A RESOLUTION accepting work by Burdine Enterprises, Inc , under
contract for Project 94-3-04
WHEREAS, the work performed by Burdine Enterprises, Inc
under contract for Project No 94-3-04 has been examined by the
City Engineer and the City Engineer has found that all work required
by the contract has been performed in apparent compliance with the
applicable project specifications and drawings, and
WHEREAS, it is the City Engineer's recommendation that the
City of Pasco formally accept the contractor's work and the project as
complete, NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO
That the City Council concurs with the City Engineer's
recommendation and thereby accepts the work performed by
Burdine Enterprises, Inc under contract for Project No 94-3-04 as
being completed in apparent conformance with the project
specifications and drawings, and
Be it further resolved that the City Clerk is hereby directed to
notify the Washington State Department of Revenue of this
acceptance, and
Be it further resolved that the final payment of retamage being
withheld pursuant to applicable laws, regulations and administrative
determination shall be released upon satisfaction of same and
verification thereof by the City Engineer and Director of Finance
PASSED by the City Council of the City of Pasco this 2nd day of
October, 1995
ATTEST
--SOLa4a.)
Catherine D Seaman
Deputy City Clerk
APP Ugh S TO FORM
Leland B Kerr
Interim City Attorney
MEMORANDUM
DATE September 26, 1995
TO Robert J Alberts, Director of Public Works
FROM Dennis Wright, City Engineer cl,ifi)
SUBJECT Engineer's Report Accepting L I D 126
Broadmoor Parkway Project No 94-3-04
Bids were opened on July 7, 1994
Award was made on July 11, 1994 to Burdine Enterprises, Inc , in the
amount of $1,315,623 43
Notice to Proceed was issued on July 28, 1994
The first working day charged to the project was August 8, 1994 and work
was substantially complete on July 14, 1995
There were eleven Change Orders issued that totaled $337,492 29
The final contract cost was $1,670,054 63, however, the contractor has
several anticipated claims which may affect the final contract price He
has 180 days in which to file those claims from the date of this acceptance
The project was completed in apparent conformance with the project
specifications and I recommend the project be accepted