HomeMy WebLinkAbout3878 Resolution RESOLUTION NO.36
A RESOLUTION ACCEPTING WORK PERFORMED BY ALLSTAR
CONSTRUCTION GROUP, UNDER CONTRACT FOR THE ROWENA CHESS SCHOOL
CROSSING PROJECT.
WHEREAS, the work performed by Allstar Construction Group., under contract for the
Rowena Chess School Crossing project has been examined by Engineering and has been found
to be in apparent compliance with the applicable project specifications and drawings,and
WHEREAS, it is Engineering's recommendation that the City of Pasco formally accept
the contractor's work and the project as complete; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO, that the
City Council concurs with Engineering's recommendation and thereby accepts the work
performed by Allstar Construction Group, under contract for Rowena Chess School Crossing
project, as being completed in apparent conformance with the project specifications and
drawings, and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington
State Department of Revenue of this acceptance, and
Be It Further Resolved, that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction
of same and verification thereof by the Public Works Director and Finance Director.
PASSED by the City Council of the City of Pasco this 3rd day of December, 2018.
Matt Watkins
Mayor
ATT ST: i/) APPR VED AS TO FORM:
(-1/60 itzrl
Daniela Erickson Leland B. Kerr
City Clerk City Attorney