HomeMy WebLinkAbout3733 ResolutionRESOLUTION NO. 3% �3
A RESOLUTION ACCEPTING WORK PERFORMED BY C & E
TRENCHING, LLC, UNDER CONTRACT FOR THE KAHLOTUS
LIFT STATION FORCE MAIN PIPE IMPROVEMENT PROJECT.
WHEREAS, the work performed by C & E Trenching, LLC, under contract for the Kahlotus Lift
Station Force Main Pipe Improvement Project has been examined by Engineering and has been found to
be in apparent compliance with the applicable project specifications and drawings, and
WHEREAS, it is Engineering's recommendation that the City of Pasco formally accept the
contractor's work and the project as complete; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO, that the City
Council concurs with Engineering's recommendation and thereby accepts the work performed by C & E
Trenching, LLC, under contract for the Kahlotus Lift Station Force Main Pipe Improvement Project, as
being completed in apparent conformance with the project specifications and drawings, and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington State
Department of Revenue of this acceptance, and
Be It Further Resolved, that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction of same
and verification thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 7a' day of November, 2016.
Matt Watkins
Mayor