RESOLUTION NO 2189
A RESOLUTION accepting work by Ray Poland and Sons, Inc, under
contract for Project No 94-5-01
WHEREAS, the work performed by Ray Poland and Sons, Inc, under
contract for Project No 94-5-01 has been examined by the City Engineer
and the City Engineer has found that all work required by the contract
has been performed in apparent compliance with the applicable project
specifications and drawings, and
WHEREAS, it is the City Engineer's recommendation that the City of
Pasco formally accept the contractor's work and the project as complete,
Now, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO
That the City Council concurs with the City Engineer's
recommendation and thereby accepts the work performed by Ray Poland
and Sons, Inc, under contract for Project No 94-5-01 as being completed
in apparent conformance with the project specifications and drawings,
and
Be it further resolved that the City Clerk is hereby directed to
notify the Washington State Department of Revenue of this acceptance,
and
Be it further resolved that the final payment of retainage being
withheld pursuant to applicable laws, regulations and administrative
determination shall be released upon satisfaction of same and
verification thereof by the City Engineer and Director of Finance
PASSED by the City Council of the City of Pasco this 5th day of
June, 1995
_
ATTEST
Catherine D Seaman
Deputy City Clerk
MEMORANDUM
DATE May 23, 1995
TO Robert J Alberts, Director of Public Works
FROM Dennis Wright, City Engineer%
SUBJECT Engineer's Report Accepting Stadium Grading
Project No 94-5-01
Bids were opened on Monday, December 19, 1994
Council awarded the contract on December 19, 1994
Award was made to Ray Poland and Sons, Inc , in the amount of
$103,278 00
Notice to Proceed was issued on December 22, 1994
The first working day charged to the project was January 2, 1995,
and was substantially completed on January 27, 1995
There were two Change Orders issued for this project totaling
1 Deletion of Soil Stabilization ($10,350), and
2 Sales tax of $7,248 38
The final contract cost was $100,176 38
The project was completed in apparent conformance with the project
specifications and I recommend the project be accepted