HomeMy WebLinkAbout2244 ResolutionCharles D Kilbury, i ayor
RESOLUTION NO
A RESOLUTION accepting work by Pacific Crest Construction, Inc under
contractor for Project No 94-1-03
WHEREAS, the work performed by Pacific Crest Construction, Inc
under contract for Project No 94-1-03 has been examined by HDR
Engineering, Inc and has found that all work required by the contract
has been performed in apparent compliance with the applicable project
specifications and drawings, and
WHEREAS, it is the Public Works Director's recommendation that
the City of Pasco formally accept the contractor's work and the project as
complete, NOW, THEREFORE,
BE TT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO
That the City Council concurs with the Public Works Director's
recommendation and thereby accepts the work performed by Pacific
Crest Construction, Inc under contract for Project No 94-1-03 as being
completed in apparent conformance with the project specifications and
drawings, and
Be it further resolved that the City Clerk is hereby directed to
notify the Washington State Department of Revenue of this acceptance,
and
Be it further resolved that the final payment of retainage being
withheld pursuant to applicable laws, regulations and administrative
determination shall be released upon satisfaction of same and
verification thereof by the Director of Public Works and Director of
Finance
PASSED by the City Council of the City of Pasco this 1st day of
April, 1996
Catherine D Seaman
Deputy City Clerk
APPROVED AS TO FORM
HDR Engineerin 0 , Inc
Anthony H Krutsch, P
March 14, 1996
CITY OF PASCO
CONTRACT 2 - DIGESTER FACILITIES PROJECT
PASCO WASTEWATER TREATMENT FACILITIES
PACIFIC CREST CONSTRUCTION, INC
AND CITY OF PASCO
CERTIFICATION OF COMPLETION
NAME OF PROJECT Contract 2 - Digester Facilities Project
DESCRIPTION The work for Digester Facilities, Contract No 2 includes, but is not
limited to, the furnishing of labor, materials, equipment, and the
construction of the following a new primary digester, new primary
digestion equipment, a new digester control building with associated
equipment, a new gas flare, new natural gas service to the plant site, a
new primary power service, buried power service to new and existing
plant facilities, intertie new and existing digester facilities, new primary
sludge pumps for the existing rectangular primary clarifier, new digested
sludge pumps in the existing Digester Building, miscellaneous gas,
sludge, potable water, non-potable water, storm drainage, drains,
sewers, hot water, and overflow piping, and construct additional site
improvements as may be needed to make a complete project
NAME OF OWNER City of Pasco, Public Works Department, 525 North 3rd, Pasco,
Washington, 99301
WDOE PROJECT NO SRF No L9400013
DATE PROJECT COMPLETED March 13, 1996
,
WDOE PLAN AND SPECIFICATION APPROVAL DATE Unknown
CERTIFICATION I hereby declare that I am the project engineer of the above identified
project and that said project was reviewed and observed by me or my
authorized agent in accordance with the provisions of the construction
quality assurance plan I further declare that said project was to the
best of my knowledge and information constructed and completed in
accordance with the plans and specifications and major change orders
approved by the department of ecology and as shown on the owner's
"as-built" plans
SIGNATURE
DATE
c \pasco \certform pac