Loading...
HomeMy WebLinkAboutTotal Site Services Change Order 10 C5-GN-9A-14-01 Police Community Services BuildingCITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 10 Project No: C5 -GN -9A-14-01 Project Title: Pasco Police Community Services Building Contractor: Total Site Services Description of Change: Shower floor drains not included in the approved plans (CP -4); North Wing furniture revision (CP -20); Dog kennel expansion (CP -31); and Add/install flag pole (CP -34) Detail as Appropriate: See Attached Contract Bid Amount: SALES TAX @ 8.6%: Total: $ 6,582,112.00 $ 566,061.63 $ 7,148,173.63 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal $ 409,974.56 Subtotal $ 39,327.00 Sales tax @ 8.6% $ 35,257.81 Sales tax @ 8.6% $ 3,382.12 Total $ 445,232.37 Total $ 42,709.12 Total Change Orders To Date $ 487,941.49 New Contract Amount $ 7,636,115.13 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER r—Y—E—S-1 NO Contract Time Prior to this Change Order Modification to Contract time by this Change Order ............... 5 Days revised Total Contract Time. .......... ......... _. _ ... _ .. ......... It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: NTRACTOR bate APPROVED: PROJECT MANAGER Date Total Site Services, LLC CHANGE PROPOSAL (CP) NO: 4 TO: City of Pasco 525 North Third Ave Pasco, WA 99301 ATTN: Kent McCue, Construction Manager CP DESCRIPTION PROJECT NAME: Pasco Police Cor Services Building CONTRACT #: C5 -GN -9A-14-01 PROJECT NO: 15-006 DATE: 7/29/2015 VIA: E -Mail FROM: Dennis Hollis RFI -028 - Pricing for floor drains at showers - Contract drawings did not call out for floor drains at the shower location, only the mixing valve fixtures were called out (P7 and P8). The specifications called out "Solid Base" for the showers but was not called out on the Plumbing Fixture schedule (drawing 1000). A solid base would have the drain built in. therefore the noted floor drains were not included in the bid. This Change Proposal is in response to RFI -028 The total cost of the proposed change is: This Change Proposal is good through: The schedule effect of this change is: Enclosures in support of this proposal includes: 1) TSS Estimate for Change 2) ACM Proposal 3) RFI -024 4) Product data for floor drain QUALIFICATIONS ■ This proposal covers only the specific items that have been priced as listed on the attached cost breakdown. RFI -028 $3,647.00 8/31/2015 0 Working Days Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained in their quotes SUBMITTED BY: Dennis Hollis - Project Manager BY: 07/29/15 DATE DATE \ } \ C; c; { � `� ) - - - -- \ \ \ ( ; /8}@a;} ( ------- � |� - b; § \) )/ \\ 32 § M $` - § ° \ +7! § ( / / _ \ ) _ �!&e -, , a \)§2§ 2))7� #\,i7\\ \ )! \: \ � 00 ,CK k»!k | _ -_ !§ )} � | §§ !/;;;\;� e 0§!§§§| §§ §£;#2 1 Total Site Services, LLC CHANGE PROPOSAL (CP) NO: 20 TO: City of Pasco 525 North Third Ave PROJECT NAME: Pasco Police Con Pasco, WA 99301 Services Building ATTN: Kent McCue, Construction Manager CONTRACT #: C5 -GN -9A-14-01 PROJECT NO: 15.006 DATE: 4/20/2016 VIA: E -Mail FROM: Chris Canario CP DESCRIPTION North Wing furniture revisions per RFI response and drawings 1113R, and 1153R This scope of work effects critical path of electrical inspection, and drywall. This Change Proposal, consisting of an estimate, responds to your Request for Proposal No. Owner Request The total cost of the proposed change is: $8,481.00 This Change Proposal is good through: 5/4/2016 The schedule effect of this change is: 2 Working Days Enclosures in support of this proposal includes: 1 ) TSS Estimate for Change 2) Arc Electric quote 3) 4) QUALIFICATIONS ■ This proposal covers only the specific items that have been priced as listed on the attached cost breakdown. Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained in their quotes 04/20/16 SUBMITTED BY: Christopher Canario - Field Engineer DATE APPROVED BY: City of Pasco DATE !!;|;;....|... � §_ .............. ....... .., . / � � $ ; ! § � - � ! § l,•, , § ! § , } �� ^ !! ! {!\ //\} )� §|| / ;;;l;; ; §§§)�§/\� ) \! ,� ! : | � Total Site Services, LLC CHANGE TO: City of Pasco 525 North Third Ave Pasco, WA 99301 ATTN: Kent McCue, Construction Mam CP DESCRIPTION Dog Kennel expansion NO: 31 PROJECT NAME: CONTRACT#: PROJECT NO: DATE: VIA: FROM: Pasco Police Cor Services Building C5 -GN -9A-14-01 15-006 6/28/2016 E -Mail Kyle Hintz This Change Proposal, consisting of an estimate, responds to your Request for Proposal P Owner Request The total cost of the proposed change is: $19,807.00 This Change Proposal is good through: 7/15/2016 The schedule effect of this change is: 1 Working Days Enclosures in support of this proposal includes: 1 ) TSS Estimate for Change 2) Contractors Estimate for change 3) 4) QUALIFICATIONS ■ This proposal covers only the specific items that have been priced as listed on the attached cost breakdown. Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained in their quotes 06/28/16 SUBMITTED BY: Kyle Hintz - Field Engineer DATE APPROVED BY: City of Pasco DATE _ |;;'I|i') |\!!§| ■ | .. .............} ;.\\(`§ \ . } l,.,...... . !` \ |...,.,., � ! \0(|,)„/| Total Site Services, LLC CHANGE PROPOSAL (CP) NO: 34 TO: City of Pasco 525 North Third Ave PROJECT NAME: Pasco Police Comn Pasco, WA 99301 Services Building ATTN: Kent McCue, Construction Marr CONTRACT #: C5 -GN -9A-14-01 PROJECT NO: 15-006 DATE: 6/22/2016 VIA: E -Mail FROM: Kyle Hintz CP DESCRIPTION Add/install flag pole This Change Proposal, consisting of an estimate, responds to your Request for Proposal P Owner Request The total cost of the proposed change is: This Change Proposal is good through: The schedule effect of this change is: Enclosures in support of this proposal includes: 1) TSS Estimate for Change 2) Pole Tech quote 3) Big D quote 4) QUALIFICATIONS $7,392.00 7/15/2016 2 Working Days IN This proposal covers only the specific items that have been priced as listed on the attached cost breakdown. Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained in their quotes ��� 06/22/16 SUBMITTED BY: Kyle Hintz - Field Engineer DATE 4g' zr APPROVED BY: City of Pasco _ DATE § ;||() !; ;.\\/. � ) | l;l\ / ! §) �§ �,j) | � \ ! ;!;■`! , ;§!)�]!6 §!!a! _ - |,■,!:()§ , ��