CONTRACT CHANGE ORDER NO. 5
Project No: C7 -SE -1A-15-42 Project Title: WWTP Caustic Soda Improvements
Contractor: Industrial Constructors Inc.
Description of Change: Reconfigure suction piping and install fill piping etc
Detail as Appropriate: See Attached
Contract Bid Amount: $ 164,200.00
SALES TAX @ 8.6%: $ 14,121.20
Total: $ 178,321.20
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 22,624.17
Subtotal $ 7,375.66
Sales tax @ 8.6% $ 1,945.68
Sales tax @ 8.6% $ 634.31
Total $ 24,569.85
Total 8,009.97
Total Change Orders To Date $ 32,579.82
New Contract Amount $ 210,901.02
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES I
Contract Time Prior to this Change Order ................................. 103
Modification to Contract time by this Change Order .................... 0
revised Total Contract Time .................................................... 103
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
R D TO AND ACCEPTED:
N CTOR ate
APPROVED:
EIVf3tPoEEit GDAJu a ate
APPROV_
PROJECT MANAGER ate
APP O F
PU� IC DIRECTOR Date
a&3'(�7
Memo
Public Works Department
Engineering Division
To:
Dan Ford, City Engineer
CC:
Brenda Timpany, Admin Assistant 1
From:
David Tanner, P.E., Civil Engineer
Date:
May 25, 2016
Re:
Change Order#5, WWTP Caustic Soda Improvements
Change Order No. 5 reflects the revisions to the W WTP Caustic Soda Improvements listed below. This
change order was negotiated by the City and Contractor to address additional work, not addressed in the
contract documents, necessary to the completion of the project as described below:
Due to unexpected flow test results the contractor was directed to revise the suction piping to attach to the %"
outlet instead of the 2" outlet as recommended by Northstar Chemical Inc. Work for this item included
additional testing of the system once completed. The final price is a result of negotiation between the City and
Contractor on work necessary to complete the requested work.
Staff recommends approval of Change Order #5 for $7375.66 plus tax.
0 Page 1
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 6
Project No: C7 -SE -1A-1542 Project Title: WWTP Caustic Soda Improvements
Contractor: Industrial Constructors Inc.
Description of Change: Change order to reconfigure suction piping for side outlet
Detail as Appropriate: See Attached
Contract Bid Amount: $ 164,200.00
SALES TAX @ 8.6%: $ 14,121.20
Total: $ 178,321.20
PREVIOUS -6 ANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 29,999.83
Subtotal $ 6,613.75
Sales tax @ 8.6% $ 2,579.99
Total
Sales tax @ 8.6% $ 568.78
$ 32,579.82
Total 7,182.53
Total Change Orders To Date $ 39,762.35
New Contract Amount $ 218,083.55
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER r--7ffS-1 NO
Contract Time Prior to this Change Order ................................. 103
Modification to Contract time by this Change Order .................... 0
revised Total Contract Time .......................................... 103
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply t t is Change Order.
E TO AND ACCEPTED: APPROVEDL__
G TOR Date PROJECT MANRGER Date
APPROV D:
PUB DIRECTOR atP
Memo
Public Works Department
Engineering Division
To:
Dan Ford, City Engineer
CC:
Brenda Timpany, Admin Assistant 1
From:
David Tanner, P.E., Civil Engineer
Date:
May 25, 2016
Re:
Change Order #6, W WTP Caustic Soda Improvements
Change Order No. 6 reflects the revisions to the W WTP Caustic Soda Improvements listed below. This
change order was negotiated by the City and Contractor to address additional work, not addressed in the
contract documents, necessary to the completion of the project as described below:
After continued testing of the system and discussions with all parties involved, Northstar Chemical agreed
with the City's Design Engineer (RH2 Engineering) that a side outlet for the suction piping was needed to
maximize the potential delivery of the caustic soda design. Northstar chemical has agreed to pay for the
installation of the side outlet in the Tank. This change order reflects the work necessary for the City's
Contractor to reconfigure the suction line piping to connect to the new side outlet. The final costs for this work
are approximately $2,000 less than the original estimate provided.
Staff recommends approval of Change Order #5 for $6,613.75 plus tax.