HomeMy WebLinkAbout2247 ResolutionMay, 1996
ATTEST
Charles D Kil ury, Mayor
RESOLUTION NO 2.2 44
A RESOLUTION accepting work by John M Keltch, Inc under contract for
Project No 95-1-02
WHEREAS, the work performed by John M Keltch, Inc, under
contract for Project No 95-1-02 has been examined by the City Engineer
and the City Engineer has found that all work required by the contract
has been performed in apparent compliance with the applicable project
specifications and drawings, and
WHEREAS, it is the City Engineer's recommendation that the City of
Pasco formally accept the contractor's work and the project as complete,
Now, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO
That the City Council concurs with the City Engineer's
recommendation and thereby accepts the work performed by John M
Keltch, Inc, under contract for Project No 95-1-02 as being completed in
apparent conformance with the project specifications and drawings, and
Be it further resolved that the City Clerk is hereby directed t o
notify the Washington State Department of Revenue of this acceptance,
and
Be it further resolved that the final payment of retainage being
withheld pursuant to applicable laws, regulations and administrative
determination shall be released upon satisfaction of same a n d
verification thereof by the City Engineer and Director of Finance
PASSED by the City Council the City of Pasco this 6th day of
Catherine D Seaman
Deputy City Clerk
APPR S TO FORM
Lee Kerr, Interim City Attorney
MEMORANDUM
DATE May 1, 1996
TO Robert J Alberts, Director of Public Works
FROM Dennis Wright, City Engineer
SUBJECT Engineer's Report Accepting First Avenue Sewer Relay
Project No 95-1-02
Bids were opened Thursday, June 15, 1995
Council awarded the contract on June 19, 1995
Award was made to John M Keltch, Inc in the amount of $37,801 36
The first working day charged to the project was July 10, 1995 and work
was substantially complete on July 28, 1995
There were two Change Orders issued for this project which increased the
size of two manholes to better accommodate the new pipe and provided
for the reconnecting of two existing sewers to the new system
The final contract cost was $39,804 20
The project was completed in apparent conformance with the project
specifications and I recommend the project be accepted