HomeMy WebLinkAboutIndustrial Constructors WWTP Caustic Soda C7-SE-1A-15-42CITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 5 Project No: C7 -SE -1A-15-42 Project Title: WWTP Caustic Soda Improvements Contractor: Industrial Constructors Inc. Description of Change: Reconfigure suction piping and install fill piping etc Detail as Appropriate: See Attached Contract Bid Amount: $ 164,200.00 SALES TAX @ 8.6%: $ 14,121.20 Total: $ 178,321.20 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal $ 22,624.17 Subtotal $ 7,375.66 Sales tax @ 8.6% $ 1,945.68 Sales tax @ 8.6% $ 634.31 Total $ 24,569.85 Total 8,009.97 Total Change Orders To Date $ 32,579.82 New Contract Amount $ 210,901.02 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES I Contract Time Prior to this Change Order ................................. 103 Modification to Contract time by this Change Order .................... 0 revised Total Contract Time .................................................... 103 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. R D TO AND ACCEPTED: N CTOR ate APPROVED: EIVf3tPoEEit GDAJu a ate APPROV_ PROJECT MANAGER ate APP O F PU� IC DIRECTOR Date a&3'(�7 Memo Public Works Department Engineering Division To: Dan Ford, City Engineer CC: Brenda Timpany, Admin Assistant 1 From: David Tanner, P.E., Civil Engineer Date: May 25, 2016 Re: Change Order#5, WWTP Caustic Soda Improvements Change Order No. 5 reflects the revisions to the W WTP Caustic Soda Improvements listed below. This change order was negotiated by the City and Contractor to address additional work, not addressed in the contract documents, necessary to the completion of the project as described below: Due to unexpected flow test results the contractor was directed to revise the suction piping to attach to the %" outlet instead of the 2" outlet as recommended by Northstar Chemical Inc. Work for this item included additional testing of the system once completed. The final price is a result of negotiation between the City and Contractor on work necessary to complete the requested work. Staff recommends approval of Change Order #5 for $7375.66 plus tax. 0 Page 1 CITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 6 Project No: C7 -SE -1A-1542 Project Title: WWTP Caustic Soda Improvements Contractor: Industrial Constructors Inc. Description of Change: Change order to reconfigure suction piping for side outlet Detail as Appropriate: See Attached Contract Bid Amount: $ 164,200.00 SALES TAX @ 8.6%: $ 14,121.20 Total: $ 178,321.20 PREVIOUS -6 ANGE ORDER CURRENT CHANGE ORDER Subtotal $ 29,999.83 Subtotal $ 6,613.75 Sales tax @ 8.6% $ 2,579.99 Total Sales tax @ 8.6% $ 568.78 $ 32,579.82 Total 7,182.53 Total Change Orders To Date $ 39,762.35 New Contract Amount $ 218,083.55 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER r--7ffS-1 NO Contract Time Prior to this Change Order ................................. 103 Modification to Contract time by this Change Order .................... 0 revised Total Contract Time .......................................... 103 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply t t is Change Order. E TO AND ACCEPTED: APPROVEDL__ G TOR Date PROJECT MANRGER Date APPROV D: PUB DIRECTOR atP Memo Public Works Department Engineering Division To: Dan Ford, City Engineer CC: Brenda Timpany, Admin Assistant 1 From: David Tanner, P.E., Civil Engineer Date: May 25, 2016 Re: Change Order #6, W WTP Caustic Soda Improvements Change Order No. 6 reflects the revisions to the W WTP Caustic Soda Improvements listed below. This change order was negotiated by the City and Contractor to address additional work, not addressed in the contract documents, necessary to the completion of the project as described below: After continued testing of the system and discussions with all parties involved, Northstar Chemical agreed with the City's Design Engineer (RH2 Engineering) that a side outlet for the suction piping was needed to maximize the potential delivery of the caustic soda design. Northstar chemical has agreed to pay for the installation of the side outlet in the Tank. This change order reflects the work necessary for the City's Contractor to reconfigure the suction line piping to connect to the new side outlet. The final costs for this work are approximately $2,000 less than the original estimate provided. Staff recommends approval of Change Order #5 for $6,613.75 plus tax. 0 Page 1