HomeMy WebLinkAboutEA Engineering - Task Order No. 2018-01 14001 Harris Road Sewer Transmission Main Project - CP7-SE-2A-14-02TACK nRnVR Nn 7018-01
Reviewed By: 3 City Project Code: Y7 -5E —144
REGARDING GENERAL AGREEMENT BETWEEN CITY OF PASCO
AND
EA ENGINEERING, SCIENCE, AND TECHNOLOGY, INC., PBC
Project Description (PROJECT):
Harris Road Sewer Transmission Main Project - 14001
Scope of Services:
CONSULTANT will work with the City staff to provide Right of Way acquisition support for the PROJECT.
CONSULTANT services shall include:
Take preemptive action to make the impending Harris Road Sewer Transmission Main project
proceed without delay. Gather contact information and start preliminary discussions with landowners
in the potential area of the project and explain the project to them. Initial contacts should be
completed within 20 working days. Provide a written summary of the landowner names, addresses,
contact information, the discussions between landowners and any other pertinent information to
Brian 011e in Engineering.
Time of Performance:
Following authorization to proceed, CONSULTANT will diligently pursue completion of the PROJECT within
30 working days
Fee for Services:
All work shall be performed on a time -spent basis at the normal hourly billing rate included in the general
agreement with a maximum amount of $5,000. This maximum amount may be revised only by written
agreement of both parties. A wor hour breakdown shall be provided for each invoice submitted for payment.
Proposed: Z7�
EA Engineering, Science, and Technology, Inc., PBC at
Approved: Z w1w
�
ity of Pasco Date
Rick Terway, Interim Public Works Director
Professional Services Agreement- EA Engineering, Science, and Technology, Inc., PBC
On -Call Right -of -Way Services Page I of 1