0,000 1,000,000 3,750,000
Other - - -Expenditures -
Total r i0 750.000 1,000,000 1,000,000 1.000,000 3,750.000
Tofaf Project to Plan Plan Plan Plan Plan Pfau Plan Total
F"ngSotwces Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Unsecured Fund 3.750.000 - - - - 750.000 1.000.000 1.000.000 1.000.000 3.750.000
Total Funding 3,750,000 750,000 1,000,000 1,000,000 1,000,000 3,750,000
1
Total
712J312
Plan Plan Plan Plan Plan Plan Plan Total
operating Impact Operating Year Year Year Year Year Year Year Request
in act 2018 20'19 2020 2021 2022 2023 2024 2019-2024
Revenue - -
Ex nses - -
..
123 Capital Improvement Plan 2019-2024
CITY OF
PASO -
�,�i���lul�ll
j1 L
wr, '
Ar
cation
A �
-d
f
r 1
+n■. 46 a I
Ii06
l A
'I� 1^ - S ' • 1 � . rill� i
do
I 1
Reservoir Storage ■ ■
18041 This project would help identify a future reservoir that can best serve the c Ry for it's domestic water needs. This would inc Jude the
evaluation of two reservoirs.one previously identified in the eastern part of town,and one to serve the northwest area in consideration of
Status New the large increase in future population.The results would identify one location to best serve the cities future needs.
Department Public Works
Croup Water
Assessment Necessary
Principal Need Service Protection
Council Goals Economic Vitality
This meets the Council Goal of:
This project seeks to ensure City infrastructure is developed with future growth in mind.supporting Council goals of Economic Vitality
and Financial Sustainability. hile providing a healthy and suff c lent water utility providing the nec essary OnalitV of Life.
------------
.. ill 1111
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Fxpendrtures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
design 3.000.000 - - - 150.000 2.854.040 3.400.000
Land&Right of'v','ay - - - - - -
Constructlan 8.740.400 - - - - - 4.200.044 4,540,000 8.740,000
Other1Total Expenditures 1,700,000 150.000 2.850,0DO4,200.DDO 4.5 M 0 00 11.7C)0.000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Unsecured Revenue Bond 11.740,400 - - 154,000 2.850.400 4,206.000 4,500.000 11,700,000
TotW Furding 11,7MCOD A 150,DOO 2,850POO 4,200,D00 4,5W,DDO 11,7DO,ODO
o• o•
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating inpact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2017 2018 2019 2024 2021 2022 2023 2024 2019-2024
Revenue -
Ex enses - - -
125 Capital Improvement Plan 2019-2024
CITY OF
PASCO
a
«x.
"vva . _
F _
C. a 46" 1 'L
`-
w
•
w
i
Wate r M a in E xten si on -Alton Stree t(We h e Summary Project Description
Ave to the al I ey west of Owen St)
+ 18046 This project will install approximately 700 linear feet of 8 inch ductile iron water main along Alton Street from Wehe Avenue to the alley west
of Owen Avenue.One fin=hydrant would be installed at the intersection of Wehe Avenue and Alton Street.The existing fire hydrant on Afton
Status Ongoing Avenue between Owen Street& Beech Street will be replaced and connected to the proposed main on Alton Avenue.This project helps
Department Public Works loop the watersystem and eliminate dead ends in the area.Looping the system with a properly sized water main will provide opportunityto
Group Water replace a fire hydrant installed on an undersized main and install an additional fire hydrant.Having the proper distribution of fire hydrants
Assessment Desirable can help elevate our rating with the Washington Surveying and Rating Bureau and may help improve the fire insurance rates that property
Principal Need Quality improvement owners pay.
Council Goals Quality of Life
This meets the Council Goal of:
OUALITYOFL EE -This project will enhance community safety through hydrant availability while ensuring consistent qualityand service
of the water utility.
•OO•
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 65,000 - - - - - 65,000 - - 65,000
Land&Right of Way - - - - - - -
Construction 262,000 - - - - - 262,000 - - 262,000
0 ther - - - - - - - - - -
Total Expenditures 327,00000327,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213111017 2018 2019 2020 2421 2022 2023 2024 2019-2024
Unsecured Revenue Bond 327,000 - - - - - 327,000 - - 327,000
Total Funding 327,000 i t 327,000
OPERA TAfG IMPACT ANNUAL OPERATNG IMPACT
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating knpact Operating Year Year Year Year Year Year Year Year Request
kn act 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - - - - - -
Ex uses - - - - - - - - - -
127 Capital Improvement Plan 2019-2024
CITY OP , , ' • ,
PASO
JAL
$ -
74
�- ��� ,• J � 8�� � ter:•' � � _
l A .
,
AF
4� ���, �� 4 � •� ��1��� � �_" .a �.r ' e� '�!R� Ry�•I a.. �L "4a° � r -y r _
o
�4
,
F
Water Main Extension- - Description
to -. 40) 1 a
Project N ■ 18048 This project would install approximately 1,400 linear feet of 8 inch ductile iron water main along Riverhaven Street from Road 36 to Road
40-The dead end water mains at the southern end of these streets would be connected to the new water main,This connection would
Status Ongoing help loop the water system which would improve flow characteristics of the system and eliminate dead ends in the area. Looping the
Department Public Works system with a properly sized water main will provide betterflow forthe fire hydrants in the vicinity-Having the proper distribution of fire
Group Water hydrants can help elevate our rating with the Washington Surveying and Rating Bureau and may help improve the fire insurance rates that
Assessment Desirable property owners pay-Making this connection will also provide betterflows in the distribution system and improve water qualityfor the
Principal Need Quality Improvement customers in this area.This will also reduce the amount of flushing maintenance required to keep the water quality high. If this water main
Council Goals Quality of Life is not extended,there will continue to be a deficiency in fire flow to the fire hydrants and the continued need for additional flushing of the
dead ends.
Justification
This meets the Council Gaal of:
QUALITYOFLEE -This project will enhance community safetythrough hydrant availability while ensuring consistent quality and service
of the water utility.
-■ O• ■ ■
Total Project to Scheduled Plan Plan PYA Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 20'18 2019 2024 2021 2022 2023 2024 2019-2024
Design 50,000 - - - 60.000 60,000
Land&Right of Way - - - - -
Construction 245,000 - - - - 245,000 245,000
Other - - - - - -
Total Expendiures305,000 1 Ill 1 111
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Unsecured Revenue Bond 305,000 - - - - - - 305.000 305.000
Total . . 305,000
OPFRATING NPACT ANNUAL OPERATIVG IMPACT
Total Plan Flan Plan Pfau Plan Plan Plan Plan Total
Op erating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 1213112017 20f8 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - -
Ex R
enses - - - - - - - -
..
129 Capital Improvement Plan 2019-2024
CITY QF
PASco
uu� 11
mom
l
f - -I
�; ` u
Water Main Replacement-Star Lane (Rd 100 to Rd Summary Project Descliption
97)
Project Number-19046 This project would replace approximately 450 linear feet of existing 2 inch PVC waterline west of Road 100 and replace it with 8 inch
ductile iron pipe and also extend the line another 550 feet to connect to Road 97.The project would include the installation of 2 fire
Status New hydrants.This line is currently supplying 4 water services,it is undersized and is a system dead end.There cannot be any more services
Department Public Works supplied by this line and is too small to provide fire protection.Having the proper distribution of fire hydrants can help elevate our rating with
Group Water the Washington Surveying and Rating Bureau and may help irnprove the fire insurance rates that property owners pay.Completing this
Assessment Desirable project would also improve the'looping"of the water system for this area and eliminate a dead end.This line is currently a dead end in the
Principal bleed Quality improvement water system.
Council Goals Community Safety
This meets the Council Gaal of
COMMUNITYSAFETY-This project will enhance community safety through hydrant availability while ensuring consistent quality and
service of the water utility.
PROJECTe ' - e
Total 712-/3
ject to Scl)eduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project ate Year Year Year Year Year Year Year Request
Expenses 9/2017 2098 2099 2020 2021 2022 2023 2024 2019-2024
Design 50,000 - 50.000 - 50,000
Land&Right of Way - - - -
Construction 168,000 - 168,000 - 168,000
Other - - - -ETotal xpenditures : lil EFTW71101M
Total Project to Plan Plan Plan Plan Plat) Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/312017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Unsecured Revenue Band 218,000 - 218,000 - - - 218,000
Total : kll 218,000 Ikl
OPER TING IMPACT
Total Plan Plan Plan Plan Plan Plan Plata Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
inpact �7J3112017 2018 2019 2020 2021 2022 2023 2024 2099-_2024
Revenue - - - -
Ex nses - - - -
131 Capital Improvement Plan 2019-2024
- Water Main Replacement - South 18
Avenue (Court St to W A Ave)
cis s'�R 4-
W. CLARK 57 ++j
i
W. LEWIS 5T
-
xd
r AU
ry m 4 r
71
W.
s - 'W. 'A" ST A - - W. "A" ST - W. -A"-ST
- _ 'iYs" .. - �R�� •-,ter_ _
A ^e tee,
r
132 Capital Improvement Plan 2019-2024
-SouthWater Main Replacement • Project Description
• 19074 This project will replace an undersized 2 inch water service with an 8 inch ductile iron water main and install a new hydrant for better fire
protection.
Status Ongoing
Department Public Works
Group Water
Assessment Necessary
Principal Need Quality improvement
Council Goals Quality of Life
This meets the Council Goal of
(Z LITYOF LIFE-This project will enhance community safetythrough hydrant availabiftywhle ensuring consistent quality and service
of the water utlly.
PROJECTO•
Tonal Project ro Scheduled Plan Plan Plan Plan Plan Plan Tonal
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/312497 2418 2419 2424 2421 2412 2423 2024 2019-2024
Design 13,000 - - 93,400 - - - 13,000
Land&Right of Way - - - - -
Construction 60,000 - - 60,400 - - 60,004
Other - - - - - - -
Total ■- • 111 IFI 111
Total Project to Plan Plan Plan Plan Platt Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 12/312017 2018 2499 2424 202f 2422 2423 2424 2019.2424
Utilky R ate 73,000 , - - 73.000 - - - - 73.000
Total Funding III 73,000 73,000
a
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating inpact Operating Year Year Year Year Year Year Year Year Request
in act 921312497 2418 2019 2024 2021 2422 2423 2024 2019-2024
Revenue - - - - - -
Ex enses - - - - - -
133 Capital Improvement Plan 2019-2024
- Water Main Replacement - Alley East of
Wehe Ave
0
w
� z
rn r+ w w
�. --,4
HELENA ST
_
134 Capital Improvement Plan 2019-2024
Sum m ary ProjectDescription
•roject Number-19073 This project provides for the installation of approximately 320 linear feet of 8 inch ductile iron grater main to replacethe existing 2 inch main
in the alley directly east of Wehe Avenue north of Helena Street-The proposed main will connect to the existing full size main on Helena
Status New Street and extend north to the south limit of undeveloped parcels on this alley(parcel IQ 113854063)providing for adequate service to
Department Public Works existing customers on its alignment.This project provides the opportunity to participate with private developers along this alley for infill
Group Water development-
Assessment Desirable
Principal Need Quality Improvement
Council Goals Community Safety
This meets the Counc d Goal of:
OUAf_1TYOF LIFE-This project supports a high quality of life through the provision of adequate water utility service-
PROJECTSCOPE
'fatal Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 40.000 40.000 40,000
Land 8 Right of Way - -
Construction 100.000 100.000 100.000
Other - - -
Total Expenclikures 140.0001 +1t 140,000
'total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2024 2021 2022 2023 2024 2019-2024
Lifilky Rate 140.000 - 140,000 140,000
Totalr • 140,000 =1 1 1 owl', I I I
OPERA TIUG IMPACT AUIIUAL OPERATHIG IMPACT
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 92/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - -
Ex 9
nses - - - - - - -
135 Capital Improvement Plan 2019-2024
Water Main Replacement - Road 60
(Court St to W Pearl, 62nd Place, W
Agate between Rd 60 & 62nd Place)
-
yrr�. i► r,. � !fR
r
-- •� - "�' �. resat� ;, �.� . _..-- --- - - - "
PLM at
- I Rte, � I ,1 ] .. + ► I
Pik
�U 114
r
r �I•�itikll �
e �..�d�mi a :5�i�• {.', 1' '�Wlr�''.{16Yk�.'r�ll�fl l r� � , r i�
136 Capital Improvement Plan 2019-2024
: r Road 60(Court St to W Summary Project Description
Place,Pearl,62nd r be twee n Rd 60&62n d
Project Number-18044 This project will replace approximately 3,000 linear feet of existing 6 inch thin wall PVC waterline with approximately 1,400 linear feet of 16
inch ductile iron pipe along Road 60 and approximately 1,6001inearfeet of 8 inch ductile iron pipe along West Pearl Street,West Agate
Status Ongoing Street and 62nd Place.This project will also install three new fire hydrants.
Department Public Works
Group Water
Assessment Desirable
Principal Need Quality inprovern ent
Council Goals Q uality of Life
This meets the Council Goal of:
QUALITY OF LEE -This project will enhance community safetythrough hydrant availabilitywhile ensuring consistent quality and service
of the water utility.
PROJECT r ALLOCATION
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12,,3112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 190,000 - - - 190,004 - - - 190,000
Land&Right of Way - - - - - - - - - -
Construction 740,000 - - - 740,000 - - 740,000
Other - - - - - - I
Total Expenditures 930,000930000 930,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019.2424
Unsecured Revenue Bond 930,000 - - - - 930.000 - - - 930.000
Total Funding 930,000 i iii
OPERATING NPACT ANNUAL OPERA
Total Plan Plat) Plan Plan Plan Plan Plan Plan Total
Operating Jnp act Operating Year Year Year Year Year Year Year Year Request
Inp act 1213112017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Revenue - - - - - - - - -
Ex ienses - - - - - - -
ST!14
137 Capital Improvement Plan 2019-2024
- Water Main Replacement - Richardson
Road (Rd 92 to Rd 96)
R Y W FiMEI IN Rd
4 4
RICHARD80N Rd
4 �-- for .
Yi �w 'fin �� (•
COURT St
S'1,
r. A.
i
o a
Y`
T
T �l WHIPPLE Ave
mp'noW3 .41
138 Capital Improvement Plan 2019-2024
Summary Project Description
- :1• This project would replace approximately 1.400 linear feet of existing 4 inch and 6 inch thin wall irrigation Gass PVC water line and replace
it with an 8 inch ductile iron pipe in Richardson Road between Road 60 and Road 64.The project would include the installation of 3 fire
Status Ongoing hydrants to provide fire protection.Having the proper distribution of fire hydrants can help elevate our rating with the Washington Surveying
Department Pubic Works and Rating Bureau and may help in prove the fire insurance rates that property owners pay.
Croup Water
Assessment Desirable
Principal Need Service Protection
Council Goals Community Safety
This meets the Council Goal of.
COMMMITY SA -This project WWI enhance community safety through hydrant availab9Ry while ensuring consistent quality and
service of the water ut>lity.
PROJECTSCOP • •
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 60.000 - - - - 60.000 - 60.400
Land&Right of Way - - - - - -
Construction 440.x00 - - - - 404,404 - 404,440
Other - - - - - -
■ ■-Ifiel I ti I .1111 .k IIF .1111
Total Project to P1mt Plant Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 21018 2019 2020 2021 2022 2023 2024 2019-2024
Unsecured Revenue Bond 464.000 - - - - - 464,400 - 460,000
Total Funding •,I III •,1 1J-1 00111, 1II
DPERATM AWPACT ANNUAL ■
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 12/3712017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue -
Ex enses -L,7114 a-1-T— _ _
139 Capital Improvement Plan 2019-2024
CITY PF
PASco
ju
• '.�"i .... � _..� �. a .� � •v - � I
Ain ff
k
_f
� r
h Jr
7
V
Wj
to Court St)
• _ This project would replace approximately 1.700 linear feet of existing 4 and 6 inch thin wall irrigation class PVC water line and replace it
with 12 inch ductile iron pipe. The project would also install 4 new fire hydrants.Road 76 is intended to be one of the largerwate r mains
Status Ongoing that supplies same of the residential areas that are now beginning to see substantial development.The project would also help loop the 12
Department Public Works inch main that extends down from Argent Road to the main in Court Street.Having the proper distribution of fire hydrants can help elevate
Group Water our rating with the Washington Sur.eying and Rating Bureau and may help improve the fire insurance rates that property owners pay.
Assessment Desirable Water mains made of thin wall PVC pipe cannot be worked on in the same manner as ductile iron pipe and thicker C900 class PVC pipe,
Principal Need Quality knprovement due to the fragile nature of the pipe. Not completing this project could hinder the ability of any new properties from being able to connect to
Council Goals Community Safety the city water and 9 stops the fire department from having an uninterrupted supply of water for firefighting purposes on this street.This line
is currentlY a pinch point in the water distribution system due to the smaller size,
This meets the Council Goal of:
COMMUNEYSAFETY-This project will enhance community safetythrough hydrant availability while ensuring consistent qualityand
service of the water utility.
•OO• 111 1111 1111e
Total Project to Scheduled Plat? Plat? Plan plat) P1a11 Plat) Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/39/2097 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 200.000 - - - - - - 200.000 - 200.000
Land 8 Right of Way - - - - - -
Construction 626.000 - - - - - - 626.000 - 626.000
Other - - - - - - - - - -
Total ODi � Ili 1
Total PmJecr to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 9213912017 2018 2019 2020 2021 2022 2x23 2024 2019-2024
Unsecured Revenue Bond 826,004 - - - - 826,000 - 826.000
Total Funding rpt 826.000 $26,000
0 PERA TING MPA C T ANNUAL OPERATIVG IMPACT
Total Plan Plan Plat? Plan Plan Plan Plan Plan I Total
Op erasing Impact Op era ting Year Year Year Year Year Year Year Year Request
in act 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
R even ue -
Ex 9
nses - - -
141 Capital Improvement Plan 2019-2024
This Page Intentionally Left Blank
142 Capital Improvement Plan 2019-2024
143 Capital Improvement Plan 2019-2024
CITY OF
PASO -
�,�����>>� f II Ij iu"�
}�� -- { f 1� _ �� ` - -t• �III F- - 3 ■_ �'
1
1 1 dl
!
-116
•. i . . . Summary Prcject Description
Development
• 80This is an annual program which allows the Ctyto address both current and future irrigation system needs during pmject development,
through proper infrastructure design and installation.
Status Ongoing
Department Public Works
Group Irrigation
Assessment Necessary
Principal Need Reduce Future Costs
Council Goals Quality of Life
This meets the Council Goal of:
0UAL rfYOF LIFE-By allowing the City to make the most of development opportunities to provide a higher level of service to customers.
PROJECTSCOPE 0 ANNUAL ALLOCATION
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design - - - - - - - - - -
Land&Right of Way - - - - - - - - - -
Construction 525,000 - 25.000 200.000 200.000 25,000 25.000 25,000 25,000 500,000
Other - - - - - - - -
Total Expenditures 525,000 25,000 2DO.000 200,000 25,000 25,000 25,000 25,000 500,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2099-2024
Utilky Rate 525,000 - 25.000 200.000 200,000 25.000 25.000 25.000 25.000 500.000 .
Total . • 525,000 25,000 200,000 200,000 25,000 25,000 25AOO 25,000 500,ODO
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating rnpact Operating Year Year Year Year Year Year Year Year Request
hn act 1213112097 2098 2099 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - - - - - -
Ex enses - - - - - -
145 Capital Improvement Plan 2019-2024
Annual Irrigation Upsize - Development
J 1
146 Capital Improvement Plan 2019-2024
Annual I ni gation Upsize -Development Summary Project Description
• 18052 This project consists of setting aside an annual allotment of funds to be used to pay for potential ups¢ing of irrigation lines related to private
development installed lines. Implementation of this program improves irrigation service to the community. Developers are required to
Status Ongoing provide irrigation pipes to accommodate their developments. Sometimes there is a need to ups¢e those irrigation pipes to accommodate
Department Public Works more customers than just those identified in the Developer's project. The program enables the Cityto ups¢e irrigation lines when an
Group Irrigation opportunity presents itself with a private development or other City project in an effort to decrease use of treated potable water for irroion
Assessment Necessary purposes.
Principal Need Reduce Future Costs
Council Goais Quality of Lie
This meets the Council Goal of.
QUALITY OF LFE-By allowing the City to make the most of development opportunities to provide a higher level of service to customers,
PROJECTO• i
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/39/1017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design - - - - -
Land&Right of Way - - - -
Construction 350,000 - 50.000 50 OCJ 50.000 50.00 50.000 50.000 5C.000 300,000
Other - - -
Total . . 111 1 111 1111 1 111 1 III 1 111 1111 I I11 11 111
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 1213912017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Utility Rate 350.000 - 50.000 50.000 50,000 50,000 50.000 50.000 50.000 300,000
Total - . 350,000 50M 50,000 50,000 50,000 50,000 50,000 50po 300,000
PERA TING . ,CT .
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating hrpacr Operating Year Year Year Year Year Year Year Year Request
in act 17/39/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Revenue - - - - - -
Ex VMnses - - - - - -
147 Capital Improvement Plan 2019-2024
060 O'Mfj
System Im rovement & Rehab
� r
Proj ects
1 .� Legend
._ C=!�
- -f -3,w -----�-_ =;•-_� ____ iJ-�-rte
ij
------------
148 Capital Improvement Plan 2019-2024
System Improv r Projects Sum maiy ProjectDescription
Project Number1 These projects w0 be determined from the system evaluation study to be undertaken in 2019.This evaluation will identify system
deficiencies and recommended improvements.
Status New
Department Public Works
Group irrigation
Assessment Necessary
Principal Need Service Protection
Council Goals Quality of Life
This meets the Council Goal of.
QUALITY DF LFE- Providing funds for system improvements supports irrigation service quality and c onseq uenU y th e quality of life for
City residents.
-• . •
ALSO
Total 712MM/2017
Scheduled Plan Plan Plan Plan Plan Plan Total
Expendaures Project Year Year Year Year Year Year Year Request
Expenses 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design _ - - -
Land&R fight of Way - - - -
Construction 540,000 - 90.1MC 90.001 90.3Co 9C 01--0 90.000 90.000 540.000
Other - - - - - - - -
Total Expenditures 540.000 •1 111 90,000 90,000 90.000 90,000 90,000 540,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Prajecr Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2099-2024
Utlity Rate 540,000 - 90.000 90,000 90,000 90,000 90.000 90.000 540.000
Total Funding540,000 90,000 90,000 90,000 90R00 90,000 90.0w 540,000
OPERATING Af PACT ■
Total Plan Plan Plan Placa Plan Plan Plan Plan Total
Operating Mnpact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2097 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - -
Ex 9
enses - - - - - - -
149 Capital Improvement Plan 2019-2024
- " Chapel Hill Boulevard (Rd 84 to Rd 68)
e r
LU
_ 9 kR
'N F
M 7i
r ,
BA6INEPf, 13 15 11 19 21 39 41_ 44 32
19 'L 35 42 .'23 15 27 28
- ` VALI..EY VIFW Fz
ACTUAL ROUTING �r `•
SUBJECTO TO CHANGE
150 Capital Improvement Plan 2019-2024
Chapel Hill Boulevard -. 84 to -. 68) Summary Project Description
Project Number-18053 This project is the Chis participation with the developers)to install 6,750 linear feet of 12 inch irrigation from Messara Lane and Road 84
intersection east to Chapel Hill Boulevard and Road 68 Intersection. Developers are normally required to install 8 inch diameter irrigation,
Status Ongoing but it is the Citys desire to upsize this main to better serve both existing and future customers.
Department Public Works
Group Irrigation
Assessment Necessary
Principal Need Service Protection
Council Goals Quality of Life
This meets the Council Goal of;
QUALITYOFLIFE-By allowing the City to make the most of development opportunities to provide a higher level of service to customers.
ECONOMIC VITALITY-Continuation of efforts to encourage DNR to sellldevelop remaining state property at Road 68!1-182.
PROJECT
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design - - -
Land&R fight of Way - - - -
Construction 220,000 - 220.000 - 220,400
Other - - - - -
Total Expenditures 220,000 1 r fir
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Utility Rate 220,000 - - 220,000 - - - 220,000
Total f 220,000 220,000 220,000
IANNUAL I
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating inpact Operating Year Year Year Year Year Year Year Year Request
knpact 12/3112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - -
Ex 9enses - - - - - - - -
151 Capital Improvement Plan 2019-2024
CITY OP Chapel
, Boulevard
' , , ' Interstate '
Irrigation Main
PASO
� Lr � w - a ,d ���1i�► ,. Td
Chapel Hill Boulevard to Interstate 182
'� •i�'' `'°�+ �L'4xii�!It3�lirii�llE.i,lllNlil+�lrrefliiil�Yl���...�._=��i._.�'.'r
_ ��,� H 1:51,1 1..[.•'_l r�
i �y� ltiR i00
152 Capital Improvement Plan
ti
•
f if
2019-2024
Chapel r r toProjectDescription
Irrigation
Projectr 18054 This project includes the design and construction of 1,600 linear feet of 12 inch irrigation main from Chapel Hill Boulevard north to a point
just south of Interstate 182 for connection to an existing irrigation main under Interstate 182.This project will connect both the south and
Status Ongoing north zones to better serve existing and future customers. (Partially constructed by the private developer of the Riverhawk Subdivision.)
Deparlm ent Public Works
Group Irrigation
Assessment Necessary
Principal Need Service Protection
CouncI Goals Quafity of Life
This meets the Council Goal of.
OU-ALITY OF LEE-By allowing the City to make the most of development opportunities to provide a higher level of service to customers.
ECONOMIC VITALITY-Continuation of efforts to encourage DNR to selVdevelop remaining state property at Road 68/1-182.
PROJECTr r
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses '1213912097 2098 2019 2020 2029 2022 2023 2024 2019.2024
Design 25,000 - 25.000 - 25.000
Land&Right of Way - - -
Construction 75,000 - 75,000 75,400
Other -Total -
.- . - 100,000 toiilSf
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/39/2097 2098 2019 2020 202'1 2022 2023 2024 2019-2024
lltilit Rate 104,040 - 100 000 - - - 100,000
Total Funding 100,000 11 ill
7!0perating
otal Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating kn pact Year Year Year Year Year Year Year Year Request
act 1213112017 2018 2099 2020 2029 2022 2023 2024 2019-2024
Revenue -
Ex nses
■ 153 Capital Improvement Plan 2019-2024
CITY P� Chapel
Boulevard
' e ' , 1ee
PASO
%q���I I Mi u,
Reducing Valve (PRV)
ter.-
r
. • l � � � Ems' _ _
154Capital Improvement 2019-2024
Chapel Hill Boulevard Pressure Reducing Valve Summary Project Description
'• • 19071 These projects will address pressure differentials between the Road 84 pressure zone and the Road 68 pressure zone byeither improving
or replacing the existing PRV.
Status New
Department Public Works
Group Irrigation
Assessment Necessary
Principal Need Quality Inprovement
Council Goals Quality of Life
This meets the Council Goal of:
❑UALITYOFLIFE-Ongoing efforts to improve efficiencyand effectiveness in the use of public resources in the delivery of municipal
ser,lives, programs,and long-term maintenance and:viability of public facilities.
ECONOMIC VI)'ALff -By providing the necessary infrastructure to accommodate future DNR property deveicIpment-
PROJECTSCOPE _ ■
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 15.000 - 15.("U - - 15.000
Land&Right of Way - - - - -
Construction 75.000 75.000 - 75,000
Other - - - - -
It !F! •I SII •! !!!
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Child Rate 90,000 - - 90,000 - - - 90.000
Total Funding K000
OPER TJYG MPACT ■ '
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
ha act 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - -
Ex nses - - - - -
155 Capital Improvement Plan 2019-2024
�ITY PF , Main
Extension
' Wrigley
Drive PASC� Irrigation
I����iiglll I Ills u„� f
�i
i WRIGLEY Dr
- x
WRIGLEY D
f - -
P 'Tr
156 Capital Improvement2019-2024
g. i 1 rive Summary ProjectDescription
Project Number-19048 This project consists of extending the existing irrigation main on Wrigley Drive from Road 68 to Convention Drive as outlined in the
Irrigation Master Plan completed in December 2013
Status New
Department Public Works *This project will be coordinated with the Wrigley Drive Extension project(Transportation).
Group Irrigation
Assessment Desirable
Principal Need Quality improvement
Council Goals Quality of Life
This meets the Council Goal of:
QUALITYOF LIFE-By allowing the City to make the most of development opportunities to provide a higher level of service to customers.
PROJECTO•
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 9213112017 2018 2099 2020 2021 2022 2023 2024 2019-2024
Design 43,000 - - 43,000 - - - - - 43,000
Land&R fight of Way - - - - - - - - -
Construction 170,000 - - 57,000 113.000 - - - - 170,000
0 ther - - - - - - - - - -
Total Expendkures 213,000 100,000 113,000213,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Utility Rate 213,000 - - 100,000 113,000 - - - - 213,000
Total Funding rrr 100,000 113,000 213,000
OPERA
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Nn act 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - - - - -
Ex enses - - - - - - - - - -
157 Capital Improvement Plan 2019-2024
CITY pF
PASOSystem EvaluationProject
Ew Pwm;��llree Exi➢Gn Q. � ``' ������� � �}�
4Ar
158 Capital Improvement Plan
1
.,.
0 -
Systern Evaluation •ject Summary Project Descrotion
19070 This project will build upon the irrigation capacity assessment done in 2018 and further evaluate the irrigation system to identify operational
deficiencies and recommended improvements.
Status New
Department Public Works
Group Irrigation
Assessm ent Necessary
Principal Need Service Protection
Council Goals Quality of Life
This meets the Council Goal of.
QUAL rrY OFLFE-Providing funds for system improvements supports irrigation service quality and consequently the residents quality of
life.
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expanditmw Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design - - - -
Land&Right of Way - - - -
Construction - - - - -
other 150.040 - 150.004 - - 150,000
Total Expenciltures1111 1 iii i 111
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Frnxlrng Sourow Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Uility Rate 154.040 - - 150.004 - - - 150.000
bus ■ i• I III 1 1 1 1 rI I I
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
70peratirn�gnpact Operating Year Year Year Year Year Year Year Year Request
knpact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
- - - - - -
Ex M
es - - - - - -
159 Capital Improvement Plan 2019-2024
This Page Intentionally Left Blank
160 Capital Improvement Plan 2019-2024
161 Capital Improvement Plan 2019-2024
CITY OF
PASO
Ij iu"�
12
Y - -.
JT
II
An
. L��:.�_i w- f �•'\ �[�..i. �_ �� rr � +4 �. `� �.••r. 3c'tc-'.rte'.,'f
•t ���r�- , 1� .4 .. ` }�,y• � �..:. �L'�.� -'--��� ��`i''��-r��l �19 5�P Int Wit`
'"'a'A—'!-"'�f� +I�'°*.�.�1 �T'r`.. �.. _�,�,� I I � �-,�— � -�-�..i--'rw.r�. •�s ^-c-�--`,-t 1.,y-.`a.-��
J
F .� r -µ�'• .,, - .-r��a r�-f�-��li-d -tys
. �:•,-�-x�¢., I ;�,rf x,•T`*i-f'. .tP-dr_� �� _ .� �-.a,;"--'�-'�`•��1�C
Irt .: _
Annual Sewer System Improvements 1 • • Description
Project18057 This is an annual program to address sewer system needs and enables the City to extendlim prove sanitary sewer lines when an
opportunity presents itself with a private development or other City projects).The program anticipates future annexations and need to
Status Ongoing extend sewers.Implementation of this program improves sanitary service to the community and addresses public health issues.
Department Public Works
Group Sewer
Assessment Necessary
Prisc Oal Need Service Protection
Council Goals Duality of Life
.r.
This meets the Council Goal of
-This project supports the development and delivery of efficient municipal wastewater service.ensuring wastewater
infrastructure is in place.
R / • il / -
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/39/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design
Land&Right of Way - - -
Construction 717.000 17,000 100.000 100.000 100.000 100.000 1130.000 1130.000 100.000 600.000
Other - - - - . I
Total Expenditures717,000 17,000 100.ODO 100,000 10D,000 100,000 100,000 100,0DO I II III 600,000
Total Project to Pian Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 92/39/2097 2016 2019 2020 2029 2022 2023 2024 2019.2024
Utility Rate 717.000 17.000 100.000 100,000 100,000 100,000 100,000 100.000 100.000 600.000
17,000 1006000 100,000 10D,ODO 100,000 100,000 1006000 100ADO 6W.000
OPERA771IG IMPACT,
J '
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating knpact Operating Year Year Year Year Year Year Year Year Request
!fn act 92/39/2097 2498 2019 2020 2029 2022 2023 2024 2019-2024
Revenue
Ex enses -
163 Capital Improvement Plan 2019-2024
Annual Sewer Upsize - Development
•
M'1
164 Capital Improvement Plan 2019-2024
r D-ve lor r Description
058 This project consists of setting aside an annual allotment of funds to be used to payfor potential upsizing of sewer lines related to
developer installed sanitary sewer lines.Implementation of this program improves sanitary system service to the community.The program
Status Ongoing w 1 enable the City to ups ize sewer lines when an opportunty presents itself with a private development or other Cty project.
Department Public Warks
Group Sewer
Assessment Necessary
Principal Need Reduce Future Costs
Council Goals Quality of Life
This m eets the Council Goal of-
QUALITYOFLFE -This project supports the development and delivery of efficient m unicipaI w as tew ate r s ervic e,ensuring wastewater
infrastructure is in place-
PROJECTSCOPE ANNUAL
ALLOCATION
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expend0urea Project Date Year Year Year Year Year Year Year Request
Expenses 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 70.000 10,000 10.000 19,900 10.000 10.000 10,000 10,000 60,000
Land&Right of Way - - - - - - - - - -
Construction 630,000 - 90,000 90.000 90,400 90.000 90.000 90,000 90,000 540,000
Other - - - - - - - - - -
Total Experiftire,; 700,000 100poo 100,000 100,000 100,000 100 111100.000 100.000 600000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/3112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Utility Rate 700,000 100,000 100.000 100,000 1 DO,000 100,000 100,000 100,000 6003004
Total 11 111 100,000 100,000 100,000 1 II 111 100,000 100,000 100,000 600,000
OPERA T#VG IMPACT ANNUAL OPERA
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating knpact Operating Year Year Year Year Year Year Year Year Request
hrpact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - -
Expenses - - - - - -
165 Capital Improvement Plan 2019-2024
low
-� WWTP Facility Capital Improvement
r
Projects
t yr _ • �X �4:'
ry�,F}- - - •frr � 1
• Aja � _� .f - - _ �� � ..
166 Capital Improvement Plan 2019-2024
WVVTP Facility Capital Improvernent Projects SummaryProject Description
Project The Wastewater Treatment Plant(WWTP)Facility Plan.which is currently being developed.will determ in Capital Improvement Projects
as part of its summarization of recommended needs- Because the plan is still underway only the River Outfall Project has been identified
Status Ongoing so far-
Department Public Works
Group Sewer The anticipated estimate for this project was originally$25 million- However,this total has been reduced to reflect the River Outfall Project
Assessment Necessary as a separate project- Final costs and scheduling for this project will be further defined in the final WWTP Facility Plan-
Principal Need Regulatory Mandate
Council Goals Quality of Life
This meets the Council Goal of
QUALIFY OF LFE -This project supports the development and dei ivery of efficient municipal wastewater service. ensuring wastewater
infrastructure is in place.
PROJECTSCOPE
Total Project to Scheduled Plan Plan Pian Pian Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 42/39/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 160.000 160.000
Land S Right of Way -
Construction 18.536.000 3.536.000 5.000.000 5.000.000 5.000.000 18.536.000
Other - -Total . 000 160,000 UK= 5,000,000 5,000.000 5,000,000 18,536.000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Unsecured Revenue Bond 18,696,000 160.000 3,536.000 5.000,000 5,000,000 5.000,000 18,536,000
Total Funding iii 160,0W 3,536,DDO 5,000,000 5,000,000 5,000.000 18,536,000
•-
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Irn pact Operating Year Year Year Year Year Year Year Year Request
Impact 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue
Ex enses - -
167 Capital Improvement Plan 2019-2024
CITY OF
PASO
M
tii I
e'A Vi .1 lb ab A.A
ell ell
I
JN
Wastewater Treatment Controls ProjectDescription
Upgrades
•roje rt N umbe 18059 This project W11 replace the existing Prograrrmable Logic Controllers{PLC}and 8 remote Input/Output(V0)racks located at the Wastewater Treatment
Plant(WWTP).The current system is vintage, 1989 and no longer has drivers for any computer operating system that is currently on the market.Upgrading
Status Ongoing the controls will take advantage ofcurrent Ethemet communication technology and hate driers readily available and supported for the solware packages
Department Public Works we use.The current hardware and technology has outlasted its useful lifespan.New parts for the existing system are cast prohibitive due to the hardware
Group Sewer upgrades required to support and integrate the new parts.
Assessment Urgent
Principal Need Service Protection
Council Goals 0uality of Life
This meets the Council Goal of-
Q_IALIFY OF LFE -This project supports the development and deliveryof efficient municipal wastewater service.ensuring wastewater
infrastructure is in place.
Tonal Project ro Scheduled Plan Plan Plan Plan Plan Plan Tonal
Expenditures Project dare Year Year Year Year Year Year Year Request
Expenses 12131120'17 2016 2019 2020 2021 2022 2023 2024 2019-2024
Design 150,000 - 150,000 - - 150,000
Land&Right of Way - - -
Construction 705,000 - 705,000 - - 705,040
Other - - - - -
Total Project to Plait Plan Plata Plat Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 92/3112097 2018 2019 2020 2021 2022 2023 2024 2019-2024
Unsecured Revenue Bond 855,000 - - 8Y5.000 - - - 855,000
Total Funding rrr EET7 MIT,
OPFRATfiVG IMPACT
Total L12//31/2017
n Plan Plan Plan Plan Plan! Plan Plan Total
Operating htpact Operating r Year Year Year Year Year Year Year Request
Impact 2018 2019 2020 2021 2022 2023 2024 2019.2024
Revenue - - - - - - - - -
Ex enses - - - - - - -
169 Capital Improvement Plan 2019-2024
- River Outfall Phase I
e r
m y P `
'�K Ave--a._S 4,d`�,. .�,� `,�. _ � ��- � _— � - �_ �,• F - ,t;_°--
e
d
7- j"A
�rt
Z.
r
t �
170 Capital Improvement Plan 2019-2024
PhaseRiver Outfall I Summmy PrqJMDesaVilon
19051 This project includes the design and construction of a completely new sanitary sewer outfall pipe,eluent towmeter and mer diffuser for the Wastomter
Treatment Plan(WWTP).
Status New
Department Public Works According to a recent analysis of the existing WW1P,the size of the existing a fell pipe to the Columbia Rnrer is becoming a restriction in the City's ability
Group Sewer to increase treatment capacity at the WWTP The existing pipe also needs to he replaced due to its deteriorating condition By replacing the outfall pipe,
Assessment Necessary €mpraemants to the WWTP can increase treat men[capadtie s.
Principal Need Other
Councd Goals Dual ityof Life
This meets the Counci Goal of.
QUALITYQFL1 E.-This project supports the deielopment and delivery of efficient municipal wastewater service.ensuring wastewater
infrastructure is in place.
PROJECTO, i
Tonal Project to Scheduled Plan Plan Plan Plan Plan Plan Total
EkPand>l MMS Project Dare Year Year Year Year Year Year Year Request
Expenses 12/392017 2018 20.19 2020 2021 2022 2023 2024 2019-2024
Design 961,000 - 961,000 - - - 961,000
Land&R fight of Way - - -
Construction 5,503.000 - 503,000 5,000,040 - 5,503.400
Other - - - - - -
Total ExpendituresDOO
Total Projecr to Plan Plan Plat) Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue *312017 2018 2019 1020 2021 2022 2023 2024 2019-2024
Unsecured Rejeme Band 6,464.000 - - 1,464,000 5.000,000 - - 6,464,000
OPERA O•
Total Plan Plan Plan Plan plan Plan Plan Plan: Total
Operating fnpact Operaring Year Year Year Year Year Year Year Year Request
inacr 9213912017 2018 2019 2020 2029 2022 2023 2024 2019.2024
Revenue - - - -
Ex 9nses - - - - - - -
171 Capital Improvement Plan 2019-2024
-� Harris Road Sewer Transmission Main
� r
_ — �����.'. - -._ -. ._ .._ - -_ � _ :: Y .—4;_psi. *+ -•`��" ��.4X �`_'�. +-�-".
7
^"9e1
T`-.
' -�°���� � `� .�R i� f •� � sit 1- y -.- - � �S �a- __ ._ Y _ r. -s. �L
� ';._i ;�.j,I�.�.�-.'-��'- =►-x.71=.���G'ti"�
-
-. "L
N16
172 Capital Improvement Plan 2019-2024
Harris '... Seymr Transrni ssion Main Summary Project Description
• 14001 This project includes the design and construction of approximately 5,290 linear feet of new sanitary sewer transmission main from the
existing sewer transmission rnain located on the north side of Interstate 182 on West Court Street northeasterly uride r Interstate 182 to a
Status Ongoing termination point within Harris Road.
Department Public Works
Group Sewer Local development is anticipated to extend this sewer transm iss ion main north to Bums Road as this will provide for future development of
Assessment Urgent the Northwest area of the City.
Principal Need Council Goal
Council Goals Q ualty of Life
This meets the Council Goal of.
0UdurvoF LFE-This project supports the development and delivery of efficient municipal wastewater service.ensuring wastewater
infrastructure is in place.
lipppipillippill
•.
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12.13712077 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 449,000 114,000 335,000 - - - - -
Land&Right of Way 80,000 - 80,000 - - - - -
Construction 3,300,000 - 800,000 2,500,000 - - - - 2.500,000
Other - - - - - -
Total Expenditures 3.829,000 114.000 1,215,000 2,500.000 2.500.000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2418 2019 2420 2021 2022 2023 2024 2019-2024
UtiityRate 7,000 7,000 - - - -
Util ty2015 Revenue Bond 84,000 84,000 - - - -
Util ty2017 Revenue Bond 2,860,000 23,000 1,215,000 1,622,000 - - 1,622,000
Unsecured Fundis 878,000 - - 878,000 - - - 878,004
Total . . 3,829,000 114,000 1,215,00 2,500,000 2,500,000
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 1713112417 2018 2019 2020 2021 2422 2023 2074 2019-2024
Revenue - - - - - - - -
Ex enses - - - - - I
173 Capital Improvement Plan 2019-2024
- 9th & Washington Lift Station
� r
i 1
174 Capital Improvement Plan 2019-2024
9th&Washington Lift Station Summary Project Description
Projectr The project will address the following issues:deficient isolation and check valves,wet well access hatches,corrosion and deterioration,
drywelI access safety improvements,perimeter security,defective flow meter,transfer switch a bs ole s cen c e,harmonic conditioner
Status Ongoing obsolescence,wet well electrical connection access safety and drywell motor termination box access safety.
Department Public Works
Group Sewer This lift station was originally built in 1964 and rehabilitated in 1999, h is responsible for conveying sanitary sewer flows from the western
Assessment Urgent portions of the City to the Wastewater Treatment Plant(WV fP),
PrincOat Need Council Goal
Council Goals Qualityof Life
This meets the Council Goal of.
QUALITYOF LIFE-This project supports the development and delivery of efficient municipal wastewater service,ensuring wastewater
infrastructure is in place.
PROJECTSCOPEt
Total P
roject ro Scheduled Plat) Plan! Plan Afar Plan Plan Total
Exp endhures Project Dare Year Year Year Year Year Year Year Request
Expenses 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 62,000 27 000 35,000 - - -
Land&Right of Way - - - - - -
Construction 731,000 - 731,000 - - - - 731,000
Other - - -
Total Expenditures 793.000 27,000 35.000 731,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Font
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1,21311017 2098 2099 2020 2029 2022 2023 2024 2019-2024
Utility 2015 Revenue Bond 766,000 - 35.000 731.000 - - - - - 731 A00
Utlity2017 Revenue Bond 27,000 27.000
Total Funding t!t 27M 35,0M 731M 731AOO
OPERA
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Irrpact Operating Year Year Year Year Year Year Year Year Request
hr act 1213912097 2018 2099 2020 2021 2022 2023 2024 2099-2024
Revenue - - - - - -
Ex ieases - - - - - - - -
175 Capital Improvement Plan 2019-2024
- Pearl Street Lift Station
� r
95
•-,;_ r}yp ��..� .7=11 - '.� _ "• .,
'S
176 Capital Improvement Plan 2019-2024
Pearl Street Lift Station Summary Projectr
Project Number-15002 This project w 1 completely rebuid the existing sanitary sewer lift station in an easement Iocated south of W Pearl Street
Status Ongoing 0 riginally built in the 1950's,this station has very poor reliability and functionality.k has a track record of failing and backing up into a
Department Public Works nearby residence.The access to the control center for this lift station is in the middle of a sidewalk on a busy street posing significant
Group Sewer safety issues.The rebuilding of this lift station is a priority.
Assessment Necessary
Principal Need Service Protection
Councit Goals Quality of Life
This meets the Council Goal of.
❑LIALILY OF IFF-This project supports the development and delivery of efficient municipal wastewater seryice,ensuring wastewater
infrastructure is in place.
PROJECT ! • ■ ■
Total Project to Scheduled Plan Plat) Plat Plat) Plan Plat) Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2098 2019 2020 2029 2022 2023 2024 2019-2024
Design 240,000 17,000 223,000
Land&Right of Way 43,000 - 43,000 - -
Constluction 890,000 - 510,000 380,000 - - 890,000
Other - - - - -
Total Expendillums I01 17,000 265-6,000 510,000 380.000 890,000
Total Project ro Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213111017 2418 2019 2020 2029 2022 2023 2024 2019-2024
Utiity2015 Revenue Bond 8,000 8,000 - - - - - -
Lit W2017 Revenue Bond 808,000 9,000 266,000 510,000 23,000 533,000
Unsecured Fundinq 357,000 - - 357,000 - 357,000
Total ICI 17,000 266,000 510,001) 30,000 "I ill
OPERATING OWPACT ANNUAL OPERATVG IMPACT
JL
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating impact Operating Year Year Year Year Year Year Year Year Request
h_apacr 1213911017 2018 2019 2010 2021 2022 2023 2024 2019-2024
Revenue - - -- -- - -
Ex ens es - - - - - - - - -
177 Capital Improvement Plan 2019-2024
- Road 36 Lift Station Upgrades
� r
S r
-
F
1
}I w
178 Capital Improvement Plan 2019-2024
Road 36 Lift Station Upgrades Summary Project Description
Project 16006 This project will provide upgrades to the sanitary sewer lift station at Road 36.
Status 0 ngoing Besides normal sewer flows,this pump station has two additional lift stations pumping into it.The detention time and pump run cycles
Department Public Works indicates the current configuration is at capacity.Downstream surging is occurring,indicating small pipe sizing issues.This pump station
Group Sewer has overflowed onto airport property in the past.
Assessment Necessary
Principal Need Service Protection
Council Goals 0 uality of Life
This meets the Council Goal of
0UALILY OF LFE-This project supports the development and delivery of efficient municipal wastewater service,ensuring wastewater
infrastructure is in place.
•OO•
Focal Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expendhures Project Dare Year Year Year Year Year Year Year Request
Expenses 12112017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 57,400 12,000 45,000 - - - - - -
Land&Right of Way - - - - - - - -
Construction 281.000 - 281,000 - - - 281,000
0 ther - - - - - - - -
Total Expend�tures rig 12,ODD 45,000 281,000 281 arra
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project pare Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Utility 2015 Revenue Bond 12,000 12,000 - - -
Utilky2017 Revenue Bond 45,000 - 45,000 - - - - -
Unsecured Revenue Bond 281,000 - - 281,000 - - 281,000
Total : iii 12,000 45,DOO 281,000 281,000
OPERATING MPACT ANNUALOPERATING
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
Impact 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - - - -
Ex i
enses - - - - - - -
179 Capital Improvement Plan 2019-2024
- Maitland Lift Station - Purchase/Install
4th Pump
------JA
- - .�. - }
- _ -
V,
180 Capital Improvement Plan 2019-2024
Maitland Lift Station . Sum m ary ProjectDescription
Project Number-15003 This project includes the installation of a 4th pump and a Variable Frequency Drive(VF D)to accommodate low flaws.These
improvements will decrease slugging of the head works and minimize ragging of the impellers due to lower flows.Currently,the station
Status Ongoing pumps are oversized for the existing flows which cause the pumps to cycle frequently and run at minimum speed,which creates ragging.
Department Public Works
Group Sewer
Assessment Necessary
Principal Need Service Protection
Council Goals Quality of Life
This meets the Council Goal of
DUALITY OF LIFE-This project supports the development and deliveryof efficient municipal wastewater service.ensuring wastewater
infrastructure is in place.
PROJECTe
Total Project to Sclieduled Pian Plan Plan Pfan Plat? Plan Total
Fxpendlrtlres Project Dare Year Year Year Year Year Year Year Request
Expenses 121312017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Design 18.000 1,000 17,400 - - - - - - -
Land&Right of Way - - - - - -
Construction 132,000 - 132,000 - - - - 132,000
Other - - - - - - - - - -
NUE-11=7=71-rL 1,000 17,000 132r000 132,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 121312017 2018 2019 2020 2021 20122 2023 2024 2019.2024
Lhility 2015 Revenue Bond 1.000 1,000 - - - -
Utilly 2017 Revenue Bond 149,000 - 17,000 132,000 - - - - - 132 000
Total . . 150.000 1,000 17,000 132,000 132,000
OPERATING IWPACT ANNUAL OPERATIVG IMPACT
Total Plan Plan Plan Plan Plata Plan Plan Plan Total
Operating inpacr Operating Year Year Year Year Year Year Year Year Request
Impact 12/3111017 2018 2019 2020 2021 2422 2023 2024 2019-2024
Revenue - - - - - -
Ex enses - - - - - -
181 Capital Improvement Plan 2019-2024
-� Broadmoor Area Sewer Lift Station
� r
I
3
'1
HARRIS Rd
_ rel
182 Capital Improvement Plan 2019-2024
Broadmo,or Area Sewer LHt Station Summary Project Description
Project .-r-19050 This project is for the design and construction of a regional sanitary sewer lit station that is intended to sere the northwest area of Pasco's UGA. There is
currently a proposal for a 300+resrdentiat subdnAsron in this area The 0t would like to take the opportunty to work with the developer to locate and sr<e
Status New the lift station for tris subd mson and other lAure developments rn the area as opposed to lust what is needed for their development. Ttrs provides tM
Department Public Works distinct opportunities
Group Sewer "AtmIay to benefit tom participation wt the DeveIoper to place and size a lit station that serves the region.as wweII as the developer's proposed
properties
Assessment Urgent *AtmIay to enter rrto a latecomers agreement that will in pari, reiirriburse the Developer for upsrwrng the lit station to meet the future service area as
Principal Need Council Goal deemed necessary by the UGA.
Council Goals Quality of Life
This meets the Council Goal of
OUALEYOF ISFE-This project supports the development and delivery of efficient municipal wastewater service.ensuring wastewater
Infrastructure is In place.
PROJECTSCOPE AIMIUAL ALLOCATIO11
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 200,000 2C,0.30 200,000
Land&Right of Way -
Construction 3,300,000 3.300.30 - 3,300,000
Other 3Total Experlditiires ,500.000 FEMEMrr iii
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2224
Unsecured Revenue Bond 3,500,000 1500,000 3.500.000
Totalri Fri 3,500,000 3.500,000
OPERAT14G MPACT ANNUAL !
Toral Plan Plan Plan Man Plan Plan Plan Plan Total
Operating lnpacr Operating Year Year Year Year Year Year Year Year Request
to acr 12/34/2217 2018 2019 2020 2021 2022 2023 2024 2219 2024
Revenue
Ex rnses -
183 Capital Improvement Plan 2019-2024
CITY OP" Road
I ' & Pearl ■ ■ Station
PASO
COURT. St
184 Capital Improvement
� r
n_:�� [� 'r - �-..�� 'fur ';�' � _ - '��`,�,_�- i� '� � 3 .. �c _. y•'t
t s
Plan 2019-2024
' .., 52&Pe arl Stre a t L if t Statio n Sum m ary Project I escrip don
Project19053 The construction of a sanitary sewer lift station is needed to sustain development within the East Riveryiew area at an appropriate density.
The construction of this east lift station will allow properties within this sub-basin area(as described in the 2014 Sewer Comprehensive
Status New plan) to be served by City Sanitary Sewer.
Department Public Worcs
Group Sewer 'The City may consider a latecomers agreement to help offset the cost of this project.
Assessment Necessary
Principal Need Council Goal
Council Goals Quality of Life
This meets the Council Goal at
QUALITY OF LIFE-This project supports the development and delivery of efficient municipal wastewater seryice.ens uring wastewater
infrastructure is in place.
PROJECT /
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Fx enses 121312017 2098 2019 2020 2029 2022 2023 2024 2019-2024
Design 270.000 -�7C 000 - 270,000
Land&Right of Way - - -
Construction 1.100.000 1 'OO.CCO - - 1,100,000
Other - - - - -Total -
•- . 1,370.000 270,000 1,100,000 1,370,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 12/312017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Unsecured Revenue Bond 1,370,000 - 270.000 1.100,000 - - 1.370,000
Total Funding 1,370,000 I I!I 1,100,000 1,370,000
OPERATWG IMPACT
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating lrnpact Operating Year Year Year Year Year Year Year Year Request
M act 12/312017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue 1.096,000 - - - 1,096.000 1.096,000
Ex enses - - -
185 Capital Improvement Plan 2019-2024
- Road 84 & Roberts Drive Lift Station
� r
o
DRADIE ST oO a� 6RAD4E ST
6
o OO
LIVINGSTON RD .. d all 8"
JN RED FRANKUN RD O�
a
¢
RFCHARD.SON
m N
AVE p WHEPPLE DR C6
ARK RD L..-...TS DR
� L5
PEARL ST
CLARA ST
�✓ T -RAY CT
Proposed West
q
i
C4DURT ST
HL E STAR r_T
2 O �
CD
15
186 Capital Improvement Plan 2019-2024
Road 1 i Roberts I/ ProjectI /
•r-190 52 To sustain deVeloprnent within the West Mwrmew area at an appropriate density the construction of a sanitary sewer lift stations is needed.The
construction of this west lilt station will allow properties wit hn the west sub-basin area(as described in the 2014 Sewer Comprehensive plan)to be served
Status New by City Sanitary Sewer.
Department Public Works
Group Sewer `The city may consider a latecomers agreement to help offset the cost of this project.
Assessment Urgent
Principal Need Council Goal
Council Goals Quality of Life
This meets the Council Goal of:
QUALITY of LIFE-This project supports the development and delivery of efficient municipal wastewater service,ensuring wastewater
infrastructure is in place.
PROJECT . • 1111 1
Total Project t❑ Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 92131/2017 2018 2099 2020 2021 2022 2023 2024 2019-2024
Design 220,000 - 220.000 - 220.040
Land&Right of Way - - - - -
Construction 914,000 910.000 - 910.000
Other - - -
'Total e 1!000 tI
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project pate Year Year Year Year Year Year Year Request
Revenue 12/39/2017 2098 2099 2020 2021 2022 2023 2024 2019-2024
Unsecured Re,/enue Bond 1,130,000 220.000 910 000 - 1.130.000
Funding 1,130,000 57 ii ! 9 CCI
- . - �
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
in act 92/31/2097 2018 2099 2020 2021 2022 2023 2024 2099.2024
Revenue 904,000 - - - - 904,000 944,000
Ex enses - - - - - -
904,000 904,000
187 Capital Improvement Plan 2019-2024
Road 44 Corrosion & Odor Control
A
s?r�
— ]i rI
+lrli�rI'��rll ll�l� o �1• ��in rrrrr,nn++ruea�rw nnn
11
lrf!liri�J ��� l�; f r'r
1' it t.r- i_.:ji
188 Capital Improvement Plan 2019-2024
Road r r Odor . . • oject Description
Projectr This is Phase II cf planned improvements to improve sanitary sewer flows at the confluence of pipes located at the north end of Road 44.
This project will reduce the turbulence in the pipe system at this location by realigning 90 feet of sewer line,replacing two manholes and
Status Ongoing abandoning one of the existing pipe segments.These improvements will help eliminate the odor complaints received from residents near
Department Public Works this area.
Group Sewer
Assessment Necessary The estimate for this project does not currently include costs for the acquisition of an easement.The goal is to design the project such that
Principal Need Asset Protection an easement is not needed.
Council Goals Ouality of Life
This meets the Council Goal of:
_0UAL LEY OF IFF-This project supports the development and delivery of efficient municipal wastewater seryice.ensuring wastewater
infrastructure is in place.
Tota! Project ro 5clteduled Plan Plan Plan Plan Plan Plan Tota!
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 920,000 - 120 ODO - 120,000
Land&Right of Way - - - - - -
ConstrucWn 458,000 468 000 - 488,000
Other - - - -
Total Expenditures 00 Ire iii
Total Project to Plan Plan Plan Plan Plan Plan Plan Tonal
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 1213112017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Unsecured Funding 588.000 - 588 000 - - 588.000
Total Funding
err
0 PER A TMG AMA
Total 7Yea
Plan Plan Plan Plan Plan Plan Plan Tota!
Operating knpact Operating Year Year Year Year Year Year Year Request
Im act 2018 2019 2020 2021 2022 2023 2024 2019.2024
RevenueEx enses - - - - -
Net Impact
189 Capital Improvement Plan 2019-2024
This Page Intentionally Left Blank
190 Capital Improvement Plan 2019-2024
191 Capital Improvement Plan 2019-2024
k . Annual Stormwater Improvements -
Development
192 Capital Improvement Plan 2019-2024
Annual a i-r I mprove me nts-Development Summary Project Description
Project Number-19054 This is an annual program to address storm water system needs and enable the City to extendlmprove storm sewer lines when an
opportunity presents itself with a private development or other Cityproject(s).The program anticipates future annexations and need to
Status Ongoing extend storm sewers.Implementation of this program improves storm water service to the community and addresses public heath issues.
Department Public Works
Group Storm water
Assessment Necessary
Principal Need Asset Protection
Council Goals 0 uaity of Lite
This meets the Council Goal of,
QUALITYOFLIFE -This project supports the development and deliveryof efficient municipal stormwater service,ensuring stormwater
infrastructure is in place-
PROJECTSCOPE ANNUAL ALLOCAVOINplace-
PRO/PE
Total Project to Scheduled Plan Plan Plan Plan Plan Purr Total
Expenditures Project date Year Year Year Year Year Year Year Request
Expenses 1213112017 2098 2019 2020 2021 2022 2023 2024 2019-2024
Design
Land&Right of Way - - - - - - - -
Construction 600,000 - 100.000 100.000 100.000 100.000 100 000 100.000 600.000
Other - - - - - - - - - -
Total Expenditures ,ii iii 100,000 100,000 100,000 1 ii iii 100.000 100.000 600,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project date Year Year Year Yeer Year Year Year Request
Revenue 92/39/2097 2018 2019 2020 2021 2022 2023 2024 2019-2024
Utilty Rate 600.000 100.000 100,000 100,000 100,000 100,000 100,000 600.000
•r. {1 1{i 100,000 100,000 1 11 111 100,000 100,000 100,000 600,000
OPERATMIGMPACT ANNUAL OPERA
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impact Operating Year Year Year Year Year Year Year Year Request
knpact 12/39/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - -
Expenses - - - -
193 Capital Improvement Plan 2019-2024
-� Capital Stormwater Participation
e r
Program
�y I
IV
i1
IMPF
y
(W) .()S W w r
194 Capital Improvement Plan 2019-2024
Capital Stormwate r Parfici pation Program Summary Project Description
Project 18062 This project provides opportunity for participation in various street and development projects to include the irnplementation of stormwater
elements,such as:
Status Ongoing *Lewis Street Overpass(#13007)
Department Public Works •Oregon Avenue Phase 1(#12002)
Group Stormwater *Peanuts Park(#16014)
Assessment Desirable
Principal Need Asset Protection
Council Goals Quality of Life
This meets the Council Goal of:
QUALITY OF LFF-This project supports the development and delivery of efficient municipal stormwater service,ensuring stormwater
infrastructure is in place.
•Oe • e
Taral P
rojectScheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Year Year Year Year Year Year Year Request
Expenses 2018 2419 2024 2021 2422 2023 2424 2019.2024
Design - - - - - - - -
Land&Right of Way - - -
Construction 600,040 100 C^D0 OC.COC 100.0100 100 000 100 OCC 100.coo I 600.000
Other - - -Total -
W0,000 1 11 111 .11 411
Total Project to Plan Plan Plan Plan Plata Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2419 2420 2021 2022 2023 2424 2019-2024
Utilky Rate 640,000 - - 100,000 100,000 100,000 100,000 100,000 100,000 600,000
Total Funding 600,000 Ili I I Ili 100,000 100,000 100,000 100,000 100,000 .1 1 1 1 1
� • ANNUAL OPERA
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating Impart Operating Year Year Year Year Year Year Year Year Request
hf act 1213112017 2018 2019 2020 2021 2022 2023 2024 2019- 2024
Revenue - - -
Ex nses - - - - - - -
195 Capital Improvement Plan 2019-2024
- North Industrial Way Infiltration Retrofit
� r
Project
_ ,ice -;t lT ^.ij•! � r � '•:� � - � �.i�ic.
MxX
rd
414
- :.
• ti� - � � Y`9 - _ _. 1�' �;._ _`��.�� l _ .�� may''"
:.;
rti• r f
Y'
Y.•
196 Capital Improvement Plan 2019-2024
North i Description
Project Number-18064 The ex sting infiltration pipe and facility handles an estimated contributing area of 37 acres.It currently does not have enough capacity
during peak precipitation events, resulting in flooding that covers up to half of the North Industrial Way and downstream driveways.
Status Ongoing This project consists of installing(2)2-stage drywalls,comprised of 72 inch modified drywells with modified Type 1 catch basins for
Department Public Works pretreatment,along North Industrial Way to reduce flows to the existing infiltration facility-DrywelI overflows will surface flaw to the existing
Group Stormwater infiltration facility-Additional analysis is recommended to identify anyexiisbug onsite stormwatermanage ment within the tributa ryarea(i-e-
Assessment Necessary infiltration facilities at upstream properties)and update the infiltration facIitytrib uta ryarea to reflect the findings.
Principal Need Quality Improvement
Council Goals Quality of Life
This meets the Council Goal of-
OUALffY OF LAFE-By ensuring proper stormwater capacity,this project will s upport council goals of comm unity safety and quality of life
for those working and or traveling through the area.
PROJECTSCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2029 2020 2021 2022 2023 2024 2019-2024
Design 20,000 20.000 20 000
Land&Right of Way - -
Construction 90,000 90.000 90,000
Other - -
Total Expencirtures 110.000
t tr r rrr
Tota/ Projiedto Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project pate Year Year Year Year Year Year Year Request
Revenue 1201)"17 20118 2019 2020 2021 2022 2023 2024 2019-2024
Utility Rate 110.000 - 110,000 114,000
Total Funding 110,000 I III 110,000
/ / .1 111111111
Total 7Yea
Plan Plan Plan Plan Plan Plan Plan Total
Operating hnpact Operating Year Year Year Year Year Year Year Request
hrpact 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue -
Expenses - - -
197 Capital Improvement Plan 2019-2024
�ITY PF
PAsco
Ik
0. y
p L o x
■i� I { � �e I f� 1 �1 A�
'T11 �� q�
fA
1st Avenue Pipe Rehab Summary Project Description
Project Number-18065 This project will reline 348 linear feet of 30 inch concrete pipe under 1st Avenue between West Lewis and West Columbia,repair joint
offsets with couplings between West Sylvester and West Bonneville Streets,repair 3 sIightlyoffsetjoints located north of West Bonneville
Status ongoing and reline 842 linear feet of 18 inch pipe tributary to Volunteer Park-
Department Public Works
Group Stormwater
Assessment Necessary
Principal Need Asset Protection
Council Goals [duality of Life
This meets the Council Goal of-
OUALffYOFLAFE-This project supports the development and delivery of efficient municipal stormwater service,ensuring stormwater
infrastructure is in place.
PROJECTSCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2029 2020 2022 2022 2023 2024 2019-2024
Design 29,000 21.000 29 000
Land&Right of Way -
Construction 220,000 %2i: 220,000
Other -
Total Expenditures 249.000 rrr rrr
Tota/ Projiedto Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project pate Year Year Year Year Year Year Year Request
Revenue 12131)"17 2018 2019 2020 2021 2022 2023 2024 2019-2024
Utility Rate 249,000 - 249 000 - 249,000
111
iii rrr
Total 7Yea
Plan Plan Plan Plan Plan Plan Plan Total
Operating hnpact Operating Year Year Year Year Year Year Year Request
hrpact 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue -
Expenses - - -
199 Capital Improvement Plan 2019-2024
Sylvester Pipe Relining
�e r�
PROJECT MAP
S X11
q, 4 9 + y(d . 8
T L •Y''' WNRY51 P .
-P 6
W MA RG
k i5d ism IF
Y gyp', q•' Y ¢ �•, p Y'•,
AN B0*FH1.L. 'Y '�, I, to A_ R7 W NIMART
5T
` 1}k
' maI South iNorth -
y { I r v 'A+ !` S + �+n
ti• + + 9• .fir
– -M Manhole
• • . 'r
Columbia RIM rar- '� •� � �Infilkrakion pip a
and con dltlan(GCTYj
elin apip9(ON
y —Pro pased pipe
" O L100 X200 N 0 330 pip Proposedinfilir0ion509m
Fas# 5 ulabasin Feet r A3SUMe1111GWDWh
200 Capital Improvement Plan 2019-2024
Sylve ste r Pipe Relining Summary Project Description
Project Number-18067 This project includes the following-.
Replace at least 20 linear foot segment of the 10 inch pipe segment on North 10th Avenue at the intersection with Sylvester Street.
Status Ongoing 'Reline 361 linear feet of 10 inch pipe,738 linear feet of 12 inch pipe,809 linear feet of 15 inch pipe,and 497 linear feet of 21 inch pipe.
Department Public Works 'Reline 1,900linearfeet of 15 inch pipe,513 linear feet of 18 inch pipe,and 318 linear feet of 21 inch poe-
Group Stormwater
Assessment Necessary
Principal Need Asset Protection
Council Goals [duality of Life
This meets the Council Goal of-
OUALffYOFLAFE-This project supports the development and delivery of efficient municpal stormwater service,ensuring stormwater
infrastructure is in place.
PROJECTSCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 72/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 35,000 000
Land&Right of Way -
Construction 295,000 2(;� 295,Q00
Other -
Total ExpendRures 330,000 M rr r rrr
Tota/ Projiedto Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project pate Year Year Year Year Year Year Year Request
Revenue 72137)1077 2078 2019 2020 2021 2022 2023 2024 2019-2024
Utility Rate 330.000 - 310 000 330,000
Total Funding 330,000 ti r rrr
Total 7Yea
Plan Plan Plan Plan Plan Plan Plan Total
Operating hnpact Operating Year Year Year Year Year Year Year Request
hrpact 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue -
Expenses - - -
201 Capital Improvement Plan 2019-2024
This Page Intentionally Left Blank
202 Capital Improvement Plan 2019-2024
203 Capital Improvement Plan 2019-2024
Columbia East Force Main & Lift
�e%qjjjjjjj1111wV!,
Station
l 1
.FOSTER WELLS - I -
- SERVICE AREA -
I I
W
P4
W
H
O
&L ROCESS WATER
Q+� REUSE FACILITY
PROPOSED COLUMBIA -
EAST PUMP STATION
(CEPS)
COLUMBIA EAST 1P
` SERVICE AREA
204 Capital Improvement Plan 2019-2024
Collurribia East Force Main&Lift Stationr Description
Project = 17003 This project has had previous names.including the Kahlotus Hwy Sewer Force Main and the Dietrich Lift Station. It has been decided to
consolidate both projects into one:the Columbia East Force Main&Lift Station.
Statu s Ongoing
Department Public Works This project is for the design and construction of a lift station and two force mains that will serve multiple food processors in the
Group PWRF Commercial Ave-Kahlotus Highway area. and direct food process water(industrial waste)to the City's Process Water Reuse Facility
Assessment Necessary {PWRF}.Three food processors have expressed interest in this It station.This project will allow for the diversion of 1.5 MGD of industrial
Principal Need Council Goal waste aNray from the municipal A,astewater treatment plant and to the PWRF.
Council Goals Quality of Life
This meets the Council Goal of:
ECONOMIC VITALITY-This project is one portion of the total PWRF upgrade project. The proposed improvements•mill allow the City to
retain 1,200 existing jobs by providing long-term sustainability to the current food processing companies. It is estimated that this projects
along with the proposed expansion of the PWRF would create up to 250 additional jobs within the current users. In addition,this would also
allow capacity for 2 additional users to the facility,which could create up to 400 new jobs.In summary,this project would help retain 1.200
existing jobs and create up to 650 new jobs.
PROJECTe •
Total Project to Scheduled Plan Plan Platt Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2016 2019 2020 2021 2022 2023 2024 2019-2024
Design 640.000 122.000 518,000 - -
Land& Right of Way 610,000 - 610.000 - - -
Construction 9.259,000 - 1.389,000 6.943.000 927.000 7,870.000
Other - - - - -
Total Expenditures i I• r0i 122,000 2,517,000 6,943,000 927.000 7,870.000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Dare Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Department of Commerce Grant 2.575.000 - 1.339.000 1.091,000 145.000 - 1,236.000
EDA-Study Grant 65.000 61.000 4.000 - - - -
0.09 Grant 500.000 - 75,000 375.000 50.000 - 425.000
Economic Development 65.000 61.000 4.000 - - - -
Unsecured Funding 7.304.000 1.095,000 5.477,000 732.000 6,209.000
Total Funding 10,500,000 ikl 2,517,000 6,043,000 927,000 7,870,000
OPERA OPERATING
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating inpacr Operating Year Year Year Year Year Year Year Year Request
inpacr 12/39/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - -
Ex uses - - - - - -
205 Capital Improvement Plan 2019-2024
PWRF Solids Handling Improvements
j
I ,
+ 1
1
� I
PROPOSED LOCATION
f
PWRF Facility
p.
�4 7
206 Capital Improvement Plan 2019-2024
PVAF Solids Handling Irrprovernents Summary PrqectDescription
This project is a placeholder,to provide for the design.construction and installation of an additional dewatering structure/system to dry
solids that are removed from sand traps.clarifier and ponds at the Process Water Reuse Facility[PWRF].
Status Ongoing
Department Public Works The 2018 Budget includes 5300.000 for a similar project which will be constructed in 2018- This project is being planned in case additional
Croup PWRF solids Handling facilities for the PWRF are needed.
Assessment Urgent
Principal Need Quality Improvement
Council Goals Quality of Life
This meets the Council Goal of:
ECONOMIC VrraurY-This project supports the current PWRF operations and the upgrade project and helps retain 1,200 existing jobs
and c reate up to 650 new As-
PROJECT SCOPEjMJW
Total Project to Scheduled Plan Plan Plan Plan Plat? Plan Total
Expel cffi"s Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/7017 2018 2019 2020 2021 2022 2023 2024 2099.2024
Design 25,000 25.000 - - - -
Land&Right of Way - - - - - -
Construction 300,000 - - 300.000 - - - - 300,000
Other - - - - - - - -
Total Expenditures X0 III II Ili M
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year *W Year Year Year Request
Revenue 12131Cl017 2018 2019 2020 2021 2022 2023 2024 2019-2024
LAli ity 2013 Revenue Bond 266,000 25.000 241,000 - - - - 241,000
Lftllfty Rate 59,000 - 59.000 - - - - - 59,000
FundingTotal IIIIII 11 III 11 t I 1
OPERA77NGIMPACT A NNUA L OPERA
Total 7 -
207
Plan Plan Plan Plan Plan Plan Total
Operating Inpact Operating Year Year Year Year Year Year Request
ynpact 17720187 2019 2020 2021 2022 2023 2024 2019-2024
Revenue - - - - - - -
lEx enses - Capital Improvement Plan 2019-2024
k . PWRF Irrigation Pump Station (IPS)
Improvements
PROCESS WATER REUSE FACILITY
INDUSTRIAL PUMP STATION
208 Capital Improvement Plan 2019-2024
PYRF Irrigation Station Description
• 18000 70 The Process Water Reuse Facility(PWRF)includes an Industrial Pump Station(IPS).The IPS is in serious need of replacement due to
piping that is deteriorating to the point of failure. If the c urrent pump station were to have a major failure,there would be no way to pump the
Status Ongoing process water out of the facIityto the crop fields.Complete shut down of all food processor partners would be needed until repairs could
Department Public Works be made.
Group PWRF
Assessment Necessary This project will provide forthe design and construction of a new PS.This project is being proposed in conjunction wkh the upcoming
Principal Need Council Goal PWRF Facility plan.Depending onthe final design of the IPS,there may also be workneeded on the 115 MG pond to relocate the
Council Goals Qual'Ity of Life withdrawal paint and re-grade the bottom of the pond accordingly.This effort is not included in the costs below.
This meets the Council Goal of:
ECONOMIC VITALITY-This project supports the current PWRF operations and the upgrade project and helps retain 1,200 existing jobs
and create up to 650 new jobs.
PROJECT / •
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Dare Year Year Year Year Year Year Year Request
Expenses 12131/2017 2018 2019 2020 2021 2022 2023 2024 2019-2024
Design 183,000 - 183.000 - - - - - - -
Land&Right of Way - - - - - - - - - -
Construction 4,271,000 - - 4,271,000 - - - - - 4.271,000
Other - - - - - - - - - -
000 183000 4271,000 4,271,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12131&017 2098 2019 2020 2021 2022 2023 2024 2019.2024
lJnsecured Re.,enue Bond 3.771.000 - - 3,771,000 - - - - - 3.771.000
Haefc Loan 683.000 - 183,000 500,000 - - - - - 500,000
Total III 183,000 4,271,000 4,271,000
OPERA TPIG IMPACT ANNUAL OPERATING IMPACT
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating inpact Operating Year Year Year Year Year Year Year Year Request
In act 92/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Revenue - - - - - - - -
Ex enses - - - - - - - - - -
209 Capital Improvement Plan 2019-2024
�ITY PF Foster
eWells Automatic
' ' , e
PASO
Replacement
a
2 10
-.ie5�- 'r _-S'ti'nt.- -.-r ���--- e '�]r€� ,�r•'���- -��
Capital • • 2019-2024
Foster Wells Automatic Transfer S%vitch Replacement Summary Project Description
Project :r r I This project will replace the currently nonoperational Automatic Transfer Switch(ATS)for the Foster Wells Pump Station-The ATS is supposed
to automatically switch to a backup generator when the local power grid goes down. Currently,the switch has to be done manually at the Foster
Status Ongoing Wells Pump Station. The new ATS will be integrated into the existing pump station control system.
Department Public Works
Group PWRF
Assessment Urgent
Principle Need Service Protection
Council Goals Quality of Life
This meets the Council Goal of:
QUALITY OF LIFE-Ongoing efforts to improve efficiency and effectiveness in the use of public resources in the delivery of municipal services,
programs, and long-term maintenance and viability of public facilities.
PROJECT SCOPE
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2423 2424 2019-2024
Design 23,000 23.000 -
Land&Right of Way
Construction 150.000 150,000 - 150,000
Other - -
Total Expenditures iii 23,000 150.000 1%000
Total Project to Plan Plan Plan Plan Pian Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 9213112017 2018 2019 2020 2021 2022 2423 2024 2019-2024
Unsecured Fund 173.040 23.000 150.000 150.000
Total Funding 173,000 23,000 150,000 150,000
■
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating impact Operating Year Year Year Year Year Year Year Year Request
Impact 92/31/2017 2018 2019 2020 2021 2022 2023 2024 2099.2424
Revenue
Expenses -
■ 211 Capital Improvement Plan 2019-2024
PWRF Primary Treatment Improvement
u M!f19pLlfXf iR61G[OM��L
sauce�lAswu
p�
/yH0 ■AklR Rvtrw.owkr titwrwiRrrutr ka.tic.�no.. Al11C1/iC f�twwr �rskuwc.
rT(
CSAR/•!R 49% TVIAt WI61
UPF k UIV
AMAk1kO�kL
54
RIAMIC4 S
woo"PH sw wz�
&ANAMM 11 PWATIPU RAS7fS OVIR MW
MIT
■
fOl1d0.IAN6 HkT_
It TIIAlt k'R dL!As P*O<JM WATlA To
L/1Ay WlSTpkk
U Ti x,•1.1+1
V"Ou Ss WARN TU
PRAT/klSAS
SOILf]a�1'C1SY I
ON MUMI
Fwl71 s ISO AftD LDADwG f2M14
LOW(TV BOA ALT!RTkAt M:U"Low A WLEApr[HUMS■LAMA t
V"Ocl SS WAS R*A T"RItW IAUVTT
LM Of•ASCD,wASMMUT Okk
212 Capital Improvement Plan 2019-2024
mprove me int Summary Project Description
Project Number-19055 This project consists of improvements to the Process Water Reuse Facility{PWRF}to allow for additional capacity and improved
treatment of the food processors'industrial waste being pumped to the facility.
Status New
Department Public Works The project identfied here is a placeholder based on the preliminary PWRF Facility plan. More project details and total funding forthis
Group PWRF projectwII be updated after finalizing the PWRF Facility Pian,which is currently being carefully reviewed and coordinated with the WA
Assessment Urgent Department of Ecology and our partner Processors.
Principal Need Council Goal
Coune l Goals 0 uality of Life
This meets the Counc l Goal of:
ECONOMIC VITALITY-This project will allow the City to retain 1,200 existing jobs by providing long-term sustainablityto the current food
processing companies. Itis estimated that the proposed expansion of the PWRF would create up to 250 additional jobs within the current
users. In addition,this would also allow capacity fart additional users to the facility,which could create up to 400 new jobs.In summary,
this project would help retain 1,200 existing jobs and create up to 650 new jobs.
SOL— W0111111111
Total Project to Scheduled Plan Plan Plan Plan Plan Plan Total
Expenditures Project Date Year Year Year Year Year Year Year Request
Expenses 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
7Deign 350,000 - 260,004 90,000 - - - - 350,O00
Land&R ght of Way - - - - - -
Construction 7,009,000 - - 5.187.000 1,822,000 - 7,009,000
Other - - - - -
Total Expendtures 7,359,WO 5,447,000 1,912,000 7,359,000
Total Project to Plan Plan Plan Plan Plan Plan Plan Total
Funding Sources Project Date Year Year Year Year Year Year Year Request
Revenue 12/31/2017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Unsecured Fund 7,359,DDD - - 5,447,000 1,912,000 - - 7.359.000
Total Funding rrr 5A47,000 1,912,000 7,359,000
OPERAOPERATING IMPACT
Total
-
Total Plan Plan Plan Plan Plan Plan Plan Plan Total
Operating inpact Operating Year Year Year Year Year Year Year Year Request
in act 12/.3111017 2018 2019 2020 2021 2022 2023 2024 2019.2024
Revenue - - -
Ex enses - - - -
213 Capital Improvement Plan 2019-2024
This Page Intentionally Left Blank