PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.4
Project No: M3 -OV -3R-14-03- Project Tltle: City Hall Parking Lot Overlay (2015 Overlays)
M3 -OV -3R-15-01)
Contractor: Central Washington Asphalt, Inc.
Description of Change: Suspension of work for the City Hall parking lot overlay (Alternate 4) until
2016, after new Police Station work is completed and entire lot is available.
Detail as Appropriate: See attached Justificatin memorandum.
Contract Bid Amount: $ 588,440.50
NO SALES TAX (exempt); $ -
Total: $ 588,440.50
PREVIOUS CHANGE ORDERS CURRENT CHANGE ORDER
Subtotal $ 9,699.00 Subtotal $
No Sales tax No Sales tax $ -
Total $ 9,699.00 Total $
Total Change Orders To Date $ 9,699.00
New Contract Amount $ 598,139.50
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ............ ....................................... 42 days
Modification to Contract time by this Change Order. ......................................
Revised Total Contract Time.................................................................... 42 days
It Is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order Is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AG EED TO AND ACCEPTED:
i
91bNTR7TJ5R Date
APPROVED:
CONSTRUCTION MANAGER — Date
APP VE
zo fS
PROD T IANAGE Date
APP OVE
I
PUBLI WOna
DIRE TOR
Memo
Public Works Department
Engineering Division
To: Kent McCue, Construction Manager
CC: Ryan Mahaffey, Construction Inspector
Brenda Timpany, Admin Assistant 1
From: Andrey Avetisyan, P.E., Civil Engineer
Date: July 20, 2015
Re: Change Order #4, Project No. M3 -OV -3R-15-01, 2015 Overlays
Description of Change:
This change order suspends the work on City Hall parking lot overlay, as agreed upon with Central
Washington Asphalt, Inc. (CWA), until after completion of the new Pasco Police Community
Services Building, which is expected by summer of 2016. This change evolved as the police station
contract/construction details were discovered after the 2015 Overlays project was already awarded,
with Alternate 4 being the overlay of the City Hall parking lot. As details of police station
construction sequence showed approximately a quarter of the entire City Hall parking lot being
taken up for temporary fenced police parking, it was determined that it was in the public interest to
delay this work. City of Pasco and CWA met to discuss two options: (1) Deleting this portion of the
work as per Standard Specification 1-09.5, or (2) Suspending this work as per Standard
Specification 1-08.6. CWA chose suspension of the work option with an agreement that all bid item
work will be completed per originally agreed upon unit bid prices. CWA were also given the option
to include WSDOT Asphalt Cost Price Adjustment and Fuel Cost Adjustment general special
provisions to account for fuel and/or asphalt binder price variation, and Contractor chose to omit
those specifications. City of Pasco also made it clear to CWA that the original lump sum bid price
on mobilization for this work was a fair number and would not be changed and CWA agreed on that
as well.
Entitlement:
This work is included in the original Contract. No additional entitlement is found for the work to be
performed after suspension.
No entitlement is found for a revision to the number of working days. Suspending this work will not
increase the time to complete all critical items of work. In accordance with Section 1-08.8, no
revision to the number of working days will be made by this change order.
Price:
City of Pasco and Central Washington Asphalt, Inc. agreed on suspending this work until 2016 as
described, with no additional costs and no equitable adjustments involved. Total bid for this
Alternate 4 work was $60,635.
0 Page 1
Guarantee Period:
City of Pasco and Central Washington Asphalt, Inc. agreed that the one-year guarantee period
start dates for repairing and/or replacing all defects in workmanship and material discovered will be
split up between work performed in 2015 and 2016. The one-year guarantee period for Argent
Road overlay (Base Bid and Alternate 1) and Softball Fields parking lot overlay (Alternate 5) will
start on the day of Substantial Completion for these two parts of the project. The one-year
guarantee period for the City Hall parking lot overlay will start on the date of Final Acceptance of the
work in 2016.
Retainane:
Central Washington Asphalt, Inc. understands and agrees that with the option to keep the City Hall
parking lot overlay as part of this Contract, they will not be able to get release of retainage until 60
days following the Completion Date as per Standard Specification 1-09.9(1).
Adjusted Schedule of Work:
After Pasco Police Community Services Building work is completed and City of Pasco determines
that no other work effects overlaying the City Hall parking lot, the Engineering Department will
immediately contact Central Washington Asphalt, Inc. and provide them adequate notice to
schedule work accordingly before lifting the suspension.