RESOLUTION NO .62),i3
A RESOLUTION adopting the revised and extended
Comprehensive Street, Storm Drain and Bridge Programs for the
City of Pasco.
WHEREAS, RCW 35.77.010 provides for annual revision and
extension of the Comprehensive Street Program of each city and
town, after holding public hearings thereon; and
WHEREAS, it is now time to revise and extend the
Comprehensive Street, Storm Drain and Bridge Programs; and
NOW THEREFORE, THE CITY COUNCIL OF THE CITY OF PASCO,
WASHINGTON, DO RESOLVE AS FOLLOWS.
That the City Council of the City of Pasco hereby adopts
the revision and extension of the Comprehensive Street, Storm
Drain and Bridge Programs for the ensuing six years as attached
hereto and labeled "Recommended Street Construction Program,
Calendar Years "1995-2000" incorporated by this reference as
though fully set forth herein; and
That the Comprehensive Street, Storm Drain and Bridge
Programs shall be filed with the Department of Transportation.
PASSED by the City Council and APPROVED by the Mayor this
18th day of July, 1994
ATTEST:
19
Catherine D. Seaman,
Deputy City Clerk
SIX YEAR STREET IMPROVEMENT PROGRAM
1995 THROUGH 2000
1995 1) Annual overlays
$404,000 overlay fund
$189,000 1/2 cent gas tax
2) Burden Rd. (Rd. 68 to Rd. 44)
$822,000 L.I.D. or federal grant
$128,000 TIB Grant or Local Match
$ 593,000
$ 950,000
3) Court Street @ Road 32 Traffic Signal $ 90,000
$ 750,000 4) Multi-modal Facility
$600,000 State Grant
$150,000 Federal Funds
5) West Lewis Enhancement
$250,000 LID or Local Funds
1996 1) Annual overlays
$160,000 overlay fund
2) Study: extension of Court or Sylvester over
railroad track to Oregon Avenue
$150,000 local funds
$ 275,000
$ 160,000
$ 150,000
3) 20th Avenue @ Sun Willows Traffic Signal $ 90,000
4) Court @ Road 26 Traffic Signal
$ 100,000
1997 1) Annual overlays $ 250,000
$250,000 overlay fund
1998 1) Annual overlays $ 240,000
$240,000 overlay fund
1999 1) Annual overlays $ 490,000
$350,000 overlay fund
2000 1) Annual overlays $ 300,000
$300,000 overlay fund
TOTAL
$4,413,000
Note:
The three traffic signals, shown as items No. 3 in 1995, and 3 and 4
for 1996 do not have a source of funding indicated. The need for
each of these signals will be created by development of the adjacent
properties. For Court @ Road 26, the development of the northeast
quadrant of the intersection should generate sufficient revenue to
fund the signal. For Court @ Road 32 at least a part of the funding
should be paid by the benefiting properties. For 20th the cost of
the signal should revert to the "developer" and in this case that is
the City of Pasco.
AGENDA REPORT NO 27
FOR City Council
TO Gary Crutchfield
DATE July 13, 1994
Manager Workshop
Regular July 18, 1994
FROM Dennis Wright, City Engineer 0
SUBJECT Six Year Street Construction Program 1995 through 2000
REFERENCE(S)
1 Six Year Program
2 Resolution
II ACTION REQUESTED OF COUNCIL/STAFF RECOMMENDATIONS
1 Conduct a Public Hearing
Motion I move to adopt Resolution No which establishes
the Six Year Transportation Improvement Program for
the calendar years 1995 through 2000
III FISCAL IMPACT
None
IV HISTORY AND FACTS BRIEF
The attached Six Year Street Construction Program reflects some
additions and changes to the initial draft presented at the workshop
meeting of July 11 More specifically, the changes in the program
include changing the proposed year of construction for the traffic
signal at Road 32 and Court Street from 1996 to 1995 and the addition
of a multi-modal facility also in 1995 Another change to the
program was the addition of a project for landscaping and
beautification on West Lewis Street for 1995 That project would be
funded by a local improvement district or a combination of a local
improvement district and federal funds if the City can successfully
compete for enhancement funds The total estimated cost of that
project is $250,000