HomeMy WebLinkAboutTotal Site Services Change Orders 6 & 7 C5-GN-9A-14-01 Police Community Services BuildingCITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.6
Project No: C5 -GN -9A -14-W Project Title: Pasco Police Community Services Building
Contractor: Total Site Services
Description of Change: Addition of vision panels to office doors: Addition of sidelights to office
Detail as Appropriate: See
Contract Bid Amount:
SALES TAX @ 8.6%:
Total:
$ 6,582,112.00
$ 566,061.63
$ 7,148,173.63
PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER
Subtotal $ 47,377.67 Subtotal $ 8,886.00
Sales tax @ 8.6%$ 4,074.48 Sales tax @ 8.6% $ 764.20
Total $ 51,452.15 Total $ 9,650.20
Total Change Orders To Date $ 61,102.35
New Contract Amount $ 7,209,275.96
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order ......... ..................
Modification to Contract time by this Change Order ..............
revised Total Contract Time .............................................
YES NO
It is mutually agreeo uy uuul P -u— � �• � •- -• - ---- -
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO ND ACCEPTED: APPROVED:
N CTOR Dale
� P JECT MANAGER Date �
APPROVED:
-<aS�Zo�/�
CONSTRUCTION MANAGER Dater
APP R VED•;
^� r
t 20�
UBL WO KS Det
DIRECTOR
0Cof9
Total Site Services, LLC
CHANGE
TO: City of Pasco
525 North Third Ave
Pasco, WA 99301
ATTN: Kent McCue, Construction Manager
CP DESCRIPTION
POSAL (CP) NO: 15
PROJECT NAME: Pasco Police Cor
Services Building
CONTRACT #:
C5 -GN -9A-14-01
PROJECT NO:
15-006
DATE:
3/25/2016
VIA:
E -Mail
FROM:
Chris Canario
Pricing for addition of: Vision panels to office doors: 145,147,149A,157A,157B, 157C, 1708 - Addition of sidelights to office
doors: #121, 128 - Enlarge Sidelight #115 - Clearstory Glass windows: Room 173, 176, 178, 179.
This Change Proposal, consisting of an estimate, responds to your Request for Proposal No, Owner Request
The total cost of the proposed change is: $8,886.00
This Change Proposal is good through: 4/8/2016
The schedule effect of this change is: 0 Working Days
Enclosures in support of this proposal includes
1)
TSS Estimate for Change
2)
AM Hardware
3)
Yale Glass
4)
ARC Electric
QUALIFICATIONS
■ This proposal covers only the specific items that have been priced as listed on the attached cost breakdown.
Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained
in their quotes
ems^ - 03/25/16
SUBMITTED BY:
Christopher Canario - Field Engineer DATE
APPROVED BY:
City of Pasco DATE
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.7
Project No: C5 -GN -9A-14-01 Project Title: Pasco Police Community Services Building
Contractor: Total Site Services
Description of Change: Move conduits in six rooms to lower elevation per Cijys request. \
/rs� rp�'i7
Detail as Appropriate: See
Contract Bid Amount: $ 6,582,112.00
SALES TAX @ 8.6%: $ 566,061.63
Total: $ 7,148,173.63
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 56,263.67
Subtotal $ 6,206.00
Sales tax @ 8.6% $ 4,838.68
Sales tax @ 8.8°/6 $ 533.72
Total $ 61,102.35
Total $ 6,739.72
Total Change Orders To Date $ 67,842.06
New Contract Amount
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ...................
revised Total Contract Time ..................................................
$ 7,216,015.69
YES NO
2 Days
It Is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, It is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TOAND ACCEPTED, APPROVED:
COMTRACT09EZ& PROJECT MAA Dale
APPROVED: AP//PROVED
,��yrA�/r G
z.i 20/(0
LiLZ
ol
CONSTRUCTION AGER ate / PUBLIC w KS Dal
DIRECTOR
Total Site Services, LLC
XIM
TO: City of Pasco
525 North Third Ave
Pasco, WA 99301
E PROPOSAL
P) NO: 17
PROJECT NAME: Pasco Police Cot
Services Building
ATTN: Kent McCue, Construction Manager CONTRACT #:
C5 -GN -9A-14-01
PROJECT NO:
15-006
DATE:
4/7/2016
VIA:
E -Mail
FROM:
Chris Canario
CP DESCRIPTION
Move conduits in six rooms to lower elevation per ower request
This Change Proposal, consisting of an estimate, responds to your Request for Proposal No. Owner Request
The total cost of the proposed change is: $6,206.00
This Change Proposal is good through: 4/20/2016
The schedule effect of this change is: 2 Working Days
Enclosures in support of this proposal includes:
1 ) TSS Estimate for Change
2) ARC Electric estimate
3)
4)
QUALIFICATIONS
■ This proposal covers only the specific items that have been priced as listed on the attached cost breakdown.
Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained
in their quotes
e� 04/07/16
SUBMITTED BY:
Christopher Canario - Field Engineer
APPROVED BY:
DATE