HomeMy WebLinkAboutTotal Site Services Change Order 8 C5-GN-9A-14-01 Police Community Services BuildingCITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.,7"8
Project No: C5-GWI)A-14-01 Project Title: Pasco Police Community Services Building
Contractor: Total Site Services
Description of Change:
Detail as Appropriate:
See Attached
Contract Bid Amount: $ 6,582,112.00
SALES TAX @ 8.6a/o: $ 566,061.63
Total: $ 7,148,173.83
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 62,469.67
Subtotal
$ 203,656.89
Sales tax @ 8.6% $ 5,372.39
Sales tax @
8.6% $ 17,514,49
Total $ 87,842.06
Total
$ 221,171.38
Total Change Orders To Date $ 288,013.44
New Contract Amount $ 7,437,187.08
15 CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order .................... 27 Days
revised Total Contract Time... _ .............................................. .
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED AND CEPTED: APPROVED:
6 0,7 '
co; ;TOR oma ,.11 dY � ( iOs.%f _'A
PROJECT MANAGER Dat¢
APPROVED: APPROVE
STR�N1AGERDaDa PI1B ORKS Dina
DI CTOR
au l
Total Site Services, LLC
CHANGE PROPOSAL (CP) NO. 07
TO: City of Pasco
525 North Third Ave Pasco Police Cor
Pasco, WA 99301 PROJECT NAME:
Services Building
ATTN: Kent McCue, Construction Manager CONTRACT M C5 -GN -9A-14-01
PROJECT NO: 15-006
- - - DATE: 9/1/2015
VIA: E -Mail
CP DESCRIPTION FROM: Dennis Hollis
Excavate/Backfill and Install 44" Communication Conduits from West Basement to 10 feet past Grid Line 13. We have
excluded utilizing spacers - conduit will be placed directly on the ground and will be spaced by placing dirt between the
conduits during installation.
This Change Proposal, consisting of an estimate, responds to: Owner Request
The total cost of the proposed change without WSST is: $18,938.89
This Change Proposal is good through: 9/10/2015
The schedule effect of this change is: 3 Days - Required for Slab Prep
Enclosures in support of this proposal includes:
1) TSS Estimate for Change
2) ARC Cost Work Sheet
3)
QUALIFICATIONS
■ This proposal covers only the specific items that have been priced as listed on the attached cost breakdown.
Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained
in their quotes
SUBMITTED BY:
Dennis Hollis - Project Manager
t &-ea
APPROVED BY:
Citv of Pasco
09/01/15
DATE
Total Site Services, LLC
CHANGE P
TO: City of Pasco
525 North Third Ave
Pasco, WA 99301
NO: 09
PROJECT NAME: Pasco Police Community
Services Building
ATTN: Kent McCue, Construction Manager CONTRACT M C5 -GN -9A-14-01
PROJECT NO: 15-006
DATE: 12/7/2015
VIA: E -Mail
FROM: Dennis Hollis
CP DESCRIPTION
Lighting changes from submittal review. Lighting was put on hold till reviewed due to changes coming for final design
configuration.
This Change Proposal, consisting of an estimate, responds to:
The total cost of the proposed change without WSST is:
This Change Proposal is good through:
The schedule effect of this change is:
Enclosures in support of this proposal includes:
1 ) TSS Estimate for Change
2) ARC Electric Cost Proposal sheets (11 pages)
3)
QUALIFICATIONS
Submittal Changes by
Designer
19 days due to added work (454 Hours - 3 men)
■ This proposal covers only the specific items that have been priced as listed on the attached cost breakdown.
$139,091.00
2/29/2016
Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained
their quotes
SUBMITTED BY:
Dennis Hollis - Project Manager
f•
APPROVED BY
02/24/16
DATE
Total Site Services, LLC
CHANGE PROPOSAL (CP) NO: 11
TO: City of Pasco
525 North Third Ave PROJECT NAME: Pasco Police Community
Pasco, WA 99301 Services Building
ATTN: Kent McCue, Construction Manager CONTRACT #: C5 -GN -9A-14.01
PROJECT NO: 15.006
DATE: 1/3/2016
VIA: E -Mail
FROM: Dennis Hollis
CP DESCRIPTION
RFI 009/032/0481065 - Install Power for Building per FPUD Directions - From Existing Power Pole on East Side of 1st- New
Vault installed on west side of 1st and transformer Vault supplied and set. The final power tie-in was not shown on the electrical
site plans at Bid time. The road crossing and trenching has been traded for being able to connect into the existing sewer line so
the sewer tie in at 1 st street has been deleted.
This Change Proposal, consisting of an estimate, responds to:
The total cost of the proposed change without WSST is:
This Change Proposal is good through:
The schedule effect of this change is: 5 days
Enclosures in support of this proposal includes:
I ) TSS Estimate for Change
2) ARC Electric Cost Proposal sheets
3)
QUALIFICATIONS
IN This proposal covers only the specific items that have been priced as listed on the attached cost breakdown.
Submittal Changes by
Designer
$21,095.00
1/31/2016
■ Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained
their quotes
01/03/16
SUBMITTED BY:
Dennis Hollis - Projekt Manager DATE
APPROVED BY:
City of Pasco DATE
Total Site Services, LLC
NGE PROPOSAL (CP) NO: 12
TO: City of Pasco
525 North Third Ave
Pasco, WA 99301 PROJECT NAME
ATTN: Kent McCue, Construction Manager CONTRACT #:
PROJECT NO:
DATE:
VIA:
FROM:
CP DESCRIPTION
Sound duct return
Pasco Police Cor
Services Building
C5 -GN -9A-14-01
15-006
3/8/2016
E -Mail
Chris Canario
This Change Proposal, consisting of an estimate, responds to your Request for Proposal No. Owner Request
The total cost of the proposed change is: $19,805.00
This Change Proposal is good through: 3/10/2016
The schedule effect of this change is: 0 Working Days
Enclosures in support of this proposal includes:
1 ) TSS Estimate for Change
2) Apollo quote
3)
QUALIFICATIONS
■ This proposal covers only the specific items that have been priced as listed on the attached cost breakdown.
Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained
in their quotes �,,'
eJ —' 03/08/16
SUBMITTED BY:
Christopher Canario - Field Engineer DATE
ez/
APPRbVED BY:
Total Site Services, LLC
CHANGE PROPOSAL (CP) NO: 21
TO: City of Pasco
525 North Third Ave PROJECT NAME: Pasco Police Comrr
Pasco, WA 99301 Services Building
ATTN: Kent McCue, Construction Manager CONTRACT III: C5 -GN -9A-14-01
PROJECT NO: 15-006
DATE: 4/20/2016
VIA: E -Mail
FROM: Chris Canario
CP DESCRIPTION
Electrical changes for the projector screens based on EC2 and. EC5
This Change Proposal, consisting of an estimate, responds to your Request for Proposal No. Owner Request
The total cost of the proposed change is: $4,727.00
This Change Proposal is good through: 5/4/2016
The schedule effect of this change is: 0 Working Days
Enclosures in support of this proposal includes:
1 ) TSS Estimate for Change
2) Arc Electric quote
3)
4)
QUALIFICATIONS
■ This proposal covers only the speck items that have been priced as listed on the attached cost breakdown.
t Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained
in their quotes
04/20/16
SUBMITTED BY:
Christopher Canario - Field Engineer DATE
APPR15VED BY: