HomeMy WebLinkAbout2309 ResolutionAlpo
RESOLUTION NO D3oci
A RESOLUTION accepting work by Transtate Paving Company, Inc under
contract for Project No 94-3-03
WHEREAS, the work performed by Transtate Paving Company, Inc ,
under contract for Project No 94-3-03 has been examined by the City
Engineer and the City Engineer has found that all work required by the
contract has been performed in apparent compliance with the
applicable project specifications and drawings, and
WHEREAS, it is the City Engineer's recommendation that the City of
Pasco formally accept the contractor's work and the project as complete,
Now, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO
That the City Council concurs with the City Engineer's
recommendation and thereby accepts the work performed by Tr an s tate
Paving Company, Inc, under contract for Project No 94-3-03 as being
completed in apparent conformance with the project specifications a n d
drawings, and
Be it further resolved that the City Clerk is hereby directed t o
notify the Washington State Department of Revenue of this acceptance,
and
Be it further resolved that the final payment of retainage being
withheld pursuant to applicable laws, regulations and administrative
determination shall be released upon satisfaction of same a n d
verification thereof by the City Engineer and Director of Finance
PASSED by the City Council of tile City of Pasco this 5th day of
May, 1997
ATTEST
arles D Kilb ry, Mayor
Catherine D Seaman, Deputy City Clerk
APP gji AS TO FORM
='‘t)
City Attorney
MEMORANDUM
DATE April 28, 1997
TO Robert J Alberts, Director of Public Works
FROM Dennis Wright, City Engineerc
SUBJECT Engineer's Report Accepting A Street Overlay
Project No 94-3-04
Bids were opened on Wednesday, September 11, 1996
Council awarded the contract on September 19, 1996
Award was made to Transtate Paving Co, Inc in the amount of
$209,511 50
The first working day charged to the project was September 30, 1996 a n d
work was substantially complete on November 1, 1996
There was a Change Order issued for this project as follows
1) Contractor to place additional grinding at Public Works Shops
Lump Sum $5,476 80
The final contract cost was $212,912 18
The project was completed in apparent conformance with the project
specifications and I recommend the project be accepted
le