HomeMy WebLinkAboutClearwater Construction Change Order 6 CP7-SE-2A-13-02 Primary Clarifier UpgradeCITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 6 Project No: CP7-SE-2A-13-02 Project Title: Primary Clarifier Upgrade CHANGE ORDER #6 Contractor: Clearwater Construction, 5711 W. Garden Springs Road, Spokane, WA 99224 Description of Change: Refer to Backup Sheet Detail as Appropriate: Refer to Backup Sheet Contract Bid Amount: Sales Tax @ 8.6%: Total: $ 4,267,300.00 $ 366,987.80 $ 4,634,287.80 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal $ 74,593.94 Subtotal $ 1,906.10 Sales tax @ 8.6% $ 6,415.08 Sales tax @ 8.6% $ 163.92 Total $ 81,009.02 Total $ 2,070.02 Total Change Orders To Date $ 83,079.04 New Contract Amount $ 4,717,366.84 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO Contract Time Prior to this Change Order ................................. 304/354 Modification to Contract time by this Change Order .................... 1 Revised Total Contract Time .................................................... 305/355 It is n:utual!y agreed by both parties that this Change Order fully describes the change's) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AqREED TO AND ACCEPTED: CONTRACTOR Date APP VIED CITY ENGINE R Date APPROVED: �r- 6-10ID RlJeCANAGER Date C) (0 cO 1 T O z ly W a Of O W a z x U H U z Z O U H a W D a. a a O U w cu A ui F- a. O U 6 LUO w IL IL 6 W H a w U U Q Z Q O H 0 w w Ix0 Q O c O ~E _ O R F 7 O C p O = U E o a)E U � c3 c a o 00 E Q .. m a r C 0 N a U J O N O a 0 _N N d Z U — U 6 LUO w IL IL 6 W H a w U U Q Z Q O H 0 w w Ix0 Q City of Pasco — Public Works Department Change Order No. 6 Backup Sheet Description of Need & Cost Evaluation Prepared by: Don Tulloch, P.E. — Gray & Osborne, Inc. Date: July 21, 2016 COP 029 — 120 V Power to LCP-251 Background Information: Per Change Order Proposal 12, the location of LCP-251 was switched with the location of LCP-250 so that the control panel with the VFD would be protected inside the sludge pump room. LCP-251 was installed by the wet well where LCP-250 was originally planned. However, the original plans did not include power to the control panel located by the wet well. Therefore, additional conduit must be provided to provide 120 V power from the adjacent light pole to LCP-251. Cost Evaluation: The change order pricing is $1,906.10. These costs appear reasonable. If the power connection had been added as a part of Change Order Proposal 12, the cost likely would have been higher because more conduit would have been needed to provide power from the sludge pumping room. The final additive price for this change item is..........................................................$1,906.10 Increase contract time (calendar days)..........................................................................1 days Page 1 of 1 Memo To: Ahmad Qayoumi, P.E. - Public Works Director From: Leah C. Fisk, E.I.T. - Associate Engineer Date: July 27, 2016 Re: Change Order Number 6 for the Primary Clarifier Project ' R CITY OF PASCO ���ii�lllll 1111lIIII1 I IIIIIP Public Works This memo has been provided as supporting documentation for change order number 5 for the primary clarifier project. This change order is for a total of $2,070.02, including tax, and includes the following items: 1. 120 Volt Power to LCP-251—$2,070.02 This change order includes the cost of additional conduit that was needed to power LCP-250. This additional conduit is needed because the location of LCP-251 was switched with the location of LCP-250 so that the control panel with the VFD would be protected inside the sludge pump room; rather than next to the primary clarifier where it was originally planned to be installed. It's believed that the gases from the clarifier would shorten the expected life of the VFD. The original plans did not include power to the control panel located by the wet well. Steve Brewer and Dan Ford approved the change order on July 27, 2016. Please sign the attached change order. If you have any questions or any additional information is needed, please let me know. Thank you, Leah C. Fi9k, EIT Associate Engineer \EPSI1.ON21Eagr.mg Working FW.tl ,Proj-Sew \CPME-2A-13-02 PMh ClmifierImpmo mts a ad Pump RoomWemo$Wd -cha eordaro. 6 for primary dmifier.doc