HomeMy WebLinkAbout3780 ResolutionRESOLUTION NO. 3 -72� O
A RESOLUTION ACCEPTING WORK PERFORMED BY PREMIER
EXCAVATION INC., UNDER CONTRACT FOR THE ROAD 38 STORMWATER
RETROFIT PROJECT.
WHEREAS, the work performed by Premier Excavation Inc., under contract for the
Road 38 Stormwater Retrofit project has been examined by Engineering and has been found to
be in apparent compliance with the applicable project specifications and drawings, and
WHEREAS, it is Engineering's recommendation that the City of Pasco formally accept
the contractor's work and the project as complete; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO, that the
City Council concurs with Engineering's recommendation and thereby accepts the work
performed by C&E Trenching, LLC., under contract for the Road 38 Stormwater Retrofit
project, as being completed in apparent conformance with the project specifications and
drawings, and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington
State Department of Revenue of this acceptance, and
Be It Further Resolved, that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction
of same and verification thereof by the Public Works Director and Finance Director.
PASSED by the City Council of the City of Pasco this 17th day of July, 2017.