HomeMy WebLinkAbout1877 ResolutionWells, City Clerk
APPROVED AS
bstello, City Attorney
RESOLUTION NO. 1877
A RESOLUTION accepting work by A & B Asphalt, Inc. under contract
for Project No. 88-1-01.
WHEREAS, the work performed by A & B Asphalt, Inc. under
contract for Project No. 88-1-01 has been examined by the City
Engineer, and the City Engineer has found that all work required
by the contract has been acceptably performed and completed in
conformance with the applicable project specifications and
drawings; and
WHEREAS, it is the City Engineer's recommendation that the
City of Pasco formally accept the contractor's work and the
project as complete; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO:
That the City Council concurs with the City Engineer's
recommendation and thereby accepts the work performed by A & B
Asphalt, Inc., under contract for Project No. 88-1-01, as being
completed in conformance with the project specifications and
drawings; and
Be it further resolved that the City Clerk is hereby
directed to notify the Washington State Department of Revenue
of this acceptance; and
Be it further resolved that the final payment of retainage
being withheld pursuant to applicable laws, regulations and
administrative determination shall be released upon satisfaction
of same and verification thereof by the City Engineer and
Director of Finance.
PASSED by the City Council of the City of Pasco this
6th day of June, 1989.
Ed Hendler, Mayor
DATE: May 31, 1989
MEMORANDUM TO: Jim Ajax, Director of Public Works
FROM: Dennis H. Wright, City Engineer
SUBJECT: ENGINEER'S REPORT ACCEPTING
THE SLUDGE DRYING BEDS
PROJECT NO. 88-1-01
Council authorized the call for bids on January 17, 1989.
Bids were opened on February 7, 1989.
Council awarded the contract on February 22, 1989.
Award was made to A & B Asphalt, Inc. in the amount of
$92,395.81.
Notice to proceed was issued on March 10, 1989.
The first working day charged to the project was
March 14, 1989, and work was substantially completed on
April 25, 1989 on the last working day.
There were two change orders issued for this project, increasing
the contract amount by approximately $1200.00. These change
orders were to modify the elevation of the sludge dump box and to
modify the connection to the existing system.
The final contract cost was $95,026.59, or approximately 2.8 %
over the original contract amount.
The project was completed substantially in conformance with the
project specifications, and I recommend the project be accepted.