CONTRACT CHANGE ORDER NO. 3
Project No: CP5-ST-3A-12-57 Project Title: Oregon Ave (SR 397) Corridor Improvement, Ph 1
Contractor: Culbert Construction, Inc.
Description of Change: Field Directives 12, 14, 15, 16, 17 and 19
Detail as Appropriate: FD 12 - Additional excavation and grading, Reddaway Trucking ($1,636.12);
FD 14 - Additional excavation and grading, Coast Crane ($2,089.46); FD 15 - Grade and place drain
rock, Monarch Machine ($1,316.74); FD 16 - Remove and replace curb to avoid catch basin ($659.83);
, ✓ i , -I Xcivua,c a+ -i ivui mow, w rviai , , i uun . LUP aiyn kW I ,uay.a i h a iu r ✓ i a - r u, i ivw cnwui iy i u
waterline to verifv desian chances ($2.549.171
Contract Bid Amount: $ 6,622,707.52
SALES TAX @ 8.6%: N/A
Total: $ 6,622,707.52
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 14,754.41
Subtotal $
9,578.23
Sales tax @ 8.6% N/A
Sales tax @ 8.6%
N/A
Total $ 14,754.41
Total $
9,578.23
Total Change Orders To Date $ 24,332.64
New Contract Amount $ 6,647,040.16
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order .................... Add 4.5 Working Days
revised Total Contract Time ....................................................
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED: APPROVED:
f_—
CONTRACTOR Dates P6tOJEor mmxt
APPROVED:
DIRECTOR
Aft
lmstme
f�.. of Thmsvortafian
Contract Number
Contract Title
Federal Aid Number
CP5-ST-3A-12-57
Oregon Ave (SR397) Corridor Improvement -Phase 1
STPUS-0397
Change Order Number
Change Description
Date
003
Field Directives 12, 14, 15, 16, 17 and 19
08/23/2018
Prime Contractor/ Design -Builder
Culbert Construction
✓ Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications
❑ Change proposed by Contractor / Design -Builder
Change Description
Field Directive 12, Additional excavation and grading between STA 147+83 and STA 148+38 RT
(Reddaway Trucking) (See attached Field Directive 012) $1,636.12 + 1.0 day
Field Directive 14, Additional excavation and grading between STA 139+63 and STA 141+21 RT (Coast
Crane) (See attached Field Directive 014) $2,089.46 + 1.0 day
Field Directive 15, Grade and place Drain rock between STA 145+24 and STA 146+29 LF (Monarch
Machine) (See attached Field Directive 015) $1,316.74 + 1.0 day
Field Directive 16, Remove and replace curb to avoid catch basin at STA 1154+75 RT
(See attached Field Directive 016) $659.83 + 0 days
Continued next page.
LVerb�af Given By
Verbal Approval Date
Working Dayseiman
for Kent McCue Fity of Pasco
See Field Directives
+4.5
Original Conhact Amount
Current Contract Amount
Est. Net Change This C.O.
Est. Contract Amount
6,622,707.52
6,637,461.93
9,578.23
6,647,040.16
Approvalnd v( Approved
Approved
)
Project Engineer >
Appri) Authority per C.A. Agreement
2e /U
Date
Date
✓ Approval Recommended
Other Approval As Required
By Prime Contractor
Signature Date
Date IF LZ
Representing
WSDOT Form 140-005 Page 1
Revised 04/2015
Contract Number Contract Title Change Order Number
CP5-ST-3A-12-57 Oregon Ave (SR397) Corridor Improvement -Phase 1 003
Change Description Cont.
Field Directive 017, Relocate 24 hour Econo Mart Truck Stop sign STA 158+44.59, 80.72, LT
(See attached Field Directive 017) $1,326.91 + 0.5 days
Field Directive 019, Pot Hole Existing 16" water line to verify design changes
(See attached Field Directive 019) $2,549.17 + 1 day