RESOLUTION NO. 1912
A RESOLUTION accepting work by Ray Poland and Sons, Inc. under
contract for Project No. 89-2-02
WHEREAS, the work performed by Ray Poland and Sons, Inc.
under contract for Project No. 89-2-02 has been examined by the
City Engineer and the City Engineer has found that all work
required by the contract has been acceptably performed and
completed in conformance with the applicable project
specifications and drawings, and
WHEREAS, it is the City Engineer's recommendation that the
City of Pasco formally accept the contractor's work and the
project as complete, NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO:
That the City Council concurs with the City Engineer's
recommendation and thereby accepts the work performed by Ray
Poland and Sons, Inc. under contract for Project No. 89-2-02 as
being completed in conformance with the project specifications
and drawings, and
Be it further resolved that the City Clerk is hereby
directed to notify the Washington State Department of Revenue
of this acceptance, and
Be it further resolved that the final payment of retainage
being withheld pursuant to applicable laws, regulations and
administrative determination shall be released upon satisfaction
of same and verification thereof by the City Engineer and
Director of Finance.
DATE: February 13, 1990
MEMORANDUM TO: Jim Ajax, Director of Public Works
FROM: Dennis H. Wright, City EngineeV
SUBJECT: Engineers Report Accepting The East Lewis Water
Line
Project No. 89-2-02
Council authorized the call for bids on May 22, 1989
Bids were opened on June 13, 1989
Council awarded the contract on June 19, 1989
Award was made to Ray Poland and Sons, Inc. in the amount of
$ 176,554.30
Notice to proceed was issued on June 26, 1989
The first working day charged to the project was July 5, 1989 and
work was substantially complete on August 15, 1989.
There were three change orders issued for this project increasing
the contract amount by $ 1097.00.
The final contract cost was $175,322.39 or silghtly less than 1%
under the original contract amount.
The project was completed substantially in conformance with the
project specifications and I recommend the project be accepted.