HomeMy WebLinkAboutBig D's Construction Change Order No. 1 C7-WT-2R-15-01 Oregon Avenue WaterlineCITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 1
Project No: C7 -WT -2R-15-01 Project Title: Oregon Avenue Waterline
Contractor: Big D's Construction of Tri -Cities Inc.
Description of Change: Additional Sawcutting & Asphalt Disposal
Detail as Appropriate: Plans show an
of 8" for
Contract Bid Amount:
SALES TAX @ 8.6%:
Total:
Actual
$ 1,005,365.50
$ 86,461.43
$ 1,091,826.93
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal
Subtotal $ 56,751.71
Sales tax @ 8.6% $
Sales tax @ 8.6% $ 4,880.65
Total
Total $ 61,632.36
Total Change Orders To Date $ 61,632.36
New Contract Amount $ 1,153,459.29
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ................................. 80
Modification to Contract time by this Change Order .................... 15
revised Total Contract Time .................................................... g5
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
o•04.-?-t(-f6
CONTRACTOR D e
APPROVED:
7/7//6
■1
a-)fy
Memo
Public Works Department
Engineering Division
To: Kent McCue, Construction Manager
CC: Rene Lopez, Construction Inspector
Brenda Timpany, Admin Assistant 1
From: David Tanner, P.E., Civil Engineer
Date: June 24, 2016
Re: Change Order #1, Oregon Avenue Waterline — Sawcutting & Asphalt Disposal
Change Order No. 1 reflects the revisions to the Oregon Avenue Waterline project listed below. This change
order was negotiated by the City and Contractor to address a change in condition.
The City was notified of a change in condition for additional asphalt thickness. After reviewing the Contractors
request we agreed that a reasonable person could interpret Detail 2, sheet 16 to mean that the proposed 8"
depth of asphalt replacement is meant to replace an existing asphalt with similar to equal depth, and that the
existing 12" of asphalt in Oregon Avenue resulted in a change in condition.
The original change request was for $117,386.15, after negotiation and the removal of work items which
should not have been included in the original change order, the contractor has resubmitted the change
request with the agreed upon changes.
Staff recommends approving Change Order #1 for $56,751.71 plus tax, and an additional 15 contract days
for work associated with this change order.