RESOLUTION NO. 1 83 4
A RESOLUTION accepting work by Acme Concrete Company Inc. Asphalt
Division, .under contract for Project No. 88-3-02
WHEREAS, the work performed by Acme Concrete Company,
Inc., Asphalt Division, under contract for Project No. 88-3-02
has been examined by the City Engineer and the City Engineer has
found that all work required by the contract has been acceptably
performed and completed in conformance with the applicable
project specifications and drawings, and
WHEREAS, it is the City Engineer's recommendation that the
City of Pasco formally accept the contractor's work and the
project as complete, NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO:
That the City Council concurs with the City Engineer's
recommendation and thereby accepts the work performed by Acme
Concrete Company, Inc., Asphalt Division, under contract for
Project No.88-3-02 as being completed in conformance with the
project specifications and drawings, and
Be it further resolved that the City Clerk is hereby
directed to notify the Washington State Department of Revenue
of this acceptance, and
Be it further resolved that the final payment of retainage
being withheld pursuant to applicable laws, regulations and
administrative determination shall be released upon satisfaction
of same and verification thereof by the City Engineer and
Director of Finance.
APVVED A AStri i
4til l11014-
ubstello, C . y Attorney Gre
J•nnn
ti
BLF-
EAST Lk 8.5 sir.
AND 2LAY
FlAiR_ST AI
tt -'77- 7
DATE: June 1, 1988
MEMORANDUM TO: JIM AJAX, DIRECTOR OF PUBLIC WORKS
FROM: DENNIS WRIGHT, CITY ENGINEER
SUBJECT: ENGINEERS REPORT ACCEPTING THE OVERLAY AND WIDENING
OF EAST LEWIS STREET
PROJECT NO. 88-3-02
Council authorized the call for bids on March 7, 1988
Bids were opened on March 30, 1988
Council awarded the contract on April 4, 1988
Award was made to Acme Concrete Inc., Asphalt Division, in the
amount of $ 56,485.00
Notice to proceed was issued on April 22, 1988
The first working day charged to the project was April 25, 1988
and work was substantially completed on May 20, 1988, with 4
working days left on the contract time.
There was a change order issued for this project to change from
an asphalt to concrete curb near the start of the project,
however there was no change in project cost.
The final contract cost was $ 53,171.94 or approximately 6 %
under the original contract amount, which was due to an under run
in project quantities.
The project was completed substantially in conformance with the
project specifications and I recommend the project be accepted.
•