Loading...
HomeMy WebLinkAboutClearwater Construction & Management - Columbia East FM Change Order No. 1 CP9-SR-2A-17-01CITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO.1 Project No: CP9-SR 2A-17-01. Project Title: 17003 Columbia East Pump Station Contractor: Clearwater Construction & Management Description of Change: CO Request 113 gall as Appropriate: Elevated roof slab reIrdorcki2@eam conectlon Contract Bid Amount: $ 2,458.335.00 SALES TAX @ 8.6%: $ 211,416.81 Total: ; 2,669,751.81 Total Change Orders To Date $ 18,129.66 New Contract Amount S 2,687,$81 A7 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES [-NO Contract Time Prior to this Change Order ................................. 180 Mod"fication to Contract time by this Change Order .................... 0 revised Total Contract Time .................................................... 180 It is mutually agreed by both parties that this Change Order fully describes the change(s) #hat is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document vAll supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: APPROVED: --- /9 CONTRACT(ft F9011ECT MANAGER um 9 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal Sales tax @ 8.6% $ - Total $ - Subtotal $ 16,6933.98 Sales tax @ 8.6% $ 1435.68 Total $ 18,129.66 Total Change Orders To Date $ 18,129.66 New Contract Amount S 2,687,$81 A7 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES [-NO Contract Time Prior to this Change Order ................................. 180 Mod"fication to Contract time by this Change Order .................... 0 revised Total Contract Time .................................................... 180 It is mutually agreed by both parties that this Change Order fully describes the change(s) #hat is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document vAll supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: APPROVED: --- /9 CONTRACT(ft F9011ECT MANAGER um 9 Clearwater Construction & Management, LLC Project: 17003 East Columbia Pump Station Change Order Request #: 03 Date: 5/17/2019 Description of Change: Elevated roof slab reinforcing/Beam correction. Includes additional reinforcing per direction from PACE engineering, labor to untie beams allready installed and retie with new direction Reinforcing details did not tie the beams rebar with the wall or eachother. Direction Reason For Change: given from PACE to correct. Change Directed By: PACE En ineerin Delay's Caused By Chane TBD Labor: Crane Operator 40 hours $ 2,131.20 Carpenters supporting and assisting Hams Rebar 30 hours $ 1,598.40 TOTAL LABOR $ 3,729.60 Material: TOTAL MATERIAL $ - Crane support and remove and place rebar beams into place- (1 Equipment: week) $ 3,021.00 TOTAL EQUIPMENT $ 3,021.00 Subcontracts: Harris Rebar- beam revision CO -002 $ 7,255.16 Other Costs: TOTAL SUBCONTRACTS $ 7,255.16 Total Costs: $ 149005.76 Labor O&P 29% $ 1,081.58 Material O&P 21% $ - Equipment O&P 21% $ 634.41 Subcontractor O&P 10% $ 725.52 Total Markup $ 2,441.51 Total With Markup $ 16,447.27 Tax at 7.90% To be added to Invoice Insurance and Bond at 1.50% $ 246.71 $ 246.71 Total Amount This Change Order Request: $ 16,693.98 Additional Working Das Required: JTBD Notes: Direction given and revised week April 30th Signed: Clearwater Construction Date: Signed: Owners Representative Date: V Harris Rebar Columbia Basin Inc. Change Order No.: CO -002 CHANGE ORDER Bid Icon No.: Job No.: Job Description: Original CIO Date: CO -002 16513859 Columbia East Pump Station 05/09/19 Sen To: C10564 Clearwater Construction & Management LL 5711 West Garden Springs Road Spokane, WA 99224 USA Change Order Description: Beam revisions per engineer's review Additional right angles ail beams Description Beam revisions per engineer's review Type Quantity Add 1 LS Accepted By: Name: Date: Harris Rebar Columbia Basin Inc. PO BOX 575, Burbank, WA 99323, USA T. 509-547-2471 F. 509-547-1856 Sent To Customer Revised CIO Date: Unit Price Line Amount 7,255.16 7,255.16 Total: 7,255.16 Addition To Contract rte~-= Customer Copy