HomeMy WebLinkAboutC & E Trenching - Change Orders 1 - 3 CP7-WT-2R-14-02 Butterfield WTP 24-in Valve ReplacementCITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 1
CP7
Project No: Q8&WT-2R-14-02 Project Title: Butterfield WTP 24 -in Valve Replacement
Contractor: C&E Trenching, LLC
Description of Change: Various changes necessary to connect to existing piping, Addition of an
Air/Vac on the raw water line, and additional potholing.
Detail as Appropriate: See attached memo
Contract Bid Amount: $ 308,946.27
SALES TAX @ 8.6%: $ 26,569.38
Total: $ 335,515.65
Total Change Orders To Date $ 51,908.23
New Contract Amount $ 387,423.88
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
YES NO
0
0
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED: APPROVED: /d
44
-?-IS-17,� 3�17b7
C TRACTOR Date MANAGER Date
G:�iS�Rt7L\ \UN
�wJLC.1
I
a7Co5
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal
Sales tax @ 8.6% $ -
Total $ -
Subtotal $
Sales tax @ 8.6% $
Total $
47,797.63
4,110.60
51,908.23
Total Change Orders To Date $ 51,908.23
New Contract Amount $ 387,423.88
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
YES NO
0
0
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED: APPROVED: /d
44
-?-IS-17,� 3�17b7
C TRACTOR Date MANAGER Date
G:�iS�Rt7L\ \UN
�wJLC.1
I
a7Co5
Memo
Public Works Department
Engineering Division
To: Kent McCue, Construction Manager
CC: Will McNeal, Construction Inspector
Brenda Timpany, Admin Assistant 1
From: David Tanner, P.E., Civil Engineer
Date: March 1, 2017
Re: Change Order #1, Butterfield WTP 24 -IN Valve Replacement — Various Changes
Change Order No. 1 reflects the revisions to the Butterfield WTP 24 -IN Valve Replacement project listed
below. This change order was negotiated by the City and Contractor to address various changes in condition.
The City was notified of a change in condition for the following items:
Two 36" Romac Couplers needed to complete the lowering of the 36" Raw water line. These
couplers were not anticipated to be necessary in the design. The cost for this work is $11,356.12
plus tax, and includes $1,545.31 for labor, $7,087.10 for materials, and $1,091.96 for equipment.
The cost for this work is offset by two connections which will not be charged to the bid item
Connections to Existing Water Mains for a savings of $6,613.94. The net additional for this item is
$4,742.18 plus tax.
2" Air Vac with COP Vault. The Engineer determined after award of the project that an Air Vac was
necessary in the raw water line prior to the section being lowered. This work was not considered in
the contract documents. The cost for this work is $7,328.15 plus tax, and includes $1,424.98 for
labor, $4,001.44 for materials, and $742.84 for equipment.
Connections to existing 30" steel with welded flanges. Upon exposing the existing 30" line it was
discovered that the existing material is a spiral welded steel pipe. This item covers the necessary
material and labor to tie into this line. The cost for this work is $12,000 and includes $2,442.84 for
labor, $1,887.30 for materials, $1,273.43 for equipment, and $3,400 for a subcontract for a certified
welder. The cost for this work is offset by one connection which will not be charged to the bid item
"Connections to Existing Water Mains" for a savings of $3,306.97. The net additional for this item is
$8,693.03 plus tax.
Cap Existing 20" With Additional Thrust Block. Upon exposing the existing 24" line it was discovered
that the existing material in the location to be capped is 20" spiral welded steel pipe. This item covers
the necessary material and labor to provide caps and thrust block for this line. The cost for this work
is $6,000 and includes $814.27 for labor, $1,947.44 for materials, $424.48 for equipment, and
$1,700 for a subcontract for a certified welder. The cost of this work is offset by one "DI Water Main
Fitting 24" Cap" not having to be installed for a savings of $1,047.69. The net additional for this item
is $4,952.31 plus tax.
Two Flange by MJ Adaptors. These items were needed to make the connections into the 30" Steel
Water Main and were not anticipated in the original design. The cost for this work is $4,000.00 plus
tax, and includes $407.13 for labor, $2,430.29 for materials, and $212.24 for equipment.
0 Page 1
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 2
7
Project No: CE$ -WT -2R-14-02 Project Title: Butterfield WTP 24 -in Valve Replacement
Contractor: C&E Trenching, LLC
Description of Change: Additional time for dewatering, and addition of a hydrant and 24"x21" reducer.
Detail as Appropriate: See attached memo
Contract Bid Amount: $ 308,946.27
SALES TAX @ 8.6%: $ 26,569.38
Total: $ 335,515.65
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotat $
47,797.63
Subtotal $
9,992.33
Sales tax @ 8.6% $
4,110.61
Sales tax @ 8.6% $
859.34
Total $
51,908.24
Total $
10,851.67
Total Change Orders To Date $ 62,759.91
New Contract Amount $ 398,275.56
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ................................. 60
Modification to Contract time by this Change Order .................... 0
revised Total Contract Time .................................................... 60
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation due
or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present
Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this
Change Order.
AGREED TO AND ACCEPTED:
S -S
CO,KTRAtTOR Date
APPROVED:
,
APPji V D•
3
PRO ECT MANAGER ate
-/$1/17
x'7695
Memo
Public Works Department
Engineering Division
To: Kent McCue, Construction Manager
CC: Will McNeal, Construction Inspector
Brenda Timpany, Admin Assistant 1
From: David Tanner, P.E., Civil Engineer
Date: March 29, 2017
Re: Change Order #2, Butterfield WTP 24 -IN Valve Replacement — Various Changes
Change Order No. 2 reflects the revisions to the Butterfield WTP 24 -IN Valve Replacement project listed
below. This change order was negotiated by the City and Contractor to address various changes in condition.
The City was notified of a change in condition for the following items:
During the tie-in to the 30" Steel Water Main, the contractor spent a significant amount of time on
dewatering the line and dealt with additional water coming from the pipe throughout the tie-in
process. It is reasonable to expect that dewatering a 30" main between the existing valves is a
significant process, and that the time and effort to do so, should have been a consideration when
bidding the project. However, through negotiation, the City agreed to pay half of the costs incurred
for additional dewatering, due to excessive length between valves for this section of water main. The
cost for this work is $803.17 plus tax.
The location of the 24" Cap in 12"' Street was revised due to concerns of disturbing the existing lead
joint Tee. The revised location for the cap created a concern that stagnent water may develop in the
24" dead end pipe segment, and Water Operations Staff requested that a Hydrant be installed on
the end of the 24" line segment. The additional hydrant will provide an added benefit of having a
hydrant in a closer proximity to the existing chlorination room. The cost for this work is $6,007.99 and
includes $621.39for labor, $4161.48 for materials, and $438.14 for equipment. The cost for this work
is offset by one 24" Cap which will not be installed, for a savings of $1,047.69. The net additional for
this item is $4,960.30 plus tax.
The existing water main in 1 e Street is a 21" instead of a 24" as shown on the plans. This requires
the installation of a 24'x21" Reducer to complete the connection. The cost for this work is $3,181.17
and includes $814.27 for labor, $1,371.69 for materials, $424.48 for equipment..
The total cost for this change order is $9,992.33 which includes a contractor markup to cover profit and
overhead of 22%. The City is expecting a cost savings of $1,047.69 in uncharged bid items for a Net increase
of $8,944.64 to the final contract price.
Staff recommends approving Change Order #2 for $9,992.33 plus tax. No additional contract days were
requested in association with this change order.
• Page 1
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.3
1
Project No: CPI;I�WT-2R-14-02 Project Title: Butterfield WTP 244n Valve Replacement
Contractor. C&E Trenching, LLC
Description of Change: Relocation of two injection ports and an access manhole mislabeled on dans
Detail as Appropriate: See attached memo
Contract Bid Amount: $ 308,946.27
SALES TAX @ 8.8%: $ 26,569.38
Total: $ 335,516.65
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 57 789.96
Subtotal $ 8144.26
Sales tax a 8.6% $ 4,969.95
Sales tax @ 8.6% $ 700.41
Total $ 62,759.91
Total $ 8,844.87
Total Change Orders To Date $ 71,604.58
New Contract Amount $ 407,120.23
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ................................. 60
Modification to Contract time by this Change Order .................... 0
revised Total Contract Time .................................................... 80
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order Is full and complete and Is the only compensation due
or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present
Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this
Change Order.
AGREED TO AND ACCEPTED: AP RO
_i,
CofrRACTOR Dale PROJECT MANAGER Dab
a'Z�5-
Memo
Public Works Department
Engineering Division
To: Kent McCue, Construction Manager
CC: Will McNeal, Construction Inspector
Brenda Timpany, Admin Assistant 1
From: David Tanner, P.E., Civil Engineer
Date: June 29, 2017
Re: Change Order #3, Butterfield WTP 24 -IN Valve Replacement— Relocate Injection Ports
Change Order No. 3 reflects the revisions to the Butterfield WTP 24 -IN Valve Replacement project listed
below. This change order was negotiated by the City and Contractor to address a change in condition.
This change order covers all work necessary to relocate two injection ports and an access manhole which
were mislabeled to relocate a valve on the construction plans
The total cost for this change order is $8,144.26 which includes a contractor markup to cover profit and
overhead of 23%.
Staff recommends approving Change Order #2 for $8,144.26 plus tax. No additional contract days were
requested in association with this change order.