HomeMy WebLinkAbout3790 ResolutionRESOLUTION NO. % 0
A RESOLUTION ACCEPTING WORK PERFORMED BY PREMIER
EXCAVATION INC., UNDER CONTRACT FOR THE C&E TRENCHING, LLC. UNDER
CONTRACT FOR THE BUTTERFIELD WATER TREATMENT PLANT SLUDGE DRYING
BEDS PROJECT.
WHEREAS, the work performed by C&E Trenching, LLC. under contract for the
Butterfield Water Treatment Plant Sludge Drying Beds project. has been examined by
Engineering and has been found to be in apparent compliance with the applicable project
specifications and drawings, and
WHEREAS, it is Engineering's recommendation that the City of Pasco formally accept
the contractor's work and the project as complete; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO, that the
City Council concurs with Engineering's recommendation and thereby accepts the work
performed by C&E Trenching, LLC. under contract for the Butterfield Water Treatment Plant
Sludge Drying Beds project., as being completed in apparent conformance with the project
specifications and drawings, and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington
State Department of Revenue of this acceptance, and
Be It Further Resolved, that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction
of same and verification thereof by the Public Works Director and Finance Director.
PASSED by the City Council of the City of Pasco this _5th__ day of September, 2017.
Matt Watkins
Mayor
AT ST:
Daniela Erickson
City Clerk
APP D AS TO FORM:
Leland B. Kerr
City Attorney