HomeMy WebLinkAboutIndustrial Constructors 2, 3 & 4 Caustic Soda C7-SE-1A-15-42CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 2
Project No: C7 -SE -1A-15-42 Project Title: WWTP Caustic Soda Improvements
Contractor: Industrial Constructors Inc.
Description of Change: Change order to address work necessary for the installation of external piping,
and seismic restraint system for the caustic soda tank provided by Northstar.
Detail as Appropriate: See
Contract Bid Amount: $ 164,200.00
SALES TAX @ 8.6%: $ 14,121.20
Total: !F 178,321.20
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
ORD:
Subtotal $ 11,369.82
Subtotal $ 9,118.40
Sales tax @ 8.6% $ 977.80
Sales tax @ 8.6% $ 784.18
Total $ 12,347.62
Total 9,902.58
Total Change Orders To Date $ 22,250.20
New Contract Amount $ 200,571.40
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER r—Ws--1 NO
Contract Time Prior to this Change Order.. .... .......................... 68
Modification to Contract time by this Change Order .................... 15
revised Total Contract Time. .. - - . ... — ... ............. -- ................. 83
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
Z:'&/Z, /'I'Ki7/LGL'CUL 02/10116
CONTRACTOR Date
APP?PVEQf
4Z /0 6
CI NGINEER ate
AP
/ z$Ij
PROJECT MANAGER Data
Memo
Public Works Department
Engineering Division
To:
Dan Ford, City Engineer
CC:
Brenda Timpany, Admin Assistant 1
From:
David Tanner, P.E., Civil Engineer
Date:
February 2, 2016
Re:
Change Order #2, W WTP Caustic Soda Improvements
Change Order No. 2 reflects the revisions to the W WTP Caustic Soda Improvements listed below. This
change order was negotiated by the City and Contractor to address additional work, not addressed in the
contract documents, necessary to the completion of the project as described below:
1. Installation of the Seismic Restraint System as provided by the tank manufacturer (Northstar).
2. Installation of fill station piping and pipe supports on the exterior of the tank, including Camlock end
fitting provided by Northstar.
3. Installation of pump suction piping and pipe supports on the exterior of the tank provided by
Northstar.
This work was originally believed to be included with the installation of the tank as provided by the
manufacturer. However, the contract signed does not provide for it, and the manufacturer's representative
relayed that they typically don't install those items, and that they didn't have the proper personel to do so.
Staff recommends approval of Change Order #2 for $9,118.40 plus tax.
0 Page 1
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 3
Project No: C7-SE-lA-15-42 Project Title: W WTP Caustic Soda Improvements
Contractor: Industrial Constructors, Inc.
Description of Change: Change order to address work necessary for the installation of the temperature
controller for the caustic soda tank provided by Northstar.
Detail as Appropriate: See Attached
Contract Bid Amount: $ 164,200.00
SALES TAX @ 8.6%: $ 14,121.20
Total: $ 178,321.20
Total Change Orders To Date $ 23,946.99
New Contract Amount $ 202,268.18
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER ® NO
Contract Time Prior to this Change Order ................................. 83
Modification to Contract time by this Change Order .................... 20
revised Total Contract Time .................................................... 103
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
7')erG7i��✓`i��uy 02/10/16
CONTRACTOR Date
APPROVE r
CITY ENGINEER Data
APP OVED:
PROJECT MANAGER Date
APPRpVED
0
PUBLI TR CTOR are
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $
Sales tax @ 8.6% $
Total $
20,488.22
1,761.99
22,250.21
Subtotal $
Sales tax @ 8.6% $
Total
1,562.41
134.37
1,696.78
Total Change Orders To Date $ 23,946.99
New Contract Amount $ 202,268.18
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER ® NO
Contract Time Prior to this Change Order ................................. 83
Modification to Contract time by this Change Order .................... 20
revised Total Contract Time .................................................... 103
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
7')erG7i��✓`i��uy 02/10/16
CONTRACTOR Date
APPROVE r
CITY ENGINEER Data
APP OVED:
PROJECT MANAGER Date
APPRpVED
0
PUBLI TR CTOR are
Memo
Public Works Department
Engineering Division
To:
Dan Ford, City Engineer
CC:
Brenda Timpany, Admin Assistant 1
From:
David Tanner, P.E., Civil Engineer
Date:
February 3, 2016
Re:
Change Order #3, W WTP Caustic Soda Improvements
Change Order No. 3 reflects the revisions to the WWTP Caustic Soda Improvements listed below. This
change order was negotiated by the City and Contractor to address additional work, not addressed in the
contract documents, necessary to the completion of the project as described below:
1. Installation of the Tank Temperature Controller
This work was originally believed to be included with the installation of the tank as provided by the
manufacturer. However, the contract signed does not provide for it, and the manufacturer's representative
relayed that they typically don't install those items, and that they didn't have the electricians needed to do so.
Staff recommends approval of Change Order #3 for $1,562.41 plus tax.
0 Page 1
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 4
Project No: C7 -SE -1A-15-42 Project Title: W WTP Caustic Soda Improvements
Contractor: Industrial Constructors, Inc.
Description of Change: Change order to replace NEMA 1 Enclosure with a NEMA 4 enclosure
for the temperature controller, for the caustic soda tank provided by Northstar.
Detail as Appropriate:
Contract Bid Amount: $ 164,200.00
SALES TAX @ 8.6%: $ 14,121.20
Total: $ 178,321.20
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $
22,050.63
Subtotal $ 573.54
Sales tax @ 8.6% $
1,896.35
Sales tax @ 8.6% $ 49.32
Total $
23,946.98
Total $ 622.86
Total Change Orders To Date $ 24,569.84
New Contract Amount $ 202,891.04
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER ® NO
Contract Time Prior to this Change Order.. ............................... 103
Modification to Contract time by this Change Order .................... 20
revised Total Contract Time.. ................................. ........ ....... 123
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED: APPROVED:
Dere Nl'--� 02)10/16 Z g
CONTRACTOR Date PROJECT MANAGER Date
APP QVED-Z/
Z o
CITU ENGU ER ale
APPROVED:
Ad 0 01144
PTIC"17
CTOR I Difie
Memo
Public Works Department
Engineering Division
To:
Dan Ford, City Engineer
CC:
Brenda Timpany, Admin Assistant 1
From:
David Tanner, P.E., Civil Engineer
Date:
February 3, 2016
Re:
Change Order #4, WWTP Caustic Soda Improvements
Change Order No. 4 reflects the revisions to the WWTP Caustic Soda Improvements listed below. This
change order was negotiated by the City and Contractor to address additional work, not addressed in the
contract documents, necessary to the completion of the project as described below:
1. Replace NEMA 1 Enclosure with NEMA 4 Enclosure as recommended by the project engineer.
The Specifications did not name a speck enclosure, and while a NEMA 1 enclosure would work if it could be
protected from the elements, the project engineer recommended replacing it with a NEMA 4 enclosure.
Staff recommends approval of Change Order #4 for $573.54 plus tax.